The aim of this presentation is to introduce you to the method of building snecked rubble
  walling against a block backing. By the end of the lesson you should have developed an
understanding of the bonding arrangement and process for constructing this type of walling.
The first course is built using a repeating pattern of one riser followed by three levellers. You
should see that at the stop end of each of the returns the pattern is stopped but if the wall was
                          longer this pattern could repeat indefinately.
The second course consists of arrangements built between the risers of the first course. This
arrangement will continue throughout the remainder of the wall. Between each riser there is a
      sneck, then a riser, then two levellers. Remember the minimum overlap is 100mm.
The third course is similar to the second. A sneck is followed by a riser and two levellers. You
may find that more cuts are required on this course as you need to ensure that the bonding
   requirements are followed. Remember there are a maximum of three heads to a joint.
As you progress higher up the wall you should see that the pattern continues; sneck, riser,
leveller, leveller. By this stage of the construction you should be becoming more familiar with
   the bonding arrangements and able to plan each course with the next course in mind.
The main challenge in maintaining a regular bonding arrangement is making sure the bond is
maintained at the returns. The external return in particular requires careful consideration as the
           external arris must always be plumbed and minimum overlap adhered to.
As you approach the top of the wall you should see a pattern emerging where the position of
the risers form elongated diamond shapes. You should also notice that the courses alternate
                     between 1/3 height stones and 2/3 height stones.
On the second-to-last course the risers are levelled to finished building height. Have you
noticed that the risers have been arranged to form the external return? This is the simplest way
         of forming the return as the stones are larger and easier to keep in alignment.
The top course is completed entirely of snecks (or levellers). These are intended to represent the
  sneck, riser, leveller, leveller pattern as though they had been built and then cut to form the
  finished building height. Once complete you should level the top course and point the wall.
Developed by The Stonemasonry Department
          City of Glasgow College
                    2013

Mais conteúdo relacionado

Mais procurados

Brick walling an introduction
Brick walling an introductionBrick walling an introduction
Brick walling an introductiondoogstone
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONRavindra Patnayaka
 
Concrete Block Walling
Concrete Block WallingConcrete Block Walling
Concrete Block Wallingdoogstone
 
CTEP - UNIT - II - MASONRY
CTEP - UNIT - II - MASONRYCTEP - UNIT - II - MASONRY
CTEP - UNIT - II - MASONRYShankar Ramasamy
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation GuidelinesBENAY MUNDA
 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)swatapriya
 
Earthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columnsEarthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columnsSajjad Ahmad
 
Components of bricks and english &flemish bonds
Components of bricks and english &flemish bondsComponents of bricks and english &flemish bonds
Components of bricks and english &flemish bondsBANDISREENIVASULU1
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction purvi golecha
 
Jointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkJointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkSteve Jarvis
 
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGEBUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGEPatricia Kong
 
Illustrations. repairing of structures
Illustrations. repairing of structuresIllustrations. repairing of structures
Illustrations. repairing of structuresAvinash Kumar Gupta
 

Mais procurados (20)

Brick walling an introduction
Brick walling an introductionBrick walling an introduction
Brick walling an introduction
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTION
 
stretcher bond
 stretcher bond stretcher bond
stretcher bond
 
Brick bonds
Brick bondsBrick bonds
Brick bonds
 
Concrete Block Walling
Concrete Block WallingConcrete Block Walling
Concrete Block Walling
 
Stairs
StairsStairs
Stairs
 
Rat trap bond masonary
Rat trap bond masonaryRat trap bond masonary
Rat trap bond masonary
 
CTEP - UNIT - II - MASONRY
CTEP - UNIT - II - MASONRYCTEP - UNIT - II - MASONRY
CTEP - UNIT - II - MASONRY
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation Guidelines
 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)
 
Earthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columnsEarthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columns
 
Components of bricks and english &flemish bonds
Components of bricks and english &flemish bondsComponents of bricks and english &flemish bonds
Components of bricks and english &flemish bonds
 
Types of bonds
Types of bondsTypes of bonds
Types of bonds
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Jointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkJointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & Blockwork
 
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGEBUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
 
BRICK MASONRY
BRICK MASONRYBRICK MASONRY
BRICK MASONRY
 
Formwork
FormworkFormwork
Formwork
 
Illustrations. repairing of structures
Illustrations. repairing of structuresIllustrations. repairing of structures
Illustrations. repairing of structures
 
Bricks fin
Bricks finBricks fin
Bricks fin
 

Destaque

Destaque (20)

Snecked rubble step by step angled
Snecked rubble step by step angledSnecked rubble step by step angled
Snecked rubble step by step angled
 
ปกP (1)
ปกP (1)ปกP (1)
ปกP (1)
 
엔턴십 발표자료 소셜나눔
엔턴십 발표자료 소셜나눔엔턴십 발표자료 소셜나눔
엔턴십 발표자료 소셜나눔
 
Fragance
FraganceFragance
Fragance
 
Van Gogh Final
Van Gogh FinalVan Gogh Final
Van Gogh Final
 
Teorias del control
Teorias del controlTeorias del control
Teorias del control
 
Revolver February 2013
Revolver February 2013Revolver February 2013
Revolver February 2013
 
Hokkaido.pm.casual #03 slide
Hokkaido.pm.casual #03 slideHokkaido.pm.casual #03 slide
Hokkaido.pm.casual #03 slide
 
Finished proposal
Finished proposalFinished proposal
Finished proposal
 
Cpu portfolio global-pt-maio2013-lr
Cpu portfolio global-pt-maio2013-lrCpu portfolio global-pt-maio2013-lr
Cpu portfolio global-pt-maio2013-lr
 
Stom alum
Stom alumStom alum
Stom alum
 
Command keynote! part 1
Command keynote! part 1Command keynote! part 1
Command keynote! part 1
 
Writing and reporting project slide show
Writing and reporting project slide showWriting and reporting project slide show
Writing and reporting project slide show
 
Concept paperpakistancio summit2013
Concept paperpakistancio summit2013Concept paperpakistancio summit2013
Concept paperpakistancio summit2013
 
Rupee & dollar
Rupee & dollarRupee & dollar
Rupee & dollar
 
Ut 3
Ut 3Ut 3
Ut 3
 
Tutorials
TutorialsTutorials
Tutorials
 
Proje yonetimi-odevi
Proje yonetimi-odeviProje yonetimi-odevi
Proje yonetimi-odevi
 
Pres svh
Pres svhPres svh
Pres svh
 
Finding america
Finding americaFinding america
Finding america
 

Semelhante a Snecked rubble step by step

Masonry Presentation
Masonry PresentationMasonry Presentation
Masonry Presentationflrbc1avtech
 
HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxswethaasukumar
 
Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)Chan Yifung
 
Brick walling and joints
Brick walling and jointsBrick walling and joints
Brick walling and jointsSahil Pahal
 
Sonal Gupta , Interior Design
Sonal Gupta , Interior DesignSonal Gupta , Interior Design
Sonal Gupta , Interior Designdezyneecole
 
study of brick and brick bond
study of brick and brick bondstudy of brick and brick bond
study of brick and brick bondabhishekgunjal6
 
Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bmLin Hui
 
Brick masonry by er. rohit garg
Brick masonry by er. rohit gargBrick masonry by er. rohit garg
Brick masonry by er. rohit gargRohit Garg
 
Types of bond in brick masonry
Types of bond in brick masonryTypes of bond in brick masonry
Types of bond in brick masonryAmit sojitra
 
A PowerPoint Presentation On Superstructure
A PowerPoint Presentation On SuperstructureA PowerPoint Presentation On Superstructure
A PowerPoint Presentation On Superstructurekuntansourav
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Types of bonds in brick masonry
Types of bonds in brick masonryTypes of bonds in brick masonry
Types of bonds in brick masonryMaliha Mehr
 
STONE MASONRY - uploaded--------.pptx
STONE MASONRY - uploaded--------.pptxSTONE MASONRY - uploaded--------.pptx
STONE MASONRY - uploaded--------.pptxTChaitanyaSrikrishna
 
interior design MSc. I sem. student work
interior design MSc. I sem. student workinterior design MSc. I sem. student work
interior design MSc. I sem. student workdezyneecole
 

Semelhante a Snecked rubble step by step (20)

Masonry Presentation
Masonry PresentationMasonry Presentation
Masonry Presentation
 
HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptx
 
Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)
 
Brick Masonry.pptx
Brick Masonry.pptxBrick Masonry.pptx
Brick Masonry.pptx
 
Masonry construction
Masonry constructionMasonry construction
Masonry construction
 
Brick walling and joints
Brick walling and jointsBrick walling and joints
Brick walling and joints
 
Sonal Gupta , Interior Design
Sonal Gupta , Interior DesignSonal Gupta , Interior Design
Sonal Gupta , Interior Design
 
Brick masonry
Brick masonryBrick masonry
Brick masonry
 
MASONRY.pptx
MASONRY.pptxMASONRY.pptx
MASONRY.pptx
 
study of brick and brick bond
study of brick and brick bondstudy of brick and brick bond
study of brick and brick bond
 
Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bm
 
Brick masonry by er. rohit garg
Brick masonry by er. rohit gargBrick masonry by er. rohit garg
Brick masonry by er. rohit garg
 
Types of bond in brick masonry
Types of bond in brick masonryTypes of bond in brick masonry
Types of bond in brick masonry
 
A PowerPoint Presentation On Superstructure
A PowerPoint Presentation On SuperstructureA PowerPoint Presentation On Superstructure
A PowerPoint Presentation On Superstructure
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Types of bonds in brick masonry
Types of bonds in brick masonryTypes of bonds in brick masonry
Types of bonds in brick masonry
 
STONE MASONRY - uploaded--------.pptx
STONE MASONRY - uploaded--------.pptxSTONE MASONRY - uploaded--------.pptx
STONE MASONRY - uploaded--------.pptx
 
interior design MSc. I sem. student work
interior design MSc. I sem. student workinterior design MSc. I sem. student work
interior design MSc. I sem. student work
 
Masonry
MasonryMasonry
Masonry
 
Brick Masonry
Brick MasonryBrick Masonry
Brick Masonry
 

Mais de doogstone

Cutting a Return head
Cutting a Return headCutting a Return head
Cutting a Return headdoogstone
 
Risk assessment
Risk assessmentRisk assessment
Risk assessmentdoogstone
 
Health and safety signage
Health and safety signageHealth and safety signage
Health and safety signagedoogstone
 
Construction electrical safety
Construction electrical safetyConstruction electrical safety
Construction electrical safetydoogstone
 
Checks and splays
Checks and splaysChecks and splays
Checks and splaysdoogstone
 
Student induction 2013-14
Student induction 2013-14Student induction 2013-14
Student induction 2013-14doogstone
 
Presentation types of template
Presentation   types of templatePresentation   types of template
Presentation types of templatedoogstone
 
Presentation template making equipment
Presentation   template making equipmentPresentation   template making equipment
Presentation template making equipmentdoogstone
 
Presentation constructing a pentagon
Presentation   constructing a pentagonPresentation   constructing a pentagon
Presentation constructing a pentagondoogstone
 
Presentation constructing a heptagon
Presentation   constructing a heptagonPresentation   constructing a heptagon
Presentation constructing a heptagondoogstone
 
Presentation constructing an information panel
Presentation   constructing an information panelPresentation   constructing an information panel
Presentation constructing an information paneldoogstone
 
Surfacefinishes12
Surfacefinishes12Surfacefinishes12
Surfacefinishes12doogstone
 
Half brick walling calculations
Half brick walling calculationsHalf brick walling calculations
Half brick walling calculationsdoogstone
 
Cutting a cavetto mould
Cutting a cavetto mouldCutting a cavetto mould
Cutting a cavetto moulddoogstone
 
Cutting an ovolo mould
Cutting an ovolo mouldCutting an ovolo mould
Cutting an ovolo moulddoogstone
 
Rock formation
Rock formationRock formation
Rock formationdoogstone
 
Manual handling
Manual handlingManual handling
Manual handlingdoogstone
 

Mais de doogstone (20)

Cutting a Return head
Cutting a Return headCutting a Return head
Cutting a Return head
 
Risk assessment
Risk assessmentRisk assessment
Risk assessment
 
Health and safety signage
Health and safety signageHealth and safety signage
Health and safety signage
 
Construction electrical safety
Construction electrical safetyConstruction electrical safety
Construction electrical safety
 
Riddor
RiddorRiddor
Riddor
 
Checks and splays
Checks and splaysChecks and splays
Checks and splays
 
Student induction 2013-14
Student induction 2013-14Student induction 2013-14
Student induction 2013-14
 
Presentation types of template
Presentation   types of templatePresentation   types of template
Presentation types of template
 
Presentation template making equipment
Presentation   template making equipmentPresentation   template making equipment
Presentation template making equipment
 
Presentation constructing a pentagon
Presentation   constructing a pentagonPresentation   constructing a pentagon
Presentation constructing a pentagon
 
Presentation constructing a heptagon
Presentation   constructing a heptagonPresentation   constructing a heptagon
Presentation constructing a heptagon
 
Presentation constructing an information panel
Presentation   constructing an information panelPresentation   constructing an information panel
Presentation constructing an information panel
 
Surfacefinishes12
Surfacefinishes12Surfacefinishes12
Surfacefinishes12
 
Half brick walling calculations
Half brick walling calculationsHalf brick walling calculations
Half brick walling calculations
 
Cutting a cavetto mould
Cutting a cavetto mouldCutting a cavetto mould
Cutting a cavetto mould
 
Cutting an ovolo mould
Cutting an ovolo mouldCutting an ovolo mould
Cutting an ovolo mould
 
Rock formation
Rock formationRock formation
Rock formation
 
Manual handling
Manual handlingManual handling
Manual handling
 
Chisels
ChiselsChisels
Chisels
 
Silica dust
Silica dustSilica dust
Silica dust
 

Snecked rubble step by step

  • 1. Snecked Rubble Walling A step-by-step guide for stonemasons Stonemasonry Department 2013
  • 2. The aim of this presentation is to introduce you to the method of building snecked rubble walling against a block backing. By the end of the lesson you should have developed an understanding of the bonding arrangement and process for constructing this type of walling.
  • 3. The first course is built using a repeating pattern of one riser followed by three levellers. You should see that at the stop end of each of the returns the pattern is stopped but if the wall was longer this pattern could repeat indefinately.
  • 4. The second course consists of arrangements built between the risers of the first course. This arrangement will continue throughout the remainder of the wall. Between each riser there is a sneck, then a riser, then two levellers. Remember the minimum overlap is 100mm.
  • 5. The third course is similar to the second. A sneck is followed by a riser and two levellers. You may find that more cuts are required on this course as you need to ensure that the bonding requirements are followed. Remember there are a maximum of three heads to a joint.
  • 6. As you progress higher up the wall you should see that the pattern continues; sneck, riser, leveller, leveller. By this stage of the construction you should be becoming more familiar with the bonding arrangements and able to plan each course with the next course in mind.
  • 7. The main challenge in maintaining a regular bonding arrangement is making sure the bond is maintained at the returns. The external return in particular requires careful consideration as the external arris must always be plumbed and minimum overlap adhered to.
  • 8. As you approach the top of the wall you should see a pattern emerging where the position of the risers form elongated diamond shapes. You should also notice that the courses alternate between 1/3 height stones and 2/3 height stones.
  • 9. On the second-to-last course the risers are levelled to finished building height. Have you noticed that the risers have been arranged to form the external return? This is the simplest way of forming the return as the stones are larger and easier to keep in alignment.
  • 10. The top course is completed entirely of snecks (or levellers). These are intended to represent the sneck, riser, leveller, leveller pattern as though they had been built and then cut to form the finished building height. Once complete you should level the top course and point the wall.