SlideShare uma empresa Scribd logo
1 de 1
Baixar para ler offline
Project Breathalyzer
1.

Do you have a current, credible activity network supported by a Work Breakdown Structure?

5.

Do you know your schedule compression percentage?

Have you identified your critical path items?
What explicit provisions have you made for work that isn’t on your WBS?

Has the schedule been modified when major modifications in the software have taken place?

Does the activity network clearly organize, define, and graphically display the work to be accomplished?

Have developers and test personnel received training in the principle domain area, support software and tools?

Does the top–level activity network graphically define the project from start to finish, including all the dependencies?

Have detailed unit–level and interface design specifications been created for maximum parallel developer effort?

Does the lowest–level WBS show work packages the measurable tasks and short duration?

Does the project avoid extreme dependencies on specific individuals?

Does each task on the network have a well-defined deliverable?

Are people working abnormal hours?

Is each work package under budget control, expressed in labor hours, dollars, or other numerical units?
2.

Has the schedule bee constructed bottom up from quantitative estimates, not b y predetermined dates?

Do you know the historical schedule compression percentage on similar projects, and the results of those projects?
Is any part of the schedule compression based on use of new technologies?

Do you have a current, credible schedule and budget?

Has the percentage of software functionality been decreased in proportion to the percentage of schedule compression?

Is the schedule based on a project / activity network supported with a WBS?
Is the schedule based on realistic, historical, quantitative performance estimates?

6.

What is the estimated size of your software deliverables?

Does the schedule provide time for holidays, vacation, sick days, etc?
Does the schedule allow all the necessary quality assurance activities?

Were measurements from the previous projects used as a basis for size estimates?

Does the schedule account for resource overlaps?

Were Source Lines of Code (SLOC) used as a basis for the estimates?

Is the schedule for the three to six months as detailed as possible?

Were Function Points (FP) used as a basis for estimates?

Is the schedule consistently updated at all levels in the Gantt, PERT, and Critical Paths views?

Are the developers who do the estimating experienced in the domain area?

Can you perform to the schedule and budget?
3.

Has the project scope been clearly established?

Are estimates regularly updated to reflect software development realities?

Do you know what software you are responsible for delivering?

7.

Do you know the percentage of external interfaces that are not under your control?

Are the system’s operational requirement clearly specified?

Has each external interface been identified?

Are definitions of what the software must do to support the system operational requirements clearly specified?

Have critical dependencies of each external interface been documented?

Are system interfaces clearly specified and if appropriate prototyped?

Has each external interface Ben ranked based on potential project impact?

Is the selection of the software architecture and design method traceable to system operational characteristics?

Have procedures been established to monitor external interfaces until the risk is eliminated to substantially reduced?

Are descriptions of the system environment and relationships pf software application to the system architecture clearly
specified?

Have agreements with the external interface controlling organizations been reached and documented?
8.

Does your staff have sufficient expertise in the project domain?

Are specific development requirements explicitly defined?

Does the staffing plan include a list of the key expertise areas and estimated number of personnel needed?

Are user requirements agreed to by joint teams of developers and users?

Does most of the project staff have experience with the specific type of system being developed?

Are system requirements traceable through the software design?
4.

Do you know what the user needs, wants, and expects?

Are specific acceptance and delivery requirements explicitly defined?

Does most of the project staff have extensive experience in the software language being used?

Can you list the current top ten project risks?

Are the developers able to proceed without undue request for additional time and cost to help resolve technical problems?

Has a Risk Management role been assigned to the project?

Do the developers understand their project role and are they committed to its success?

Are risks determined through established processes for risk identification, assessment, and mitigation?

Are the developers knowledgeable in domain engineering – the process of choosing the bets model for the project and
using it throughout deign, code, and test?

Is there a database that includes all non–negligible risks in terms of probability, earliest expected visible symptom,
estimated and actual schedule, and cost effects?
Are all project personnel encouraged to become risk identifiers?

Is there a domain area expert assigned to each domain?
9.

Have you identified adequate staff to allocate to the scheduled tasks at the right time?

Is the database of top–ten risks updated regularly?

Do you have sufficient staff to support the tasks identified in the activity network?

Are user requirements reasonably stable?

Is the staffing plan based on historical data of level of effort to staff months on similar projects?

Do you know how the risks are changing over time?

Do you have adequate staffing for the current tasks and all tasks scheduled to occur in the next tow months?
Have alternative staff buildup approaches been planned?
Does the staff buildup rate match the rate at which the project leaders identify unsolved problems?
Is there sufficient range and coverage of skills on the project?

Derived from www.spmn.com

Is there adequate tile allocated for staff vacations, sick leave, training, and education?

Also abstracted in many other sources, thank you Norm Brown

Are staffing plans regularly updated to reflect reality?

Mais conteúdo relacionado

Mais procurados

Sarv Panahi_Resume (1) power plant
Sarv Panahi_Resume (1) power plantSarv Panahi_Resume (1) power plant
Sarv Panahi_Resume (1) power plantsarv Panahi
 
Critical analysis of an integrative contingency model of software project ris...
Critical analysis of an integrative contingency model of software project ris...Critical analysis of an integrative contingency model of software project ris...
Critical analysis of an integrative contingency model of software project ris...AYESHA JAVED
 
Software Startup Engineering: A Systematic Mapping Study
Software Startup Engineering: A Systematic Mapping StudySoftware Startup Engineering: A Systematic Mapping Study
Software Startup Engineering: A Systematic Mapping StudyAnh Nguyen Duc
 
Project Success Assessment
Project Success AssessmentProject Success Assessment
Project Success AssessmentGlen Alleman
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management successGlen Alleman
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project ManagementGlen Alleman
 
The Librarian Lessons Learned
The Librarian Lessons LearnedThe Librarian Lessons Learned
The Librarian Lessons LearnedH4Diadmin
 
Planning in Software Projects
Planning in Software ProjectsPlanning in Software Projects
Planning in Software ProjectsJayakumar PP
 
Enterprise Software Implementation
Enterprise Software ImplementationEnterprise Software Implementation
Enterprise Software Implementationbrh184
 
12 Step Program and 12 Reasons why PRojects Fail
12 Step Program and 12 Reasons why PRojects Fail12 Step Program and 12 Reasons why PRojects Fail
12 Step Program and 12 Reasons why PRojects Failellefsonj
 
Traits of a great software engineer
Traits of a great software engineerTraits of a great software engineer
Traits of a great software engineerBairesDev
 
Distributed Teams Infographic
Distributed Teams InfographicDistributed Teams Infographic
Distributed Teams InfographicBairesDev
 
Managing software projects
Managing software projectsManaging software projects
Managing software projectsnareshmk1
 
Srikanth Yekollu_PMPITIL
Srikanth Yekollu_PMPITILSrikanth Yekollu_PMPITIL
Srikanth Yekollu_PMPITILysrikanth_mca
 
Software engineering process
Software engineering processSoftware engineering process
Software engineering processKanchanPatil34
 

Mais procurados (19)

Sarv Panahi_Resume (1) power plant
Sarv Panahi_Resume (1) power plantSarv Panahi_Resume (1) power plant
Sarv Panahi_Resume (1) power plant
 
Critical analysis of an integrative contingency model of software project ris...
Critical analysis of an integrative contingency model of software project ris...Critical analysis of an integrative contingency model of software project ris...
Critical analysis of an integrative contingency model of software project ris...
 
Software Startup Engineering: A Systematic Mapping Study
Software Startup Engineering: A Systematic Mapping StudySoftware Startup Engineering: A Systematic Mapping Study
Software Startup Engineering: A Systematic Mapping Study
 
Cost estimating
Cost estimatingCost estimating
Cost estimating
 
Project Success Assessment
Project Success AssessmentProject Success Assessment
Project Success Assessment
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management success
 
Why Projects Fail
Why Projects FailWhy Projects Fail
Why Projects Fail
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project Management
 
The Librarian Lessons Learned
The Librarian Lessons LearnedThe Librarian Lessons Learned
The Librarian Lessons Learned
 
Planning in Software Projects
Planning in Software ProjectsPlanning in Software Projects
Planning in Software Projects
 
Enterprise Software Implementation
Enterprise Software ImplementationEnterprise Software Implementation
Enterprise Software Implementation
 
Lec1
Lec1Lec1
Lec1
 
12 Step Program and 12 Reasons why PRojects Fail
12 Step Program and 12 Reasons why PRojects Fail12 Step Program and 12 Reasons why PRojects Fail
12 Step Program and 12 Reasons why PRojects Fail
 
Traits of a great software engineer
Traits of a great software engineerTraits of a great software engineer
Traits of a great software engineer
 
Distributed Teams Infographic
Distributed Teams InfographicDistributed Teams Infographic
Distributed Teams Infographic
 
Logical frameworks
Logical frameworksLogical frameworks
Logical frameworks
 
Managing software projects
Managing software projectsManaging software projects
Managing software projects
 
Srikanth Yekollu_PMPITIL
Srikanth Yekollu_PMPITILSrikanth Yekollu_PMPITIL
Srikanth Yekollu_PMPITIL
 
Software engineering process
Software engineering processSoftware engineering process
Software engineering process
 

Destaque

Bab 1 Internet dan Intranet
Bab 1 Internet dan IntranetBab 1 Internet dan Intranet
Bab 1 Internet dan Intranetdio ratar
 
work breakdown structure
work breakdown structurework breakdown structure
work breakdown structureStefan Csosz
 
203wbs Network Gantt Chart
203wbs Network Gantt Chart203wbs Network Gantt Chart
203wbs Network Gantt Chartbtecexpert
 
Slaid bab 1.3 Keselamatan Komputer
Slaid bab 1.3 Keselamatan KomputerSlaid bab 1.3 Keselamatan Komputer
Slaid bab 1.3 Keselamatan Komputerrazak12345
 
WBS presentation
WBS presentationWBS presentation
WBS presentationjpstewar
 
Network proposal ppt
Network proposal pptNetwork proposal ppt
Network proposal pptFrankNitty II
 
Network Security
Network SecurityNetwork Security
Network SecurityMAJU
 
Work breakdown structure by muhammad talha
Work breakdown structure by muhammad talhaWork breakdown structure by muhammad talha
Work breakdown structure by muhammad talhaMuhammad Talha
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Network Security Threats and Solutions
Network Security Threats and SolutionsNetwork Security Threats and Solutions
Network Security Threats and SolutionsColin058
 

Destaque (14)

Course content
Course contentCourse content
Course content
 
Bab 1 Internet dan Intranet
Bab 1 Internet dan IntranetBab 1 Internet dan Intranet
Bab 1 Internet dan Intranet
 
work breakdown structure
work breakdown structurework breakdown structure
work breakdown structure
 
203wbs Network Gantt Chart
203wbs Network Gantt Chart203wbs Network Gantt Chart
203wbs Network Gantt Chart
 
Slaid bab 1.3 Keselamatan Komputer
Slaid bab 1.3 Keselamatan KomputerSlaid bab 1.3 Keselamatan Komputer
Slaid bab 1.3 Keselamatan Komputer
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
WBS presentation
WBS presentationWBS presentation
WBS presentation
 
Network proposal ppt
Network proposal pptNetwork proposal ppt
Network proposal ppt
 
Network Security
Network SecurityNetwork Security
Network Security
 
Network security
Network securityNetwork security
Network security
 
Work breakdown structure by muhammad talha
Work breakdown structure by muhammad talhaWork breakdown structure by muhammad talha
Work breakdown structure by muhammad talha
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Network Security Threats and Solutions
Network Security Threats and SolutionsNetwork Security Threats and Solutions
Network Security Threats and Solutions
 

Semelhante a Project breathalyzer

Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzerGlen Alleman
 
Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzerGlen Alleman
 
Project success assessment
Project success assessmentProject success assessment
Project success assessmentGlen Alleman
 
Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2Intel IoT
 
Software engineering interview questions
Software engineering interview questionsSoftware engineering interview questions
Software engineering interview questionsMuhammadTalha436
 
Common Rubric Criteria for ITSD 322Expectations Student work .docx
Common Rubric Criteria for ITSD 322Expectations Student work .docxCommon Rubric Criteria for ITSD 322Expectations Student work .docx
Common Rubric Criteria for ITSD 322Expectations Student work .docxmccormicknadine86
 
Software Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptxSoftware Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptxNikilesh8
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software EngineeringFáber D. Giraldo
 
Ingo Schobert - Manager - IT Innovation and Quality
Ingo Schobert - Manager - IT Innovation and QualityIngo Schobert - Manager - IT Innovation and Quality
Ingo Schobert - Manager - IT Innovation and QualityIngo_Schobert
 
How to Estimate Software Development Project Cost.pdf
How to Estimate Software Development Project Cost.pdfHow to Estimate Software Development Project Cost.pdf
How to Estimate Software Development Project Cost.pdfVrinsoft Technology
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPlunkettz
 
Software metric analysis methods for product development maintenance projects
Software metric analysis methods for product development  maintenance projectsSoftware metric analysis methods for product development  maintenance projects
Software metric analysis methods for product development maintenance projectsIAEME Publication
 

Semelhante a Project breathalyzer (20)

Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzer
 
Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzer
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project success assessment
Project success assessmentProject success assessment
Project success assessment
 
Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2Wind river webinar deck v1 as of april 23 2014 dw2
Wind river webinar deck v1 as of april 23 2014 dw2
 
Software engineering interview questions
Software engineering interview questionsSoftware engineering interview questions
Software engineering interview questions
 
Common Rubric Criteria for ITSD 322Expectations Student work .docx
Common Rubric Criteria for ITSD 322Expectations Student work .docxCommon Rubric Criteria for ITSD 322Expectations Student work .docx
Common Rubric Criteria for ITSD 322Expectations Student work .docx
 
Software developer
Software developerSoftware developer
Software developer
 
Lecture 1 SE.pptx
Lecture 1 SE.pptxLecture 1 SE.pptx
Lecture 1 SE.pptx
 
Software Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptxSoftware Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptx
 
Primavara
PrimavaraPrimavara
Primavara
 
Meha_Ghadge
Meha_GhadgeMeha_Ghadge
Meha_Ghadge
 
Computing Project
Computing Project Computing Project
Computing Project
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
Ingo Schobert - Manager - IT Innovation and Quality
Ingo Schobert - Manager - IT Innovation and QualityIngo Schobert - Manager - IT Innovation and Quality
Ingo Schobert - Manager - IT Innovation and Quality
 
Vivek_MK
Vivek_MKVivek_MK
Vivek_MK
 
How to Estimate Software Development Project Cost.pdf
How to Estimate Software Development Project Cost.pdfHow to Estimate Software Development Project Cost.pdf
How to Estimate Software Development Project Cost.pdf
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutlet
 
Software metric analysis methods for product development maintenance projects
Software metric analysis methods for product development  maintenance projectsSoftware metric analysis methods for product development  maintenance projects
Software metric analysis methods for product development maintenance projects
 

Mais de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Último

AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Zilliz
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Angeliki Cooney
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...Zilliz
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusZilliz
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityWSO2
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...apidays
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Victor Rentea
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 

Último (20)

AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 

Project breathalyzer

  • 1. Project Breathalyzer 1. Do you have a current, credible activity network supported by a Work Breakdown Structure? 5. Do you know your schedule compression percentage? Have you identified your critical path items? What explicit provisions have you made for work that isn’t on your WBS? Has the schedule been modified when major modifications in the software have taken place? Does the activity network clearly organize, define, and graphically display the work to be accomplished? Have developers and test personnel received training in the principle domain area, support software and tools? Does the top–level activity network graphically define the project from start to finish, including all the dependencies? Have detailed unit–level and interface design specifications been created for maximum parallel developer effort? Does the lowest–level WBS show work packages the measurable tasks and short duration? Does the project avoid extreme dependencies on specific individuals? Does each task on the network have a well-defined deliverable? Are people working abnormal hours? Is each work package under budget control, expressed in labor hours, dollars, or other numerical units? 2. Has the schedule bee constructed bottom up from quantitative estimates, not b y predetermined dates? Do you know the historical schedule compression percentage on similar projects, and the results of those projects? Is any part of the schedule compression based on use of new technologies? Do you have a current, credible schedule and budget? Has the percentage of software functionality been decreased in proportion to the percentage of schedule compression? Is the schedule based on a project / activity network supported with a WBS? Is the schedule based on realistic, historical, quantitative performance estimates? 6. What is the estimated size of your software deliverables? Does the schedule provide time for holidays, vacation, sick days, etc? Does the schedule allow all the necessary quality assurance activities? Were measurements from the previous projects used as a basis for size estimates? Does the schedule account for resource overlaps? Were Source Lines of Code (SLOC) used as a basis for the estimates? Is the schedule for the three to six months as detailed as possible? Were Function Points (FP) used as a basis for estimates? Is the schedule consistently updated at all levels in the Gantt, PERT, and Critical Paths views? Are the developers who do the estimating experienced in the domain area? Can you perform to the schedule and budget? 3. Has the project scope been clearly established? Are estimates regularly updated to reflect software development realities? Do you know what software you are responsible for delivering? 7. Do you know the percentage of external interfaces that are not under your control? Are the system’s operational requirement clearly specified? Has each external interface been identified? Are definitions of what the software must do to support the system operational requirements clearly specified? Have critical dependencies of each external interface been documented? Are system interfaces clearly specified and if appropriate prototyped? Has each external interface Ben ranked based on potential project impact? Is the selection of the software architecture and design method traceable to system operational characteristics? Have procedures been established to monitor external interfaces until the risk is eliminated to substantially reduced? Are descriptions of the system environment and relationships pf software application to the system architecture clearly specified? Have agreements with the external interface controlling organizations been reached and documented? 8. Does your staff have sufficient expertise in the project domain? Are specific development requirements explicitly defined? Does the staffing plan include a list of the key expertise areas and estimated number of personnel needed? Are user requirements agreed to by joint teams of developers and users? Does most of the project staff have experience with the specific type of system being developed? Are system requirements traceable through the software design? 4. Do you know what the user needs, wants, and expects? Are specific acceptance and delivery requirements explicitly defined? Does most of the project staff have extensive experience in the software language being used? Can you list the current top ten project risks? Are the developers able to proceed without undue request for additional time and cost to help resolve technical problems? Has a Risk Management role been assigned to the project? Do the developers understand their project role and are they committed to its success? Are risks determined through established processes for risk identification, assessment, and mitigation? Are the developers knowledgeable in domain engineering – the process of choosing the bets model for the project and using it throughout deign, code, and test? Is there a database that includes all non–negligible risks in terms of probability, earliest expected visible symptom, estimated and actual schedule, and cost effects? Are all project personnel encouraged to become risk identifiers? Is there a domain area expert assigned to each domain? 9. Have you identified adequate staff to allocate to the scheduled tasks at the right time? Is the database of top–ten risks updated regularly? Do you have sufficient staff to support the tasks identified in the activity network? Are user requirements reasonably stable? Is the staffing plan based on historical data of level of effort to staff months on similar projects? Do you know how the risks are changing over time? Do you have adequate staffing for the current tasks and all tasks scheduled to occur in the next tow months? Have alternative staff buildup approaches been planned? Does the staff buildup rate match the rate at which the project leaders identify unsolved problems? Is there sufficient range and coverage of skills on the project? Derived from www.spmn.com Is there adequate tile allocated for staff vacations, sick leave, training, and education? Also abstracted in many other sources, thank you Norm Brown Are staffing plans regularly updated to reflect reality?