SlideShare uma empresa Scribd logo
1 de 74
Baixar para ler offline
Lewis + Fowler Aerospace Capabilities Briefing (Full).pptx
V5
Copyright © 2009, Niwot Ridge, Consulting LLC 1/74
2/74
3/74
4/74
5/74
6/74
So much for our strategy of
winning through technical
dominance
7/74
Product Tree
SOW
IPTs
IMP
IMS
BOEs
CWBS
8/74
Each element of the PMB is supportive of the others
The integrated whole is the basis of a credible PMB
Attribute Beneficial Outcome from this Attribute
Maturity Flows through
Program Events
§ Performance measurement is in units of increasing
maturity of the Technical Performance Measures
§ Each event is a mini authorization to proceed
Single outcome for each
work package (AC)
§ Measure Physical Percent Complete at the WP level
§ Use 0/100 for tasks for the vast majority of work
Technical Performance
Measures are explicitly
visible in the IMS
§ Connect Cost, Schedule, and Technical Performance
§ EV does not provide a means of adjust for “off TPM,” but
make your own adjustments to the risk numbers for now
Risk retirement explicitly
visible in the IMS
§ Risk retirement is embedded in the IMS
§ Risk mitigation means waiting until the risk happens
IMS flows vertically 1st
and horizontally 2nd
§ All work supports the assessment of maturity
§ Isolate tasks dependencies within a Work Package
No Event linkage except
for long lead items
§ 0/100 requires not partial completion
Decoupled dependences
improves risk
responsiveness
§ 1st round IMS defines a free flowing process
§ Maintaining this decoupling is key to a “dynamic” IMS
that can respond to the natural changes in the program
9/74
10/74
Risk Management
Requirements
Contractor Work
Breakdown Structure
(CWBS)
CWBS Dictionary / SOW
Integrated Master Plan
(IMP)
Integrated Master Schedule
(IMS)
Earned Value Management
System
Self Assessment / Award Fee
Determinations / CPAR’s
Technical Performance
Measures (TPM)
Process Metrics
ü Specifications
ü Work Statements
ü Tailored to and outlines entire program and products
ü Provides a single numbering system for the program
ü States all deliverables and their components
ü Follows IPT and CWBS structure
ü Descriptions of work traceable to the IMS elements
ü Event–driven Plan provides
roadmap of processes for program
ü Event–driven Schedule expands IMP
into Work Packages
ü Provides details and timing
ü Builds in risk mitigation activities
ü Connects measures of progress with
measures of increasing maturity
ü Connects System
Performance with
Continuous
Technical
Improvements
ü Connects Cost
Performance
with the IMS
Performance
ü Determined by program execution
11/74
Program
Events
Statement of
Work
CWBS
Significant
Accomplishments
Accomplishment
Criteria
CDRLs and
Deliverables
Tasks Contained
in Work Packages
Measures the progress to plan using Physical & Complete at the Accomplishment Criteria
(AC) and CWBS level
Defines
Aligned Aligned
Aligned
Aligned
Aligned
Completed SA’s are
entry criteria for
Program Events
Completed Work
Packages are exit
criteria for Tasks
Describes increasing
product maturity as 0/100 or
EVMS SD guidance
Documents the product
maturity that is aligned with
SOW and CWBS
Work necessary to
mature products
grouped by CWBS
Work structure
aligned to
SOW
12/74
13/74
14/74
DoD Guide DAG SEMP CWBS
IMP
IMS ISE
Technical Reviews
Event Timing of Technical Reviews X X X X X
Success criteria Technical Reviews X X X X X
Include entry and exit criteria for Technical Reviews
in IMP/IMS X X
Assess Technical Maturity in Technical Reviews X X X X
Integrate SEP with: IMP/IMS, TPMs, and EVM X X X X
Integrate CWBS with: Requirements specification,
Statement of Work, and IMP/IMS/EVMS X X X
Link risk management and mitigation plans with
technical reviews, TPM, EVMS, and IMS X
Integrated Reviews
Include Technical Baseline Review (TBR) in IMS; X
Integrated Baseline Review: plans for event based
technical reviews, including entry and exit criteria
Correlation of TPM’s, IMP. IMS, and EVMS
X
15/74
16/74
17/74
18/74
19/74
20/74
Only put these on your bookshelf after you’ve read them
21/74
IMS
IMP
Describes the
strategy for
successful
program
delivery
Supplemental Schedules in CAM Notebook
Tasks Contained in Work Packages
Accomplishment
Criteria
Significant
Accomplishments
Program
Events
Integrated Master Plan (IMP)
§ Identifies program events, significant accomplishments, and
accomplishment criteria. System level, controlled document.
Integrated Master Schedule (IMS)
§ Logic network schedule of program planned activities
keyed to the imp’s accomplishment criteria
Supplemental Schedule
§ Created (as needed) to provide lower
levels of detail data within CAM notebook
§ Establishes the structure, parameters and basis for the
integrated master schedule (IMS) development
§ Basis of performance measurement system; common
element integrating cost, schedule, & performance
§ Constructed to provide integrated planning down to the
work package task level, provides horizontal & vertical
§ Supports control account schedules and
the management of day–to–day
operations
traceability, summarization of info and critical path
identification and analysis
schedules and are summarized in the IMS
and part of the program’s PMB
22/74
Form IMP
Development
Team
Gather Inputs
Establish
Criteria For
Events
Define And Or
Derive
Deliverable
Products
Define Events
For Program
And Products
Define IPT
Structure To
Implement
Product
Structure
Expand WBS
To IPT
Structure
Produce The
Product IMP
Matrix With
CWBS
Data
Dictionary
IMS Inputs
OBS Update CWBS Update
Define Program
Demonstration
Capabilities
Define
Accomplishments
For Each
Capability
Set Order Of
Program Events
Select Topics For
IMP Narratives
Define Tasks And
Work Products
For Each
Accomplishment
IMS Inputs
Summary Of IMP
With E/A/C
Initial Approval Of
IMP
Demonstrate How
Subject Are
Managed
Release To Baseline
Control For Use By IMS
… is an event–based plan depicting the overall structure of the
program and the key processes and activities. It defines
accomplishments and criteria for each event.
With the IMP, the increasing maturity of the program is stated
explicitly in the Significant Accomplishments (SA) and their
Accomplishment Criteria (AC).
It’s these key processes and activities that are the basis of the
credibility assessment.
Events are NOT milestones, they are mini–Authorizations to
Proceed. These mini-ATPs are the basis of maturity assessments
of the products and services of the program.
Work performed beyond the upcoming Program Event is
actually done “as risk.” 23/74
24/74
25/74
26/74
27/74
28/74
29/74
30/74
Through PDR, the majority of the work is building the deliverables from the CDRLs.
Each CDRL should be assigned to a single AC and be connected to a single PE for the defined maturity level.
31/74
32/74
33/74
34/74
35/74
§ Without an IMP there
is no strategy
§ Without an IMP the
us no place for the
work to reside
§ Without an IMP there
is no way to answer to
the question: “Why
are we doing this?”
§ Without an IMP there
is no way to measure
the increasing
maturity of the
deliverables
36/74
37/74
All work flows
vertically from
bottom up.
From Work Package
content to the Exit
Criteria of the WP
(AC), to the
Significant
Accomplishments
(SA) to the Program
Events (PE).
This flow is a
description of the
work that produces
increasing maturity.
38/74
The activities of a
Work Package
“exit” through the
Accomplishment
Criteria (AC).
Interconnections
between Work
Packages at the
task level should
be avoided.
Only 100%
complete work
should start the
next Work
Package.
PE
SA
ACs
Tasks
Completing AC starts
task in next AC
Completed Task
lands on AC
PE
SAs
ACs
Tasks
39/74
40/74
Cost Performance Baseline
Schedule Performance Baseline
Technical Performance Baseline
Perform
Functional
Analysis
Determine
Scope and
Approach
Develop
Technical
Logic
Develop
Technical
Baseline
Develop WBS
Define
Activities
Estimate
Time
Durations
Sequence
Activities
Finalize
Schedule
Identify
Apportioned
Milestones
Determine
Resource
Requirements
Prepare Cost
Estimate
Resource
Load
Schedule
Finalize
Apportioned
Milestones
Determine
Funding
Constraints
Approve
PMB
41/74
42/74
Program Events
Define the availability
of a Capability at a point in
time.
Accomplishments
Represent requirements
that enable Capabilities.
Criteria
Represent Work Packages that
fulfill Requirements.
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
package
§ The increasing maturing of a product or service is described through Events or Milestones,
Accomplishments, Criteria, and their Work Packages.
§ Each Event or Milestone represents the availability of one or more capabilities.
§ The presence of these capabilities is measured by the Accomplishments and their Criteria.
§ Accomplishments are the pre–conditions for the maturity assessment of the product or service at
each Event or Milestone.
§ This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the
activities which produce deliverables. This hierarchy also describes increasing program maturity
resulting from the activities contained in the Work Packages.
§ Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or
Milestones is measured in units of “physical percent complete” by connecting Earned Value with
Technical Performance Measures.
The Structure of a
Deliverables Based Plan
Work
Package
Monthly Status Report:
§ Validate schedule status
(start/complete/slip)
§ Validate work package
% complete
§ Take earned value from % Cmplt
§ Identify/process cost ETCs
Weekly Status Report:
§ Roll up of lower level schedule
status
§ Roll up of lower level % complete
or
§ Milestone start/complete
§ Milestone slip (early/late,
start/complete)
§ Physical % Complete of tasks
Weekly Status Report:
§ Milestone start/complete
§ Milestone slip (early/late,
start/complete)
§ % complete of tasks
Near term Rolling Wave
Control account span
IMS Activities
(at Work Package level
WP’s < 45 work days)
20 to 40
Workday tasks
Or even
weekly tasks
IMS Tasks
(one and two levels
below WP level)
IMP
WBS
Levels
1, 2, and 3
WBS
Levels
4 and 5
WBS’s
Below
Work
Package
Planning Package
43/74
44/74
45/74
Cost, Schedule, Technical Performance†
WBS
Task 100
Task 101
Task 102
Task 103
Task 104
Task 105
Task 106
†This is a Key concept. This is the part of the process
that integrates the cost and schedule risk impacts to
provide the basis of a credible schedule.
Without Technical Performance measures, Cost and
Schedule cannot show physical percent complete.
Probability
Density
Function
§ Research the Project
§ Find Analogies
§ Ask Endless Questions
§ Analyze the Results
§ What can go wrong?
§ How likely is it to go wrong?
§ What is the cause?
§ What is the consequence?
Monte Carlo Simulation
Tool is Mandatory
1.0
.8
.6
.4
.2
0 Days, Facilities, Parts, People
Cumulative Distribution Function
Days, Facilities,
Parts and People
46/74
DID–81650 calls out the
details of the IMS and it’s
statistical analysis
A ship on the beach is a lighthouse
to the sea – Dutch Proverb
47/74
48/74
49/74
50/74
51/74
§ In the example above, the Work Package Managers collectively come to an agreement on how the sequence of
how the work will be performed within each AC.
§ The result is a collective ownership of the outcome. This ownership comes from the collective development of
the project plan.
§ This process is a Product Development Kaizen (PDK) and used in major aerospace, defense and product
development firms. 52/74
53/74
54/74
55/74
56/74
57/74
58/74
59/74
60/74
61/74
AC: 005
Work Pkg
Work Pkg
Work Pkg
Work Pkg
AC
AC:023
Work Pkg
Work Pkg
Work Pkg
Work Pkg
AC
§ The 100% completed work in AC:005 is needed to start the work in AC:023
§ In the IMP/IMS paradigm, there is no Task-to-Task connection across
Accomplishment Criteria (AC) boundaries, only within an AC
§ The AC-to-AC linking states “…all work in the predecessor AC must be complete
before starting the successor work, assuring the minimum of rework due to
partially defined requirements or partially completed products”
62/74
PE: B
PE: A
SA: 001
SA: 002
SA: 003
SA: 004
PE: A
Task
Task
Task
AC: 006
§ The best arrangement has the completion of Event A start the first task in Event B.
§ All work performed beyond the date of Event A is done at risk.
§ At PDR (Event A), approval to proceed Event B (CDR) is given
§ Only long lead items should cross Program Event boundaries
§ All other work terminates on the Program Event where a formal review of the
planned maturity is conducted – SRR, SFR, PDR, CDR, …
§ This topology assures a complete assessment of “progress to plan,” is available at
each Program Event
63/74
SA: 008
PE: B
64/74
A Credible Performance Measurement Baseline
Assures Program Management has the needed performance information to deliver
on‒time, on‒budget, and on‒specification
Technical Performance Measures
Cost Schedule
Conventional Earned Value
+
=
§ The Master Schedule
used to derive Basis of
Estimate (BOE) not the
other way around.
§ Probabilistic cost
estimating uses past
performance and cost risk
modeling.
§ Labor, Materiel, and other
direct costs accounted for
in Work Packages.
§ Risk adjustments for all
elements of cost.
Cost Baseline
§ Earned Value is diluted by
missing technical
performance.
§ Earned Value is diluted by
postponed features.
§ Earned Value is diluted by
non compliant quality.
§ All these dilutions require
adjustments to the
Estimate at Complete
(EAC) and the To
Complete Performance
Index (TCPI).
Technical Performance
§ Requirements are
decomposed into physical
deliverables.
§ Deliverables are produced
through Work Packages.
§ Work Packages are
assigned to accountable
manager.
§ Work Packages are
sequenced to form the
highest value stream with
the lowest technical and
programmatic risk.
Schedule Baseline
65/74
66/74
67/74
68/74
This approach is called Product Development Kaizen and is used by Lean Six Sigma firms to
ferret out the system capabilities before any technical or operational requirements are defined.
Use this to reverse engineer or validate the WBS and connect WHAT with WHY before
proceeding to build the CWBS or confirm the WBS.
69/74
Update Contractor
System Spec
Update Program
Development
Allocate
Functional
Reqmts
Update Functional
System Design
Develop HWCI
Specifications
Develop SIL
Specifications
Build Astp1
F-18 IRR
SIL Baseline 1.0
Update SIL Test
Cases
Develop Prelim
SIL CSCI
Critical
Components
AstP 1,2
SSpS 1,2,3
1
2
3
4
6
7
5
8
10
9
11
13
14
15
Update AS Test
I&T on CVN
I&T on LHA
12
Contract Award + 15 days
Systems Requirements Review (SRR)
System Functional Review (SFR)
HW Preliminary Design Review (PDR)
System PDR
EDM 1.0
Baseline
EDM 2.0
Baseline
Mfg Docs
Available
TBD
TRR 1.0
EDM 7-8 TRR
70/74
§ Each collection point provides
an assessment of incremental
mission value.
§ Defining these points before
the project starts is the basis of
measuring progress to plan.
§ Because then you know what
done looks like before it
arrives.
Deliverables
WBS
Tasks and Schedule
Business Need
Process Invoices for
Top Tier Suppliers
1st Level
Electronic Invoice
Submittal
1st Level
Routing to Payables
Department
2nd Level
Payables Account
Verification
2nd Level
Payment Scheduling
2nd Level
Material receipt
verification
2nd Level
“On hand” balance
Updates
Work
Package
(WP)
1 2
3
4
6
5 A
B
Deliverables defined in WP
Terminal Node in the WBS
defines the products or
services that produce the
products of the project
Terminal node of the
WBS defined by a Work
Package.
Tasks within the Work
Package produce the
Deliverables
100% Completion of the
deliverables is the measure of
performance for the Work Package
Management of the
Work Package Tasks is
the responsibility of
the WP Manager.
A decomposition of the work
needed to fulfill the business
requirements
71/74
72/74
Maturity Action
Product Product State
Adjective Verb
Noun Verb
Complete
Design
Model/Sim
Preliminary
Risk: CEV-037 - Loss of Critical Functions During Descent
Planned Risk Level Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete)
Risk
Score
24
22
20
18
16
14
12
10
8
6
4
2
0
Conduct Force and Moment Wind
Develop analytical model to de
Conduct focus splinter review
Conduct Block 1 w ind tunnel te
Correlate the analytical model
Conduct w ind tunnel testing of
Conduct w ind tunnel testing of
Flight Application of Spacecra
CEV block 5 w ind tunnel testin
In-Flight development tests of
Damaged TPS flight test
31.Mar.05
5.Oct.05
3.Apr.06
3.Jul.06
15.Sep.06
1.Jun.07
1.Apr.08
1.Aug.08
1.Apr.09
1.Jan.10
16.Dec.10
1.Jul.11
Risk Response
and Risk ID in
IMS
Milestone Date
traceable between
RM Tool and IMS
73/74
Glen B. Alleman
Niwot Ridge Consulting
4347 Pebble Beach Drive
Niwot, Colorado 80503
303.241.9633
glen.alleman@niwotridge.com
Performance Based Planning®
Integrated Master Plan
Integrated Master Schedule
Earned Value
Risk Management
Proposal Support Services

Mais conteúdo relacionado

Mais procurados

NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersGlen Alleman
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management ProceduresGlen Alleman
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineGlen Alleman
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Glen Alleman
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned valueGlen Alleman
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceGlen Alleman
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio managementGlen Alleman
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11tony1234
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Design Patterns in Electronic Data Management
Design Patterns in Electronic Data ManagementDesign Patterns in Electronic Data Management
Design Patterns in Electronic Data ManagementGlen Alleman
 

Mais procurados (20)

NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio management
 
Lifecycle
LifecycleLifecycle
Lifecycle
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
IMP IMS overview
IMP IMS overviewIMP IMS overview
IMP IMS overview
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Design Patterns in Electronic Data Management
Design Patterns in Electronic Data ManagementDesign Patterns in Electronic Data Management
Design Patterns in Electronic Data Management
 

Semelhante a Building the Performance Measurement Baseline

Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIGlen Alleman
 
Integrating cost schedule and technical performance
Integrating cost schedule and technical performanceIntegrating cost schedule and technical performance
Integrating cost schedule and technical performanceGlen Alleman
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projectsGlen Alleman
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
EVMS with Technical Performance Measures
EVMS with Technical Performance MeasuresEVMS with Technical Performance Measures
EVMS with Technical Performance MeasuresGlen Alleman
 
Implementing Technical Performance Measures
Implementing Technical Performance MeasuresImplementing Technical Performance Measures
Implementing Technical Performance MeasuresGlen Alleman
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance ProgressGlen Alleman
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)Glen Alleman
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Glen Alleman
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessGlen Alleman
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
Increasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementIncreasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementGlen Alleman
 

Semelhante a Building the Performance Measurement Baseline (20)

Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
Integrating cost schedule and technical performance
Integrating cost schedule and technical performanceIntegrating cost schedule and technical performance
Integrating cost schedule and technical performance
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
EVMS with Technical Performance Measures
EVMS with Technical Performance MeasuresEVMS with Technical Performance Measures
EVMS with Technical Performance Measures
 
Implementing Technical Performance Measures
Implementing Technical Performance MeasuresImplementing Technical Performance Measures
Implementing Technical Performance Measures
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
Increasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementIncreasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value Management
 

Mais de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)Glen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Writing Proposal Text
Writing Proposal TextWriting Proposal Text
Writing Proposal TextGlen Alleman
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project RiskGlen Alleman
 

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Writing Proposal Text
Writing Proposal TextWriting Proposal Text
Writing Proposal Text
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 

Último

A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 

Último (20)

A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 

Building the Performance Measurement Baseline

  • 1. Lewis + Fowler Aerospace Capabilities Briefing (Full).pptx V5 Copyright © 2009, Niwot Ridge, Consulting LLC 1/74
  • 7. So much for our strategy of winning through technical dominance 7/74
  • 8. Product Tree SOW IPTs IMP IMS BOEs CWBS 8/74 Each element of the PMB is supportive of the others The integrated whole is the basis of a credible PMB
  • 9. Attribute Beneficial Outcome from this Attribute Maturity Flows through Program Events § Performance measurement is in units of increasing maturity of the Technical Performance Measures § Each event is a mini authorization to proceed Single outcome for each work package (AC) § Measure Physical Percent Complete at the WP level § Use 0/100 for tasks for the vast majority of work Technical Performance Measures are explicitly visible in the IMS § Connect Cost, Schedule, and Technical Performance § EV does not provide a means of adjust for “off TPM,” but make your own adjustments to the risk numbers for now Risk retirement explicitly visible in the IMS § Risk retirement is embedded in the IMS § Risk mitigation means waiting until the risk happens IMS flows vertically 1st and horizontally 2nd § All work supports the assessment of maturity § Isolate tasks dependencies within a Work Package No Event linkage except for long lead items § 0/100 requires not partial completion Decoupled dependences improves risk responsiveness § 1st round IMS defines a free flowing process § Maintaining this decoupling is key to a “dynamic” IMS that can respond to the natural changes in the program 9/74
  • 10. 10/74
  • 11. Risk Management Requirements Contractor Work Breakdown Structure (CWBS) CWBS Dictionary / SOW Integrated Master Plan (IMP) Integrated Master Schedule (IMS) Earned Value Management System Self Assessment / Award Fee Determinations / CPAR’s Technical Performance Measures (TPM) Process Metrics ü Specifications ü Work Statements ü Tailored to and outlines entire program and products ü Provides a single numbering system for the program ü States all deliverables and their components ü Follows IPT and CWBS structure ü Descriptions of work traceable to the IMS elements ü Event–driven Plan provides roadmap of processes for program ü Event–driven Schedule expands IMP into Work Packages ü Provides details and timing ü Builds in risk mitigation activities ü Connects measures of progress with measures of increasing maturity ü Connects System Performance with Continuous Technical Improvements ü Connects Cost Performance with the IMS Performance ü Determined by program execution 11/74
  • 12. Program Events Statement of Work CWBS Significant Accomplishments Accomplishment Criteria CDRLs and Deliverables Tasks Contained in Work Packages Measures the progress to plan using Physical & Complete at the Accomplishment Criteria (AC) and CWBS level Defines Aligned Aligned Aligned Aligned Aligned Completed SA’s are entry criteria for Program Events Completed Work Packages are exit criteria for Tasks Describes increasing product maturity as 0/100 or EVMS SD guidance Documents the product maturity that is aligned with SOW and CWBS Work necessary to mature products grouped by CWBS Work structure aligned to SOW 12/74
  • 13. 13/74
  • 14. 14/74
  • 15. DoD Guide DAG SEMP CWBS IMP IMS ISE Technical Reviews Event Timing of Technical Reviews X X X X X Success criteria Technical Reviews X X X X X Include entry and exit criteria for Technical Reviews in IMP/IMS X X Assess Technical Maturity in Technical Reviews X X X X Integrate SEP with: IMP/IMS, TPMs, and EVM X X X X Integrate CWBS with: Requirements specification, Statement of Work, and IMP/IMS/EVMS X X X Link risk management and mitigation plans with technical reviews, TPM, EVMS, and IMS X Integrated Reviews Include Technical Baseline Review (TBR) in IMS; X Integrated Baseline Review: plans for event based technical reviews, including entry and exit criteria Correlation of TPM’s, IMP. IMS, and EVMS X 15/74
  • 16. 16/74
  • 17. 17/74
  • 18. 18/74
  • 19. 19/74
  • 20. 20/74 Only put these on your bookshelf after you’ve read them
  • 21. 21/74 IMS IMP Describes the strategy for successful program delivery Supplemental Schedules in CAM Notebook Tasks Contained in Work Packages Accomplishment Criteria Significant Accomplishments Program Events Integrated Master Plan (IMP) § Identifies program events, significant accomplishments, and accomplishment criteria. System level, controlled document. Integrated Master Schedule (IMS) § Logic network schedule of program planned activities keyed to the imp’s accomplishment criteria Supplemental Schedule § Created (as needed) to provide lower levels of detail data within CAM notebook § Establishes the structure, parameters and basis for the integrated master schedule (IMS) development § Basis of performance measurement system; common element integrating cost, schedule, & performance § Constructed to provide integrated planning down to the work package task level, provides horizontal & vertical § Supports control account schedules and the management of day–to–day operations traceability, summarization of info and critical path identification and analysis schedules and are summarized in the IMS and part of the program’s PMB
  • 22. 22/74 Form IMP Development Team Gather Inputs Establish Criteria For Events Define And Or Derive Deliverable Products Define Events For Program And Products Define IPT Structure To Implement Product Structure Expand WBS To IPT Structure Produce The Product IMP Matrix With CWBS Data Dictionary IMS Inputs OBS Update CWBS Update Define Program Demonstration Capabilities Define Accomplishments For Each Capability Set Order Of Program Events Select Topics For IMP Narratives Define Tasks And Work Products For Each Accomplishment IMS Inputs Summary Of IMP With E/A/C Initial Approval Of IMP Demonstrate How Subject Are Managed Release To Baseline Control For Use By IMS
  • 23. … is an event–based plan depicting the overall structure of the program and the key processes and activities. It defines accomplishments and criteria for each event. With the IMP, the increasing maturity of the program is stated explicitly in the Significant Accomplishments (SA) and their Accomplishment Criteria (AC). It’s these key processes and activities that are the basis of the credibility assessment. Events are NOT milestones, they are mini–Authorizations to Proceed. These mini-ATPs are the basis of maturity assessments of the products and services of the program. Work performed beyond the upcoming Program Event is actually done “as risk.” 23/74
  • 24. 24/74
  • 25. 25/74
  • 26. 26/74
  • 27. 27/74
  • 28. 28/74
  • 29. 29/74
  • 30. 30/74
  • 31. Through PDR, the majority of the work is building the deliverables from the CDRLs. Each CDRL should be assigned to a single AC and be connected to a single PE for the defined maturity level. 31/74
  • 32. 32/74
  • 33. 33/74
  • 34. 34/74
  • 35. 35/74
  • 36. § Without an IMP there is no strategy § Without an IMP the us no place for the work to reside § Without an IMP there is no way to answer to the question: “Why are we doing this?” § Without an IMP there is no way to measure the increasing maturity of the deliverables 36/74
  • 37. 37/74 All work flows vertically from bottom up. From Work Package content to the Exit Criteria of the WP (AC), to the Significant Accomplishments (SA) to the Program Events (PE). This flow is a description of the work that produces increasing maturity.
  • 38. 38/74 The activities of a Work Package “exit” through the Accomplishment Criteria (AC). Interconnections between Work Packages at the task level should be avoided. Only 100% complete work should start the next Work Package. PE SA ACs Tasks Completing AC starts task in next AC Completed Task lands on AC
  • 40. 40/74
  • 41. Cost Performance Baseline Schedule Performance Baseline Technical Performance Baseline Perform Functional Analysis Determine Scope and Approach Develop Technical Logic Develop Technical Baseline Develop WBS Define Activities Estimate Time Durations Sequence Activities Finalize Schedule Identify Apportioned Milestones Determine Resource Requirements Prepare Cost Estimate Resource Load Schedule Finalize Apportioned Milestones Determine Funding Constraints Approve PMB 41/74
  • 42. 42/74 Program Events Define the availability of a Capability at a point in time. Accomplishments Represent requirements that enable Capabilities. Criteria Represent Work Packages that fulfill Requirements. Work Package Work Package Work Package Work Package Work Package Work Package Work Package Work package § The increasing maturing of a product or service is described through Events or Milestones, Accomplishments, Criteria, and their Work Packages. § Each Event or Milestone represents the availability of one or more capabilities. § The presence of these capabilities is measured by the Accomplishments and their Criteria. § Accomplishments are the pre–conditions for the maturity assessment of the product or service at each Event or Milestone. § This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the activities which produce deliverables. This hierarchy also describes increasing program maturity resulting from the activities contained in the Work Packages. § Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or Milestones is measured in units of “physical percent complete” by connecting Earned Value with Technical Performance Measures. The Structure of a Deliverables Based Plan Work Package
  • 43. Monthly Status Report: § Validate schedule status (start/complete/slip) § Validate work package % complete § Take earned value from % Cmplt § Identify/process cost ETCs Weekly Status Report: § Roll up of lower level schedule status § Roll up of lower level % complete or § Milestone start/complete § Milestone slip (early/late, start/complete) § Physical % Complete of tasks Weekly Status Report: § Milestone start/complete § Milestone slip (early/late, start/complete) § % complete of tasks Near term Rolling Wave Control account span IMS Activities (at Work Package level WP’s < 45 work days) 20 to 40 Workday tasks Or even weekly tasks IMS Tasks (one and two levels below WP level) IMP WBS Levels 1, 2, and 3 WBS Levels 4 and 5 WBS’s Below Work Package Planning Package 43/74
  • 44. 44/74
  • 45. 45/74
  • 46. Cost, Schedule, Technical Performance† WBS Task 100 Task 101 Task 102 Task 103 Task 104 Task 105 Task 106 †This is a Key concept. This is the part of the process that integrates the cost and schedule risk impacts to provide the basis of a credible schedule. Without Technical Performance measures, Cost and Schedule cannot show physical percent complete. Probability Density Function § Research the Project § Find Analogies § Ask Endless Questions § Analyze the Results § What can go wrong? § How likely is it to go wrong? § What is the cause? § What is the consequence? Monte Carlo Simulation Tool is Mandatory 1.0 .8 .6 .4 .2 0 Days, Facilities, Parts, People Cumulative Distribution Function Days, Facilities, Parts and People 46/74 DID–81650 calls out the details of the IMS and it’s statistical analysis
  • 47. A ship on the beach is a lighthouse to the sea – Dutch Proverb 47/74
  • 48. 48/74
  • 49. 49/74
  • 50. 50/74
  • 51. 51/74
  • 52. § In the example above, the Work Package Managers collectively come to an agreement on how the sequence of how the work will be performed within each AC. § The result is a collective ownership of the outcome. This ownership comes from the collective development of the project plan. § This process is a Product Development Kaizen (PDK) and used in major aerospace, defense and product development firms. 52/74
  • 53. 53/74
  • 54. 54/74
  • 55. 55/74
  • 56. 56/74
  • 57. 57/74
  • 58. 58/74
  • 59. 59/74
  • 60. 60/74
  • 61. 61/74
  • 62. AC: 005 Work Pkg Work Pkg Work Pkg Work Pkg AC AC:023 Work Pkg Work Pkg Work Pkg Work Pkg AC § The 100% completed work in AC:005 is needed to start the work in AC:023 § In the IMP/IMS paradigm, there is no Task-to-Task connection across Accomplishment Criteria (AC) boundaries, only within an AC § The AC-to-AC linking states “…all work in the predecessor AC must be complete before starting the successor work, assuring the minimum of rework due to partially defined requirements or partially completed products” 62/74
  • 63. PE: B PE: A SA: 001 SA: 002 SA: 003 SA: 004 PE: A Task Task Task AC: 006 § The best arrangement has the completion of Event A start the first task in Event B. § All work performed beyond the date of Event A is done at risk. § At PDR (Event A), approval to proceed Event B (CDR) is given § Only long lead items should cross Program Event boundaries § All other work terminates on the Program Event where a formal review of the planned maturity is conducted – SRR, SFR, PDR, CDR, … § This topology assures a complete assessment of “progress to plan,” is available at each Program Event 63/74 SA: 008 PE: B
  • 64. 64/74
  • 65. A Credible Performance Measurement Baseline Assures Program Management has the needed performance information to deliver on‒time, on‒budget, and on‒specification Technical Performance Measures Cost Schedule Conventional Earned Value + = § The Master Schedule used to derive Basis of Estimate (BOE) not the other way around. § Probabilistic cost estimating uses past performance and cost risk modeling. § Labor, Materiel, and other direct costs accounted for in Work Packages. § Risk adjustments for all elements of cost. Cost Baseline § Earned Value is diluted by missing technical performance. § Earned Value is diluted by postponed features. § Earned Value is diluted by non compliant quality. § All these dilutions require adjustments to the Estimate at Complete (EAC) and the To Complete Performance Index (TCPI). Technical Performance § Requirements are decomposed into physical deliverables. § Deliverables are produced through Work Packages. § Work Packages are assigned to accountable manager. § Work Packages are sequenced to form the highest value stream with the lowest technical and programmatic risk. Schedule Baseline 65/74
  • 66. 66/74
  • 67. 67/74
  • 68. 68/74
  • 69. This approach is called Product Development Kaizen and is used by Lean Six Sigma firms to ferret out the system capabilities before any technical or operational requirements are defined. Use this to reverse engineer or validate the WBS and connect WHAT with WHY before proceeding to build the CWBS or confirm the WBS. 69/74
  • 70. Update Contractor System Spec Update Program Development Allocate Functional Reqmts Update Functional System Design Develop HWCI Specifications Develop SIL Specifications Build Astp1 F-18 IRR SIL Baseline 1.0 Update SIL Test Cases Develop Prelim SIL CSCI Critical Components AstP 1,2 SSpS 1,2,3 1 2 3 4 6 7 5 8 10 9 11 13 14 15 Update AS Test I&T on CVN I&T on LHA 12 Contract Award + 15 days Systems Requirements Review (SRR) System Functional Review (SFR) HW Preliminary Design Review (PDR) System PDR EDM 1.0 Baseline EDM 2.0 Baseline Mfg Docs Available TBD TRR 1.0 EDM 7-8 TRR 70/74 § Each collection point provides an assessment of incremental mission value. § Defining these points before the project starts is the basis of measuring progress to plan. § Because then you know what done looks like before it arrives.
  • 71. Deliverables WBS Tasks and Schedule Business Need Process Invoices for Top Tier Suppliers 1st Level Electronic Invoice Submittal 1st Level Routing to Payables Department 2nd Level Payables Account Verification 2nd Level Payment Scheduling 2nd Level Material receipt verification 2nd Level “On hand” balance Updates Work Package (WP) 1 2 3 4 6 5 A B Deliverables defined in WP Terminal Node in the WBS defines the products or services that produce the products of the project Terminal node of the WBS defined by a Work Package. Tasks within the Work Package produce the Deliverables 100% Completion of the deliverables is the measure of performance for the Work Package Management of the Work Package Tasks is the responsibility of the WP Manager. A decomposition of the work needed to fulfill the business requirements 71/74
  • 72. 72/74 Maturity Action Product Product State Adjective Verb Noun Verb Complete Design Model/Sim Preliminary
  • 73. Risk: CEV-037 - Loss of Critical Functions During Descent Planned Risk Level Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete) Risk Score 24 22 20 18 16 14 12 10 8 6 4 2 0 Conduct Force and Moment Wind Develop analytical model to de Conduct focus splinter review Conduct Block 1 w ind tunnel te Correlate the analytical model Conduct w ind tunnel testing of Conduct w ind tunnel testing of Flight Application of Spacecra CEV block 5 w ind tunnel testin In-Flight development tests of Damaged TPS flight test 31.Mar.05 5.Oct.05 3.Apr.06 3.Jul.06 15.Sep.06 1.Jun.07 1.Apr.08 1.Aug.08 1.Apr.09 1.Jan.10 16.Dec.10 1.Jul.11 Risk Response and Risk ID in IMS Milestone Date traceable between RM Tool and IMS 73/74
  • 74. Glen B. Alleman Niwot Ridge Consulting 4347 Pebble Beach Drive Niwot, Colorado 80503 303.241.9633 glen.alleman@niwotridge.com Performance Based Planning® Integrated Master Plan Integrated Master Schedule Earned Value Risk Management Proposal Support Services