The document summarizes an October 4, 2017 citizen information meeting about Phase IV of the Georgetown Pike Walkway project from Seneca Road to Falls Bridge Lane. The meeting included a presentation on the project design featuring a 6-foot asphalt walkway along the roadway attempting to minimize tree loss and utility conflicts. Attendees were invited to ask questions and provide written comments on the proposed design by October 27th to be considered in finalizing the design. The project schedule outlined pre-final plans in early 2018, right of way acquisition from fall 2018 to spring 2019, utility relocations in summer/fall 2019, and construction from spring to summer 2020.
1. Georgetown Pike Walkway
Phase IV
Citizen Information Meeting
October 4, 2017, 7PM to 9PM Great Falls Library
(Formal Presentation Starts at 7:30)
1
2. Project Team
Ms. Brook Khorashadi, P.E., Section Chief, Transportation Design Division
Mr. John Dresser, Project Manager, Transportation Design Division
Mr. Doug Miller, Environmental Specialist
Mr. Chris Wells, Bike/Ped Manager
___________________________________________________________
Supervisor John Foust, Dranesville District Supervisor
___________________________________________________________
2
3. Tonight’s Agenda
• Phase IV – Presentation followed by Q&A
• Return to display boards, one-on-one discussion,
individual questions
• Meeting Ends – 9:00PM
3
4. Tonight’s Meeting:
• Provide an overview of Phase IV project design
• Provide an update on current Phase IV project activities,
current status, and schedule
• Solicit comments regarding the proposed design
Tonight we will answer questions, but please submit all
comments in writing to enable them to be part of the public
record.
4
6. • Project Background:
• Locally Funded project
• Public walkway will meet VDOT & County design
standards and will comply with Americans with Disabilities
Act (ADA).
• Facility will be maintained by Fairfax County
6
7. 7
Design Features:
• 1200’ - 6’ wide asphalt walkway along roadway behind
drainage ditch
• Provides pedestrian connectivity from an existing walkway
at Seneca Square to Falls Bridge Lane
• Design alignment attempts to minimize tree loss and utility
conflict
12. 12
Project Schedule
• Citizens Information Meeting – 10/4/17
• Pre-Final Plans submittal – Early Spring, 2018
• Right of Way Acquisition – Fall, 2018 to Late Spring, 2019
• Utility Relocations – Summer/Late Fall 2019
• Construction – Spring, 2020 through Summer, 2020
13. 13
Questions about Phase IV?
Reminder:
Please submit all comments in writing by October 27 in order
for them to be considered in final design.
14. Citizen Input
14
Ways to Comment
• Fill out & submit a comment sheet tonight (Comment Box Provided)
• Comment section on project website:
http://www.fairfaxcounty.gov/fcdot/pedestrian/georgetownpiketrail.htm
• Email John Dresser: john.dresser@fairfaxcounty.gov
• Fill out and mail a comment sheet:
John Dresser
Fairfax County Dept. of Transportation
4050 Legato Road, Suite 400
Fairfax, VA 22033
Submit written
comments by
October 27, 2017