PM Notebook
Summarizing Project Management Concepts for the PMP
Exam
Mohammad Elsheimy Road to PMP
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
1
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS
BASED ON DATA/INFORMATION GATHERED FROM VARIOUS
RELIABLE SOURCES. NONE OF THIS DATA/INFORMATION IS A
PROPERTY OF THE AUTHOR. NONE IS INTENDED TO MAKE A
PROFIT IN ANY WAY. THIS IS FOR PERSONAL USE ONLY.
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
2
No great man ever complains of want of opportunity.
Ralph Waldo Emerson
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
3
Table of Contents
Chapter 6 – Schedule Management................................................................................................................... 4
Key Terms ............................................................................................................................................................... 4
Project Work vs. Project Manager Work....................................................................................................... 4
Duration vs. Effort.............................................................................................................................................. 4
Dependencies .................................................................................................................................................. 4
Processes................................................................................................................................................................ 4
1 – Plan Schedule Management (Planning)............................................................................................... 4
2 – Define Activities (Planning)....................................................................................................................... 5
3 – Sequence Activities (Planning)................................................................................................................ 6
4 – Estimate Activity Durations (Planning).................................................................................................... 7
5 – Develop Schedule (Planning).................................................................................................................. 8
6 – Control Schedule (Monitoring & Controlling) ....................................................................................... 9
Activities ............................................................................................................................................................... 10
Types ................................................................................................................................................................. 10
Relationships.................................................................................................................................................... 12
Critical Path Method (CPM) / Logic-Driven Scheduling............................................................................. 12
Float / Slack ..................................................................................................................................................... 12
Components ................................................................................................................................................... 13
Critical Chain Method (CCM) ......................................................................................................................... 13
Schedule Compression ..................................................................................................................................... 14
Resource Optimization Techniques ................................................................................................................ 14
Additional Terms ................................................................................................................................................. 14
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
4
Key Terms
Project Work vs. Project Manager Work
Project Work – The activities that will create the project scope.
Project Manager Work / Level-of-Effort (LOE) – The activities you have to do in order to manage
the project. E.g. quality control, inspection, creation of reports, etc.
Duration vs. Effort
Activity Duration / Calendar Time / Expected Activity Duration (EAD) – The total number of work
periods required to complete a task.
Effort/Person Hours – Total number of labor units required to complete a task.
Dependencies
Mandatory Dependencies / Hard Logic – Legally or contractually required order of activities. It is
the natural order of activities.
Discretionary Dependencies / Preferred/Preferential / Soft Logic – A preferred order of activities
defined by the team. Important when analyzing how to compress the schedule.
External Dependencies – Based on the needs or desires of a party outside the project. E.g.
vendors, inspectors, and other projects that deliver required components.
Internal Dependencies – A type of hard logic. Based on the needs of the project and may be
something the project team can control. E.g. waiting for team member who is taking a vacation,
requiring a specific order because the management asked for that.
Processes
1 – Plan Schedule Management (Planning)
 Schedule Model – The flow of your project activities in your activity list. It is a scaled down, less
complex representation of the actual project.
 Scheduling Methodology - defines the rules and approaches for the scheduling process.
 Units of measurement (hours, days, weeks).
 Control thresholds.
 Rules for performance measurements.
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
5
Inputs
1. Project Management Plan
 Scope Management Plan
 Development Approach
2. Project Charter
3. OPAs
4. EEFs
Tools
1. Expert Judgment
2. Data Analysis Techniques
 Alternatives Analysis
3. Meetings
Outputs
1. Schedule Management Plan
2 – Define Activities (Planning)
 Activity list is a separate document.
 Involves taking the WBS work packages and decomposing them into activities.
 Basis for estimating, scheduling, and controlling work.
Inputs
1. Project Management Plan
 Schedule Management Plan
 Scope Baseline – WBS, WBS Dictionary, Scope Statement
2. OPAs
3. EEFs
Tools
1. Decomposition – Decomposing WBS to activities.
2. Expert Judgment
3. Rolling Wave Planning – Planning the project in waves as the project proceeds and details
become clearer.
4. Meetings
Outputs
1. Activity List – Lower-level than WBS. Contains activity identifier, activity name, and
description.
2. Activity Attributes –
 Unique activity identifier
 WBS ID
 Activity label
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
6
3. Milestone List – Significant events with the project schedule. A milestone has a duration of
zero (0).
 Milestone Chart – A way to visualize project milestone schedule. An up triangle means
planned value. A down triangle means actual value. Line between the two shows how
much variance.
4. Change Requests
5. Project Management Plan Updates
3 – Sequence Activities (Planning)
Inputs
1. Project Management Plan
 Schedule Management Plan
 Scope Baseline
2. Project Documents
 Activity List
 Activity Attributes
 Assumptions Log
 Milestone List
3. OPAs
4. EEFs
Tools
1. Diagramming Models –
 Precedence Diagramming Method (PDM) / Network Diagram / Activity-on-Node (AON)
/ Pure Logic Diagram –
1) Most common.
2) Shows activities and relationships without a time scale.
 Arrow Diagramming Model (ADM) / Activity-on-Arrow (AOA) –
1) Uses finish-to-start representation only.
2) Arrows are used to represent activities.
3) May use dummy activities.
 Graphical Evaluation and Review Technique (GERT) –
1) Allows loops between activities (activities may be performed more than once.)
2) Some activities may not be performed or performed only in part.
2. Dependency Determination
3. Leads and Lags –
 Lead/Accelerated/Negative Time – When the successor (S) starts before predecessor
(P) is done. Allows activities to overlap.
 Lag/Waiting/Positive Time – When the successor starts after predecessor with some time.
4. Project Management Information System (PMIS)
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
7
Outputs
1. Project Schedule Network Diagram – A summary narrative can accompany the schedule
network diagram to describe the approach used to sequence the activities in the network.
2. Project Document Updates
 Activity List Updates
 Activity Attributes Updates
 Risk Register Updates
4 – Estimate Activity Durations (Planning)
 Estimating should be done by the person doing the work whenever possible to improve
accuracy.
 Padding – Extra time added to a schedule that you do not really think you need but that you
add just to feel confident in the estimate. Not acceptable project management practice.
Inputs
1. Project Management Plan
 Schedule Management Plan
 Scope Baseline
2. Project Documents
 Activity List
 Activity Attributes
 Assumptions Log
 Milestone List
 Resource Breakdown Structure (RBS)
 Resource Calendars
 Resource Requirements
 Risk Register
 Project Staff Assignments
3. EEFs
4. OPAs
Tools
1. Expert Judgment
2. Estimating Techniques
3. Data Analysis Techniques
 Alternatives Analysis
 Reserve Analysis / Contingency Reserve/Buffer – Adding extra time.
4. Group Decision-Making Techniques
5. Meetings
Outputs
1. Activity Duration Estimates
2. Basis of Estimates
3. Project Document Updates
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
8
5 – Develop Schedule (Planning)
 Unrealistic schedule is project manager’s fault.
 Calendar-based.
 Must be approved.
Inputs
1. Project Management Plan
 Schedule Management Plan
 Scope Baseline
2. Project Documents
 Activity List
 Activity Attributes
 Assumptions Log
 Milestone List
 Resource Breakdown Structure (RBS)
 Resource Calendars
 Resource Requirements
 Risk Register
 Project Schedule Network Diagram
 Activity Duration Estimates
 Project Staff Assignments
3. Agreements
4. EEFs
5. OPAs
Tools
1. Schedule Network Analysis
2. Critical Path Method (CPM)
3. Critical Chain Method (CCM)
4. Resource Optimization Techniques
5. Modeling Techniques –
 What-if Analysis
 Simulation – Using a computer to model uncertainty.
1) Monte Carlo Simulation
6. Project Management Information System (PMIS)
7. Leads and Lags
8. Schedule Compression
9. Agile Release Planning
Outputs
1. Project Schedule
2. Schedule Data – Detailed information about activities, activity attributes, resource
requirements, identified assumptions, alternate best-case and work-case schedules, and
contingency reserves.
3. Schedule Baseline
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
9
4. Project Calendars
5. Project Management Plan Updates
6. Project Document Updates
 Activity List
 Activity Attributes
 Risk Register
6 – Control Schedule (Monitoring & Controlling)
 Measuring and assessing work performance data against the schedule baseline.
 Involves taking corrective and preventive action over and over again.
 Involves prioritizing the remaining work and to properly allocate remaining resources based
on their availability.
 If the project is running ahead of the schedule, Project Manager should evaluate reducing
staff for the project. This could lead to savings for organization.
 Involves ensuring that the critical path does not change.
Inputs
1. Project Management Plan
 Schedule Management Plan
 Performance Measurement Baseline
1) Schedule Baseline
2) Scope Baseline
2. Project Documents
 Project Calendars
 Project Schedule
 Resource Calendar
 Schedule Data
3. Work Performance Data
4. OPAs
Tools
1. Data Analysis Techniques
 What-if Analysis
2. Project Management Information System (PMIS)
3. Performance Reviews –
 Schedule Variance (SV) – Indicates how much ahead (positive) or behind (negative)
schedule the project is. When a project finished SV will always be zero.
 Schedule Performance Index (SPI) – A measurement of schedule efficiency expressed
as the ratio of earned value (EV) to planned value (PV.)
 Trend Analysis
4. Resource Optimization Techniques
5. Adjusting Leads and Lags
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | ACTIVITIES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
10
Outputs
1. Work Performance Information
2. Schedule Forecasts
3. Change Requests
4. OPAs Updates
5. Project Management Plan Updates
6. Project Document Updates
Activities
Types
By Effort
Level-of-Effort (LOE) – Support activities. Like reporting and budgeting.
Discrete Effort – Activities required to complete project scope
Apportioned Effort – Project management work. Like quality assurance and communications.
By Duration
Effort-Driven Activities – The more labor we put on the sooner the activity can get done.
Fixed-Duration Activities – Adding more labor will not make the activity finish faster.
By Convergence
Merge Activities / Path Converge/Convergence – When two or more parallel activities are
merged together.
Burst Activities – When one activity is split into multiple activities.
By Sequence
Serial Activities – Those that flow from one to the next, in sequence.
Concurrent / Parallel – When one or more activities are completed on the same time.
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | ACTIVITIES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
11
Other Types
Dangling Activities / Open-Ended Activities – Any activity that is disconnected from either sides or
connected from both sides with relations that do not govern the links.
Dangling activities result in a schedule baseline that is not reliable due to the omission of
substantial sequential constraints.
Hammock Activity – It is a type of activity that is used for grouping smaller activities that hang
between two dates. The size of the hammock, or the duration of the hammock is calculated by
the start date of the earliest task, and the finish date of the last task.
Laddering Activities – It is when work elements in an activity are progressively released to the next
activity thus causing them to be overlapped during their execution.
PM NOTEBOOK
CHAPTER 6 – SCHEDULE MANAGEMENT | CRITICAL PATH METHOD (CPM)
/ LOGIC-DRIVEN SCHEDULING
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
12
Relationships
Types of relationships between two dependencies A (first) and B (second) –
1. Finish to Start (FS) – B(S) = A(F) [ + 1 ]
2. Start to Start (SS) – B(S) = A(S)
3. Finish to Finish (FF) – B(F) = A(F)
4. Start to Finish (SF) – B(F) = A(S) [ - 1 ]
Critical Path Method (CPM) / Logic-Driven Scheduling
Critical Path Method involves measuring the longest sequence of activities, it focuses on activity
order.
 Critical Path (CP) – The string of activities that is longer than any other path. A delay in any
one of the critical activities will delay the whole project.
 Near-Critical Path – The path that is close in duration to the critical path. Sometimes, the
near-critical path becomes the critical.
Please note that following regarding critical path –
 Multiple critical paths increase project risk.
 Critical path has zero or negative float in case that there is a constraint set on the project
finish date.
Float / Slack
The amount of time that an activity can slip before it causes the project to be delayed.
Total Float (Slack) – The amount of time an activity can be delayed without delaying the project
end date. It cannot be aggregated, and is shared across the path.
Free Float – The amount of time an activity can be delayed without delaying the early start date
of its successor (S).
Project Float – The amount of time a project can be delayed without delaying the externally
imposed project completion date required by the customer or management.
Negative Float – Means that estimated completion date is after the desired date.
PM NOTEBOOK
CHAPTER 6 – SCHEDULE MANAGEMENT | CRITICAL CHAIN METHOD
(CCM)
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
13
Components
 Early Start (ES) – The earliest time that an activity can start.
 Early Finish (EF) – The earliest time that an activity can finish.
 Late Start (LS) – The latest time that an activity can start.
 Late Finish (LF) – The latest time that an activity can finish without delaying the project.
 Forward Pass – For early start and finish.
ES = Maximum EF of all predecessors + 1
EF = ES + Duration − 1
 Backward Pass – For late start and finish.
LF – Minimum LS of all successors – 1
LS – LF − Duration + 1
 Float –
F = LF − EF or LS − ES
Critical Chain Method (CCM)
Critical Chain Method involves the longest sequence of activities considering activity buffers and
resource constraints.
 It focuses on resources.
 Focuses on managing the remaining buffer durations against the remaining duration of task
chains.
 Buffer –
o Protects the critical chain from slippage.
o The size of each buffer accounts for the uncertainty in the duration of the chain of
dependent tasks that lead up to the buffer.
o Usually set to 50-percent of the critical chain duration. While 50 percent sounds like a
lot, it is often less than the total of hidden safety margins in individual tasks.
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | SCHEDULE COMPRESSION
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
14
Schedule Compression
Crashing – Adding resources or moving them around to shorten it.
 Applies to effort-driven activities.
 Adds cost.
 While crashing equal activities, choose the earlier one.
 First step in crashing is calculating the cost and time slope for each critical activity that can
be expedited.
 When crashing, start with the lowest crashing cost.
 Slope – The cost per day of crashing the project.
𝑪𝒓𝒂𝒔𝒉 𝑪𝒐𝒔𝒕 (𝑪𝑪) − 𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕 (𝑵𝑪)
𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵𝑫) − 𝑪𝒓𝒂𝒔𝒉 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪𝑫)
 Law of Diminishing Returns – Refers to a point at which the level of profits or benefits
gained is less than the amount of money or energy invested (ROI). At this point, adding
more input will not produce a proportional increase in productivity.
Fast-tracking – Performing phases or activities in parallel or partially parallel. Adds risk.
Resource Optimization Techniques
To adjust the use of resources.
Resource Leveling – Adjusting start and finish dates based on resource constraints for balancing
demand of resources with the available supply.
 Used when individual bars of resource histogram extend beyond the maximum allowed
hours (i.e. over-allocation.)
 Used to produce a resource-limited schedule.
 May lengthen the schedule and increase cost.
 Include adding more resources or modifying the schedule.
Resource Smoothing – Adjusting activities so that requirements for resources do not exceed
certain predefined resource limits.
 Used when time constraint takes priority.
 Usually applied after leveling.
 May not optimize all resources.
Resource Reallocation – Moving activities from and to critical path.
PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | ADDITIONAL TERMS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
15
Additional Terms
Control Threshold – A predetermined range of acceptable variances, such as +/–10 percent off
schedule.
Fragnet/Subnet – A representation of a project network diagram that is often used for outsourced
portions of a project, repetitive work within a project, or a subproject.
Kanban Board – is a work and workflow visualization tool that enables you to optimize the flow of
your work.
 Kanban for Work-in-Progress (WIP) – To visualize work in progress.
Lean Management – an approach to running an organization that supports the concept of
continuous improvement, a long-term approach to work that systematically seeks to achieve
small, incremental changes in processes in order to improve efficiency and quality.
 Uses a product backlog.
Sub-networks / Fragment Networks – Several identical or nearly identical series of activities that
are repeated throughout the project.

Mais conteúdo relacionado

Mais procurados

Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource ManagementSaqib Raza
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACEChris Carson
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryMichael Pink
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 

Mais procurados (20)

Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule Assessment
 
Rita's Process Chart
Rita's Process ChartRita's Process Chart
Rita's Process Chart
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 

Semelhante a PM Notebook - Chapter 6 - Schedule Management

Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project SchedulesAcumen
 
How To Make A Construction Software Schedule In 5 Steps
How To Make A Construction Software Schedule In 5 StepsHow To Make A Construction Software Schedule In 5 Steps
How To Make A Construction Software Schedule In 5 StepsCarlos Philip Bardales
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
10 me667 chap4 project scheduling
10 me667 chap4   project scheduling10 me667 chap4   project scheduling
10 me667 chap4 project schedulingPavan Kumar
 
Construction Scheduling, Work Study & Work Measurement
Construction Scheduling, Work Study & Work Measurement Construction Scheduling, Work Study & Work Measurement
Construction Scheduling, Work Study & Work Measurement Aishwarya Phalke
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Nam Trung
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
Analyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionAnalyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionMichael Pink
 

Semelhante a PM Notebook - Chapter 6 - Schedule Management (20)

Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project Schedules
 
Chapter 06
Chapter 06Chapter 06
Chapter 06
 
How To Make A Construction Software Schedule In 5 Steps
How To Make A Construction Software Schedule In 5 StepsHow To Make A Construction Software Schedule In 5 Steps
How To Make A Construction Software Schedule In 5 Steps
 
Dynamic Scheduling Methodology
Dynamic Scheduling MethodologyDynamic Scheduling Methodology
Dynamic Scheduling Methodology
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
10 me667 chap4 project scheduling
10 me667 chap4   project scheduling10 me667 chap4   project scheduling
10 me667 chap4 project scheduling
 
3. project time management
3. project time management3. project time management
3. project time management
 
Construction Scheduling, Work Study & Work Measurement
Construction Scheduling, Work Study & Work Measurement Construction Scheduling, Work Study & Work Measurement
Construction Scheduling, Work Study & Work Measurement
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
ETCA_1
ETCA_1ETCA_1
ETCA_1
 
Strategy Report
Strategy ReportStrategy Report
Strategy Report
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
Analyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionAnalyzing data, performance and impacts in construction
Analyzing data, performance and impacts in construction
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 

Mais de Mohammad Elsheimy

Mohammad Elsheimy - Solution Developer (CV)
Mohammad Elsheimy - Solution Developer (CV)Mohammad Elsheimy - Solution Developer (CV)
Mohammad Elsheimy - Solution Developer (CV)Mohammad Elsheimy
 
PM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetPM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetMohammad Elsheimy
 
PM Notebook - Appendix G - Interpersonal/Team/Soft Skills
PM Notebook - Appendix G - Interpersonal/Team/Soft SkillsPM Notebook - Appendix G - Interpersonal/Team/Soft Skills
PM Notebook - Appendix G - Interpersonal/Team/Soft SkillsMohammad Elsheimy
 
PM Notebook - Appendix F - Forecasting Methods
PM Notebook - Appendix F - Forecasting MethodsPM Notebook - Appendix F - Forecasting Methods
PM Notebook - Appendix F - Forecasting MethodsMohammad Elsheimy
 
PM Notebook - Appendix E - Estimating Techniques
PM Notebook - Appendix E - Estimating TechniquesPM Notebook - Appendix E - Estimating Techniques
PM Notebook - Appendix E - Estimating TechniquesMohammad Elsheimy
 
PM Notebook - Appendix D - Decision-Making Techniques
PM Notebook - Appendix D - Decision-Making TechniquesPM Notebook - Appendix D - Decision-Making Techniques
PM Notebook - Appendix D - Decision-Making TechniquesMohammad Elsheimy
 
PM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation ToolsPM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation ToolsMohammad Elsheimy
 
PM Notebook - Appendix B - Data Gathering Techniques
PM Notebook - Appendix B - Data Gathering TechniquesPM Notebook - Appendix B - Data Gathering Techniques
PM Notebook - Appendix B - Data Gathering TechniquesMohammad Elsheimy
 
PM Notebook - Chapter 14 - Professional and Social Responsibility
PM Notebook - Chapter 14 - Professional and Social ResponsibilityPM Notebook - Chapter 14 - Professional and Social Responsibility
PM Notebook - Chapter 14 - Professional and Social ResponsibilityMohammad Elsheimy
 
PM Notebook - Chapter 13 - Stakeholder Management
PM Notebook - Chapter 13 - Stakeholder ManagementPM Notebook - Chapter 13 - Stakeholder Management
PM Notebook - Chapter 13 - Stakeholder ManagementMohammad Elsheimy
 
PM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement ManagementPM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement ManagementMohammad Elsheimy
 
PM Notebook - Chapter 11: Risk Management
PM Notebook - Chapter 11: Risk ManagementPM Notebook - Chapter 11: Risk Management
PM Notebook - Chapter 11: Risk ManagementMohammad Elsheimy
 
PM Notebook - Chapter 2: Organizations
PM Notebook - Chapter 2: OrganizationsPM Notebook - Chapter 2: Organizations
PM Notebook - Chapter 2: OrganizationsMohammad Elsheimy
 
PM Notebook - Chapter 1: Introduction
PM Notebook - Chapter 1: IntroductionPM Notebook - Chapter 1: Introduction
PM Notebook - Chapter 1: IntroductionMohammad Elsheimy
 
Microsoft Silverlight - An Introduction
Microsoft Silverlight - An IntroductionMicrosoft Silverlight - An Introduction
Microsoft Silverlight - An IntroductionMohammad Elsheimy
 
Marshaling with C# Pocket Reference
Marshaling with C# Pocket ReferenceMarshaling with C# Pocket Reference
Marshaling with C# Pocket ReferenceMohammad Elsheimy
 

Mais de Mohammad Elsheimy (18)

Mohammad Elsheimy - Solution Developer (CV)
Mohammad Elsheimy - Solution Developer (CV)Mohammad Elsheimy - Solution Developer (CV)
Mohammad Elsheimy - Solution Developer (CV)
 
PM Notebook
PM NotebookPM Notebook
PM Notebook
 
PM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetPM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula Sheet
 
PM Notebook - Appendix G - Interpersonal/Team/Soft Skills
PM Notebook - Appendix G - Interpersonal/Team/Soft SkillsPM Notebook - Appendix G - Interpersonal/Team/Soft Skills
PM Notebook - Appendix G - Interpersonal/Team/Soft Skills
 
PM Notebook - Appendix F - Forecasting Methods
PM Notebook - Appendix F - Forecasting MethodsPM Notebook - Appendix F - Forecasting Methods
PM Notebook - Appendix F - Forecasting Methods
 
PM Notebook - Appendix E - Estimating Techniques
PM Notebook - Appendix E - Estimating TechniquesPM Notebook - Appendix E - Estimating Techniques
PM Notebook - Appendix E - Estimating Techniques
 
PM Notebook - Appendix D - Decision-Making Techniques
PM Notebook - Appendix D - Decision-Making TechniquesPM Notebook - Appendix D - Decision-Making Techniques
PM Notebook - Appendix D - Decision-Making Techniques
 
PM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation ToolsPM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation Tools
 
PM Notebook - Appendix B - Data Gathering Techniques
PM Notebook - Appendix B - Data Gathering TechniquesPM Notebook - Appendix B - Data Gathering Techniques
PM Notebook - Appendix B - Data Gathering Techniques
 
PM Notebook - Chapter 14 - Professional and Social Responsibility
PM Notebook - Chapter 14 - Professional and Social ResponsibilityPM Notebook - Chapter 14 - Professional and Social Responsibility
PM Notebook - Chapter 14 - Professional and Social Responsibility
 
PM Notebook - Chapter 13 - Stakeholder Management
PM Notebook - Chapter 13 - Stakeholder ManagementPM Notebook - Chapter 13 - Stakeholder Management
PM Notebook - Chapter 13 - Stakeholder Management
 
PM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement ManagementPM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement Management
 
PM Notebook - Chapter 11: Risk Management
PM Notebook - Chapter 11: Risk ManagementPM Notebook - Chapter 11: Risk Management
PM Notebook - Chapter 11: Risk Management
 
PM Notebook - Chapter 2: Organizations
PM Notebook - Chapter 2: OrganizationsPM Notebook - Chapter 2: Organizations
PM Notebook - Chapter 2: Organizations
 
PM Notebook - Chapter 1: Introduction
PM Notebook - Chapter 1: IntroductionPM Notebook - Chapter 1: Introduction
PM Notebook - Chapter 1: Introduction
 
What's New in Silverlight 5
What's New in Silverlight 5What's New in Silverlight 5
What's New in Silverlight 5
 
Microsoft Silverlight - An Introduction
Microsoft Silverlight - An IntroductionMicrosoft Silverlight - An Introduction
Microsoft Silverlight - An Introduction
 
Marshaling with C# Pocket Reference
Marshaling with C# Pocket ReferenceMarshaling with C# Pocket Reference
Marshaling with C# Pocket Reference
 

Último

internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 

Último (20)

internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 

PM Notebook - Chapter 6 - Schedule Management

  • 1. PM Notebook Summarizing Project Management Concepts for the PMP Exam Mohammad Elsheimy Road to PMP
  • 2. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 1 DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA/INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA/INFORMATION IS A PROPERTY OF THE AUTHOR. NONE IS INTENDED TO MAKE A PROFIT IN ANY WAY. THIS IS FOR PERSONAL USE ONLY.
  • 3. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 2 No great man ever complains of want of opportunity. Ralph Waldo Emerson
  • 4. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 3 Table of Contents Chapter 6 – Schedule Management................................................................................................................... 4 Key Terms ............................................................................................................................................................... 4 Project Work vs. Project Manager Work....................................................................................................... 4 Duration vs. Effort.............................................................................................................................................. 4 Dependencies .................................................................................................................................................. 4 Processes................................................................................................................................................................ 4 1 – Plan Schedule Management (Planning)............................................................................................... 4 2 – Define Activities (Planning)....................................................................................................................... 5 3 – Sequence Activities (Planning)................................................................................................................ 6 4 – Estimate Activity Durations (Planning).................................................................................................... 7 5 – Develop Schedule (Planning).................................................................................................................. 8 6 – Control Schedule (Monitoring & Controlling) ....................................................................................... 9 Activities ............................................................................................................................................................... 10 Types ................................................................................................................................................................. 10 Relationships.................................................................................................................................................... 12 Critical Path Method (CPM) / Logic-Driven Scheduling............................................................................. 12 Float / Slack ..................................................................................................................................................... 12 Components ................................................................................................................................................... 13 Critical Chain Method (CCM) ......................................................................................................................... 13 Schedule Compression ..................................................................................................................................... 14 Resource Optimization Techniques ................................................................................................................ 14 Additional Terms ................................................................................................................................................. 14
  • 5. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | KEY TERMS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 4 Key Terms Project Work vs. Project Manager Work Project Work – The activities that will create the project scope. Project Manager Work / Level-of-Effort (LOE) – The activities you have to do in order to manage the project. E.g. quality control, inspection, creation of reports, etc. Duration vs. Effort Activity Duration / Calendar Time / Expected Activity Duration (EAD) – The total number of work periods required to complete a task. Effort/Person Hours – Total number of labor units required to complete a task. Dependencies Mandatory Dependencies / Hard Logic – Legally or contractually required order of activities. It is the natural order of activities. Discretionary Dependencies / Preferred/Preferential / Soft Logic – A preferred order of activities defined by the team. Important when analyzing how to compress the schedule. External Dependencies – Based on the needs or desires of a party outside the project. E.g. vendors, inspectors, and other projects that deliver required components. Internal Dependencies – A type of hard logic. Based on the needs of the project and may be something the project team can control. E.g. waiting for team member who is taking a vacation, requiring a specific order because the management asked for that. Processes 1 – Plan Schedule Management (Planning)  Schedule Model – The flow of your project activities in your activity list. It is a scaled down, less complex representation of the actual project.  Scheduling Methodology - defines the rules and approaches for the scheduling process.  Units of measurement (hours, days, weeks).  Control thresholds.  Rules for performance measurements.
  • 6. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 5 Inputs 1. Project Management Plan  Scope Management Plan  Development Approach 2. Project Charter 3. OPAs 4. EEFs Tools 1. Expert Judgment 2. Data Analysis Techniques  Alternatives Analysis 3. Meetings Outputs 1. Schedule Management Plan 2 – Define Activities (Planning)  Activity list is a separate document.  Involves taking the WBS work packages and decomposing them into activities.  Basis for estimating, scheduling, and controlling work. Inputs 1. Project Management Plan  Schedule Management Plan  Scope Baseline – WBS, WBS Dictionary, Scope Statement 2. OPAs 3. EEFs Tools 1. Decomposition – Decomposing WBS to activities. 2. Expert Judgment 3. Rolling Wave Planning – Planning the project in waves as the project proceeds and details become clearer. 4. Meetings Outputs 1. Activity List – Lower-level than WBS. Contains activity identifier, activity name, and description. 2. Activity Attributes –  Unique activity identifier  WBS ID  Activity label
  • 7. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 6 3. Milestone List – Significant events with the project schedule. A milestone has a duration of zero (0).  Milestone Chart – A way to visualize project milestone schedule. An up triangle means planned value. A down triangle means actual value. Line between the two shows how much variance. 4. Change Requests 5. Project Management Plan Updates 3 – Sequence Activities (Planning) Inputs 1. Project Management Plan  Schedule Management Plan  Scope Baseline 2. Project Documents  Activity List  Activity Attributes  Assumptions Log  Milestone List 3. OPAs 4. EEFs Tools 1. Diagramming Models –  Precedence Diagramming Method (PDM) / Network Diagram / Activity-on-Node (AON) / Pure Logic Diagram – 1) Most common. 2) Shows activities and relationships without a time scale.  Arrow Diagramming Model (ADM) / Activity-on-Arrow (AOA) – 1) Uses finish-to-start representation only. 2) Arrows are used to represent activities. 3) May use dummy activities.  Graphical Evaluation and Review Technique (GERT) – 1) Allows loops between activities (activities may be performed more than once.) 2) Some activities may not be performed or performed only in part. 2. Dependency Determination 3. Leads and Lags –  Lead/Accelerated/Negative Time – When the successor (S) starts before predecessor (P) is done. Allows activities to overlap.  Lag/Waiting/Positive Time – When the successor starts after predecessor with some time. 4. Project Management Information System (PMIS)
  • 8. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 7 Outputs 1. Project Schedule Network Diagram – A summary narrative can accompany the schedule network diagram to describe the approach used to sequence the activities in the network. 2. Project Document Updates  Activity List Updates  Activity Attributes Updates  Risk Register Updates 4 – Estimate Activity Durations (Planning)  Estimating should be done by the person doing the work whenever possible to improve accuracy.  Padding – Extra time added to a schedule that you do not really think you need but that you add just to feel confident in the estimate. Not acceptable project management practice. Inputs 1. Project Management Plan  Schedule Management Plan  Scope Baseline 2. Project Documents  Activity List  Activity Attributes  Assumptions Log  Milestone List  Resource Breakdown Structure (RBS)  Resource Calendars  Resource Requirements  Risk Register  Project Staff Assignments 3. EEFs 4. OPAs Tools 1. Expert Judgment 2. Estimating Techniques 3. Data Analysis Techniques  Alternatives Analysis  Reserve Analysis / Contingency Reserve/Buffer – Adding extra time. 4. Group Decision-Making Techniques 5. Meetings Outputs 1. Activity Duration Estimates 2. Basis of Estimates 3. Project Document Updates
  • 9. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 8 5 – Develop Schedule (Planning)  Unrealistic schedule is project manager’s fault.  Calendar-based.  Must be approved. Inputs 1. Project Management Plan  Schedule Management Plan  Scope Baseline 2. Project Documents  Activity List  Activity Attributes  Assumptions Log  Milestone List  Resource Breakdown Structure (RBS)  Resource Calendars  Resource Requirements  Risk Register  Project Schedule Network Diagram  Activity Duration Estimates  Project Staff Assignments 3. Agreements 4. EEFs 5. OPAs Tools 1. Schedule Network Analysis 2. Critical Path Method (CPM) 3. Critical Chain Method (CCM) 4. Resource Optimization Techniques 5. Modeling Techniques –  What-if Analysis  Simulation – Using a computer to model uncertainty. 1) Monte Carlo Simulation 6. Project Management Information System (PMIS) 7. Leads and Lags 8. Schedule Compression 9. Agile Release Planning Outputs 1. Project Schedule 2. Schedule Data – Detailed information about activities, activity attributes, resource requirements, identified assumptions, alternate best-case and work-case schedules, and contingency reserves. 3. Schedule Baseline
  • 10. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | PROCESSES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 9 4. Project Calendars 5. Project Management Plan Updates 6. Project Document Updates  Activity List  Activity Attributes  Risk Register 6 – Control Schedule (Monitoring & Controlling)  Measuring and assessing work performance data against the schedule baseline.  Involves taking corrective and preventive action over and over again.  Involves prioritizing the remaining work and to properly allocate remaining resources based on their availability.  If the project is running ahead of the schedule, Project Manager should evaluate reducing staff for the project. This could lead to savings for organization.  Involves ensuring that the critical path does not change. Inputs 1. Project Management Plan  Schedule Management Plan  Performance Measurement Baseline 1) Schedule Baseline 2) Scope Baseline 2. Project Documents  Project Calendars  Project Schedule  Resource Calendar  Schedule Data 3. Work Performance Data 4. OPAs Tools 1. Data Analysis Techniques  What-if Analysis 2. Project Management Information System (PMIS) 3. Performance Reviews –  Schedule Variance (SV) – Indicates how much ahead (positive) or behind (negative) schedule the project is. When a project finished SV will always be zero.  Schedule Performance Index (SPI) – A measurement of schedule efficiency expressed as the ratio of earned value (EV) to planned value (PV.)  Trend Analysis 4. Resource Optimization Techniques 5. Adjusting Leads and Lags
  • 11. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | ACTIVITIES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 10 Outputs 1. Work Performance Information 2. Schedule Forecasts 3. Change Requests 4. OPAs Updates 5. Project Management Plan Updates 6. Project Document Updates Activities Types By Effort Level-of-Effort (LOE) – Support activities. Like reporting and budgeting. Discrete Effort – Activities required to complete project scope Apportioned Effort – Project management work. Like quality assurance and communications. By Duration Effort-Driven Activities – The more labor we put on the sooner the activity can get done. Fixed-Duration Activities – Adding more labor will not make the activity finish faster. By Convergence Merge Activities / Path Converge/Convergence – When two or more parallel activities are merged together. Burst Activities – When one activity is split into multiple activities. By Sequence Serial Activities – Those that flow from one to the next, in sequence. Concurrent / Parallel – When one or more activities are completed on the same time.
  • 12. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | ACTIVITIES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 11 Other Types Dangling Activities / Open-Ended Activities – Any activity that is disconnected from either sides or connected from both sides with relations that do not govern the links. Dangling activities result in a schedule baseline that is not reliable due to the omission of substantial sequential constraints. Hammock Activity – It is a type of activity that is used for grouping smaller activities that hang between two dates. The size of the hammock, or the duration of the hammock is calculated by the start date of the earliest task, and the finish date of the last task. Laddering Activities – It is when work elements in an activity are progressively released to the next activity thus causing them to be overlapped during their execution.
  • 13. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | CRITICAL PATH METHOD (CPM) / LOGIC-DRIVEN SCHEDULING DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 12 Relationships Types of relationships between two dependencies A (first) and B (second) – 1. Finish to Start (FS) – B(S) = A(F) [ + 1 ] 2. Start to Start (SS) – B(S) = A(S) 3. Finish to Finish (FF) – B(F) = A(F) 4. Start to Finish (SF) – B(F) = A(S) [ - 1 ] Critical Path Method (CPM) / Logic-Driven Scheduling Critical Path Method involves measuring the longest sequence of activities, it focuses on activity order.  Critical Path (CP) – The string of activities that is longer than any other path. A delay in any one of the critical activities will delay the whole project.  Near-Critical Path – The path that is close in duration to the critical path. Sometimes, the near-critical path becomes the critical. Please note that following regarding critical path –  Multiple critical paths increase project risk.  Critical path has zero or negative float in case that there is a constraint set on the project finish date. Float / Slack The amount of time that an activity can slip before it causes the project to be delayed. Total Float (Slack) – The amount of time an activity can be delayed without delaying the project end date. It cannot be aggregated, and is shared across the path. Free Float – The amount of time an activity can be delayed without delaying the early start date of its successor (S). Project Float – The amount of time a project can be delayed without delaying the externally imposed project completion date required by the customer or management. Negative Float – Means that estimated completion date is after the desired date.
  • 14. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | CRITICAL CHAIN METHOD (CCM) DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 13 Components  Early Start (ES) – The earliest time that an activity can start.  Early Finish (EF) – The earliest time that an activity can finish.  Late Start (LS) – The latest time that an activity can start.  Late Finish (LF) – The latest time that an activity can finish without delaying the project.  Forward Pass – For early start and finish. ES = Maximum EF of all predecessors + 1 EF = ES + Duration − 1  Backward Pass – For late start and finish. LF – Minimum LS of all successors – 1 LS – LF − Duration + 1  Float – F = LF − EF or LS − ES Critical Chain Method (CCM) Critical Chain Method involves the longest sequence of activities considering activity buffers and resource constraints.  It focuses on resources.  Focuses on managing the remaining buffer durations against the remaining duration of task chains.  Buffer – o Protects the critical chain from slippage. o The size of each buffer accounts for the uncertainty in the duration of the chain of dependent tasks that lead up to the buffer. o Usually set to 50-percent of the critical chain duration. While 50 percent sounds like a lot, it is often less than the total of hidden safety margins in individual tasks.
  • 15. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | SCHEDULE COMPRESSION DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 14 Schedule Compression Crashing – Adding resources or moving them around to shorten it.  Applies to effort-driven activities.  Adds cost.  While crashing equal activities, choose the earlier one.  First step in crashing is calculating the cost and time slope for each critical activity that can be expedited.  When crashing, start with the lowest crashing cost.  Slope – The cost per day of crashing the project. 𝑪𝒓𝒂𝒔𝒉 𝑪𝒐𝒔𝒕 (𝑪𝑪) − 𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕 (𝑵𝑪) 𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵𝑫) − 𝑪𝒓𝒂𝒔𝒉 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪𝑫)  Law of Diminishing Returns – Refers to a point at which the level of profits or benefits gained is less than the amount of money or energy invested (ROI). At this point, adding more input will not produce a proportional increase in productivity. Fast-tracking – Performing phases or activities in parallel or partially parallel. Adds risk. Resource Optimization Techniques To adjust the use of resources. Resource Leveling – Adjusting start and finish dates based on resource constraints for balancing demand of resources with the available supply.  Used when individual bars of resource histogram extend beyond the maximum allowed hours (i.e. over-allocation.)  Used to produce a resource-limited schedule.  May lengthen the schedule and increase cost.  Include adding more resources or modifying the schedule. Resource Smoothing – Adjusting activities so that requirements for resources do not exceed certain predefined resource limits.  Used when time constraint takes priority.  Usually applied after leveling.  May not optimize all resources. Resource Reallocation – Moving activities from and to critical path.
  • 16. PM NOTEBOOK CHAPTER 6 – SCHEDULE MANAGEMENT | ADDITIONAL TERMS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 15 Additional Terms Control Threshold – A predetermined range of acceptable variances, such as +/–10 percent off schedule. Fragnet/Subnet – A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject. Kanban Board – is a work and workflow visualization tool that enables you to optimize the flow of your work.  Kanban for Work-in-Progress (WIP) – To visualize work in progress. Lean Management – an approach to running an organization that supports the concept of continuous improvement, a long-term approach to work that systematically seeks to achieve small, incremental changes in processes in order to improve efficiency and quality.  Uses a product backlog. Sub-networks / Fragment Networks – Several identical or nearly identical series of activities that are repeated throughout the project.