Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
Update on Tysons Transportation Projects - April 1, 2020
1. Update on Tysons Transportation Projects
Tysons Partnership – Transportation Council
April 1, 2020
Tom Biesiadny, Director
Fairfax County Department of Transportation
2. Presentation Overview
• Transportation Projects
Major Roadway Projects (Tysons-wide)
Table 7B Projects
Grid of Streets
Tysons Circulator Service
Tysons Metrorail System Access Management Projects
Neighborhood Intersection Improvements Study
Bike Lanes and Bikeshare
2
3. Major Roadway Projects (Tysons-wide)
Tysons-wide Improvements:
• The Comp Plan
Amendment identified 17
Tysons-wide roadway
improvements necessary to
support the anticipated
growth.
• 1 of the 17 is complete
• 1 of the 17 is under
construction
• 1 is in land acquisition
• 4 others in study,
preliminary engineering, or
design 3
4. Route 7 Bridge over Dulles Toll Road –
Completed May 2018
4
Major Roadway Projects (Cont.)
5. Jones Branch Connector – Completion Spring 2020
5
• Two Lanes in Each Direction Open to Traffic in November 2019
• Pedestrian walkway completed: February 2020
Major Roadway Projects (Cont.)
6. Route 7 Widening -
(Reston Avenue to Dulles Toll Road)
6
• Widen Route 7 from 4 to 6 lanes from Jarrett Valley Drive to Reston Avenue
Intersection improvements
Shared use trail on both sides
Upgraded bus stops
• Total Project Estimate: $314 million
VDOT is the project administrator with County input
• Project Schedule:
Contract awarded: August 2018
Construction start: Spring 2019
Estimated completion: Fall 2024
• Current Status:
Completed early improvements at Baron Cameron Avenue and opened third left-turn lane
from Route 7 to Baron Cameron Avenue in August 2019.
Design plans approved for construction on 10/2/19.
Noise analysis finalized in November 2019; reviewed and approved by FHWA and VDOT. All
environmental permits (DEQ, USACE, VMRC) have been issued.
Major Roadway Projects (Cont.)
7. Route 7 Widening (Route 123 to I-495)
7
• Widen existing 6 lanes to 8 lanes with pedestrian improvements
• Bus Rapid Transit proposed through the corridor (Envision Route 7 – NVTC)
• Route 7 widening study is being coordinated with the BRT study
• BRT final recommendations: Spring 2020
• Design will continue following BRT lane configuration recommendations
Major Roadway Projects (Cont.)
8. I-495 Overpass at Tysons Corner Center
8
• Tysons-Old Meadow Road Bike/Ped Improvements
Shared use trail from the intersection of Route 123 and Old Meadow Road
east of I-495
• Total Project Estimate: $12.2 million
$4.6 million Service District Funds
• Project Schedule:
Design approval: November 2018
Right of way acquisition: Fall 2019 – Summer 2020
Construction phase: Spring 2021 – Spring 2022
Major Roadway Projects (Cont.)
10. Other Major Roadway Projects
10
Major Roadway Projects (Cont.)
• Alternative analysis underway, three alternatives are being
evaluated
• Draft recommendations to be shared with stakeholders and
public in Fall 2020
• $10.5 million in service district funds approved for design
and land acquisition
Route 7 Widening
(I-495 to I-66)
Project #12
• Pre-scoping to start in early 2020
• Will include aerial imaging and ground surveys
• $1 million in service district funds approved for
study/engineering
Ramp from
Greensboro Drive to
Dulles Toll Road
Project #6
11. Tysons Table 7B Projects
11
• Super Street Option selected in the previous study (30%
design completed)
• Included in the Route 123 corridor study
• Multiple options being considered
Route 123 Widening
(I-495 to the Dulles
Connector Road)
• Staff continues analysis of the Comprehensive Plan
recommendation to widen Route 123 from 6 to 8 lanes
• Multiple options being considered
Route 123 Widening
(I-495 to International
Drive)
• Consultant selection completed
• Analysis of Future Conditions: Jan 2020
• Final recommendation and phasing analyses: Summer
2020
Both Projects
12. Tysons Table 7B Projects (Cont.)
12
• Modification to the eastbound off-ramp from the Dulles
Access Road to Route 123
• Two preferred alternatives: Braided Ramp and an
Auxiliary Lane concepts
• Included in the Route 123 corridor study
Cleveland Ramp
• To allow additional capacity
• Advancing to 15% design based on charrette
recommendations
• Two concepts are being considered
• Stakeholder meetings are anticipated in Spring 2020
Route 7/Route 123
Interchange
• To I-495 SB Ramp
• Study to be initiated in the future
Gallows Road at
Gallows Branch
14. Lincoln Street
14
• Street to connect Route 123 to Magarity Road.
• Will allow access to existing/approved developments along Old Meadow
Road from Magarity Road.
• Additional access to residential units on Old Meadow Road.
• The Board has approved a total of $8.2 million for study and design
• Design work underway
Feasibility study completed
15% design completed
Est. completion: June 2020
• Construction begins in 2024
• Estimated project completion: 2025
15. Old Meadow Road Realignment
15
• This project is a part of Dulles Rail Phase I funding
• Design is 100% complete
• Utility Relocation: Complete in Spring 2020
One utility is remaining and ongoing
• Construction start: Spring 2020
After utility relocation, construction to be
completed in 4 phases with no total road
closures
• Phase 1 and 2 – Major road construction
• Phase 3 and 4 – ADA ramps and final
pavement
• Estimated completion: Summer 2020
Cable Relocation
17. Transit Service
17
• Enhance transit service in the Tysons area
• Support transit-oriented development
• Provide transit connections from the Metrorail stations to areas of Tysons not
within walking distance
Purpose
• 2009 - Neighborhood routes from McLean and Vienna
• 2013 - I-495 Express Lanes service from Burke Centre, Lorton, and Springfield
• 2014 - Circulator routes serving Tysons’ Metrorail Stations
• 2019 – New mid-day and late-night service on route 467 from Vienna
neighborhoods to Tysons
Implemented Service
• Bus Rapid Transit along Route 7 from Tysons to Alexandria
• Work groups are evaluating alignment, station locations, and roadway design
• Final BRT report to be completed by Fall 2020
• 2021 - Route optimization study will re-evaluate the Tysons routes and better
align bus service with evolving demands
• DRPT Study considering additional express service to Tysons using I-66
Outside of the Beltway toll revenues
Future Improvements
18. Transit Service (Cont.)
18
• Service began July 24, 2014
• Service changes in May 2015 and June 2016 in response
to passenger feedback
• Weekend service implemented on Route 424 in June
2016
Tysons Circulator
Service
• Overall ridership is increasing in FY 2019 compared to FY
2018 for the following routes:
• 422 , 423, 424, 721, and 724Ridership Trends
• After completion of Jones Branch extension across I-495,
planning staff will evaluate realigning Route 424 to serve
the north side of McLean Metrorail Station
• Tysons – Vienna Route Optimization Study (2021)
Future Improvements
19. Tysons Metrorail Station Access Management Study
19
• To prioritize access improvements to the Metrorail
stations in Tysons.
• Study completed in 2011
Purpose of (TMSAMS)
• Staff recommendations approved by the Board in May
2012
• Staff is currently working to design/construct these
projects
Timeline
• 34 of 41 projects completed
• 5 in Construction/Utility Relocation
• 1 in Land Acquisition
• 1 in Design
Progress Update
21. TMSAMS (Cont.)
21
• Construction completed: January 2019
• Ribbon cutting ceremony completed
Vesper Trail from
Vesper Court to
Route 7
22. TMSAMS (Cont.)
• North side construction completed: October 2018
• South side construction completed: August 2018
Route 7 Walkways on
Both Sides under
Route 123
North Side South Side
23. TMSAMS (Cont.)
23
• Portion of work from south of DTR to Jarrett Valley
completed in May 2018
• The remaining construction will be included in the Route
7 Widening project from Jarrett Valley to Reston Parkway
• Estimated completion: July 2024
Route 7 Walkway
from Dulles Toll Road
to Beulah Road
• Design and land acquisition completed
• Construction is 50% complete
• Estimated completion: Fall 2020
Scotts Run Walkway
through Scotts Run
Stream Valley Park
• Design and land acquisition completed
• Utility relocation complete
• Construction is 50% complete
• Estimated completion: Spring 2020
Route 123 from Great
Falls Street to McLean
Station
24. 24
Tysons Bike Lanes
More bike lanes will be
added through future
repaving and development
Vesper Trail was completed in
January 2019
Jones Branch Connector
provides bike/ped connection
to McLean Metrorail Station
in February 2020.
Scotts Run Trail is under
construction.
Dolley Madison Blvd Trail is
under construction.
25. 25
Tysons BikeShare
14 of 15 bikeshare
stations planned for
launch currently
installed
18 additional
stations underway
(Providence Dist.)
Approximately
8,600 trips taken in
Tysons in CY2019,
an increase of 60%
from CY2018.
Nearby Merrifield
and City of Falls
Church launched in
May 2019
26. Tysons Neighborhood Traffic Study
26
•Evaluate existing (at the time 2008) and future (2030) traffic
impacts and potential mitigation measures for 30 intersections in
the areas surrounding Tysons
•13 intersections were shown to have either AM, PM, or both peak
hours failing (LOS F is considered failing) under 2008 conditions
Purpose
•Intersections were chosen based on input from Dranesville,
Providence, and Hunter Mill Supervisors
•Staff evaluated 2030 conditions and potential mitigation measures
and decided upon a series of proposed next steps
Selection Method
•Annually monitor locations that currently do not fail that are
projected to potentially fail by 2030
•Locations in the “Monitor” category will be evaluated regularly,
with potential solutions generated for locations with LOS
deteriorating towards failure
•Feasibility studies, design, construction activities are underway for
specific projects.
Proposed Next Steps
28. Tysons Neighborhood Study (Cont.)
28
•Finalizing detailed traffic analysis of Offset T-Intersection
alternative
•Public information meeting: Spring 2020 (upon end of current
restrictions)
•Estimated completion of study: June/July 2020
Lewinsville Road and
Spring Hill Road
•Part of the VDOT Route 7 Widening Project (Jarrett Valley Drive to
Reston Avenue)
•Concept for this intersection is a displaced left turn
•Estimated Completion: July 2024
Lewinsville Road and
Leesburg Pike
•Preferred T-Intersection Improvements Option A.1 to be advance
to design
•Advance property acquisition completed in October 2018
•Walkway connections to Balls Hill Rd/Churchill Rd, Balls Hill
Rd/Spring Side Way and Old Dominion Dr/Forestwood Dr.
•Design to begin in Spring 2020
Balls Hill Road and
Old Dominion Drive
Projects Advancing:
29. Tysons Neighborhood Study (Cont.)
29
• Dolley Madison Boulevard Corridor Study
• Includes the following Neighborhood Study
intersections:
Dolley Madison Boulevard at Lewinsville Road/ Great
Falls Street
Dolley Madison Boulevard at Old Dominion Drive
Lewinsville Road at Balls Hill Road
• Also includes:
Great Falls Street and Chain Bridge Road
Lewinsville Road and Old Maple Drive
Dolley Madison Boulevard and Ingleside Avenue
Old Dominion Drive and Ingleside Avenue/Park Avenue
• Analysis of short-term and long-term mitigation measures has been completed
• A community meeting was conducted in June 2019
• A survey concerning mitigation measures was conducted during Summer 2019
• A meeting was held with the District Supervisor in February 2020 to discuss next steps
• The next community meeting is proposed for Fall 2020
30. Silver Line Phase II
30
• Overall Phase 2 – 98% complete
• Package A (Rail, System & Stations) – 98% complete
• Package B (Rail Yard at Dulles)- 98% complete
Project Status
•Dynamic testing, site inspections, and walkdowns ongoing
•Property conveyances and maintenance agreements in final
review
•Wiehle Reston East Station scheduled shutdowns for testing
General Activities
•Concrete Panel Deficiencies
•Fouled Ballast at Dulles Rail Yard
•Concrete Ties/Cross-Level Deficiencies
MWAA and WMATA
Concerns
31. Silver Line Phase II (Cont.)
31
•Civil – Utilities relocation work completed; paving operations,
stormwater management ponds, storm drains ongoing
•Stations – Interior finishes, station clean up, elevator and
escalator testing, and lighting installation and other electrical
work ongoing
•Systems – Traction Power Substations (TPSS) and station
equipment testing and final connections, all TPSS have been
energized providing power to the contact rails, communications
cabling installation and testing, testing of train control systems,
and preparing track for dynamic testing
•Rail Yard – Punchlist work for all building at the yard, remedial
track work and installation of hoist equipment ongoing
Construction Status
•Package A (Rail, System & Stations) completion – Mid 2020
(Target)
•Package B (Rail Yard at Dulles) completion – Fall 2020 (Target)
•WMATA Board to establish Revenue Operations Date - TBD
Project Schedule
This a map of the 17 Tysons-wide roadway projects that are approved in the Comprehensive Plan.
2 of the 17 projects are under construction, and 4 others are in study, preliminary engineering, or design.
This is a picture of the Route 7 pedestrian bridge over the Dulles Toll Road that was completed in May 2018.
The widening of Route 7 over the Dulles Toll Road had a total project cost of approximately $44.82 million and was fully funded through NVTA and Bridge funds. The ribbon cutting ceremony was held on May 22, 2018. The project widened Route 7 from four lanes to six lanes, approximately from just west of Jarrett Valley Drive to just west of Tyco Road, for a total length of approximately 0.4 miles. The decks of the two existing bridges over Dulles Airport Toll Road (DTR) were replaced and widened in the middle to accommodate one extra lane on each side of the bridge. A shared use path was built for pedestrians and bikes to travel in each direction.
This is a picture of the Jones Branch Connector project that is currently in construction. As of December 2018 one lane in each direction is open. The pedestrian walkway is scheduled to be completed in February 2020, and the entire project should be completed by Spring 2020.
The Jones Branch Connector has a total project estimate of $60 million, and is fully funded by the following revenues: $13.5 million in state Revenue Sharing (RS); $28 million in local commercial and industrial tax and proffer revenues; and, $18.5 million in federal Regional Surface Transportation Program (RSTP) funds.
The Route 7 Widening (Jarrett Valley Drive/Dulles Toll Road to Reston Avenue) has a total project estimate of approximately $314 million and is fully funded from the following sources: $104 million in federal RSTP funding; approximately $120 million in state funding approved by the Commonwealth Transportation Board on June 15, 2016; and $10 million approved by the Northern Virginia Transportation Authority (NVTA) on July 14, 2016. CTB approved the award of a contract July 18, 2018 to Shirley LLC in the amount of $252,871,777 for design and construction of the project. A project kick-off meeting is scheduled for Fall 2018. Construction on the project is scheduled to start in Spring 2019.
This project will build a pedestrian and bicycle bridge over the beltway, in the vicinity of Route 123 and I-495, to improve bicycle and pedestrian safety and connectivity in the Tysons area. Improvements include a new 10-foot shared-use path from near Tysons One Place and Fashion Boulevard to Route 123 and Old Meadow Road via a new pedestrian and bicycle bridge over I-495; the path will mostly follow Old Meadow Road.
This is a picture of what the completed project is expected to look like.
Projects resulting from further analysis of the road network and planned land use densities included in Comprehensive Plan Amendment was approved by the Board on March 14, 2017.
Refinement of concepts for Route 123 inside the Beltway and improvement option identification for Route 123 outside the Beltway.
Evaluation of options to reconfigure the intersection of Route 7 and Route 123 to accommodate future traffic demand.
The conceptual grid of streets adopted in the Comprehensive Plan as Map 7 sets forth a street network in Tysons that provides greater network diversity, more direct connections among various locations, and accommodates a variety of modes of transportation. It is envisioned that the grid will be implemented primarily through the redevelopment process.
This map illustrates progress on the implementation of the conceptual Tysons road network as of August 2018. The map shows the existing road network prior to the adoption of the conceptual Tysons network in the Comprehensive Plan (“Existing”), network links that have been implemented since adoption of the Plan (“Constructed”), and network links that have been approved (“Approved Through Rezoning”) but not yet built, or are currently proposed (“Pending Rezoning”) by a rezoning application. The County will continue to monitor and report on the implementation of the grid of streets annually.
Lincoln Street, as part of the future Tysons’ Grid of Streets Plan, will provide connection between Old Meadow Road and Magarity Road as a two-lane local roadway with multimodal accommodations.
The Plan calls for a robust transit network to provide alternatives to automobile travel and to support a balance between land use and transportation. As of Spring 2018, 13 bus routes operated circulator, express, peak and local bus service in Tysons.
The TMSAMS study was completed in 2011. Staff is currently working to complete design and construction of these projects.
This is a map that shows all the TMSAMS project locations.
Construction was completed on Vesper Trail in January 2019.
The Vesper Trail includes 2,025 linear feet of a shared use path connecting Vesper Court to Route 7 and the Spring Hill Metrorail Station. The trail will be lighted and include one 90-foot bridge. It is currently under construction and is scheduled for completion by Fall 2018.
Construction was completed on Vesper Trail in January 2019.
The Vesper Trail includes 2,025 linear feet of a shared use path connecting Vesper Court to Route 7 and the Spring Hill Metrorail Station. The trail will be lighted and include one 90-foot bridge. It is currently under construction and is scheduled for completion by Fall 2018.
The Scott’s Run Trail project will provide 2,676 linear feet of new 8-foot wide pedestrian trail connecting Magarity Road at Westgate Elementary School to Colshire Meadow Drive near the McLean Metrorail Station. Its purpose is to facilitate pedestrian access to/from the Metrorail station for local residents. The trail will be lighted and include a 90’ bridge over Scotts Run Stream and a 50’ bridge over a tributary. The trail will be located within Scott’s Run Stream Valley Park and Westgate Park. Construction is set to begin in Spring 2019.
Jones Branch Connector will provide new bike/ped connections between Tysons and McLean
In Fall 2016, after approximately ten miles of bike lanes were added in Tysons, the Tysons Partnership and FCDOT brought Capital Bikeshare to Tysons. The Tysons Partnership partners with the County to financially support the cost of launching and running the system. In January 2016, the Board of Supervisors approved a $1.7 million plan to launch the Capital Bikeshare system in Reston and Tysons. Capital Bikeshare launched on October 21, 2016, with eight of the planned 14 stations. Since then, five additional stations have been installed and two more stations are in planning and design.
Level of service
13 intersections were chosen based on Supervisors input
Talk about purpose of Dolley Madison Study – looking for short term improvements within the corridor that can be done with minimal ROW impacts. Dolley Madison in many areas is constrained. Looking for improvements that can address traffic issues now but also hold up for the next 10 years but do not require right of way.