SlideShare uma empresa Scribd logo
1 de 19
YOUR ROLE AS A
CONTROL ACCOUNT
MANAGER IN THE
INTEGRATED
BASELINE REVIEW
(IBR)
As a CAM you’re the critical success factor in
the IBR
What’s an Integrated Baseline
Review?
What’s a Control Account
Manager?
 The Control Account Manager does what its
name says: Manages the Control Account
 What is a Control Account?
Project CAMs, Is Your Name
Here?
The Participants in the IBR
5
 Develop list of activities
and intermediate
milestones associated with
control accounts.
 Define the duration for
each work activity.
 Specify the labor, material,
and subcontract resource
assignments for each
activity.
 Specify risks, uncertainties,
and to the extent possible,
mitigation strategies.
 Assure compliance with
subcontracts.
 Define framework for the
resource-loaded schedules.
 Entering activity information
required for integration with the
earned value reporting.
 Performing time analysis and
budget/cost calculations.
 Work with CAM and PM to
analyze schedule and budget to
arrive at a credible Performance
Measurement Baseline (PMB).
 Update the PMB schedule
 Update schedule forecast to the
Estimate To Complete (ETC) to
develop the new Estimate At
Completion (EAC).
 Collecting and entering schedule
progress information into the
scheduling program throughout
the project lifecycle.
 Provide schedule reports to
CAMs and senior project
management.
 Establish project technical
requirements and criteria.
 Develop project work scope
using design and engineering
services to create a technical
description.
 Define WBS, WBS Dictionary,
OBS, and RAM for control and
reporting.
 Work with customer and
management to establish
programmatic milestones.
 Work with CAMs to establish
intermediate milestones.
 Work with CAMs and functional
line management to identify the
resources for the project.
 Maintaining WBS, WBS
Dictionary, OBS, and RAM as
controlled documents.
 Establish and mediate interfaces
between control accounts.
 Assure compliance with contract.
The IBR Team
Being a CAM is about managing
the work in the Control Account
(CA)
 All CA management starts with answering the
question “how much money do I have for this
work?”
When the IBR is complete, what will we
know about the program that we don’t know
now?
How will the Probability of Program
Success (PoPS) improve by conducting the
IBR?
What does DONE look like for the IBR?
6 Exit Criteria for the IBR8
† Stephen Covey, Seven Habits of Highly Effective People
1. Confirm the Work Scope
Matches The Schedule9
2. Confirm Schedule Is Credible
10
3. Validate the Allocation Of
Funds11
4. Conduct a EVMS
Assessment12
5. Establish A Dialogue
13
6. The Final Question
14
The mapping of IBR artifacts to the technical
and schedule plans, focuses on the end state
of the IBR to ensure a collaborative
environment is established for program
success.
‒ Ivan Bembers,
IBR Lead, National Geospatial Intelligence
Agency
IBR Work Products15
IBR Work Elements
16
Feeds
Shows
The Elements of the PMB
Performance
Measurement
Baseline
2004 2005 2006
4 1 2 3 4 1 2 3 4 1 2 3 4 1
Scheduled Finish Baseline Finish
Program Milestones Impact Baseline Impact No Impact
Page 1 of 6 8/19/04
by Project
Interface Milestones / Risk Items Report
Standard Missile 3 Program
Finish
Baseline
Finish
Name
Deliver
To
Owner
Ahead/
Behind
Status
Total
Slac
3/1/0512/18/03SW - Deliver Build 6.0 SoftwareSW -20 R -5
1/2/041/2/04HW - Deliver RPU & IMU for IDR-1HW 0 Y 784
1/30/041/30/04HW - Deliver RPU & IMU for IDR-2HW 0 Y 764
3/31/043/31/04HW - Deliver RPU & IMU for IDR-3HW 0 G 721
4/28/044/28/04HW - Deliver RPU & IMU for IDR-4HW 0 G 531
5/4/045/4/04HW - Deliver RPU & IMU for IDR-5HW 0 G 529
5/14/045/14/04Initial BLK I IOM Proofing CompleteIT&A0-0h- 0 G 381
5/17/045/17/04IT&A - Deliver EOM-1 and InertIT&A 0 G 523
5/28/045/28/04HW - Deliver RPU & IMU for IDR-SpHW 0 G 664
6/28/046/28/04SW - Conduct ASP In-Process0-0h-SW 0 G 494
8/16/048/16/04Receive Boeing Block I PVR0-0h-SE 0 G 625
8/23/048/23/04Receive Block IA GP for KW CIL fromSW0-0h- 0 G 469
8/23/048/23/04SW - Deliver Build 6.1 SoftwareHWSW 0 G 469
8/31/048/31/04Prop - Deliver TSRM For IDR-5IT&APROP 0 G 488
9/1/049/1/04Receive BLK I IOM-3A GS Kit48023.0-0h- 0 G 29
9/1/049/1/04Receive BLK I IOM-3A AS48023.0-0h- 0 G 28
9/3/049/3/04S2 Build 6.2 Provide Scenario0-0h- 0 G 383
9/7/049/7/04Release IOM-7 to CamdenIT&A 0 G 609
9/13/049/13/04S3 Build 6.2 Provide Scenario0-0h- 0 G 331
9/22/049/22/04F986-7 Available for Production GS144060-0 hrs- 0 G 335
Interface and Risk Items
2003 2004 2005 2006 2007
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Page 1 of 14 8/19/04
Intermediate View
SM-3 Program Integrated Master Schedule
Out
Lev
Name row
2Program Milestones 1
2Flight Test Program (CLIN 0001) 2
5Mission Flight Dates 3
5Initial Deployment Rounds - RFI 4
5SW - Complete FM-7 Software Update 5
5SW - Complete FM-8 Software Update 6
5SW - Complete FM-9 Software Update 7
5SW - Complete FM-10 (a) Software Update 8
5SW - Complete FM-11 Software Update 9
4FTR-11 10
6HW - Hardware For FTR-11 11
6Prop - Propulsion For FTR-11 12
6IT&A - Conduct Permit To Ship to WSMR for 13
6IT&A - FTR-11 Ready for RFI for FTR-11 14
4FT-Spare 15
5HW - Hardware For FT-Spare 16
5Prop - Propulsion For FT-Spare 17
3IDR Development 18
4IDR-1 19
BLK I IPR
BLK IA Mfg IPR
BLK IA CDR
Blk IA IPR
FM-7 FM-8 FM-9 FM-10(b)
FM-10(a)
FM-11 FM-12
1 2
3
45
Load Software into FM-7
Load Software into FM-8
Load Software into FM-9
Load Software into FM-10(a)
Load Software into FM-11
Hardware For FM-10 (b)
Propulsion For FM-10 (b)
Permit To Ship For FM-10 (b)
RFI For FM-10 (b)
Hardware For FT -Spare
Propulsion For FT-Spare
Intermediate
Schedule
2004 2005
A M J J A S O N D J F M
Path 1
6d
Path 2
19d
Path 3
19d
Path 4
28d
Path 5
28d
8/19/04
FM-7
Critical Paths 1-5 to Milestone
FM-7 Softw are Received for FQT
FM-7 Update Softw are Test Plans
FM-7 Perform Dry Runs
FM-7 Conduct TRR
FM-7 Perform FQT
FM-7 Conduct FQT Data Review
FM-7 Complete FQT High Priority Action Items
Complete FM-7 Softw are Update
IT&A - Retest & Encan for FM-7
IT&A - Conduct Delta Permit to Ship for FM-7
IT&A - Ready for RFI for FM-7
2/9
FM-7
Integration & Test ITD Actuals Aug 03 thru Aug 04
FM-7 Update Test Scenarios
FM-7 Update Test Evaluation Scripts
Functional Design ITD Actuals Aug 03 thru Aug 04
Support FM-7 Sep 2004 - Dec 2004
Support FM-7 Jan 2005 - Feb 2005
HIL ITD Actuals Aug 03 thru August 04
Complete HIL Block I Upgrades to Support Next Block 1 Flig
PerformPre Flight Analysis to Support FM-7
PerformHIL Analysis to Support FM-7
HIL Analysis Data to Support FM-7 MCP
SE- Conduct Mission Control Panel (MCP) for FM-7
Critical Path Analysis
FY03 FY04 FY05 FY06 FY07 FY08 FY09
2003 2004 2005 2006 2007 2008 2009
Missile Del by CY 5 8 14 20 24 3
CUM 5 13 27 47 71 74
Missile Del by FY 5 6 12 18 24 9
CUM 5 11 23 41 65 74
SM-3 Missile Program Schedule - 06/14/04
AEGIS BMD
Buy Missiles
Blk I (IDR) & CY05 Blk I
CY06 & CY07 Blk IA
CY08 BLK IA
Deliver Missiles
Blk I (IDR) & CY05 Blk I
CY06 & CY07 Blk IA
CY08 BLK IA
Flight Tests
Missile Reviews
11
ATP
8
LLM
10
ATP
3
LLM
10
ATP3
Phase I
LLM
10
Phase II
LLM &
ATP
3
LLM
10
ATP
1 1 1
1 1111 11 1 11 1 1 11111 111111
1111222 22222
22222222222221
11
FM-4
6
FM-5
12
FM-6
2
FTM
04-1
5
FTM
04-2
9
FTM
04-3
33
FTM
06-1a/1b
999
FTM
06-2a/2b/2c
32
FTM
06-3a/3b
9
FTM
06-4
4
FTM
08-1
9
FTM
08-2
2
FTM
08-3
8
FTM
08-4
9
JCTV-1
2
JFM-1
3
BlkI
IPR
5
BlkI
CDR
9
BlkI
Mfg
IPR
9
BlkIA
Mfg
IPR
10
BlkIA
CDR &
SDACS
3
Blk
I/IA
IPR
8
BlkIA
Delta
SRR
9
BlkIA
Delta
CDR
SM-3 Block IA
Prepared by: Lana Becker
Date Prepared: 23 July 2004
Revision: 2.1
Planned for PR05
SM-3 Block I
Unclassified
Qty -12
Qty -20
Qty - 27
Qty - 6
Master Schedule
CAM View
Detail Schedules
Earned Management System Deployment
Performance Measurement Baseline Development
The Road to IBR
18
Schedule Baseline Cost Baseline
Technical and Programmatic Risk
Pre-IBRDRAFT IMS DRAFT PMB
CAM Training
CAP + CAM Note
Book
CAP Baseline CPR Dry Run
Gaps &
REQM
IPM 2010
Selectio
n
EVMS Roll Out
1st Integration 1st Sys Demo
OT&E
Pre-Val Review
RFA
Corrections
PMB of
CLIN0001/05
ANSI-748-B
Criteria
SD DRAFT
Work
Instructions
SD Walk Through
SD Rollout
RFA Fix
CAM Prep
Xfer to
PGM
EVMS Ready
PMB Ready
for IBR
Your Role as a Control Account Manager in the Integrated Baseline Review (IBR)

Mais conteúdo relacionado

Mais procurados

Why agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practiceWhy agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practiceGlen Alleman
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short CourseGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingGlen Alleman
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance ManagementGlen Alleman
 
Calculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsCalculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsGlen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to programGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsGlen Alleman
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Scheduleellefsonj
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentGlen Alleman
 
Credible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsCredible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsGlen Alleman
 
Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)Glen Alleman
 

Mais procurados (20)

Why agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practiceWhy agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practice
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
Calculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsCalculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile Projects
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to program
 
WBS is Paramount
WBS is ParamountWBS is Paramount
WBS is Paramount
 
Dashboard reporting
Dashboard reporting Dashboard reporting
Dashboard reporting
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile Projects
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Credible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsCredible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control Systems
 
Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)
 

Semelhante a Your Role as a Control Account Manager in the Integrated Baseline Review (IBR)

FY2016 F-35 SAR
FY2016 F-35 SARFY2016 F-35 SAR
FY2016 F-35 SARDragon029
 
Executive Transport Detatchment Sigonella
Executive Transport Detatchment SigonellaExecutive Transport Detatchment Sigonella
Executive Transport Detatchment Sigonellakingstonmj
 
Example-Business Project Sponsor Meeting
Example-Business Project Sponsor MeetingExample-Business Project Sponsor Meeting
Example-Business Project Sponsor MeetingPeter Zhou
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountGlen Alleman
 
Phase II CoA_SIT_AU and PNG.pptx
Phase II CoA_SIT_AU and PNG.pptxPhase II CoA_SIT_AU and PNG.pptx
Phase II CoA_SIT_AU and PNG.pptxssuser23cbfc
 
EGYPT PBN Implementation Status
EGYPT PBN Implementation StatusEGYPT PBN Implementation Status
EGYPT PBN Implementation StatusKhaled Eltanany
 
Discovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet DivisionDiscovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet DivisionIrina Dzhambazova
 
Petronas procedures and guidelines for planning and budgeting
Petronas procedures and guidelines for planning and budgetingPetronas procedures and guidelines for planning and budgeting
Petronas procedures and guidelines for planning and budgetingEaswaran Kanason
 
2014_ATIP_Final.pdf
2014_ATIP_Final.pdf2014_ATIP_Final.pdf
2014_ATIP_Final.pdf健 李
 
Leading 20 Airborne ISR Companies 2014
Leading 20 Airborne ISR Companies 2014Leading 20 Airborne ISR Companies 2014
Leading 20 Airborne ISR Companies 2014Visiongain
 
Aerospace & Defence Telemetry Market 2017-2027
Aerospace & Defence Telemetry Market 2017-2027Aerospace & Defence Telemetry Market 2017-2027
Aerospace & Defence Telemetry Market 2017-2027Visiongain
 
由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差Alex Yin
 
PROCUREMENT: Expediting How To - General
PROCUREMENT: Expediting How To - GeneralPROCUREMENT: Expediting How To - General
PROCUREMENT: Expediting How To - GeneralSierra Romeo
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance ProgressGlen Alleman
 
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...Peter Stinson
 
Work Project 1-latest
Work Project 1-latestWork Project 1-latest
Work Project 1-latestRanjit David
 

Semelhante a Your Role as a Control Account Manager in the Integrated Baseline Review (IBR) (20)

FY2016 F-35 SAR
FY2016 F-35 SARFY2016 F-35 SAR
FY2016 F-35 SAR
 
Executive Transport Detatchment Sigonella
Executive Transport Detatchment SigonellaExecutive Transport Detatchment Sigonella
Executive Transport Detatchment Sigonella
 
Example-Business Project Sponsor Meeting
Example-Business Project Sponsor MeetingExample-Business Project Sponsor Meeting
Example-Business Project Sponsor Meeting
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
iaf.pptx
iaf.pptxiaf.pptx
iaf.pptx
 
Phase II CoA_SIT_AU and PNG.pptx
Phase II CoA_SIT_AU and PNG.pptxPhase II CoA_SIT_AU and PNG.pptx
Phase II CoA_SIT_AU and PNG.pptx
 
EGYPT PBN Implementation Status
EGYPT PBN Implementation StatusEGYPT PBN Implementation Status
EGYPT PBN Implementation Status
 
Discovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet DivisionDiscovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet Division
 
Petronas procedures and guidelines for planning and budgeting
Petronas procedures and guidelines for planning and budgetingPetronas procedures and guidelines for planning and budgeting
Petronas procedures and guidelines for planning and budgeting
 
2014_ATIP_Final.pdf
2014_ATIP_Final.pdf2014_ATIP_Final.pdf
2014_ATIP_Final.pdf
 
Leading 20 Airborne ISR Companies 2014
Leading 20 Airborne ISR Companies 2014Leading 20 Airborne ISR Companies 2014
Leading 20 Airborne ISR Companies 2014
 
Aerospace & Defence Telemetry Market 2017-2027
Aerospace & Defence Telemetry Market 2017-2027Aerospace & Defence Telemetry Market 2017-2027
Aerospace & Defence Telemetry Market 2017-2027
 
Cost Forecast Report
Cost Forecast ReportCost Forecast Report
Cost Forecast Report
 
由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差
 
PROCUREMENT: Expediting How To - General
PROCUREMENT: Expediting How To - GeneralPROCUREMENT: Expediting How To - General
PROCUREMENT: Expediting How To - General
 
dfpds.ppt
dfpds.pptdfpds.ppt
dfpds.ppt
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...
 
Work Project 1-latest
Work Project 1-latestWork Project 1-latest
Work Project 1-latest
 
xza
xzaxza
xza
 

Mais de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 

Último

Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdfChristopherTHyatt
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 

Último (20)

Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 

Your Role as a Control Account Manager in the Integrated Baseline Review (IBR)

  • 1. YOUR ROLE AS A CONTROL ACCOUNT MANAGER IN THE INTEGRATED BASELINE REVIEW (IBR) As a CAM you’re the critical success factor in the IBR
  • 2. What’s an Integrated Baseline Review?
  • 3. What’s a Control Account Manager?  The Control Account Manager does what its name says: Manages the Control Account  What is a Control Account?
  • 4. Project CAMs, Is Your Name Here?
  • 5. The Participants in the IBR 5  Develop list of activities and intermediate milestones associated with control accounts.  Define the duration for each work activity.  Specify the labor, material, and subcontract resource assignments for each activity.  Specify risks, uncertainties, and to the extent possible, mitigation strategies.  Assure compliance with subcontracts.  Define framework for the resource-loaded schedules.  Entering activity information required for integration with the earned value reporting.  Performing time analysis and budget/cost calculations.  Work with CAM and PM to analyze schedule and budget to arrive at a credible Performance Measurement Baseline (PMB).  Update the PMB schedule  Update schedule forecast to the Estimate To Complete (ETC) to develop the new Estimate At Completion (EAC).  Collecting and entering schedule progress information into the scheduling program throughout the project lifecycle.  Provide schedule reports to CAMs and senior project management.  Establish project technical requirements and criteria.  Develop project work scope using design and engineering services to create a technical description.  Define WBS, WBS Dictionary, OBS, and RAM for control and reporting.  Work with customer and management to establish programmatic milestones.  Work with CAMs to establish intermediate milestones.  Work with CAMs and functional line management to identify the resources for the project.  Maintaining WBS, WBS Dictionary, OBS, and RAM as controlled documents.  Establish and mediate interfaces between control accounts.  Assure compliance with contract.
  • 7. Being a CAM is about managing the work in the Control Account (CA)  All CA management starts with answering the question “how much money do I have for this work?”
  • 8. When the IBR is complete, what will we know about the program that we don’t know now? How will the Probability of Program Success (PoPS) improve by conducting the IBR? What does DONE look like for the IBR? 6 Exit Criteria for the IBR8 † Stephen Covey, Seven Habits of Highly Effective People
  • 9. 1. Confirm the Work Scope Matches The Schedule9
  • 10. 2. Confirm Schedule Is Credible 10
  • 11. 3. Validate the Allocation Of Funds11
  • 12. 4. Conduct a EVMS Assessment12
  • 13. 5. Establish A Dialogue 13
  • 14. 6. The Final Question 14
  • 15. The mapping of IBR artifacts to the technical and schedule plans, focuses on the end state of the IBR to ensure a collaborative environment is established for program success. ‒ Ivan Bembers, IBR Lead, National Geospatial Intelligence Agency IBR Work Products15
  • 17. The Elements of the PMB Performance Measurement Baseline 2004 2005 2006 4 1 2 3 4 1 2 3 4 1 2 3 4 1 Scheduled Finish Baseline Finish Program Milestones Impact Baseline Impact No Impact Page 1 of 6 8/19/04 by Project Interface Milestones / Risk Items Report Standard Missile 3 Program Finish Baseline Finish Name Deliver To Owner Ahead/ Behind Status Total Slac 3/1/0512/18/03SW - Deliver Build 6.0 SoftwareSW -20 R -5 1/2/041/2/04HW - Deliver RPU & IMU for IDR-1HW 0 Y 784 1/30/041/30/04HW - Deliver RPU & IMU for IDR-2HW 0 Y 764 3/31/043/31/04HW - Deliver RPU & IMU for IDR-3HW 0 G 721 4/28/044/28/04HW - Deliver RPU & IMU for IDR-4HW 0 G 531 5/4/045/4/04HW - Deliver RPU & IMU for IDR-5HW 0 G 529 5/14/045/14/04Initial BLK I IOM Proofing CompleteIT&A0-0h- 0 G 381 5/17/045/17/04IT&A - Deliver EOM-1 and InertIT&A 0 G 523 5/28/045/28/04HW - Deliver RPU & IMU for IDR-SpHW 0 G 664 6/28/046/28/04SW - Conduct ASP In-Process0-0h-SW 0 G 494 8/16/048/16/04Receive Boeing Block I PVR0-0h-SE 0 G 625 8/23/048/23/04Receive Block IA GP for KW CIL fromSW0-0h- 0 G 469 8/23/048/23/04SW - Deliver Build 6.1 SoftwareHWSW 0 G 469 8/31/048/31/04Prop - Deliver TSRM For IDR-5IT&APROP 0 G 488 9/1/049/1/04Receive BLK I IOM-3A GS Kit48023.0-0h- 0 G 29 9/1/049/1/04Receive BLK I IOM-3A AS48023.0-0h- 0 G 28 9/3/049/3/04S2 Build 6.2 Provide Scenario0-0h- 0 G 383 9/7/049/7/04Release IOM-7 to CamdenIT&A 0 G 609 9/13/049/13/04S3 Build 6.2 Provide Scenario0-0h- 0 G 331 9/22/049/22/04F986-7 Available for Production GS144060-0 hrs- 0 G 335 Interface and Risk Items 2003 2004 2005 2006 2007 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Page 1 of 14 8/19/04 Intermediate View SM-3 Program Integrated Master Schedule Out Lev Name row 2Program Milestones 1 2Flight Test Program (CLIN 0001) 2 5Mission Flight Dates 3 5Initial Deployment Rounds - RFI 4 5SW - Complete FM-7 Software Update 5 5SW - Complete FM-8 Software Update 6 5SW - Complete FM-9 Software Update 7 5SW - Complete FM-10 (a) Software Update 8 5SW - Complete FM-11 Software Update 9 4FTR-11 10 6HW - Hardware For FTR-11 11 6Prop - Propulsion For FTR-11 12 6IT&A - Conduct Permit To Ship to WSMR for 13 6IT&A - FTR-11 Ready for RFI for FTR-11 14 4FT-Spare 15 5HW - Hardware For FT-Spare 16 5Prop - Propulsion For FT-Spare 17 3IDR Development 18 4IDR-1 19 BLK I IPR BLK IA Mfg IPR BLK IA CDR Blk IA IPR FM-7 FM-8 FM-9 FM-10(b) FM-10(a) FM-11 FM-12 1 2 3 45 Load Software into FM-7 Load Software into FM-8 Load Software into FM-9 Load Software into FM-10(a) Load Software into FM-11 Hardware For FM-10 (b) Propulsion For FM-10 (b) Permit To Ship For FM-10 (b) RFI For FM-10 (b) Hardware For FT -Spare Propulsion For FT-Spare Intermediate Schedule 2004 2005 A M J J A S O N D J F M Path 1 6d Path 2 19d Path 3 19d Path 4 28d Path 5 28d 8/19/04 FM-7 Critical Paths 1-5 to Milestone FM-7 Softw are Received for FQT FM-7 Update Softw are Test Plans FM-7 Perform Dry Runs FM-7 Conduct TRR FM-7 Perform FQT FM-7 Conduct FQT Data Review FM-7 Complete FQT High Priority Action Items Complete FM-7 Softw are Update IT&A - Retest & Encan for FM-7 IT&A - Conduct Delta Permit to Ship for FM-7 IT&A - Ready for RFI for FM-7 2/9 FM-7 Integration & Test ITD Actuals Aug 03 thru Aug 04 FM-7 Update Test Scenarios FM-7 Update Test Evaluation Scripts Functional Design ITD Actuals Aug 03 thru Aug 04 Support FM-7 Sep 2004 - Dec 2004 Support FM-7 Jan 2005 - Feb 2005 HIL ITD Actuals Aug 03 thru August 04 Complete HIL Block I Upgrades to Support Next Block 1 Flig PerformPre Flight Analysis to Support FM-7 PerformHIL Analysis to Support FM-7 HIL Analysis Data to Support FM-7 MCP SE- Conduct Mission Control Panel (MCP) for FM-7 Critical Path Analysis FY03 FY04 FY05 FY06 FY07 FY08 FY09 2003 2004 2005 2006 2007 2008 2009 Missile Del by CY 5 8 14 20 24 3 CUM 5 13 27 47 71 74 Missile Del by FY 5 6 12 18 24 9 CUM 5 11 23 41 65 74 SM-3 Missile Program Schedule - 06/14/04 AEGIS BMD Buy Missiles Blk I (IDR) & CY05 Blk I CY06 & CY07 Blk IA CY08 BLK IA Deliver Missiles Blk I (IDR) & CY05 Blk I CY06 & CY07 Blk IA CY08 BLK IA Flight Tests Missile Reviews 11 ATP 8 LLM 10 ATP 3 LLM 10 ATP3 Phase I LLM 10 Phase II LLM & ATP 3 LLM 10 ATP 1 1 1 1 1111 11 1 11 1 1 11111 111111 1111222 22222 22222222222221 11 FM-4 6 FM-5 12 FM-6 2 FTM 04-1 5 FTM 04-2 9 FTM 04-3 33 FTM 06-1a/1b 999 FTM 06-2a/2b/2c 32 FTM 06-3a/3b 9 FTM 06-4 4 FTM 08-1 9 FTM 08-2 2 FTM 08-3 8 FTM 08-4 9 JCTV-1 2 JFM-1 3 BlkI IPR 5 BlkI CDR 9 BlkI Mfg IPR 9 BlkIA Mfg IPR 10 BlkIA CDR & SDACS 3 Blk I/IA IPR 8 BlkIA Delta SRR 9 BlkIA Delta CDR SM-3 Block IA Prepared by: Lana Becker Date Prepared: 23 July 2004 Revision: 2.1 Planned for PR05 SM-3 Block I Unclassified Qty -12 Qty -20 Qty - 27 Qty - 6 Master Schedule CAM View Detail Schedules
  • 18. Earned Management System Deployment Performance Measurement Baseline Development The Road to IBR 18 Schedule Baseline Cost Baseline Technical and Programmatic Risk Pre-IBRDRAFT IMS DRAFT PMB CAM Training CAP + CAM Note Book CAP Baseline CPR Dry Run Gaps & REQM IPM 2010 Selectio n EVMS Roll Out 1st Integration 1st Sys Demo OT&E Pre-Val Review RFA Corrections PMB of CLIN0001/05 ANSI-748-B Criteria SD DRAFT Work Instructions SD Walk Through SD Rollout RFA Fix CAM Prep Xfer to PGM EVMS Ready PMB Ready for IBR