Developing of a web-based application to facilitate patient treatment adherence in individuals with sleep apnea treated with Continuous Positive Airway Pressure (CPAP) devices [5 Aud 1330 Dickerson]
Semelhante a Developing of a web-based application to facilitate patient treatment adherence in individuals with sleep apnea treated with Continuous Positive Airway Pressure (CPAP) devices [5 Aud 1330 Dickerson]
Semelhante a Developing of a web-based application to facilitate patient treatment adherence in individuals with sleep apnea treated with Continuous Positive Airway Pressure (CPAP) devices [5 Aud 1330 Dickerson] (20)
Call Girls Service Surat Samaira ❤️🍑 8250192130 👄 Independent Escort Service ...
Developing of a web-based application to facilitate patient treatment adherence in individuals with sleep apnea treated with Continuous Positive Airway Pressure (CPAP) devices [5 Aud 1330 Dickerson]
1.
2. Developing a web- application to facilitate patient treatment adherence . Suzanne S. Dickerson DNS RN Associate Professor Grace Dean PhD RN Assistant Professor
12. Timeline Initial 4 months Secure developmental server Protocols Base use cases Technology platform selection Network Admini-strator PIs Principal engineer Set up developmental Server and test security Software development: Finalized protocols Write software initial requirements Month 1–4 milestone Team member Task Timeline
13. Next 2 months Prototype users scenarios (personas) Interaction task scenarios UI screen designs Data type and flow definitions PIs Principal engineer Graphic designer Interaction and interface design Data model design Month 4-6 milestone Team member Task Timeline
14. Time line 6-8 months Model-View-Controller software design Implementation Plan Principal engineer Graphic designer Programmer Design tech-centric components techniques Month 6-8 milestone Team member Task Timeline
15. Timeline 8-10 months Completion of initial implementation plan System test all functionality Complete fixes for high priority defects; Finalize setup of the production environment Release final deploy package PI Principal engineer Programmer Build and test Month 8-10 milestone Team member Task Timeline
16. Final months Publish the application to the production environment Production test to verify installation Ready for feasibility study PIs Principal engineer Programmer Deploy and activate Months 10-12 milestone Team member Task Timeline