Introduction to heat waves and Heatwaves in Bangladesh.pptx
Energietransitie in industrie: de impact op de netten - Shell Energy and Chemicals Park Rotterdam
1. Copyright of Shell International B.V.
Dutch Power Event
Energietransitie in industrie: de impact op de netten
Shell Energy and Chemicals Park Rotterdam
Arie de Wit
Electrical Specialist Engineer
1
10 March 2022
3. Copyright of Shell International B.V. 3
Shell Energy and Chemicals Park Rotterdam plant overview
4. Copyright of Shell International B.V.
Shell Energy and Chemicals Park Rotterdam in numbers
160,000 km
60 plants
200 metres
24/7
Safety: 1,900
2,000 4,000
405,000
High pressure
1,000
10,000
120,000
10,000
450,000
4
10 March 2022
5. Copyright of Shell International B.V.
Introduction Shell Energy and Chemicals Park Rotterdam
Electrical Infrastructure & Equipment
◼ One of the largest petrochemicals sites in Europe with over 550 hectares
◼ Shell Pernis has an own distribution grid and generators:
◼ Substations: ~100 HV (66kV to 3kV) and LV;
◼ Load Pernis: ~200MW (~500.000 households);
◼ Generation Pernis: 180MW by 9 generators (steam- and gas-turbine driven).
◼ The system provides electrical power to the plant installations, e.g.:
◼ 6.000 LV motors, 700 HV motors;
◼ 2.100 LV switchboards, 120 HV switchboards;
◼ One of Main Challenges:
◼ There is a large and complex project scope to replace aged equipment (e.g. oldest switchboard from
1947, 70 years old)
5
10 March 2022
7. Copyright of Shell International B.V.
Shell Energy and Chemicals Park Rotterdam
8. Copyright of Shell International B.V.
(2020 = modelled reference year)
▪ Reduction Scope 1 + 2 CO2 emissions (4.9 Mtpa):
▪ Reduction Scope 3 CO2 emissions (55.8 Mtpa):
▪ CO2 intensity (73 gCO2/MJ):
▪ % of margin from non- fossil fuels (34%):
(2020 = modelled reference year)
▪ Reduction Scope 1 + 2 CO2 emissions:
▪ Reduction Scope 3 CO2 emissions:
▪ CO2 intensity:
▪ % of margin from non- fossil fuels :
Our goals
9. Copyright of Shell International B.V.
▪ 2.8 mln t/yr CO2 reduction (scope 3)
▪ 0.2 mln t/yr CO2 reduction (scope 1)
▪ 0.8 mln t/yr bio transport fuels
▪ PIT in 2024
▪ Pre-FID work already started
BIOFUELS PRODUCTION
▪ 0.15 mln t/j CO2 reduction (scope 2)
▪ 200 MW, and up to 80 tpd green H2
▪ H2 to Pernis and Mobility
▪ FID 2022, RFSU 2025
ELECTROLYSER HH1
This visual is courtesy of the Port of Rotterdam
This visual is courtesy of the Port hos project
This visual is courtesy of the Portthos Project
PORTHOS
▪ 1.1 mln t/yr CO2 reduction (scope 1)
▪ FID 2022, RFSU 2024
Our first big steps in the transformation
10. Copyright of Shell International B.V.
Complex puzzle
◼ The energy transition is a complex puzzle this impacts not only the electrical system but also other utilities
on site like steam, compressed air, fuel gas and natural gas.
◼ Overall trends are:
◼ Increase in electrical load due to electrification, the addition of new plants and processes such as CCS
and E-boilers.
◼ Reduction in steam demand by energy efficiency improvement and network optimization, replacement
of turbine driven compressors and shutdown of old plants.
◼ Inputs for this puzzle are interdependent and not easy to plan, for example:
◼ Shut down of units depends on remaining lifetime and marked demand for products.
◼ A gas turbine driven generator fed with fuel gas can only be switched of when less fuel gas is
produced, the steam demand is reduced and an alternative source of electricity is in place.
◼ Therefore flexibility and quick project execution are key.
10
10 March 2022
11. Copyright of Shell International B.V.
Impact on electrical infrastructure
◼ Step size increase of power consumption which was not anticipated in the original design and stretches
an already congested electrical network beyond it’s original design limits.
◼ Shift from redundancy N+1+G to a more risk based approach which requires a change in mentality and
operation of the network.
◼ The expansion of the internal network and an increased electricity demand from the grid are part of all
scenario’s. Exact implementation schedule is not clear so the design needs to be as flexible as possible.
11
10 March 2022
12. Copyright of Shell International B.V.
Challenges, solutions and
cooperation
12
10 March 2022
13. Copyright of Shell International B.V.
Challenges and solutions
◼ Limited physical space
◼ HDD Horizontal Directional Drilling
◼ Smart design preserving as much of the existing infrastructure as possible
◼ Limitations in qualified personnel for all roles
◼ Standardisation of design
◼ Training of personnel
◼ Innovation in remote operation and predictive maintenance
◼ Quick changing scenario’s
◼ Modular construction
◼ Acceptance of (temporary) reduced redundancy
13
10 March 2022
14. Copyright of Shell International B.V. 14
All equipment failures
are avoidable
Relevant data is
complete, accurate, and
readily available
Pernis is sustainable and
CO2 neutral
Pernis is not
heard/smelled/seen
No turn around scope
for inspection activities
Fully automated
operation, inspection
and maintenance
1 2 3 4 5 6
Engineering Pernis Digitalisation/Innovation roadmap – Vision statements
10 March 2022
15. Copyright of Shell International B.V.
Cooperation
◼ Accommodation of an multiple times higher electrical power demand in de coming years requires open
discussion between customer and grid company for example on redundancy.
◼ Exact phasing and execution of the roadmap for the energy transition depends on large number of
parameters, therefore alignment between all stakeholders in all stages of the transition is key for success.
◼ Future sources of electricity will have a more intermitted character, also the electrification of plants will
cause more fluctuation of the electrical energy demand of a site, this can ether be a risk or a chance
depending on how it is handled.
◼ Electric heaters and drives can be switch on/off faster and can be controlled more easily than
conventional gas fired heaters and turbine driven equipment. This increases the possibilities of demand
management but requires changes in the operational philosophy and design of the plants.
15
10 March 2022
16. Copyright of Shell International B.V.
Questions and Answers
16
10 March 2022
17. Copyright of Shell International B.V.
Contact details
Arie de Wit
Electrical Specialist Engineer
Tel: +31 10 431 4248
Mobile: +31 6 52 438 007
Email: Arie.deWit@Shell.com
17
10 March 2022