AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
Royal Lake Dredging and Restoration
1.
2. Dredging Program and Project Background
Project Benefits
Royal Lake Conditions
Phased Approach
Dredging Methods and Alternatives
Park Access and Community Coordination
Next Steps
Royal Lake: Meeting Agenda
3. History
– Lakes previously dredged by DPWES Stormwater
– Limited to small quantities
– Dewatered on site
Lake Barton completed in 2011
Currently working on:
– Huntsman Lake, Woodglen Lake, Royal Lake
Dredging and Lake Restoration Program
4. Completed Data Collection
Developing Lake Dredging and Management Plan
Community coordination at design and construction
phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: Pardon Our Dust meeting
December 2013: Final Design
Construction in Fiscal Year 2015 (July 2014)
Royal Lake Dredging and Restoration
Project Timeline and Coordination
5. Restore sediment pool capacity
– Downstream water quality benefits
– Lake water quality
– Aesthetics
Improve lake water quality and habitat
Provide long term maintenance improvements
Project Goals and Benefit
6. Lake Barton Dredging and Restoration
Area Treated
(acres)
Phosphorous Removal Nitrogen Removal Sediment Removal
544 77,000 lbs dredged 115,500 lbs dredged 38,500 tons dredged
Annual benefit from
increased trapping
efficiency
130 lbs/year 200 lbs/year 65 tons/year
7. Royal Lake Facts
Drainage area =
2,477 acres (3.67 square miles)
Lake surface area =
37.5 acres
Sediment pool capacity =
416,000 cubic yards (CY)
Current sediment in lake =
100,400 CY
Estimated annual sediment load =
4,400 CY
50 feet
100,400 CY
13. Dredging Methods and Alternatives
1. Mechanically dredge
deposited sediment and
haul wet
2. Drain lake and dry
deposited sediment in
place before hauling
14. PRE-DREDGING:
An estimated
35,000 cubic yards
of sediment had
accumulated in
the lake, forming
islands and
reducing water
levels to less than
three feet in most
areas.
Lake Barton Example
19. North Park Lake Example Allegheny County, Pennsylvania
Dredging:
The lake was drained
and the sediment was
dried in-place.
20. North Park Lake Example Allegheny County, Pennsylvania
Temporary Diversion
Channels
Equipment Working
on Next Slide
21. North Park Lake: Dredging Allegheny County, Pennsylvania
Truck Wash
Temporary
Diversion Channel
Low Pressure
Excavator
Bulldozer
Bulldozer
Excavator
and DozerTruck Access
Staging
22. General Sequence
– Establish access and staging areas
– Conduct dredging utilizing barges
– Haul wet sediment to disposal site
for drying
Benefits
– Less weather dependent
– Quicker initial start to dredging
– Less potential for schedule
extensions or delay
Concerns
– Increased sediment handling effort
at disposal area
– Potentially higher cost
Dredge Alternative – In the Wet
23. General Sequence
– Initiate drawdown of lake
– Establish access and staging areas
– Establish diversion channels within lake
– Conduct dredging
Benefits
– Higher daily sediment removal rates
– Minimal sediment handling effort at disposal
area
– Potentially lower cost
Concerns
– Very weather dependent
– Higher potential for delays due to weather
– Typically more odor from sediment exposed
– Need to relocate/salvage fish
Dredge Alternative – In the Dry
24. In-lake forebay
Wetland planting
Shoreline stabilization
Fish habitat
Fish stocking
Lake Restoration
Fish habitat created
from salvaged trees
Lake Barton:
Fish stocking by Virginia Game and Inland Fisheries
31. Staging Area 1 Potential Expansion
Berm/Cofferdam
to be built
Area to be dewatered and
backfilled to expand staging
area after berm/cofferdam
is built
34. Access During Construction
Public Access:
Pedestrian gates will be
provided. Access
through work areas and
trails around the lake
after work hours.
35. Community coordination at design and construction phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: “Pardon Our Dust” meeting
December 2013: Final Design
Construction in Fiscal Year 2015 (Starts July 2014)
Project Duration:
– Phase 1, Base Dredge: Dredge 40,000 CY = 5 to 6 Months
– Phase 2, Full Dredge: 9 to 12 Months
Royal Lake Dredging and Restoration
Project Timeline and Coordination
36. Contacts:
Martin Chang, Project Manager
703-324-5825 | Martin.Chang@fairfaxcounty.gov
Dipmani Kumar, Section Chief
703-324-4612 | Dipmani.Kumar@fairfaxcounty.gov
http://www.fairfaxcounty.gov/dpwes/stormwater/
Royal Lake DredgingandRestoration
http://www.fairfaxcounty.gov/NVSWCD/ http://www.fairfaxcounty.gov/parks/