8. Next Steps Moving Forward
ā¢ January 2017- Completion of Foundation / Start of Walls
ā¢ February 2017 ā Building Shell Construction
ā¢ March 2017ā Building Shell Completion
ā¢ April 2017- Interior Building Completion
ā¢ April 2017 ā Playground Construction & Completion
ā¢ Spring 2017 - Project Completion (Memorial Weekend)