A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Florence Lane Outfall Restoration
Project Number: SD-000031-201
District: Lee
November 8, 2018
Florence Lane Outfall Restoration
Stormwater/Maintenance and Stormwater Management Division
Completed Project
2
Florence Lane Outfall Restoration
Stormwater/Maintenance and Stormwater Management Division
Project Details
Description:
The Florence Lane Outfall Restoration Project was substantially completed on October 30, 2018. The project
consisted of the restoration of 128 linear feet of eroded channel. The goals of the project were to address
public safety concerns, stabilize a deeply eroded channel by using natural stream design techniques, and
provide enhanced water quality. Stormwater staff worked and coordinated with Wastewater Collections
Division staff to repair a sanitary sewer connection within the limits of disturbance along the channel bank.
Project Overview:
 Restore the outfall channel with reinforced bed mix riffle sections and grading for bank stabilization
 Stabilize channel banks using coir matting and native vegetation
 Revegetate disturbed areas with native plants and shrubs to promote reforestation
Project Team:
 Stormwater: Jack Meritt, P.E., Maintenance and Stormwater Management Division
 Wastewater: Tom Richardson, P.E., Wastewater Collections Division
 Project Design: Wetland Studies and Solutions, Inc.
 Construction Contractor: Utilities Unlimited, LLC
 Revegetation Contractor: GroundFX
3
Florence Lane Outfall Restoration
Stormwater/Maintenance and Stormwater Management Division
Project Location: Tax Map 082-4, Lee District
4
Florence Lane Outfall Restoration
Stormwater/Maintenance and Stormwater Management Division
Pre-Construction Condition
5
Florence Lane Outfall Restoration
Stormwater/Maintenance and Stormwater Management Division
Construction Photos
6
Florence Lane Outfall Restoration
Stormwater/Maintenance and Stormwater Management Division
Before and After
7
Additional Information
For additional information, please contact
www.fairfaxcounty.gov/publicworks
Florence Lane Outfall Restoration
Stormwater/Maintenance and Stormwater Management Division 8
Irene Haske
703-324-5821
Irene.Haske@fairfaxcounty.gov

Mais conteúdo relacionado

Mais procurados

Adaptive methods to restore Lake Erie hydrology_Kroll
Adaptive methods to restore Lake Erie hydrology_KrollAdaptive methods to restore Lake Erie hydrology_Kroll
Adaptive methods to restore Lake Erie hydrology_Kroll
Healthy Lakes, Healthy Lives
 

Mais procurados (20)

Green Hollow Court Outfall Restoration
Green Hollow Court Outfall RestorationGreen Hollow Court Outfall Restoration
Green Hollow Court Outfall Restoration
 
Toll House Road Outfall Restoration
Toll House Road Outfall RestorationToll House Road Outfall Restoration
Toll House Road Outfall Restoration
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall Restoration
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Habitat Improvement for Cleaner Water
Habitat Improvement for Cleaner WaterHabitat Improvement for Cleaner Water
Habitat Improvement for Cleaner Water
 
Lenox Drive Outfall Restoration
Lenox Drive Outfall RestorationLenox Drive Outfall Restoration
Lenox Drive Outfall Restoration
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
 
Innisvale Drive Outfall Restoration
Innisvale Drive Outfall RestorationInnisvale Drive Outfall Restoration
Innisvale Drive Outfall Restoration
 
Fairfax police academy pond improvement project
Fairfax police academy pond improvement projectFairfax police academy pond improvement project
Fairfax police academy pond improvement project
 
Barton Hill Sediment Removal Project
Barton Hill Sediment Removal ProjectBarton Hill Sediment Removal Project
Barton Hill Sediment Removal Project
 
Long Branch Central Watershed Management Area Project Overview October 26, 2020
Long Branch Central Watershed Management Area Project Overview October 26, 2020Long Branch Central Watershed Management Area Project Overview October 26, 2020
Long Branch Central Watershed Management Area Project Overview October 26, 2020
 
Willamette River Basin Inundation Mapping - Brandt
Willamette River Basin Inundation Mapping - BrandtWillamette River Basin Inundation Mapping - Brandt
Willamette River Basin Inundation Mapping - Brandt
 
Grand Lake St. Marys Constructed Wetlands LIA Presentation Dec. 2017
Grand Lake St. Marys Constructed Wetlands LIA Presentation Dec. 2017Grand Lake St. Marys Constructed Wetlands LIA Presentation Dec. 2017
Grand Lake St. Marys Constructed Wetlands LIA Presentation Dec. 2017
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
Laurel Hill Reclaimed Water
Laurel Hill Reclaimed WaterLaurel Hill Reclaimed Water
Laurel Hill Reclaimed Water
 
Impact of Agricultural Stream Restoration on Riparian Hydrology and Biogeoche...
Impact of Agricultural Stream Restoration on Riparian Hydrology and Biogeoche...Impact of Agricultural Stream Restoration on Riparian Hydrology and Biogeoche...
Impact of Agricultural Stream Restoration on Riparian Hydrology and Biogeoche...
 
NVSWCD introduction 02 11-2021
NVSWCD introduction  02 11-2021NVSWCD introduction  02 11-2021
NVSWCD introduction 02 11-2021
 
Adaptive methods to restore Lake Erie hydrology_Kroll
Adaptive methods to restore Lake Erie hydrology_KrollAdaptive methods to restore Lake Erie hydrology_Kroll
Adaptive methods to restore Lake Erie hydrology_Kroll
 
Popes Head Creek at Brecon Ridge Resident Meeting
Popes Head Creek at Brecon Ridge Resident MeetingPopes Head Creek at Brecon Ridge Resident Meeting
Popes Head Creek at Brecon Ridge Resident Meeting
 

Semelhante a Florence Lane Outfall Restoration

Semelhante a Florence Lane Outfall Restoration (20)

Dead Run Drive Outfall Restoration
Dead Run Drive Outfall RestorationDead Run Drive Outfall Restoration
Dead Run Drive Outfall Restoration
 
Harvest Green Project Completion
Harvest Green Project CompletionHarvest Green Project Completion
Harvest Green Project Completion
 
Rainbow Bridge Land Outfall Restoration
Rainbow Bridge Land Outfall RestorationRainbow Bridge Land Outfall Restoration
Rainbow Bridge Land Outfall Restoration
 
Terrett Court Storm Drainage Improvements
Terrett Court Storm Drainage ImprovementsTerrett Court Storm Drainage Improvements
Terrett Court Storm Drainage Improvements
 
Ulysses Court Outfall Restoration
Ulysses Court Outfall RestorationUlysses Court Outfall Restoration
Ulysses Court Outfall Restoration
 
Stone Mill Court Project Completion
Stone Mill Court Project CompletionStone Mill Court Project Completion
Stone Mill Court Project Completion
 
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
 
Robey Avenue Outfall Restoration
Robey Avenue Outfall RestorationRobey Avenue Outfall Restoration
Robey Avenue Outfall Restoration
 
Crestmont circle outfall restoration
Crestmont circle outfall restorationCrestmont circle outfall restoration
Crestmont circle outfall restoration
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream Restoration
 
Newington Commons Pond Improvement
Newington Commons Pond ImprovementNewington Commons Pond Improvement
Newington Commons Pond Improvement
 
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3
 
Lake Martin Public Meeting Feb 2016
Lake Martin Public Meeting Feb 2016Lake Martin Public Meeting Feb 2016
Lake Martin Public Meeting Feb 2016
 
Hunting Creek at Fairfield Stream Restoration
Hunting Creek at Fairfield Stream RestorationHunting Creek at Fairfield Stream Restoration
Hunting Creek at Fairfield Stream Restoration
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall Restoration
 
Flatlick Branch III Stream Restoration June 6, 2020
Flatlick Branch III Stream Restoration June 6, 2020Flatlick Branch III Stream Restoration June 6, 2020
Flatlick Branch III Stream Restoration June 6, 2020
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 
BSantelik_resume
BSantelik_resumeBSantelik_resume
BSantelik_resume
 
Banks Property Stream Restoration (DC9218)
Banks Property Stream Restoration (DC9218)Banks Property Stream Restoration (DC9218)
Banks Property Stream Restoration (DC9218)
 

Mais de Fairfax County

Mais de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
zubnm
 
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi EscortsHigh Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
Monica Sydney
 
Corporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptxCorporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptx
arnab132
 

Último (20)

Jumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptxJumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptx
 
Water Pollution
Water Pollution Water Pollution
Water Pollution
 
High Profile Call Girls Service in Udhampur 9332606886 High Profile Call G...
High Profile Call Girls Service in Udhampur   9332606886  High Profile Call G...High Profile Call Girls Service in Udhampur   9332606886  High Profile Call G...
High Profile Call Girls Service in Udhampur 9332606886 High Profile Call G...
 
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
 
Call Girls in Tiruppur 9332606886 ust Genuine Escort Model Sevice
Call Girls in Tiruppur  9332606886  ust Genuine Escort Model SeviceCall Girls in Tiruppur  9332606886  ust Genuine Escort Model Sevice
Call Girls in Tiruppur 9332606886 ust Genuine Escort Model Sevice
 
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
 
Climate Change
Climate ChangeClimate Change
Climate Change
 
Low Rate Call Girls Boudh 9332606886 HOT & SEXY Models beautiful and charmin...
Low Rate Call Girls Boudh  9332606886 HOT & SEXY Models beautiful and charmin...Low Rate Call Girls Boudh  9332606886 HOT & SEXY Models beautiful and charmin...
Low Rate Call Girls Boudh 9332606886 HOT & SEXY Models beautiful and charmin...
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
 
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...
 
Role of Copper and Zinc Nanoparticles in Plant Disease Management
Role of Copper and Zinc Nanoparticles in Plant Disease ManagementRole of Copper and Zinc Nanoparticles in Plant Disease Management
Role of Copper and Zinc Nanoparticles in Plant Disease Management
 
Vip Salem Call Girls 8250092165 Low Price Escorts Service in Your Area
Vip Salem Call Girls 8250092165 Low Price Escorts Service in Your AreaVip Salem Call Girls 8250092165 Low Price Escorts Service in Your Area
Vip Salem Call Girls 8250092165 Low Price Escorts Service in Your Area
 
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi EscortsHigh Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
 
Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667
Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667
Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667
 
Russian Escort Dubai 0503464457 Dubai Escorts
Russian Escort Dubai 0503464457 Dubai EscortsRussian Escort Dubai 0503464457 Dubai Escorts
Russian Escort Dubai 0503464457 Dubai Escorts
 
Corporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptxCorporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptx
 
Call girl in Ajman 0503464457 Ajman Call girl services
Call girl in Ajman 0503464457 Ajman Call girl servicesCall girl in Ajman 0503464457 Ajman Call girl services
Call girl in Ajman 0503464457 Ajman Call girl services
 
A Review on Integrated River Basin Management and Development Master Plan of ...
A Review on Integrated River Basin Management and Development Master Plan of ...A Review on Integrated River Basin Management and Development Master Plan of ...
A Review on Integrated River Basin Management and Development Master Plan of ...
 
Sensual Call Girls in Surajpur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
Sensual Call Girls in Surajpur { 9332606886 } VVIP NISHA Call Girls Near 5 St...Sensual Call Girls in Surajpur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
Sensual Call Girls in Surajpur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
 

Florence Lane Outfall Restoration

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Florence Lane Outfall Restoration Project Number: SD-000031-201 District: Lee November 8, 2018
  • 2. Florence Lane Outfall Restoration Stormwater/Maintenance and Stormwater Management Division Completed Project 2
  • 3. Florence Lane Outfall Restoration Stormwater/Maintenance and Stormwater Management Division Project Details Description: The Florence Lane Outfall Restoration Project was substantially completed on October 30, 2018. The project consisted of the restoration of 128 linear feet of eroded channel. The goals of the project were to address public safety concerns, stabilize a deeply eroded channel by using natural stream design techniques, and provide enhanced water quality. Stormwater staff worked and coordinated with Wastewater Collections Division staff to repair a sanitary sewer connection within the limits of disturbance along the channel bank. Project Overview:  Restore the outfall channel with reinforced bed mix riffle sections and grading for bank stabilization  Stabilize channel banks using coir matting and native vegetation  Revegetate disturbed areas with native plants and shrubs to promote reforestation Project Team:  Stormwater: Jack Meritt, P.E., Maintenance and Stormwater Management Division  Wastewater: Tom Richardson, P.E., Wastewater Collections Division  Project Design: Wetland Studies and Solutions, Inc.  Construction Contractor: Utilities Unlimited, LLC  Revegetation Contractor: GroundFX 3
  • 4. Florence Lane Outfall Restoration Stormwater/Maintenance and Stormwater Management Division Project Location: Tax Map 082-4, Lee District 4
  • 5. Florence Lane Outfall Restoration Stormwater/Maintenance and Stormwater Management Division Pre-Construction Condition 5
  • 6. Florence Lane Outfall Restoration Stormwater/Maintenance and Stormwater Management Division Construction Photos 6
  • 7. Florence Lane Outfall Restoration Stormwater/Maintenance and Stormwater Management Division Before and After 7
  • 8. Additional Information For additional information, please contact www.fairfaxcounty.gov/publicworks Florence Lane Outfall Restoration Stormwater/Maintenance and Stormwater Management Division 8 Irene Haske 703-324-5821 Irene.Haske@fairfaxcounty.gov