SlideShare uma empresa Scribd logo
1 de 67
Baixar para ler offline
There are many approaches to managing projects in every domain.
This seminar lays the foundations for increasing the probability of project success, no matter the
domain, what technology, what approach to delivering the outcomes of the project.
The principles of this approach are immutable.
The practices for implementing the principles are universally applicable.
Each chart in this presentation, contains guidance that can be applied to your project, no matter the
domain.
In our short hour here, we’re going to cover a lot of material.
The bibliography contains the supporting materials we can tailor to your individual project
Increasing Probability of Project Success
PGCS 2020 0:20
1/70
We only have 50 minutes to go through this webinar so it will be fast and furious as the movie says.
But what I want to leave you with are the principles which you can then turn into the practices and
processes suitable for your projects
2
11/11/20
Glen B. Alleman
PGCS 2020
Let’s look at a universal source of problems on all projects no matter the domain that technology or
the business content.
The root cause of project overspending and overrunning the schedule is because the projects are
complex when we think that they’re just complicated.
Managing in the presence of this complexity requires special processes and practices based on the
five immutable principles needed to increase the Probability of Project Success.
3
11/11/20
Glen B. Alleman
PGCS 2020
In our project management domain, like many others, there is always advice from the Greeks that is
applicable to our problems of today.
PGCS 2020
Increasing Probability of Project Success 4/70
To increase the Probability of Project Success start with risk management.
Risk management is based on Root Cause Analysis.
Find the root cause of uncertainties that create risk first, then probability of project success can
increase.
From research, here are four key factors that reduce the probability of project success.
Increasing Probability of Project Success
PGCS 2020
5/70
The five immutable principles of project success are:
1. Know where we are going by defining “done” at some point in the future.
2. Have some kind of plan to get to where we are going.. The fidelity of the plan depends on the
tolerance for risk by the users of the plan.
3. Understand what resources are needed to execute the plan. How much time and money is
needed to reach the destination.
4. Identify the impediments to progress along the way to Done. Have some means of correcting,
preventing, removing, avoiding, or ignoring these impediments.
5. Have some way to measure planned progress, not just current progress, measured in units of
physical percent complete meaningful to the decision makers.
6/70
PGCS 2020
The path to showing up on time, on budget, with the needed capabilities, with the planned a set of
tangible goals, starts by defining the unit of measure to assess if the actual work is following the
planned path.
To do this we need units of measure that are meaningful that represent the actual performance of
the work, with precision and accuracy within the limits of the assessment process.
The primary measures needed for this process are: Effectiveness and Performance.
Increasing Probability of Project Success
PGCS 2020
7/70
Here are 5 Practices used to implement the 5 Principles
1. Identify Needed Capabilities that achieve the project objectives or the particular end state.
Define these capabilities through scenarios from the customer point of view in units of Measures
of Effectiveness (MoE) meaningful to the customer.
2. Define The Technical And Operational Requirements to be fulfilled for the system capabilities to
be available to the customer. Define these requirements in terms isolated from any
implementation of the products. Only then bind the requirements with technology.
3. Build The Performance Measurement Baseline – describing the work to be performed, the
budgeted cost for this work, the organizational elements that produce the outcomes from this
work, and Measures of Performance (MoP) showing the work is proceeding according to cost,
schedule, and technical plan.
4. Execute the PMB’s Work Packages ‒ in the planned order, assuring Performance assessments
are 0%/100% complete before proceeding. No rework, no transfer of activities to the future.
Assure every requirement is traceable to work and all work is traceable to requirements.
5. Apply Continuous Risk Management for each Performance Based Management process to
Identify, Analyze, Plan, Track, Control, and Communicate projectmatic and technical risk.
Increasing Probability of Project Success
PGCS 2020
8/70
Here are the principles and practices, connected to increase the probability of project success.
Practices without principles provide the opportunity to modify the approach without understanding
why.
Principles without practices are interesting discussions without measurable business benefits.
We must start with the principles, then move to the practices.
Without principles, there is no way to test practices to confirm they are on solid footing when they
need to be adapted to the situation.
With these connections, we’ll have the basis of a handbook to increase the probability of success, in
any domain, for any technology.
PGCS 2020
9/70
Increasing Probability of Project Success
Here’s a map of the 23 steps we’ll use to connect Principles and Practices in the coming charts.
Each connection is presented in the section with the numbers 1 through 23.
PGCS 2020
10/70
Increasing Probability of Project Success
Connecting principles with practices is a critical success factor for any approach to increasing the
probability of project success.
Practices without principles provide the opportunity to modify the approach without understanding
why.
Principles without practices are interesting discussions without measurable business benefits.
Both are needed, both must be present for success.
But we must start with the principles, then move to the practices.
Without principles, there is no way to test practices to confirm they are on solid footing when they
need to be adapted to the situation.
Increasing Probability of Project Success
PGCS 2020
11/70
The Practice of Identifying the needed Capabilities is guided by 5 principles.
Where are we going ‒ is answered by Concept of Operations that states, for the users point of view,
what the system is doing when it is working.
How are we going to get there and what do we need along the way ‒ is answered by an Integrated
Master Plan defining the assessment of the increasing maturity of the Capabilities.
What Impediments Will We Encounter Along The Way ‒ is answered by the Risk Register developed
from each Capability defining the handling strategies to correct or prevent the risk from occurring.
How Do We Measure Progress ‒ is answered by assessing physical percent complete assessment of
the Measures of Effectiveness of the Capabilities to fulfill the mission or business strategy.
PGCS 2020
12/70
Increasing Probability of Project Success
Capabilities drive requirements, but rarely do requirements by themselves have value
The stakeholders want a capability to accomplish a mission or fulfill a strategy.
Capabilities are what we would do with the resulting system.
The stakeholder puts the Capabilities to accomplish some goal.
If we don’t know want capabilities we need to produce from the project, we really can’t talk about
the project value, and we really can’t speak about what DONE looks like in a meaningful way other
than the passage of time and consumption of money.
PGCS 2020
13/70
Increasing Probability of Project Success
The purpose of the CONOPS is to describe the operational needs, desires, visions, and expectations
of the user without being overly technical or formal.
A Concept of Operations (CONOPS) is a user-oriented document that "describes systems
characteristics for a proposed system from a user's perspective.
A CONOPS also describes the user organization, mission, and objectives from an integrated systems
point of view and is used to communicate overall quantitative and qualitative system characteristics
to stakeholders
A CONOPS "describes the proposed system in terms of the user needs it will fulfill, its relationship to
existing systems or procedures, and the ways it will be used.
CONOPS can be tailored for many purposes, for example, to obtain consensus among the acquirer,
developers, supporters, and user organization on the operational concept of a proposed system.
A CONOPS may focus on communicating the user's needs to the developer or the developer's ideas
to the user and other interested parties.
Increasing Probability of Project Success
PGCS 2020
14/70
The Integrated Master Plan (IMP) is a representation of the increasing maturity of the projects
deliverables through a series of Events that assess that maturity.
The IMP is an event-driven plan that documents the significant accomplishments necessary to
complete the work and ties each accomplishment to a key project event.
It defines how the project is organized, structured, and conducted and how the total process will be
controlled to provide a product that satisfies stakeholder requirements.
Increasing Probability of Project Success
PGCS 2020
15/70
The structure of the Integrated Master Plan (IMP) and Integrated Master Schedule (IMS)
provides a framework for assessing the increasing maturity of the project’s outcomes in units
of measure meaningful to the decision makers.
Together, the IMP and IMS demonstrate the project is adequately structured, realistic, and
executable and the planned tasks are achievable within schedule and cost constraints at an
acceptable level of risk.
The IMP and IMS are business tools to manage and provide oversight of projects.
In this picture Work Packages contain Tasks that consume resources (labor and materials)
and are the basis of the Integrated Master Schedule.
Each Work Package produces a tangible outcome defined through an Exit Criteria stated in
a measurable unit meaningful to the decision makers.
These Criteria are entry conditions to the Accomplishments needed t to move forward as
planned.
The Accomplishments define the Entry Criteria for the Events that assess the increasing
maturity of the project as a whole.
Increasing Probability of Project Success
PGCS 2020
16/70
All projects are complex.
The two separate complexities on projects are the tasks themselves and the relationships between
those tasks.
Each of these complexities creates risk and risk must be dealt with in the project plan.
The handling of these complexities have to be part of the project plan itself and without this
handling strategy the probability of success of the project is greatly reduced.
A quote that should be remember here is
Risk Management is How Adults Manage Projects ‒ Tim Lister
Increasing Probability of Project Success
PGCS 2020
17/70
Measures of Effectiveness are the primary assessments of a project’s progress to plan and the
ultimate success of the deliverables from that work effort.
The definition of Measures of Effectiveness belongs to the stakeholders or those paying for the work.
This is the effectiveness of the project’s outcomes to accomplish the mission or fulfill a business
goal.
Defining and managing the measures of effectiveness is the critical success factor for all projects.
Research shows missing or poorly defined measures of effectiveness are the root cause of project
failure.
Increasing Probability of Project Success
PGCS 2020
18/70
With the capabilities identified, we now need the technical and operational requirements that will
implement these capabilities.
With the requirements we can start to plan the project implementation activities to deliver those
requirements for the needed cost at needed time.
A failure mode for many projects is to start with requirements skipping the capabilities phase.
Increasing Probability of Project Success
PGCS 2020
19/70
The connection between Principles and Practices for the Requirements Baseline include:
Where are we going ‒ for each Capability, a technical or operational plan defines the facilities to
implement the Capability.
How are we going to get there What do we need along the way ‒ the Work Breakdown Structure
defines the deliverables and the processes needed to produce these deliverables. These individual
elements are rolled up to higher level deliverables, until we reach to top level of the project
deliverable.
What do we need along the way ‒ the resources, staff, equipment, facilities, and processes are
defined in a Resource Management Plan connected to the WBS. These resources are budgeted in
Work Packages and their Tasks, and summed in Control Accounts
What Impediments Will We Encounter Along The Way ‒ the Risk Register developed from each
Deliverable in the WBS defines the handling strategies to correct or prevent the risk from occurring.
How Do We Measure Progress ‒ physical percent complete assessment of the Technical
Performance Measures of the Capabilities to fulfill the mission or business strategy.
PGCS 2020
20/70
Increasing Probability of Project Success
The first step in identifying requirements that fulfill the needed capabilities is to separate “product”
requirements from “process” requirements.
The product could be a service as well, but the product (or service) is not the same as the process
that delivers the service that may be enabled by the product.
We can see there are several components of this separation.
While this type of taxonomy looks unnecessary, later on we’ll see it can serve to reduce complexity,
focus our efforts on important parts of requirements management, and reduce the overall effort of
managing these requirements.
Increasing Probability of Project Success
PGCS 2020
21/70
Value stream mapping is an approach to defining the needed capabilities for the business.
The value stream defines a sequence of deliverables that have measurable value to the business or
to the fulfillment of a mission.
Each of the deliverables has a measured value that can be assessed against the needed capabilities
of the project’s outcomes.
These outcomes include technical performance, efficacy of risk reduction, on schedule, on cost.
The key here is to have all measures be meaningful to the decision makers.
Increasing Probability of Project Success
PGCS 2020
22/70
The work breakdown structure defines the decomposition of the deliverables from the project.
The WBS is not a breakdown of the work it is a breakdown of the outcomes of the work. The WBS is
the bill of materials for the project.
The WBS collects cost and the parent child relationship between the deliverable items.
A consistent WBS structure across the business or government agency allows comparison of past
cost to future estimated costs by WBS Number.
The WBS is one of the pieces of glue connecting all the work across the project.
Increasing Probability of Project Success
PGCS 2020
23/70
Resources are needed to deliver outcomes for all projects.
These resources are typically the staffing that does the work, but it also includes, material,
equipment, and external services.
Having a plan by resource category is needed to define the cost basis for the project.
This resource plan is used as the basis for the integrated master schedule to sequence these
resources to make sure they are available when needed.
Increasing Probability of Project Success
PGCS 2020
24/70
It cannot be stated enough, risk management is the basis of project success.
Each element in the WBS needs some type of risk assessment.
This information is held in the risk register for analysis and handling plans.
The connection between the Risk Register and the WBS is a critical success factor for the project.
Increasing Probability of Project Success
PGCS 2020
25/70
Here’s an example of a risk register with its analysis connected to the WBS and the Integrated
Master Schedule.
Each element in the risk register has a probability of occurrence or some statistical assessment of its
variability and the impact on the outcome of the risk were to come true.
A critical success factor is to have the pre-mitigation and the post mitigation risk analysis in one
place to confirm to the project management staff that risks are actually being bought down.
This approach provides information about risks that cannot be reduced to zero so the project can
provide margin, management reserve, or cost contingency to cover that situation.
Increasing Probability of Project Success
PGCS 2020
26/70
Measures of Performance describe the physical and functional attributes of the deliverable.
How fast, how slow, how big, how small, how reliable, how maintainable are all of the physical
measurements of the outcomes are part of measures of performance.
With this assessment it can be determined how much margin or contingency is needed if the item
does not meet the performance requirements.
The Measures of Performance are directly connected to the Capabilities produced by the project.
Increasing Probability of Project Success
PGCS 2020
27/70
The Performance Measurement Baseline (PMB) is an important tool in the assessment of project
performance used by project Managers and Systems Engineers in the Technical Assessment Process
to appraise a project technical progress to plan.
It includes the undistributed budget, all summary level planning package budgets, and all control
account budgets but does not include management reserve.
It establishes the contract level timed phased baseline against which contract level performance
metrics are computed.
It establishes the scope, schedule, and budget targets for the project.
The PMB is usually a contractual document whose changes must go through the change control
process.
This is done during the planning process, and records what the project had planned, scheduled,
budgeted for, in terms of the schedule, scope and cost.
It should contain everything that the customer needs, as per the agreed scope.
The Cost, Schedule, and Scope baselines put together are called the Performance Measurement
Baseline.
Increasing Probability of Project Success
PGCS 2020
28/70
The connection between Principles and Practices for the Performance Measurement Baseline
include. The practices of establishing the PMB are guided by the principles of:
Where are we going ‒ the MOE’s and MOP’s define the incremental maturity of the deliverables
assessed against the planned maturity.
How are we going to get there and what do we need along the way ‒ a resource loaded Integrated
Master Schedule described the tasks and Work Packages needed to produce the deliverables from
the project.
What Impediments Will We Encounter Along The Way ‒ the Risk Register developed from each
deliverable in the in the WBS defines the handling strategies to correct or prevent the risk from
occurring.
How Do We Measure Progress ‒ physical percent complete assessment of the Technical
Performance Measures inform the progress to plan.
PGCS 2020
29/70
Increasing Probability of Project Success
Eisenhower said “In preparing for battle I have always found that plans are useless, but planning is
indispensable.”
The Performance Measurement Baseline contains cost, schedule, and technical performance goals.
These are the basis of not only measuring progress to plan, but defining what Done looks like and
how we’re going to get to Done as needed.
PGCS 2020
Increasing Probability of Project Success 30/70
Establishing the Performance Measurement Baseline is the process of integrating the scope,
schedule, and cost baselines into a single project baseline from which to manage and
control project performance throughout execution.
The Performance Measurement Baseline of the project is actually three baselines:
1. The technical baseline assures that all the deliverables are identified. Even if the details
are not known, the needed capabilities must be defined in some meaningful manner.
Otherwise the project will have no way to control the scope.
2. The schedule baseline says when the needed capabilities will be available, and
3. The cost baseline says how much each of these capabilities is planned to cost.
In addition to the scope, cost, and schedule elements, the performance measurement
baseline (PMB) also incorporates undistributed budget (UB) (along with its corresponding
work) and contingency reserves (alongside with the corresponding risks).
PGCS 2020
31/70
Increasing Probability of Project Success
As the project progresses we need to incrementally assess the maturity of the project deliverables.
This incremental method is a critical success factor to avoid the big bang outcome of the project.
The big bang happens when we wait till the end to find out that what we’re delivering is not what
the stakeholders expect us to do.
Increment and iterative processes are critical success factors for all projects no matter the domain
technology or methods used to develop outcomes.
This incremental and iterative approach to project management is not just for agile software
projects it is applicable to all projects.
The Big Bang produces a smoking hole where the project was, with all the money gone.
Increasing Probability of Project Success
PGCS 2020
32/70
An Integrated Master Schedule (IMS) is a network of tasks linked from project start through project
finish, reflecting the interdependencies between tasks and milestones.
It begins with the Integrated Master Plan (IMP), which details the contractual deliverables developed
from the Statement of Work/Objectives (SOW/SOO).
The Integrated Master Schedule (IMS) is a time-based schedule containing the networked, detailed
tasks necessary to ensure successful project execution.
The IMS is used to verify attainability of the project objectives, to evaluate progress toward meeting
project objectives, and to integrate the project schedule activities with all related components.
The IMS utilizes Critical Path network management techniques to optimize the relationship of critical
activities.
The IMS is a hierarchical, tiered structure capable of rolling up to a high-level summary
representations of activities as well as breaking down to the lowest level of task details showing
dependencies, resources, durations, and constraints.
Increasing Probability of Project Success
PGCS 2020
33/70
Risk is always present on projects no matter the domain, technology, or business environment.
To have a credible project with a credible project plan that will increase the probability of project success we
must manage in the presence of uncertainty that creates risk.
Developing a risk adjusted cost and schedule starts with making a single point estimate of cost or duration of
the work.
This estimate is the most likely value that will occur in the presence of uncertainty.
With the most likely value we can then estimate the higher or lower value.
With this information we can then develop a model of the expected cost and expected duration of the work
defined in the schedule.
Monte Carlo simulation is a method to develop this confidence estimate. This approach has four steps:
§ Identify risks and uncertainties related to task durations, their start and finish time, cost and resources.
§ Perform monte carlo simulation.
§ Analyze risk-adjusted project schedule.
§ Perform probabilistic cost and work analysis of project schedules.
The discussion of Monte Carlo simulation is beyond the scope of this presentation, but detailed resources will
be provided in the bibliography.
Increasing Probability of Project Success
PGCS 2020
34/70
Here is an example of a project schedule and the most likely values of the optimistic values and the
pessimistic values of the duration of tasks.
With this information a Monte Carlo simulation of the most likely value for the completion date can
be developed.
In the example here, the final testing plan completion date is planned for February, 10, 2003.
In the next chart will see the Monte Carlo simulation showing the confidence of completing on or
before that date.
Increasing Probability of Project Success
PGCS 2020
35/70
With the Monte Carlo tool we can see the confidence of completing on or before a specific date.
Using the integrated master schedule from the previous chart and the high and low ranges of
duration for each task, the Monte Carlo tool shows the confidence of completing on or before the
needed date of Feb 10, 2003.
In this case the probability is low 40%.
A higher probability is shown in the chart in the lower right-hand corner.
We have an 80% confidence of completing on or before February 18, 2003.
This approach to schedule risk analysis is mandated in many domains including the United States
government domains.
Increasing Probability of Project Success
PGCS 2020
36/70
Another critical success factor for increasing the probability of project success is the integration of
risk buy down into the integrated master schedule.
This describes how we need to plan to reduce risk as the project proceeds.
We can then assess the actual risk reduction against the planned risk reduction to determine if we’re
meeting the risk management plans and goals.
This risk buydown planning is considered a Technical Performance Measure.
This chart is produced by the same tool that uses the Monte Carlo simulation to assess the
performance of the schedule.
Increasing Probability of Project Success
PGCS 2020
37/70
Since all projects have uncertainty, both reducible and irreducible, we must have a risk adjusted in a
graded master schedule.
This integrated master schedule in the presence of uncertainty requires a plan A and a Plan B should
the risks from the uncertainty turn into issues.
No schedule without margin can be correct.
Schedules without margin are late on day one.
Increasing Probability of Project Success
PGCS 2020
38/70
Schedule margin is a project management tool for dealing with schedule contingencies.
Schedule margin provides a separately designated "buffer" in the schedule to "protect" the delivery
dates.
There are two approaches to schedule margin.
§ In the first the final task is baselined to finish ten days before an End Of Contract (EOC) milestone
aligned with the contract need date. The calculated difference between the final task completion
and the contract need date is the schedule margin to the contract need date.
§ In the second the EOC milestone is baselined to finish immediately after the final task – which is
still baselined to finish before the contract need date. The calculated difference is defined as the
schedule margin to the contract need date.
The example shows that margin can be placed before the deliverable date or after the deliverable
date.
Increasing Probability of Project Success
PGCS 2020
39/70
It is impossible to estimate precisely how much something will cost or how long it will take.
If we want projects to meet cost and schedule commitments, we must budget and fund them with a
higher probability of success.
A Joint Cost and Schedule Confidence Level (JCL) is a quantitative probability statement about the
ability of a project to meet its cost and schedule targets.
Decision-makers and cost analysts should always think of a cost estimate as a probability
distribution, NOT as a deterministic number.
The best that can be provided to decision-makers is the cost probability distribution.
It is up to the decision-maker to decide at which confidence level they want to set the budget.
The probability distribution provides a quantitative basis for making this determination.
Increasing Probability of Project Success
PGCS 2020
40/70
JCL is a process that combines a project’s cost, schedule, and risk into a complete picture.
If cost, schedule, or both are below a defined confidence level, the management team must make
decisions about risk mitigation measures and/or changing the project scope.
There are six steps to developing a Joint Confidence Level:
1. Identify goals for the JCL.
2. Build a JCL schedule/logic network (a summary analysis schedule).
3. Load cost onto the schedule activities.
4. Incorporate risk list.
5. Conduct uncertainty analysis.
6. Calculate and view results, and iterate as required.
Increasing Probability of Project Success
PGCS 2020
41/70
Here’s a picture of a Joint Confidence Level, where the x-axis represents the final completion date, and the y-
axis represents the final cost through that completion date.
The scatterplot shows the simulated outcomes of the cost and schedule risk analysis.
Each dot in the scatterplot represents a specific result, or scenario, from the simulation calculation of the cost
and schedule.
In this example, the blue lines (the crosshair) intercept at the project’s baseline plan or point estimate (PE).
To the bottom left, the green dots represent all the scenarios that are at or below the baseline cost and
schedule.
The yellow line represents the “frontier curve,” or indifference curve, that specifies all the cost and schedule
combinations that will meet a targeted JCL.
Anything the the left and below the Yellow line is an acceptable cost and schedule for the project.
Anything to the right and above the Yellow line is an unacceptable cost and schedule.
The goal of project management is to keep the cost and schedule below and to the left of the Yellow line,
while maintaining the delivery of the needed capabilities.
This is called Keeping the project Green.
Increasing Probability of Project Success
PGCS 2020
42/70
Technical Performance Measures are an assessment of the measures of performance and the
measures of effectiveness for the deliverables of the projects to meet the technical requirements.
The passage of time and consumption of money are measures of project progress.
But if these measures are not matched against the increasing maturity of the technical performance
measures the project will not deliver the needed value to those paying for those outcomes.
We must always remember the cost, schedule, and technical performance are tightly integrated.
Management of all three of these variables is the role of the project manager.
To increase the probability of project success all three variables must be tightly controlled.
Increasing Probability of Project Success
PGCS 2020
43/70
The technical performance measure has a planned increase in its maturity as the project proceeds.
In this example the TPM is the Mean Time Between Failure of some article produced by the project.
As the project proceeds the MTBF needs to increase.
The current assessment of the meantime between failures is shown in the line achieved to date.
The planned value for the MTBF at this date is different than the actual value.
This variance is inside the lower limit and upper limit of the plan value.
As the project proceeds the MTBF must reach the threshold value for the project to meet the
technical performance measures.
If the actual values were to go outside the upper and lower control limits at any specific time a
collective or preventive action will be needed to put this variance back inside those upper and lower
limits.
Increasing Probability of Project Success
PGCS 2020
44/70
With the performance measurement baseline established, we now need to execute that baseline to
deliver outcomes from the project.
45/70
Increasing Probability of Project Success
PGCS 2020
The connection between Principles and Practices for Executing the PMB include:
Where are we going ‒ measures of Physical Percent Complete are the only measure of progress to
place. Not the passage of time or consumption of money.
How are we going to get there ‒ using incremental delivery, the progress can be measured on fine
grained boundaries.
What do we need along the way ‒ with the measures of progress to plan and risk adjusted
Integrated Master Schedule, future performance can be modeled.
What Impediments Will We Encounter Along The Way ‒ the Risk Register developed from each
Deliverable in the WBS defines the handling strategies to correct or prevent the risk from occurring
and contained in a risk adjusted PMB.
How Do We Measure Progress ‒ physical percent complete assessment of the Technical
Performance Measures of the Capabilities to fulfill the mission or business strategy is used by the
Earned Value Management System to produce and Estimate to Complete and and Estimate at
Completion.
PGCS 2020
Increasing Probability of Project Success 46/70
Physical percent complete is often confused with percent complete in a scheduling tools.
Physical percent complete requires tangible evidence of progress to plan for the technical
performance, cost, and schedule targets.
Here are several ways to calculate physical percent complete.
Never is physical percent complete calculated by the passage of time and consumption of money.
Only the contractual legal term, tangible evidentiary materials, is used to calculate physical percent
complete.
The description of this tangible evidence needs to be defined before the work starts.
This physical evidence needs to be useful to those paying for the work.
For example the number of drawings produced may be interesting to assess the performance of the
engineers, but it does not measure physical percent complete of the design.
Care is needed in defining the units of physical percent complete.
Again the passage of time and consumption of money is not physical percent complete.
Increasing Probability of Project Success
PGCS 2020
47/70
Iterative and Incremental Delivery (IID) are terms often used in software development, but they are
applicable in any project domain.
The basic idea behind this method is to develop a system through repeated cycles (iterations) and in smaller
portions at a time (increments).
IID grew from the 1930s work of Walter Shewhart, a quality expert at Bell Labs who proposed a series of short
“plan-do-study-act” (PDSA) cycles for quality improvement.
The X-15 hypersonic jet in the 1950’s applied IID and the practice as a major contribution to the X-15’s
success.
There are many examples of iterative and incremental development and delivery at NASA in 1960’s starting
with Project Mercury, which ran ½ days iterations that were time boxed.
Some of those Mercury engineers later formed a new division within IBM, where "another early and striking
example of a major IID success [was] the very heart of NASA’s space shuttle software—the primary avionics
software system, which [they] built from 1977 to 1980.
The team applied IID in a series of 17 iterations over 31 months, averaging around eight weeks per iteration.
Their motivation for avoiding the waterfall life cycle was that the shuttle project’s requirements were
changing during the software development process.
Increasing Probability of Project Success
PGCS 2020
48/70
The success of any project is likely to be judged by how well it achieves a defined outcome while
meeting performance expectations.
Most projects would not be undertaken if management had little confidence in a successful
outcome.
Many projects are subject to being cancelled, even late in the project cycle, if the forecasted
outcome does not meet expectations.
These factors drive the need throughout the project for updated forecasts of the project outcome.
Project forecasting is the process of making conjectures about future performance, which can help
managers decide whether to cancel this project, create new projects, or to continue with existing
projects.
Increasing Probability of Project Success
PGCS 2020
49/70
Future Project Performance can be lumped under the project management principle of change management.
If we can’t forecast the outcome of a change, the probability of project success is low.
There are four different, though interrelated, challenges in dealing with change and the ability to forecast the
impact of that change
The first deals with the reality that the project's boundaries change as the project progresses.
Specific selections of equipment, systems, or processes impact the content of the project.
Refining judgments of capabilities leads to increases in scope more frequently than decreases in scope.
Competition for resources, changes in performance intensity, and external factors all put pressure on the
project plan.
A most common change in project forecasting is the increase that occurs when a greater scope of work is
attempted in the same amount of time.
Another factor is the reality that, as the project progresses, it is easy to record the spending of dollars and
difficult to assess what those dollars have bought.
This is why Capabilities Based Planning is a critical success factor for all projects.
Maintaining the connection of requirements to needed capabilities is critical to increasing the probability of
success.
Increasing Probability of Project Success
PGCS 2020
50/70
All projects and projects are plagued by cost and schedule overruns and technical shortfalls.
Sources of these issues are summarized in four notions by Mr. Bliss, Director Performance Assessment and
Root cause Analyses (PARCA), US Department of Defense.
1. Unrealistic performance expectations with missing Measures of Effectiveness (MOE) and Measures of
Performance (MOP).
2. Unrealistic cost and schedule estimates based on inadequate risk adjusted growth models.
3. Inadequate assessment of risk and unmitigated exposure to these risks without proper handling
strategies.
4. Unanticipated technical issues without missing alternative plans and solutions to maintain the
effectiveness and performance of project deliverables.
All project work operates in the presence of uncertainty. Cost uncertainty, schedule uncertainty, technical
uncertainty that creates risk.
Knowledge of project risk provides information needed to make decisions in the presence of uncertainty,
where predicting future outcomes is part of the project management process.
Risk is the consequence of Uncertainty.
Managing in the presence of uncertainty is the role of the project manager, and risk management is the basis
of increasing the Probability of Project Success.
Increasing Probability of Project Success
PGCS 2020
51/70
Earned Value is a fundamental measurement of a project’s performance but far from sufficient for
the project’s success.
Integration of risk, technical performance measures, and systems engineering processes are needed
to increase the probability of project success.
Success starts with a winning proposal, installing the right tools and work processes, establishing a
credible Performance Measurement Baseline, identifying and handling programmatic and technical
risk, and through project execution a variety of technical, operational, and staffing processes are
needed and based on Earned Value Management processes.
Increasing the probability of project success requires the application of 5 simultaneous project
management processes.
These 5 processes are inter-related, dependent, and supportive of each other.
Earned Value is at the heart of each of these 5 processes with the focus on measures needed to
forecast the future, rather than just reporting past performance.
Increasing Probability of Project Success
PGCS 2020
52/70
All projects operate in the presence of uncertainty.
All risk comes from uncertainty.
Uncertainty comes in two forms on projects
Epistemic uncertainty, which comes from lack of knowledge, which is reducible
Aleatory uncertainty, from naturally occurring processes, which is irreducible
Managing in the presence of uncertainty is the critical success factor for increasing the probability of
project success.
Let’s repeat the quote that says it all about risk management and the success of project
management
Risk Management is How Adults Manage Projects ‒ Tim Lister.
The purpose of risk management is to identify potential problems before they occur so that risk-
handling activities may be planned and invoked as needed across the life of the product or project to
mitigate adverse impacts on achieving objectives.
Increasing Probability of Project Success
PGCS 2020
53/70
The connection between Principles and Practices for Continuous Risk Management answers the
questions:
Where are we going? ‒ by identify the uncertainties on the project that create risk. These can be
reducible uncertainties or irreducible uncertainties.
How are we going to get there? ‒ by analyzing these uncertainties to find their root causes and the
properties of these causes.
What do we need along the way? ‒ by developing risk handling strategies to correct or prevent the
root cause from creating the uncertainties that create the risk.
What Impediments Will We Encounter Along The Way? ‒ we need to place the risks, with their
handling strategies in a Risk Register and assess the risk buydown effectiveness on fine grained
boundaries.
How Do We Measure Progress to Plan? ‒ we measure the effectiveness of the risk buy down
activities on the probability of success for cost, schedule, and technical performance measures.
PGCS 2020
Increasing Probability of Project Success 54/70
Continuous Risk Management, when performed successfully, provides 5 key benefits:
§ Identify uncertainties that create risk.
§ Correct or Prevent problems before they occur – by identifying potential risks and deals with
them when it is easier and cheaper to do so – before they are issues.
§ Improve product or service quality – by focusing on the project’s objectives and looking for things
that many effect quality throughout the project lifecycle.
§ Enable better use of resources – by allowing the early identification of potential problems –
proactive management to input into management decisions regarding resource allocation.
§ Promotes teamwork – involving personnel at all levels of the project.
Increasing Probability of Project Success 55/70
PGCS 2020
Risk identification is a process of transforming uncertainties and issues about the project into distinct
(tangible) risks that can be described and measured.
Identifying risks involves two activities:
§ Capturing a statement of risk.
§ Capturing the context of that risk.
The objective of risk identification is to locate risks before they become problems and to incorporate this
information into the project management process.
The data items found in risk identification include:
§ Individual uncertainties and issues about the project and project’s progress.
§ Groups of activities and issues which may risks.
§ Project data supporting information consisting of items such as the schedule, budget, plans, work
breakdown structure, that may provide information helpful in identifying risks.
§ For each risk identified, a statement of the risk with the associated context.
§ A Risk Register containing all this information about the risks identified for the project, their handling
plans, the probability or occurrence or naturally occurring variance, the probability of effectiveness of the
corrective or preventive actions needed to handle the risk
Increasing Probability of Project Success
PGCS 2020
56/70
A well written risk statement can answer the following questions:
§ What is the root cause that creates the risk?
§ Why could it happen? What’s the probability of occurrence for event based risks and what’s the
impact from a naturally occurring risks?
§ If the risk becomes an issue, What is the impact on the project?
The risk statement provides clear and descriptive information required for a reasoned and defensible
assessment of the risk's probability or occurrence or natural variability and areas of impact.
A well-written risk statement contains two components. They are a statement of the Condition
Present and the Associated Risk Event.
In a risk statement, the Condition Present is itself an event: it is an event that has occurred or is
presently occurring.
Associated Risk Events are future events that might occur because of the Condition Present.
The Condition Present acts as the departure point from which one or more Associated Risk Events
may originate.
Increasing Probability of Project Success
PGCS 2020
57/70
The main objective of Risk Analysis and assessments of the uncertainties that create risk, is the basis of
informed decision-making needed to increase the probability of project success.
Risk analysis is the process of systematically evaluating each identified, approved risk to estimate the
probability of occurrence (likelihood) and consequence of occurrence (impact), and then converting the
results to a corresponding risk level or rating.
Traditional Risk Analysis starts with evaluating and prioritizing risk, assessing the probability of risk occurrence
and probability of impact of the risk on project success, and placing this information in a Risk Register.
With this information. decisions can be made about to respond to risk should it become an issue.
This approach starts with qualitative analysis but fails to recognize there are still phenomena not taken into
account by classical project risk management.
These include propagation of simple risk, loops in this propagation model, reaction chains and non-linear
couplings of interrelationships between risks creating other risks, propagation of risks between
interrelationships creating further risk, analysis of alternatives and their risk assessment, the premortem
analysis needed to remove the uncertainties, and the dynamic evolving connections between cost, schedule,
and technical performance.
Quantitative risk analysis determines the root cause(s) of the uncertainties, but reducible and irreducible, that
create risk.
Risk Handling strategies are then created to correct or prevent the occurrence of the risk, used to the
Probability of Project Success (PoPS).
Increasing Probability of Project Success
PGCS 2020
58/70
Risk Handling Plans are similar to any other type of project planning or problem‒solving activity.
Planning of the Risk Handling Strategy starts with translating risk information into decisions and handling actions and the
plans to implement those actions.
Risk planning is possibly the least practiced risk management process, but the most important.
Little or no formal risk planning typically exists on many projects.
This weakens risk management process effectiveness by causing risk issues to be missed, analyses to be inaccurate or
inconsistent, poor risk handling approaches, and subjective risk monitoring.
Formal risk planning should be performed on all projects and will aid overall risk management process effectiveness.
For Risk Planning to be credible it needs to address:
§ Risk Identification ‒ by defining the triggers of the risks and the planning sessions for handling the risk.
§ Risk Analysis and Modeling ‒ by assessing the feasibility of meeting cost, schedule, and technical performance.
§ Risk Planning ‒ by defining the roles and responsibilities of the participants in the risk management process.
§ Risk Tracking and Control ‒ for project cost, schedule, and technical performance and report this in short interval
status meetings.
Never forget, we must always answer the question how long are we willing to wait before we find out we are late. Assess
progress to plan at half that distance.
Increasing Probability of Project Success
PGCS 2020
59/70
Risk Tracking (sometimes called Risk Monitoring) is an activity of systematically tracking and evaluating the
performance of risk handling actions against target metrics throughout the project management process and
develops further risk handling options or executes risk handling plans, as appropriate.
Its intent is to ensure successful Risk Handling and should be done as part of technical reviews, risk review
board meetings, or periodic project reviews.
Risk Tracking provides information back to other risk management activities of identification, analysis,
handling plans, and handling plan implementation.
Risk Tracking activities include:
§ Communicating risks to all affected Stakeholders,
§ Monitoring risk handling plans for their effectiveness,
§ Reviewing regular status updates,
§ Displaying risk management dynamics,
§ Tracking risk status within the Risk Reporting process, and
§ Alerting management when Risk Handling Plans should be implemented or adjusted.
The key to the tracking activity is to establish a management indicator system over the entire project.
The Project Manager (PM) uses this indicator system to evaluate the status of the project throughout its life-
cycle to assure risk impacts are being reduced as planned.
Risk Tracking should provide an early warning when the likelihood of occurrence or the severity of
consequence exceeds pre-set thresholds or limits or is trending toward exceeding pre-set thresholds or limits
so timely management actions to handle these problems can be taken.
Increasing Probability of Project Success
PGCS 2020
60/70
Risk Control is one of four Risk Handling strategies, that include:
§ Risk Avoidance ‒ reconfigures the project so the risk is removed or is reduced.
§ Rick Control ‒ Risk Control is when risks are controlled by managing the cause and consequences
of the risk.
§ Risk Transfer or Sharing ‒ is when the risk is shared with a 3rd party.
§ Risk Assumption ‒ is accepting the loss, benefit or gain, from the risk when it occurs.
Risk control can take the form of installing data-gathering or early warning systems that provide
information to assess more accurately the impact, likelihood, or timing of a risk.
If warning of a risk can be obtained early enough to take action against it, then information gathering
may be preferable to more tangible and possibly more expensive actions.
Increasing Probability of Project Success
PGCS 2020
61/70
Risk management is a continuous, forward-looking process that is a critical part of business and
technical management.
Risk management should address issues that could endanger achievement of critical objectives.
A continuous risk management approach is applied to effectively anticipate and handle risks that
have critical impact on the project.
Here are 17 processes that must be in place to effectively manage risk on projects.
Start with determining the sources of risk, which are the uncertainties on the project and put them
first into categories ‒ reducible or irreducible.
Then into the technical and operational categories.
Build plans for handling the risks and monitoring the progress of the plans in correcting or
preventing the causes of the uncertainties that create the risk.
Increasing Probability of Project Success
PGCS 2020
62/70
With the Risk Register, and Handling Plans, build a formal risk management process defined in the
Project Management Plan (PMP) for assuring risk management is part of the business process.
This includes the proper resources, policies, roles and responsibilities, and training to properly apply
risk management across all project activities.
Increasing Probability of Project Success
PGCS 2020
63/70
Put Risk Management under the same change control process as all other project activities.
Assure the stakeholders are informed and concur with the risk management process and provide
them with short interval updates of the status of the project risks and the current status of he
Probability of Project Success.
Increasing Probability of Project Success
PGCS 2020
64/70
Applying the 5 principles and 5 practices, we now have the tools needed to start on the path of
increasing our probability of project success.
PGCS 2020
Increasing Probability of Project Success 65/70
If there is any message from this last 50 minutes, it’s without a credible and effective risk
management process, the Principles and Practices the Project Success has a low probability of
happening.
PGCS 2020
Increasing Probability of Project Success 66/70
Increasing Probability of Project Success
PGCS 2020
67/70

Mais conteúdo relacionado

Mais procurados

The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
Glen Alleman
 

Mais procurados (20)

NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 
PGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPMPGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPM
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio management
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principles
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
EDM/PDM Implementation
EDM/PDM ImplementationEDM/PDM Implementation
EDM/PDM Implementation
 
The Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System DeploymentThe Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System Deployment
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
 

Semelhante a Increasing the Probability of Project Success with Five Principles and Practices

Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-Final
SEKHAR KOMMURI
 
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-ProjectsDeveloping-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
NIDHI SEN
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
Tom Cremins
 

Semelhante a Increasing the Probability of Project Success with Five Principles and Practices (20)

Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
 
Project management playbook innovate vancouver (2019)
Project management playbook   innovate vancouver (2019)Project management playbook   innovate vancouver (2019)
Project management playbook innovate vancouver (2019)
 
Project Report on Employee Management System.docx
Project Report on Employee Management System.docxProject Report on Employee Management System.docx
Project Report on Employee Management System.docx
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-Final
 
Del
DelDel
Del
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
 
Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases Introduction
 
Optimizing Organizational Performance by Managing Project Benefits
Optimizing Organizational Performance by Managing Project BenefitsOptimizing Organizational Performance by Managing Project Benefits
Optimizing Organizational Performance by Managing Project Benefits
 
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-ProjectsDeveloping-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
Developing-Monitoring-And-Evaluation-Framework-for-Budget-Work-Projects
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 
computer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morecomputer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for more
 
Project Benefit Validation - Lean Six Sigma
Project Benefit  Validation - Lean Six SigmaProject Benefit  Validation - Lean Six Sigma
Project Benefit Validation - Lean Six Sigma
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 

Mais de Glen Alleman

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 
Writing Proposal Text
Writing Proposal TextWriting Proposal Text
Writing Proposal Text
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 

Último

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Último (20)

A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Developing An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilDeveloping An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of Brazil
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 

Increasing the Probability of Project Success with Five Principles and Practices

  • 1. There are many approaches to managing projects in every domain. This seminar lays the foundations for increasing the probability of project success, no matter the domain, what technology, what approach to delivering the outcomes of the project. The principles of this approach are immutable. The practices for implementing the principles are universally applicable. Each chart in this presentation, contains guidance that can be applied to your project, no matter the domain. In our short hour here, we’re going to cover a lot of material. The bibliography contains the supporting materials we can tailor to your individual project Increasing Probability of Project Success PGCS 2020 0:20 1/70
  • 2. We only have 50 minutes to go through this webinar so it will be fast and furious as the movie says. But what I want to leave you with are the principles which you can then turn into the practices and processes suitable for your projects 2 11/11/20 Glen B. Alleman PGCS 2020
  • 3. Let’s look at a universal source of problems on all projects no matter the domain that technology or the business content. The root cause of project overspending and overrunning the schedule is because the projects are complex when we think that they’re just complicated. Managing in the presence of this complexity requires special processes and practices based on the five immutable principles needed to increase the Probability of Project Success. 3 11/11/20 Glen B. Alleman PGCS 2020
  • 4. In our project management domain, like many others, there is always advice from the Greeks that is applicable to our problems of today. PGCS 2020 Increasing Probability of Project Success 4/70
  • 5. To increase the Probability of Project Success start with risk management. Risk management is based on Root Cause Analysis. Find the root cause of uncertainties that create risk first, then probability of project success can increase. From research, here are four key factors that reduce the probability of project success. Increasing Probability of Project Success PGCS 2020 5/70
  • 6. The five immutable principles of project success are: 1. Know where we are going by defining “done” at some point in the future. 2. Have some kind of plan to get to where we are going.. The fidelity of the plan depends on the tolerance for risk by the users of the plan. 3. Understand what resources are needed to execute the plan. How much time and money is needed to reach the destination. 4. Identify the impediments to progress along the way to Done. Have some means of correcting, preventing, removing, avoiding, or ignoring these impediments. 5. Have some way to measure planned progress, not just current progress, measured in units of physical percent complete meaningful to the decision makers. 6/70 PGCS 2020
  • 7. The path to showing up on time, on budget, with the needed capabilities, with the planned a set of tangible goals, starts by defining the unit of measure to assess if the actual work is following the planned path. To do this we need units of measure that are meaningful that represent the actual performance of the work, with precision and accuracy within the limits of the assessment process. The primary measures needed for this process are: Effectiveness and Performance. Increasing Probability of Project Success PGCS 2020 7/70
  • 8. Here are 5 Practices used to implement the 5 Principles 1. Identify Needed Capabilities that achieve the project objectives or the particular end state. Define these capabilities through scenarios from the customer point of view in units of Measures of Effectiveness (MoE) meaningful to the customer. 2. Define The Technical And Operational Requirements to be fulfilled for the system capabilities to be available to the customer. Define these requirements in terms isolated from any implementation of the products. Only then bind the requirements with technology. 3. Build The Performance Measurement Baseline – describing the work to be performed, the budgeted cost for this work, the organizational elements that produce the outcomes from this work, and Measures of Performance (MoP) showing the work is proceeding according to cost, schedule, and technical plan. 4. Execute the PMB’s Work Packages ‒ in the planned order, assuring Performance assessments are 0%/100% complete before proceeding. No rework, no transfer of activities to the future. Assure every requirement is traceable to work and all work is traceable to requirements. 5. Apply Continuous Risk Management for each Performance Based Management process to Identify, Analyze, Plan, Track, Control, and Communicate projectmatic and technical risk. Increasing Probability of Project Success PGCS 2020 8/70
  • 9. Here are the principles and practices, connected to increase the probability of project success. Practices without principles provide the opportunity to modify the approach without understanding why. Principles without practices are interesting discussions without measurable business benefits. We must start with the principles, then move to the practices. Without principles, there is no way to test practices to confirm they are on solid footing when they need to be adapted to the situation. With these connections, we’ll have the basis of a handbook to increase the probability of success, in any domain, for any technology. PGCS 2020 9/70 Increasing Probability of Project Success
  • 10. Here’s a map of the 23 steps we’ll use to connect Principles and Practices in the coming charts. Each connection is presented in the section with the numbers 1 through 23. PGCS 2020 10/70 Increasing Probability of Project Success
  • 11. Connecting principles with practices is a critical success factor for any approach to increasing the probability of project success. Practices without principles provide the opportunity to modify the approach without understanding why. Principles without practices are interesting discussions without measurable business benefits. Both are needed, both must be present for success. But we must start with the principles, then move to the practices. Without principles, there is no way to test practices to confirm they are on solid footing when they need to be adapted to the situation. Increasing Probability of Project Success PGCS 2020 11/70
  • 12. The Practice of Identifying the needed Capabilities is guided by 5 principles. Where are we going ‒ is answered by Concept of Operations that states, for the users point of view, what the system is doing when it is working. How are we going to get there and what do we need along the way ‒ is answered by an Integrated Master Plan defining the assessment of the increasing maturity of the Capabilities. What Impediments Will We Encounter Along The Way ‒ is answered by the Risk Register developed from each Capability defining the handling strategies to correct or prevent the risk from occurring. How Do We Measure Progress ‒ is answered by assessing physical percent complete assessment of the Measures of Effectiveness of the Capabilities to fulfill the mission or business strategy. PGCS 2020 12/70 Increasing Probability of Project Success
  • 13. Capabilities drive requirements, but rarely do requirements by themselves have value The stakeholders want a capability to accomplish a mission or fulfill a strategy. Capabilities are what we would do with the resulting system. The stakeholder puts the Capabilities to accomplish some goal. If we don’t know want capabilities we need to produce from the project, we really can’t talk about the project value, and we really can’t speak about what DONE looks like in a meaningful way other than the passage of time and consumption of money. PGCS 2020 13/70 Increasing Probability of Project Success
  • 14. The purpose of the CONOPS is to describe the operational needs, desires, visions, and expectations of the user without being overly technical or formal. A Concept of Operations (CONOPS) is a user-oriented document that "describes systems characteristics for a proposed system from a user's perspective. A CONOPS also describes the user organization, mission, and objectives from an integrated systems point of view and is used to communicate overall quantitative and qualitative system characteristics to stakeholders A CONOPS "describes the proposed system in terms of the user needs it will fulfill, its relationship to existing systems or procedures, and the ways it will be used. CONOPS can be tailored for many purposes, for example, to obtain consensus among the acquirer, developers, supporters, and user organization on the operational concept of a proposed system. A CONOPS may focus on communicating the user's needs to the developer or the developer's ideas to the user and other interested parties. Increasing Probability of Project Success PGCS 2020 14/70
  • 15. The Integrated Master Plan (IMP) is a representation of the increasing maturity of the projects deliverables through a series of Events that assess that maturity. The IMP is an event-driven plan that documents the significant accomplishments necessary to complete the work and ties each accomplishment to a key project event. It defines how the project is organized, structured, and conducted and how the total process will be controlled to provide a product that satisfies stakeholder requirements. Increasing Probability of Project Success PGCS 2020 15/70
  • 16. The structure of the Integrated Master Plan (IMP) and Integrated Master Schedule (IMS) provides a framework for assessing the increasing maturity of the project’s outcomes in units of measure meaningful to the decision makers. Together, the IMP and IMS demonstrate the project is adequately structured, realistic, and executable and the planned tasks are achievable within schedule and cost constraints at an acceptable level of risk. The IMP and IMS are business tools to manage and provide oversight of projects. In this picture Work Packages contain Tasks that consume resources (labor and materials) and are the basis of the Integrated Master Schedule. Each Work Package produces a tangible outcome defined through an Exit Criteria stated in a measurable unit meaningful to the decision makers. These Criteria are entry conditions to the Accomplishments needed t to move forward as planned. The Accomplishments define the Entry Criteria for the Events that assess the increasing maturity of the project as a whole. Increasing Probability of Project Success PGCS 2020 16/70
  • 17. All projects are complex. The two separate complexities on projects are the tasks themselves and the relationships between those tasks. Each of these complexities creates risk and risk must be dealt with in the project plan. The handling of these complexities have to be part of the project plan itself and without this handling strategy the probability of success of the project is greatly reduced. A quote that should be remember here is Risk Management is How Adults Manage Projects ‒ Tim Lister Increasing Probability of Project Success PGCS 2020 17/70
  • 18. Measures of Effectiveness are the primary assessments of a project’s progress to plan and the ultimate success of the deliverables from that work effort. The definition of Measures of Effectiveness belongs to the stakeholders or those paying for the work. This is the effectiveness of the project’s outcomes to accomplish the mission or fulfill a business goal. Defining and managing the measures of effectiveness is the critical success factor for all projects. Research shows missing or poorly defined measures of effectiveness are the root cause of project failure. Increasing Probability of Project Success PGCS 2020 18/70
  • 19. With the capabilities identified, we now need the technical and operational requirements that will implement these capabilities. With the requirements we can start to plan the project implementation activities to deliver those requirements for the needed cost at needed time. A failure mode for many projects is to start with requirements skipping the capabilities phase. Increasing Probability of Project Success PGCS 2020 19/70
  • 20. The connection between Principles and Practices for the Requirements Baseline include: Where are we going ‒ for each Capability, a technical or operational plan defines the facilities to implement the Capability. How are we going to get there What do we need along the way ‒ the Work Breakdown Structure defines the deliverables and the processes needed to produce these deliverables. These individual elements are rolled up to higher level deliverables, until we reach to top level of the project deliverable. What do we need along the way ‒ the resources, staff, equipment, facilities, and processes are defined in a Resource Management Plan connected to the WBS. These resources are budgeted in Work Packages and their Tasks, and summed in Control Accounts What Impediments Will We Encounter Along The Way ‒ the Risk Register developed from each Deliverable in the WBS defines the handling strategies to correct or prevent the risk from occurring. How Do We Measure Progress ‒ physical percent complete assessment of the Technical Performance Measures of the Capabilities to fulfill the mission or business strategy. PGCS 2020 20/70 Increasing Probability of Project Success
  • 21. The first step in identifying requirements that fulfill the needed capabilities is to separate “product” requirements from “process” requirements. The product could be a service as well, but the product (or service) is not the same as the process that delivers the service that may be enabled by the product. We can see there are several components of this separation. While this type of taxonomy looks unnecessary, later on we’ll see it can serve to reduce complexity, focus our efforts on important parts of requirements management, and reduce the overall effort of managing these requirements. Increasing Probability of Project Success PGCS 2020 21/70
  • 22. Value stream mapping is an approach to defining the needed capabilities for the business. The value stream defines a sequence of deliverables that have measurable value to the business or to the fulfillment of a mission. Each of the deliverables has a measured value that can be assessed against the needed capabilities of the project’s outcomes. These outcomes include technical performance, efficacy of risk reduction, on schedule, on cost. The key here is to have all measures be meaningful to the decision makers. Increasing Probability of Project Success PGCS 2020 22/70
  • 23. The work breakdown structure defines the decomposition of the deliverables from the project. The WBS is not a breakdown of the work it is a breakdown of the outcomes of the work. The WBS is the bill of materials for the project. The WBS collects cost and the parent child relationship between the deliverable items. A consistent WBS structure across the business or government agency allows comparison of past cost to future estimated costs by WBS Number. The WBS is one of the pieces of glue connecting all the work across the project. Increasing Probability of Project Success PGCS 2020 23/70
  • 24. Resources are needed to deliver outcomes for all projects. These resources are typically the staffing that does the work, but it also includes, material, equipment, and external services. Having a plan by resource category is needed to define the cost basis for the project. This resource plan is used as the basis for the integrated master schedule to sequence these resources to make sure they are available when needed. Increasing Probability of Project Success PGCS 2020 24/70
  • 25. It cannot be stated enough, risk management is the basis of project success. Each element in the WBS needs some type of risk assessment. This information is held in the risk register for analysis and handling plans. The connection between the Risk Register and the WBS is a critical success factor for the project. Increasing Probability of Project Success PGCS 2020 25/70
  • 26. Here’s an example of a risk register with its analysis connected to the WBS and the Integrated Master Schedule. Each element in the risk register has a probability of occurrence or some statistical assessment of its variability and the impact on the outcome of the risk were to come true. A critical success factor is to have the pre-mitigation and the post mitigation risk analysis in one place to confirm to the project management staff that risks are actually being bought down. This approach provides information about risks that cannot be reduced to zero so the project can provide margin, management reserve, or cost contingency to cover that situation. Increasing Probability of Project Success PGCS 2020 26/70
  • 27. Measures of Performance describe the physical and functional attributes of the deliverable. How fast, how slow, how big, how small, how reliable, how maintainable are all of the physical measurements of the outcomes are part of measures of performance. With this assessment it can be determined how much margin or contingency is needed if the item does not meet the performance requirements. The Measures of Performance are directly connected to the Capabilities produced by the project. Increasing Probability of Project Success PGCS 2020 27/70
  • 28. The Performance Measurement Baseline (PMB) is an important tool in the assessment of project performance used by project Managers and Systems Engineers in the Technical Assessment Process to appraise a project technical progress to plan. It includes the undistributed budget, all summary level planning package budgets, and all control account budgets but does not include management reserve. It establishes the contract level timed phased baseline against which contract level performance metrics are computed. It establishes the scope, schedule, and budget targets for the project. The PMB is usually a contractual document whose changes must go through the change control process. This is done during the planning process, and records what the project had planned, scheduled, budgeted for, in terms of the schedule, scope and cost. It should contain everything that the customer needs, as per the agreed scope. The Cost, Schedule, and Scope baselines put together are called the Performance Measurement Baseline. Increasing Probability of Project Success PGCS 2020 28/70
  • 29. The connection between Principles and Practices for the Performance Measurement Baseline include. The practices of establishing the PMB are guided by the principles of: Where are we going ‒ the MOE’s and MOP’s define the incremental maturity of the deliverables assessed against the planned maturity. How are we going to get there and what do we need along the way ‒ a resource loaded Integrated Master Schedule described the tasks and Work Packages needed to produce the deliverables from the project. What Impediments Will We Encounter Along The Way ‒ the Risk Register developed from each deliverable in the in the WBS defines the handling strategies to correct or prevent the risk from occurring. How Do We Measure Progress ‒ physical percent complete assessment of the Technical Performance Measures inform the progress to plan. PGCS 2020 29/70 Increasing Probability of Project Success
  • 30. Eisenhower said “In preparing for battle I have always found that plans are useless, but planning is indispensable.” The Performance Measurement Baseline contains cost, schedule, and technical performance goals. These are the basis of not only measuring progress to plan, but defining what Done looks like and how we’re going to get to Done as needed. PGCS 2020 Increasing Probability of Project Success 30/70
  • 31. Establishing the Performance Measurement Baseline is the process of integrating the scope, schedule, and cost baselines into a single project baseline from which to manage and control project performance throughout execution. The Performance Measurement Baseline of the project is actually three baselines: 1. The technical baseline assures that all the deliverables are identified. Even if the details are not known, the needed capabilities must be defined in some meaningful manner. Otherwise the project will have no way to control the scope. 2. The schedule baseline says when the needed capabilities will be available, and 3. The cost baseline says how much each of these capabilities is planned to cost. In addition to the scope, cost, and schedule elements, the performance measurement baseline (PMB) also incorporates undistributed budget (UB) (along with its corresponding work) and contingency reserves (alongside with the corresponding risks). PGCS 2020 31/70 Increasing Probability of Project Success
  • 32. As the project progresses we need to incrementally assess the maturity of the project deliverables. This incremental method is a critical success factor to avoid the big bang outcome of the project. The big bang happens when we wait till the end to find out that what we’re delivering is not what the stakeholders expect us to do. Increment and iterative processes are critical success factors for all projects no matter the domain technology or methods used to develop outcomes. This incremental and iterative approach to project management is not just for agile software projects it is applicable to all projects. The Big Bang produces a smoking hole where the project was, with all the money gone. Increasing Probability of Project Success PGCS 2020 32/70
  • 33. An Integrated Master Schedule (IMS) is a network of tasks linked from project start through project finish, reflecting the interdependencies between tasks and milestones. It begins with the Integrated Master Plan (IMP), which details the contractual deliverables developed from the Statement of Work/Objectives (SOW/SOO). The Integrated Master Schedule (IMS) is a time-based schedule containing the networked, detailed tasks necessary to ensure successful project execution. The IMS is used to verify attainability of the project objectives, to evaluate progress toward meeting project objectives, and to integrate the project schedule activities with all related components. The IMS utilizes Critical Path network management techniques to optimize the relationship of critical activities. The IMS is a hierarchical, tiered structure capable of rolling up to a high-level summary representations of activities as well as breaking down to the lowest level of task details showing dependencies, resources, durations, and constraints. Increasing Probability of Project Success PGCS 2020 33/70
  • 34. Risk is always present on projects no matter the domain, technology, or business environment. To have a credible project with a credible project plan that will increase the probability of project success we must manage in the presence of uncertainty that creates risk. Developing a risk adjusted cost and schedule starts with making a single point estimate of cost or duration of the work. This estimate is the most likely value that will occur in the presence of uncertainty. With the most likely value we can then estimate the higher or lower value. With this information we can then develop a model of the expected cost and expected duration of the work defined in the schedule. Monte Carlo simulation is a method to develop this confidence estimate. This approach has four steps: § Identify risks and uncertainties related to task durations, their start and finish time, cost and resources. § Perform monte carlo simulation. § Analyze risk-adjusted project schedule. § Perform probabilistic cost and work analysis of project schedules. The discussion of Monte Carlo simulation is beyond the scope of this presentation, but detailed resources will be provided in the bibliography. Increasing Probability of Project Success PGCS 2020 34/70
  • 35. Here is an example of a project schedule and the most likely values of the optimistic values and the pessimistic values of the duration of tasks. With this information a Monte Carlo simulation of the most likely value for the completion date can be developed. In the example here, the final testing plan completion date is planned for February, 10, 2003. In the next chart will see the Monte Carlo simulation showing the confidence of completing on or before that date. Increasing Probability of Project Success PGCS 2020 35/70
  • 36. With the Monte Carlo tool we can see the confidence of completing on or before a specific date. Using the integrated master schedule from the previous chart and the high and low ranges of duration for each task, the Monte Carlo tool shows the confidence of completing on or before the needed date of Feb 10, 2003. In this case the probability is low 40%. A higher probability is shown in the chart in the lower right-hand corner. We have an 80% confidence of completing on or before February 18, 2003. This approach to schedule risk analysis is mandated in many domains including the United States government domains. Increasing Probability of Project Success PGCS 2020 36/70
  • 37. Another critical success factor for increasing the probability of project success is the integration of risk buy down into the integrated master schedule. This describes how we need to plan to reduce risk as the project proceeds. We can then assess the actual risk reduction against the planned risk reduction to determine if we’re meeting the risk management plans and goals. This risk buydown planning is considered a Technical Performance Measure. This chart is produced by the same tool that uses the Monte Carlo simulation to assess the performance of the schedule. Increasing Probability of Project Success PGCS 2020 37/70
  • 38. Since all projects have uncertainty, both reducible and irreducible, we must have a risk adjusted in a graded master schedule. This integrated master schedule in the presence of uncertainty requires a plan A and a Plan B should the risks from the uncertainty turn into issues. No schedule without margin can be correct. Schedules without margin are late on day one. Increasing Probability of Project Success PGCS 2020 38/70
  • 39. Schedule margin is a project management tool for dealing with schedule contingencies. Schedule margin provides a separately designated "buffer" in the schedule to "protect" the delivery dates. There are two approaches to schedule margin. § In the first the final task is baselined to finish ten days before an End Of Contract (EOC) milestone aligned with the contract need date. The calculated difference between the final task completion and the contract need date is the schedule margin to the contract need date. § In the second the EOC milestone is baselined to finish immediately after the final task – which is still baselined to finish before the contract need date. The calculated difference is defined as the schedule margin to the contract need date. The example shows that margin can be placed before the deliverable date or after the deliverable date. Increasing Probability of Project Success PGCS 2020 39/70
  • 40. It is impossible to estimate precisely how much something will cost or how long it will take. If we want projects to meet cost and schedule commitments, we must budget and fund them with a higher probability of success. A Joint Cost and Schedule Confidence Level (JCL) is a quantitative probability statement about the ability of a project to meet its cost and schedule targets. Decision-makers and cost analysts should always think of a cost estimate as a probability distribution, NOT as a deterministic number. The best that can be provided to decision-makers is the cost probability distribution. It is up to the decision-maker to decide at which confidence level they want to set the budget. The probability distribution provides a quantitative basis for making this determination. Increasing Probability of Project Success PGCS 2020 40/70
  • 41. JCL is a process that combines a project’s cost, schedule, and risk into a complete picture. If cost, schedule, or both are below a defined confidence level, the management team must make decisions about risk mitigation measures and/or changing the project scope. There are six steps to developing a Joint Confidence Level: 1. Identify goals for the JCL. 2. Build a JCL schedule/logic network (a summary analysis schedule). 3. Load cost onto the schedule activities. 4. Incorporate risk list. 5. Conduct uncertainty analysis. 6. Calculate and view results, and iterate as required. Increasing Probability of Project Success PGCS 2020 41/70
  • 42. Here’s a picture of a Joint Confidence Level, where the x-axis represents the final completion date, and the y- axis represents the final cost through that completion date. The scatterplot shows the simulated outcomes of the cost and schedule risk analysis. Each dot in the scatterplot represents a specific result, or scenario, from the simulation calculation of the cost and schedule. In this example, the blue lines (the crosshair) intercept at the project’s baseline plan or point estimate (PE). To the bottom left, the green dots represent all the scenarios that are at or below the baseline cost and schedule. The yellow line represents the “frontier curve,” or indifference curve, that specifies all the cost and schedule combinations that will meet a targeted JCL. Anything the the left and below the Yellow line is an acceptable cost and schedule for the project. Anything to the right and above the Yellow line is an unacceptable cost and schedule. The goal of project management is to keep the cost and schedule below and to the left of the Yellow line, while maintaining the delivery of the needed capabilities. This is called Keeping the project Green. Increasing Probability of Project Success PGCS 2020 42/70
  • 43. Technical Performance Measures are an assessment of the measures of performance and the measures of effectiveness for the deliverables of the projects to meet the technical requirements. The passage of time and consumption of money are measures of project progress. But if these measures are not matched against the increasing maturity of the technical performance measures the project will not deliver the needed value to those paying for those outcomes. We must always remember the cost, schedule, and technical performance are tightly integrated. Management of all three of these variables is the role of the project manager. To increase the probability of project success all three variables must be tightly controlled. Increasing Probability of Project Success PGCS 2020 43/70
  • 44. The technical performance measure has a planned increase in its maturity as the project proceeds. In this example the TPM is the Mean Time Between Failure of some article produced by the project. As the project proceeds the MTBF needs to increase. The current assessment of the meantime between failures is shown in the line achieved to date. The planned value for the MTBF at this date is different than the actual value. This variance is inside the lower limit and upper limit of the plan value. As the project proceeds the MTBF must reach the threshold value for the project to meet the technical performance measures. If the actual values were to go outside the upper and lower control limits at any specific time a collective or preventive action will be needed to put this variance back inside those upper and lower limits. Increasing Probability of Project Success PGCS 2020 44/70
  • 45. With the performance measurement baseline established, we now need to execute that baseline to deliver outcomes from the project. 45/70 Increasing Probability of Project Success PGCS 2020
  • 46. The connection between Principles and Practices for Executing the PMB include: Where are we going ‒ measures of Physical Percent Complete are the only measure of progress to place. Not the passage of time or consumption of money. How are we going to get there ‒ using incremental delivery, the progress can be measured on fine grained boundaries. What do we need along the way ‒ with the measures of progress to plan and risk adjusted Integrated Master Schedule, future performance can be modeled. What Impediments Will We Encounter Along The Way ‒ the Risk Register developed from each Deliverable in the WBS defines the handling strategies to correct or prevent the risk from occurring and contained in a risk adjusted PMB. How Do We Measure Progress ‒ physical percent complete assessment of the Technical Performance Measures of the Capabilities to fulfill the mission or business strategy is used by the Earned Value Management System to produce and Estimate to Complete and and Estimate at Completion. PGCS 2020 Increasing Probability of Project Success 46/70
  • 47. Physical percent complete is often confused with percent complete in a scheduling tools. Physical percent complete requires tangible evidence of progress to plan for the technical performance, cost, and schedule targets. Here are several ways to calculate physical percent complete. Never is physical percent complete calculated by the passage of time and consumption of money. Only the contractual legal term, tangible evidentiary materials, is used to calculate physical percent complete. The description of this tangible evidence needs to be defined before the work starts. This physical evidence needs to be useful to those paying for the work. For example the number of drawings produced may be interesting to assess the performance of the engineers, but it does not measure physical percent complete of the design. Care is needed in defining the units of physical percent complete. Again the passage of time and consumption of money is not physical percent complete. Increasing Probability of Project Success PGCS 2020 47/70
  • 48. Iterative and Incremental Delivery (IID) are terms often used in software development, but they are applicable in any project domain. The basic idea behind this method is to develop a system through repeated cycles (iterations) and in smaller portions at a time (increments). IID grew from the 1930s work of Walter Shewhart, a quality expert at Bell Labs who proposed a series of short “plan-do-study-act” (PDSA) cycles for quality improvement. The X-15 hypersonic jet in the 1950’s applied IID and the practice as a major contribution to the X-15’s success. There are many examples of iterative and incremental development and delivery at NASA in 1960’s starting with Project Mercury, which ran ½ days iterations that were time boxed. Some of those Mercury engineers later formed a new division within IBM, where "another early and striking example of a major IID success [was] the very heart of NASA’s space shuttle software—the primary avionics software system, which [they] built from 1977 to 1980. The team applied IID in a series of 17 iterations over 31 months, averaging around eight weeks per iteration. Their motivation for avoiding the waterfall life cycle was that the shuttle project’s requirements were changing during the software development process. Increasing Probability of Project Success PGCS 2020 48/70
  • 49. The success of any project is likely to be judged by how well it achieves a defined outcome while meeting performance expectations. Most projects would not be undertaken if management had little confidence in a successful outcome. Many projects are subject to being cancelled, even late in the project cycle, if the forecasted outcome does not meet expectations. These factors drive the need throughout the project for updated forecasts of the project outcome. Project forecasting is the process of making conjectures about future performance, which can help managers decide whether to cancel this project, create new projects, or to continue with existing projects. Increasing Probability of Project Success PGCS 2020 49/70
  • 50. Future Project Performance can be lumped under the project management principle of change management. If we can’t forecast the outcome of a change, the probability of project success is low. There are four different, though interrelated, challenges in dealing with change and the ability to forecast the impact of that change The first deals with the reality that the project's boundaries change as the project progresses. Specific selections of equipment, systems, or processes impact the content of the project. Refining judgments of capabilities leads to increases in scope more frequently than decreases in scope. Competition for resources, changes in performance intensity, and external factors all put pressure on the project plan. A most common change in project forecasting is the increase that occurs when a greater scope of work is attempted in the same amount of time. Another factor is the reality that, as the project progresses, it is easy to record the spending of dollars and difficult to assess what those dollars have bought. This is why Capabilities Based Planning is a critical success factor for all projects. Maintaining the connection of requirements to needed capabilities is critical to increasing the probability of success. Increasing Probability of Project Success PGCS 2020 50/70
  • 51. All projects and projects are plagued by cost and schedule overruns and technical shortfalls. Sources of these issues are summarized in four notions by Mr. Bliss, Director Performance Assessment and Root cause Analyses (PARCA), US Department of Defense. 1. Unrealistic performance expectations with missing Measures of Effectiveness (MOE) and Measures of Performance (MOP). 2. Unrealistic cost and schedule estimates based on inadequate risk adjusted growth models. 3. Inadequate assessment of risk and unmitigated exposure to these risks without proper handling strategies. 4. Unanticipated technical issues without missing alternative plans and solutions to maintain the effectiveness and performance of project deliverables. All project work operates in the presence of uncertainty. Cost uncertainty, schedule uncertainty, technical uncertainty that creates risk. Knowledge of project risk provides information needed to make decisions in the presence of uncertainty, where predicting future outcomes is part of the project management process. Risk is the consequence of Uncertainty. Managing in the presence of uncertainty is the role of the project manager, and risk management is the basis of increasing the Probability of Project Success. Increasing Probability of Project Success PGCS 2020 51/70
  • 52. Earned Value is a fundamental measurement of a project’s performance but far from sufficient for the project’s success. Integration of risk, technical performance measures, and systems engineering processes are needed to increase the probability of project success. Success starts with a winning proposal, installing the right tools and work processes, establishing a credible Performance Measurement Baseline, identifying and handling programmatic and technical risk, and through project execution a variety of technical, operational, and staffing processes are needed and based on Earned Value Management processes. Increasing the probability of project success requires the application of 5 simultaneous project management processes. These 5 processes are inter-related, dependent, and supportive of each other. Earned Value is at the heart of each of these 5 processes with the focus on measures needed to forecast the future, rather than just reporting past performance. Increasing Probability of Project Success PGCS 2020 52/70
  • 53. All projects operate in the presence of uncertainty. All risk comes from uncertainty. Uncertainty comes in two forms on projects Epistemic uncertainty, which comes from lack of knowledge, which is reducible Aleatory uncertainty, from naturally occurring processes, which is irreducible Managing in the presence of uncertainty is the critical success factor for increasing the probability of project success. Let’s repeat the quote that says it all about risk management and the success of project management Risk Management is How Adults Manage Projects ‒ Tim Lister. The purpose of risk management is to identify potential problems before they occur so that risk- handling activities may be planned and invoked as needed across the life of the product or project to mitigate adverse impacts on achieving objectives. Increasing Probability of Project Success PGCS 2020 53/70
  • 54. The connection between Principles and Practices for Continuous Risk Management answers the questions: Where are we going? ‒ by identify the uncertainties on the project that create risk. These can be reducible uncertainties or irreducible uncertainties. How are we going to get there? ‒ by analyzing these uncertainties to find their root causes and the properties of these causes. What do we need along the way? ‒ by developing risk handling strategies to correct or prevent the root cause from creating the uncertainties that create the risk. What Impediments Will We Encounter Along The Way? ‒ we need to place the risks, with their handling strategies in a Risk Register and assess the risk buydown effectiveness on fine grained boundaries. How Do We Measure Progress to Plan? ‒ we measure the effectiveness of the risk buy down activities on the probability of success for cost, schedule, and technical performance measures. PGCS 2020 Increasing Probability of Project Success 54/70
  • 55. Continuous Risk Management, when performed successfully, provides 5 key benefits: § Identify uncertainties that create risk. § Correct or Prevent problems before they occur – by identifying potential risks and deals with them when it is easier and cheaper to do so – before they are issues. § Improve product or service quality – by focusing on the project’s objectives and looking for things that many effect quality throughout the project lifecycle. § Enable better use of resources – by allowing the early identification of potential problems – proactive management to input into management decisions regarding resource allocation. § Promotes teamwork – involving personnel at all levels of the project. Increasing Probability of Project Success 55/70 PGCS 2020
  • 56. Risk identification is a process of transforming uncertainties and issues about the project into distinct (tangible) risks that can be described and measured. Identifying risks involves two activities: § Capturing a statement of risk. § Capturing the context of that risk. The objective of risk identification is to locate risks before they become problems and to incorporate this information into the project management process. The data items found in risk identification include: § Individual uncertainties and issues about the project and project’s progress. § Groups of activities and issues which may risks. § Project data supporting information consisting of items such as the schedule, budget, plans, work breakdown structure, that may provide information helpful in identifying risks. § For each risk identified, a statement of the risk with the associated context. § A Risk Register containing all this information about the risks identified for the project, their handling plans, the probability or occurrence or naturally occurring variance, the probability of effectiveness of the corrective or preventive actions needed to handle the risk Increasing Probability of Project Success PGCS 2020 56/70
  • 57. A well written risk statement can answer the following questions: § What is the root cause that creates the risk? § Why could it happen? What’s the probability of occurrence for event based risks and what’s the impact from a naturally occurring risks? § If the risk becomes an issue, What is the impact on the project? The risk statement provides clear and descriptive information required for a reasoned and defensible assessment of the risk's probability or occurrence or natural variability and areas of impact. A well-written risk statement contains two components. They are a statement of the Condition Present and the Associated Risk Event. In a risk statement, the Condition Present is itself an event: it is an event that has occurred or is presently occurring. Associated Risk Events are future events that might occur because of the Condition Present. The Condition Present acts as the departure point from which one or more Associated Risk Events may originate. Increasing Probability of Project Success PGCS 2020 57/70
  • 58. The main objective of Risk Analysis and assessments of the uncertainties that create risk, is the basis of informed decision-making needed to increase the probability of project success. Risk analysis is the process of systematically evaluating each identified, approved risk to estimate the probability of occurrence (likelihood) and consequence of occurrence (impact), and then converting the results to a corresponding risk level or rating. Traditional Risk Analysis starts with evaluating and prioritizing risk, assessing the probability of risk occurrence and probability of impact of the risk on project success, and placing this information in a Risk Register. With this information. decisions can be made about to respond to risk should it become an issue. This approach starts with qualitative analysis but fails to recognize there are still phenomena not taken into account by classical project risk management. These include propagation of simple risk, loops in this propagation model, reaction chains and non-linear couplings of interrelationships between risks creating other risks, propagation of risks between interrelationships creating further risk, analysis of alternatives and their risk assessment, the premortem analysis needed to remove the uncertainties, and the dynamic evolving connections between cost, schedule, and technical performance. Quantitative risk analysis determines the root cause(s) of the uncertainties, but reducible and irreducible, that create risk. Risk Handling strategies are then created to correct or prevent the occurrence of the risk, used to the Probability of Project Success (PoPS). Increasing Probability of Project Success PGCS 2020 58/70
  • 59. Risk Handling Plans are similar to any other type of project planning or problem‒solving activity. Planning of the Risk Handling Strategy starts with translating risk information into decisions and handling actions and the plans to implement those actions. Risk planning is possibly the least practiced risk management process, but the most important. Little or no formal risk planning typically exists on many projects. This weakens risk management process effectiveness by causing risk issues to be missed, analyses to be inaccurate or inconsistent, poor risk handling approaches, and subjective risk monitoring. Formal risk planning should be performed on all projects and will aid overall risk management process effectiveness. For Risk Planning to be credible it needs to address: § Risk Identification ‒ by defining the triggers of the risks and the planning sessions for handling the risk. § Risk Analysis and Modeling ‒ by assessing the feasibility of meeting cost, schedule, and technical performance. § Risk Planning ‒ by defining the roles and responsibilities of the participants in the risk management process. § Risk Tracking and Control ‒ for project cost, schedule, and technical performance and report this in short interval status meetings. Never forget, we must always answer the question how long are we willing to wait before we find out we are late. Assess progress to plan at half that distance. Increasing Probability of Project Success PGCS 2020 59/70
  • 60. Risk Tracking (sometimes called Risk Monitoring) is an activity of systematically tracking and evaluating the performance of risk handling actions against target metrics throughout the project management process and develops further risk handling options or executes risk handling plans, as appropriate. Its intent is to ensure successful Risk Handling and should be done as part of technical reviews, risk review board meetings, or periodic project reviews. Risk Tracking provides information back to other risk management activities of identification, analysis, handling plans, and handling plan implementation. Risk Tracking activities include: § Communicating risks to all affected Stakeholders, § Monitoring risk handling plans for their effectiveness, § Reviewing regular status updates, § Displaying risk management dynamics, § Tracking risk status within the Risk Reporting process, and § Alerting management when Risk Handling Plans should be implemented or adjusted. The key to the tracking activity is to establish a management indicator system over the entire project. The Project Manager (PM) uses this indicator system to evaluate the status of the project throughout its life- cycle to assure risk impacts are being reduced as planned. Risk Tracking should provide an early warning when the likelihood of occurrence or the severity of consequence exceeds pre-set thresholds or limits or is trending toward exceeding pre-set thresholds or limits so timely management actions to handle these problems can be taken. Increasing Probability of Project Success PGCS 2020 60/70
  • 61. Risk Control is one of four Risk Handling strategies, that include: § Risk Avoidance ‒ reconfigures the project so the risk is removed or is reduced. § Rick Control ‒ Risk Control is when risks are controlled by managing the cause and consequences of the risk. § Risk Transfer or Sharing ‒ is when the risk is shared with a 3rd party. § Risk Assumption ‒ is accepting the loss, benefit or gain, from the risk when it occurs. Risk control can take the form of installing data-gathering or early warning systems that provide information to assess more accurately the impact, likelihood, or timing of a risk. If warning of a risk can be obtained early enough to take action against it, then information gathering may be preferable to more tangible and possibly more expensive actions. Increasing Probability of Project Success PGCS 2020 61/70
  • 62. Risk management is a continuous, forward-looking process that is a critical part of business and technical management. Risk management should address issues that could endanger achievement of critical objectives. A continuous risk management approach is applied to effectively anticipate and handle risks that have critical impact on the project. Here are 17 processes that must be in place to effectively manage risk on projects. Start with determining the sources of risk, which are the uncertainties on the project and put them first into categories ‒ reducible or irreducible. Then into the technical and operational categories. Build plans for handling the risks and monitoring the progress of the plans in correcting or preventing the causes of the uncertainties that create the risk. Increasing Probability of Project Success PGCS 2020 62/70
  • 63. With the Risk Register, and Handling Plans, build a formal risk management process defined in the Project Management Plan (PMP) for assuring risk management is part of the business process. This includes the proper resources, policies, roles and responsibilities, and training to properly apply risk management across all project activities. Increasing Probability of Project Success PGCS 2020 63/70
  • 64. Put Risk Management under the same change control process as all other project activities. Assure the stakeholders are informed and concur with the risk management process and provide them with short interval updates of the status of the project risks and the current status of he Probability of Project Success. Increasing Probability of Project Success PGCS 2020 64/70
  • 65. Applying the 5 principles and 5 practices, we now have the tools needed to start on the path of increasing our probability of project success. PGCS 2020 Increasing Probability of Project Success 65/70
  • 66. If there is any message from this last 50 minutes, it’s without a credible and effective risk management process, the Principles and Practices the Project Success has a low probability of happening. PGCS 2020 Increasing Probability of Project Success 66/70
  • 67. Increasing Probability of Project Success PGCS 2020 67/70