SlideShare uma empresa Scribd logo
1 de 36
Baixar para ler offline
 Dredging Program and Project Background
 Project Benefits
 Royal Lake Conditions
 Phased Approach
 Dredging Methods and Alternatives
 Park Access and Community Coordination
 Next Steps
Royal Lake: Meeting Agenda
 History
– Lakes previously dredged by DPWES Stormwater
– Limited to small quantities
– Dewatered on site
 Lake Barton completed in 2011
 Currently working on:
– Huntsman Lake, Woodglen Lake, Royal Lake
Dredging and Lake Restoration Program
 Completed Data Collection
 Developing Lake Dredging and Management Plan
 Community coordination at design and construction
phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: Pardon Our Dust meeting
 December 2013: Final Design
 Construction in Fiscal Year 2015 (July 2014)
Royal Lake Dredging and Restoration
Project Timeline and Coordination
 Restore sediment pool capacity
– Downstream water quality benefits
– Lake water quality
– Aesthetics
 Improve lake water quality and habitat
 Provide long term maintenance improvements
Project Goals and Benefit
Lake Barton Dredging and Restoration
Area Treated
(acres)
Phosphorous Removal Nitrogen Removal Sediment Removal
544 77,000 lbs dredged 115,500 lbs dredged 38,500 tons dredged
Annual benefit from
increased trapping
efficiency
130 lbs/year 200 lbs/year 65 tons/year
Royal Lake Facts
 Drainage area =
2,477 acres (3.67 square miles)
 Lake surface area =
37.5 acres
 Sediment pool capacity =
416,000 cubic yards (CY)
 Current sediment in lake =
100,400 CY
 Estimated annual sediment load =
4,400 CY
50 feet
100,400 CY
Royal Lake
Royal Lake: Sediment Thickness
Royal Lake: Water Depth
Royal Lake: Dredging Areas
 Phase 1: Base Dredge = 40,000 CY
 Phase 2: Up to an additional 60,000 CY
Zone D
12,400 CY
Royal Lake: Partial Drawdown
Dredging Methods and Alternatives
1. Mechanically dredge
deposited sediment and
haul wet
2. Drain lake and dry
deposited sediment in
place before hauling
PRE-DREDGING:
An estimated
35,000 cubic yards
of sediment had
accumulated in
the lake, forming
islands and
reducing water
levels to less than
three feet in most
areas.
Lake Barton Example
Lake Barton Example: Pre-Dredging
LakeBartonExample: DredginginProgress
Dredging:
Dredging took
place without
draining the lake.
LakeBartonExample: DredginginProgress
Lake Barton Example: Disposal Site
North Park Lake Example Allegheny County, Pennsylvania
Dredging:
The lake was drained
and the sediment was
dried in-place.
North Park Lake Example Allegheny County, Pennsylvania
Temporary Diversion
Channels
Equipment Working
on Next Slide
North Park Lake: Dredging Allegheny County, Pennsylvania
Truck Wash
Temporary
Diversion Channel
Low Pressure
Excavator
Bulldozer
Bulldozer
Excavator
and DozerTruck Access
Staging
 General Sequence
– Establish access and staging areas
– Conduct dredging utilizing barges
– Haul wet sediment to disposal site
for drying
 Benefits
– Less weather dependent
– Quicker initial start to dredging
– Less potential for schedule
extensions or delay
 Concerns
– Increased sediment handling effort
at disposal area
– Potentially higher cost
Dredge Alternative – In the Wet
 General Sequence
– Initiate drawdown of lake
– Establish access and staging areas
– Establish diversion channels within lake
– Conduct dredging
 Benefits
– Higher daily sediment removal rates
– Minimal sediment handling effort at disposal
area
– Potentially lower cost
 Concerns
– Very weather dependent
– Higher potential for delays due to weather
– Typically more odor from sediment exposed
– Need to relocate/salvage fish
Dredge Alternative – In the Dry
 In-lake forebay
 Wetland planting
 Shoreline stabilization
 Fish habitat
 Fish stocking
Lake Restoration
Fish habitat created
from salvaged trees
Lake Barton:
Fish stocking by Virginia Game and Inland Fisheries
Royal Lake: Shoreline Restoration
Royal Lake: Shoreline Restoration
Royal Lake
Existing
Conditions
Shoreline Protection Options
Fish Habitat Structures
Royal Lake: Site Access and Staging
Optional?
Royal Lake: Site Access and Staging
Staging Area 1 Potential Expansion
Berm/Cofferdam
to be built
Area to be dewatered and
backfilled to expand staging
area after berm/cofferdam
is built
Royal Lake: Dewatering Basin
Inactive
Dewatering Basin
Access During Construction
Public Access:
The park will remain
open and existing
parking lot will be
available.
Access During Construction
Public Access:
Pedestrian gates will be
provided. Access
through work areas and
trails around the lake
after work hours.
 Community coordination at design and construction phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: “Pardon Our Dust” meeting
 December 2013: Final Design
 Construction in Fiscal Year 2015 (Starts July 2014)
 Project Duration:
– Phase 1, Base Dredge: Dredge 40,000 CY = 5 to 6 Months
– Phase 2, Full Dredge: 9 to 12 Months
Royal Lake Dredging and Restoration
Project Timeline and Coordination
Contacts:
 Martin Chang, Project Manager
703-324-5825 | Martin.Chang@fairfaxcounty.gov
 Dipmani Kumar, Section Chief
703-324-4612 | Dipmani.Kumar@fairfaxcounty.gov
 http://www.fairfaxcounty.gov/dpwes/stormwater/
Royal Lake DredgingandRestoration
http://www.fairfaxcounty.gov/NVSWCD/ http://www.fairfaxcounty.gov/parks/

Mais conteúdo relacionado

Mais procurados

Subject cataloging a review
Subject cataloging   a reviewSubject cataloging   a review
Subject cataloging a review
Ime Amor Mortel
 

Mais procurados (20)

Institutional Repositories
Institutional RepositoriesInstitutional Repositories
Institutional Repositories
 
Geographical sources 1
Geographical sources 1Geographical sources 1
Geographical sources 1
 
UGC NET - Unit 3 (INFORMATION RESOURCES)
UGC NET - Unit 3 (INFORMATION RESOURCES)UGC NET - Unit 3 (INFORMATION RESOURCES)
UGC NET - Unit 3 (INFORMATION RESOURCES)
 
Dissertation research proposal
Dissertation research proposalDissertation research proposal
Dissertation research proposal
 
INTERNET AND E-MAIL IN ‎LIBRARIES
INTERNET AND E-MAIL IN ‎LIBRARIESINTERNET AND E-MAIL IN ‎LIBRARIES
INTERNET AND E-MAIL IN ‎LIBRARIES
 
Intellectual Freedom Fin
Intellectual Freedom FinIntellectual Freedom Fin
Intellectual Freedom Fin
 
What is e resource
What is e resourceWhat is e resource
What is e resource
 
Soft skills for librarian
Soft skills for librarian Soft skills for librarian
Soft skills for librarian
 
Electronic information resources for teachers and students
Electronic information resources for teachers and studentsElectronic information resources for teachers and students
Electronic information resources for teachers and students
 
The Role of Librarians in the 21st Century
The Role of Librarians in the 21st CenturyThe Role of Librarians in the 21st Century
The Role of Librarians in the 21st Century
 
COMMUNITY INFORMATION SERVICE 2.0: APPLICATION OF WEB 2.0 TOOLS IN DESIGNING...
COMMUNITY INFORMATION SERVICE 2.0: APPLICATION OF  WEB 2.0 TOOLS IN DESIGNING...COMMUNITY INFORMATION SERVICE 2.0: APPLICATION OF  WEB 2.0 TOOLS IN DESIGNING...
COMMUNITY INFORMATION SERVICE 2.0: APPLICATION OF WEB 2.0 TOOLS IN DESIGNING...
 
Subject cataloging a review
Subject cataloging   a reviewSubject cataloging   a review
Subject cataloging a review
 
International Digital Library Initiatives
International Digital Library InitiativesInternational Digital Library Initiatives
International Digital Library Initiatives
 
Lecture 1c: Collection Development
Lecture 1c: Collection DevelopmentLecture 1c: Collection Development
Lecture 1c: Collection Development
 
SEARS LIST OF SUBJECT HEADINGS (PRACTICE)
SEARS LIST OF SUBJECT HEADINGS (PRACTICE)SEARS LIST OF SUBJECT HEADINGS (PRACTICE)
SEARS LIST OF SUBJECT HEADINGS (PRACTICE)
 
New trends and skill in library automation: impact of Artificial Intelligence...
New trends and skill in library automation: impact of Artificial Intelligence...New trends and skill in library automation: impact of Artificial Intelligence...
New trends and skill in library automation: impact of Artificial Intelligence...
 
Library congress subject headings
Library congress subject headings Library congress subject headings
Library congress subject headings
 
Knowing Your Library Collection
Knowing Your Library CollectionKnowing Your Library Collection
Knowing Your Library Collection
 
Creating a New Bibliographic Record in Koha with MARC 21 Fields
Creating a New Bibliographic Record in Koha with MARC 21 FieldsCreating a New Bibliographic Record in Koha with MARC 21 Fields
Creating a New Bibliographic Record in Koha with MARC 21 Fields
 
Managing e resources
Managing e resourcesManaging e resources
Managing e resources
 

Semelhante a Royal Lake Dredging and Restoration

Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead Haven
SWCNabi
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Phillip Rury
 

Semelhante a Royal Lake Dredging and Restoration (20)

Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation Project
 
Flood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt MachielseFlood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt Machielse
 
Truckee River Restoration
Truckee River RestorationTruckee River Restoration
Truckee River Restoration
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meeting
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead Haven
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
 
Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11
 
Lake shady plans
Lake shady plansLake shady plans
Lake shady plans
 

Mais de Fairfax County

Mais de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
PsychicRuben LoveSpells
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
Diya Sharma
 

Último (20)

Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt
 
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
 
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
 
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
 
Pakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfPakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdf
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 

Royal Lake Dredging and Restoration

  • 1.
  • 2.  Dredging Program and Project Background  Project Benefits  Royal Lake Conditions  Phased Approach  Dredging Methods and Alternatives  Park Access and Community Coordination  Next Steps Royal Lake: Meeting Agenda
  • 3.  History – Lakes previously dredged by DPWES Stormwater – Limited to small quantities – Dewatered on site  Lake Barton completed in 2011  Currently working on: – Huntsman Lake, Woodglen Lake, Royal Lake Dredging and Lake Restoration Program
  • 4.  Completed Data Collection  Developing Lake Dredging and Management Plan  Community coordination at design and construction phases – Preliminary Design (65%) – Final Design (95%) – Preconstruction: Pardon Our Dust meeting  December 2013: Final Design  Construction in Fiscal Year 2015 (July 2014) Royal Lake Dredging and Restoration Project Timeline and Coordination
  • 5.  Restore sediment pool capacity – Downstream water quality benefits – Lake water quality – Aesthetics  Improve lake water quality and habitat  Provide long term maintenance improvements Project Goals and Benefit
  • 6. Lake Barton Dredging and Restoration Area Treated (acres) Phosphorous Removal Nitrogen Removal Sediment Removal 544 77,000 lbs dredged 115,500 lbs dredged 38,500 tons dredged Annual benefit from increased trapping efficiency 130 lbs/year 200 lbs/year 65 tons/year
  • 7. Royal Lake Facts  Drainage area = 2,477 acres (3.67 square miles)  Lake surface area = 37.5 acres  Sediment pool capacity = 416,000 cubic yards (CY)  Current sediment in lake = 100,400 CY  Estimated annual sediment load = 4,400 CY 50 feet 100,400 CY
  • 11. Royal Lake: Dredging Areas  Phase 1: Base Dredge = 40,000 CY  Phase 2: Up to an additional 60,000 CY Zone D 12,400 CY
  • 13. Dredging Methods and Alternatives 1. Mechanically dredge deposited sediment and haul wet 2. Drain lake and dry deposited sediment in place before hauling
  • 14. PRE-DREDGING: An estimated 35,000 cubic yards of sediment had accumulated in the lake, forming islands and reducing water levels to less than three feet in most areas. Lake Barton Example
  • 15. Lake Barton Example: Pre-Dredging
  • 18. Lake Barton Example: Disposal Site
  • 19. North Park Lake Example Allegheny County, Pennsylvania Dredging: The lake was drained and the sediment was dried in-place.
  • 20. North Park Lake Example Allegheny County, Pennsylvania Temporary Diversion Channels Equipment Working on Next Slide
  • 21. North Park Lake: Dredging Allegheny County, Pennsylvania Truck Wash Temporary Diversion Channel Low Pressure Excavator Bulldozer Bulldozer Excavator and DozerTruck Access Staging
  • 22.  General Sequence – Establish access and staging areas – Conduct dredging utilizing barges – Haul wet sediment to disposal site for drying  Benefits – Less weather dependent – Quicker initial start to dredging – Less potential for schedule extensions or delay  Concerns – Increased sediment handling effort at disposal area – Potentially higher cost Dredge Alternative – In the Wet
  • 23.  General Sequence – Initiate drawdown of lake – Establish access and staging areas – Establish diversion channels within lake – Conduct dredging  Benefits – Higher daily sediment removal rates – Minimal sediment handling effort at disposal area – Potentially lower cost  Concerns – Very weather dependent – Higher potential for delays due to weather – Typically more odor from sediment exposed – Need to relocate/salvage fish Dredge Alternative – In the Dry
  • 24.  In-lake forebay  Wetland planting  Shoreline stabilization  Fish habitat  Fish stocking Lake Restoration Fish habitat created from salvaged trees Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
  • 25. Royal Lake: Shoreline Restoration
  • 26. Royal Lake: Shoreline Restoration Royal Lake Existing Conditions
  • 29. Royal Lake: Site Access and Staging Optional?
  • 30. Royal Lake: Site Access and Staging
  • 31. Staging Area 1 Potential Expansion Berm/Cofferdam to be built Area to be dewatered and backfilled to expand staging area after berm/cofferdam is built
  • 32. Royal Lake: Dewatering Basin Inactive Dewatering Basin
  • 33. Access During Construction Public Access: The park will remain open and existing parking lot will be available.
  • 34. Access During Construction Public Access: Pedestrian gates will be provided. Access through work areas and trails around the lake after work hours.
  • 35.  Community coordination at design and construction phases – Preliminary Design (65%) – Final Design (95%) – Preconstruction: “Pardon Our Dust” meeting  December 2013: Final Design  Construction in Fiscal Year 2015 (Starts July 2014)  Project Duration: – Phase 1, Base Dredge: Dredge 40,000 CY = 5 to 6 Months – Phase 2, Full Dredge: 9 to 12 Months Royal Lake Dredging and Restoration Project Timeline and Coordination
  • 36. Contacts:  Martin Chang, Project Manager 703-324-5825 | Martin.Chang@fairfaxcounty.gov  Dipmani Kumar, Section Chief 703-324-4612 | Dipmani.Kumar@fairfaxcounty.gov  http://www.fairfaxcounty.gov/dpwes/stormwater/ Royal Lake DredgingandRestoration http://www.fairfaxcounty.gov/NVSWCD/ http://www.fairfaxcounty.gov/parks/