SlideShare uma empresa Scribd logo
1 de 9
Baixar para ler offline
ASSESSING ENTERPRISE
PROJECT RISK
Probability of Program Success P(s)
Assessing Schedule Risk is One Step
2
Probability of Success P(s)
Assesses a project’s
performance using 4 simple
metrics.
It is the Planning metric that
can be assessed using two
methods deployed by Lewis &
Fowler
 Monte Carlo Simulation
 Schedule Health
3
The Data Elements of a Project are Random Variables
Cost, Schedule, Technical Performance and Risk
 Each is drawn from a
probability
distribution.
 The shape of this
distribution has direct
impact on the
confidence of the
outcome.
 Modeling this
probability
distributions and
their outcomes is
what a Monte Carlo
tool does.
The Schedule Assessment Process
 Topology
 Task with no successors
 Tasks with no
predecessors
 Constraints
 Must Finish On
 Finish No Later Than
 Must Start On
 Start No Later Than
 Margin analysis
 Task duration
probability
distributions
 Confidence of
completing on or
before a planned
date
Schedule Health Schedule Risk
Every Manager Should Know…
5
 When will this project finish?
 Is the project’s schedule realistic and achievable?
 What will it cost when we are done?
 How is the project performing against its plan?
 What deliverables are slipping?
 How are we going to get the deliverables back on schedule?
 What does past performance say about the future performance?
 What is the impact on the schedule of any change requests?
 Is there enough schedule slack and reserve to cover the risk?
 Is there enough management reserve to cover any overrun?
 Where is the risk in the schedule?
 How can we get the work done sooner to reduce risk?
 How can we recover from any foreseen delays?
 How can we work around a problem?
EXAMPLE SCHEDULE RISK
ANALYSIS
7
Monte Carlo Risk analysis starts with a credible
schedule and defines the probabilistic behavior of
each activities and how it drives the deliverables
The Risk+ tool sets the upper and lower bounds of the possible durations
8
Date: 2/25/2009 3:34:12 PM
Samples: 300
Unique ID: 30
Name: Final Testing
Completion Std Deviation: 5.51d
95% Confidence Interval: 0.62d
Each bar represents 2d
Completion Date
Frequency
CumulativeProbability
Tue 2/11/03Mon 1/20/03 Mon 3/3/03
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16 Completion Probability Table
Prob ProbDate Date
0.05 Wed 1/29/03
0.10 Fri 1/31/03
0.15 Tue 2/4/03
0.20 Wed 2/5/03
0.25 Wed 2/5/03
0.30 Thu 2/6/03
0.35 Fri 2/7/03
0.40 Mon 2/10/03
0.45 Mon 2/10/03
0.50 Tue 2/11/03
0.55 Wed 2/12/03
0.60 Thu 2/13/03
0.65 Fri 2/14/03
0.70 Fri 2/14/03
0.75 Mon 2/17/03
0.80 Tue 2/18/03
0.85 Wed 2/19/03
0.90 Thu 2/20/03
0.95 Tue 2/25/03
1.00 Mon 3/3/03
The output of Risk+ is a Probability Distribution Function and a
Cumulative Distribution of all the possible dates that “watched”
activity could take.
This shows the Confidence in the target date – 2/10/3
It shows 40% chance of completely on or before 2/10/03
Beneficial Outcomes
 A confidence metric that the project will complete
on or before the planned date
 Measures of the integrity of the activity network
 Overly constrained plan
 Activities with no dependencies
 Visibility into the Probability of Success from a
schedule point of view

Mais conteúdo relacionado

Mais procurados

Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
Glen Alleman
 

Mais procurados (20)

EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
Monte Carlo Simulation for Agile Development
Monte Carlo Simulation for Agile DevelopmentMonte Carlo Simulation for Agile Development
Monte Carlo Simulation for Agile Development
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management Guidance
 
Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Estimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulationEstimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulation
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program success
 

Semelhante a Assessing Enterprise Project Risk

Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
Mihai Buta
 
Project-Planning
Project-PlanningProject-Planning
Project-Planning
Ron Drew
 
2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt
AsBali1
 

Semelhante a Assessing Enterprise Project Risk (20)

Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
 
Project Risk Analysis with Risk Event and Event Chain
Project Risk Analysis with Risk Event and Event ChainProject Risk Analysis with Risk Event and Event Chain
Project Risk Analysis with Risk Event and Event Chain
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Improved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentImproved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric Assessment
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
Free-ebook-rex-black advanced-software-testing
Free-ebook-rex-black advanced-software-testingFree-ebook-rex-black advanced-software-testing
Free-ebook-rex-black advanced-software-testing
 
Risk analysis
Risk analysis Risk analysis
Risk analysis
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk AnalysisAdopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
 
4-ProjectPlanning.ppt
4-ProjectPlanning.ppt4-ProjectPlanning.ppt
4-ProjectPlanning.ppt
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project-Planning
Project-PlanningProject-Planning
Project-Planning
 
2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt
 
Rsc 04
Rsc 04Rsc 04
Rsc 04
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Project Assignments PowerPoint Presentation Slides
Project Assignments PowerPoint Presentation Slides Project Assignments PowerPoint Presentation Slides
Project Assignments PowerPoint Presentation Slides
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7critic
 

Mais de Glen Alleman

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 

Último

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Último (20)

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 

Assessing Enterprise Project Risk

  • 2. Assessing Schedule Risk is One Step 2 Probability of Success P(s) Assesses a project’s performance using 4 simple metrics. It is the Planning metric that can be assessed using two methods deployed by Lewis & Fowler  Monte Carlo Simulation  Schedule Health
  • 3. 3 The Data Elements of a Project are Random Variables Cost, Schedule, Technical Performance and Risk  Each is drawn from a probability distribution.  The shape of this distribution has direct impact on the confidence of the outcome.  Modeling this probability distributions and their outcomes is what a Monte Carlo tool does.
  • 4. The Schedule Assessment Process  Topology  Task with no successors  Tasks with no predecessors  Constraints  Must Finish On  Finish No Later Than  Must Start On  Start No Later Than  Margin analysis  Task duration probability distributions  Confidence of completing on or before a planned date Schedule Health Schedule Risk
  • 5. Every Manager Should Know… 5  When will this project finish?  Is the project’s schedule realistic and achievable?  What will it cost when we are done?  How is the project performing against its plan?  What deliverables are slipping?  How are we going to get the deliverables back on schedule?  What does past performance say about the future performance?  What is the impact on the schedule of any change requests?  Is there enough schedule slack and reserve to cover the risk?  Is there enough management reserve to cover any overrun?  Where is the risk in the schedule?  How can we get the work done sooner to reduce risk?  How can we recover from any foreseen delays?  How can we work around a problem?
  • 7. 7 Monte Carlo Risk analysis starts with a credible schedule and defines the probabilistic behavior of each activities and how it drives the deliverables The Risk+ tool sets the upper and lower bounds of the possible durations
  • 8. 8 Date: 2/25/2009 3:34:12 PM Samples: 300 Unique ID: 30 Name: Final Testing Completion Std Deviation: 5.51d 95% Confidence Interval: 0.62d Each bar represents 2d Completion Date Frequency CumulativeProbability Tue 2/11/03Mon 1/20/03 Mon 3/3/03 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0.02 0.04 0.06 0.08 0.10 0.12 0.14 0.16 Completion Probability Table Prob ProbDate Date 0.05 Wed 1/29/03 0.10 Fri 1/31/03 0.15 Tue 2/4/03 0.20 Wed 2/5/03 0.25 Wed 2/5/03 0.30 Thu 2/6/03 0.35 Fri 2/7/03 0.40 Mon 2/10/03 0.45 Mon 2/10/03 0.50 Tue 2/11/03 0.55 Wed 2/12/03 0.60 Thu 2/13/03 0.65 Fri 2/14/03 0.70 Fri 2/14/03 0.75 Mon 2/17/03 0.80 Tue 2/18/03 0.85 Wed 2/19/03 0.90 Thu 2/20/03 0.95 Tue 2/25/03 1.00 Mon 3/3/03 The output of Risk+ is a Probability Distribution Function and a Cumulative Distribution of all the possible dates that “watched” activity could take. This shows the Confidence in the target date – 2/10/3 It shows 40% chance of completely on or before 2/10/03
  • 9. Beneficial Outcomes  A confidence metric that the project will complete on or before the planned date  Measures of the integrity of the activity network  Overly constrained plan  Activities with no dependencies  Visibility into the Probability of Success from a schedule point of view