SlideShare uma empresa Scribd logo
1 de 47
Innovation in Design
  Using Pre-fabricated
     Truss Bridges
          Presented By:

       Petrina Butler, P.E.
       SynTerra Corporation

       Dennis Gonano, P.E.
           U.S. Bridge
Ezell Road
                 Before


                     • Low structural rating
                     • Single lane




• Blind curves on
  approach roadway
Ezell Road
                                              Alignment




2009 and 2011 aerials provided by USDA NCRS
Overhead Bridge Road
      Before
Overhead Bridge Road
                                                  Alignment




2009 and 2011 aerials provided by USDA NCRS
Design Criteria


• Increase Safety
• Increase Capacity
• Minimize Railroad Interference
• Economic Solution
Bridge Replacement
               Options

• Prestressed Concrete Girder Bridge


• Steel Plate Girder Bridge


• Pre-fabricated Truss Bridge
Advantages of
       Pre-fabricated Bridge

• Shallowest structure depth
• Reduced construction activity
  within railroad right-of-way
• Significant cost savings
Shallowest
                    Structure Depth

  Prestressed           Steel Plate         Pre-fabricated
     Girder               Girder                Truss




   Deck = 8¼”           Deck = 8¼”           Deck = 8¼”
Cross Slope = 2¾”    Cross Slope = 2¾”   Cross Slope = 3½”
  Haunch = 1½”         Haunch = 1½”      Bottom Chord = 31”
   Beam = 54”           Beam = 42”         TOTAL = 42¾”
 TOTAL = 66½”         TOTAL = 54½”


                                          DEPTH IS UP TO
                                           2 FEET LESS
Cross Section at
Bridge Approach
Integral Abutments
Reduced Construction Activity
          Within Railroad Right of Way

•   Accelerate construction schedule
•   Smaller footprint for staging area
•   Increase Safety
•   Reduce road closure duration
Significant Cost Savings


  $1,690,000                       Total Cost of Plate Girder Option
  - $400,000                       Savings for Superstructure
  - $110,000                       Savings for Roadway Items
  - $40,000                        Savings for Railroad Flagman

  $1,140,000                       Total Cost of US Bridge Option


       TOTAL COST SAVINGS = $550,000
         OVER 30% COST REDUCTION

Cost basis - bid unit cost from actual construction
Advantages of
             Pre-fabricated Bridge

•       Shallowest structure depth
    •     Less fill for approaches
    •     Smaller footprint
    •     Same loading capacity
•       Reduced construction activity within
        railroad right-of-way
    •     Accelerate construction schedule
    •     Smaller footprint for staging area
    •     Increase safety
    •     Reduce delay
Advantages of
        Pre-fabricated Bridge

Significant cost savings
  •   Savings of $550,000 for both projects
  •   30% cost reduction
“... the bridges are great. They provided an economical and
aesthetically pleasing solution to obtaining adequate clearance
over CSXT.”
                              Todd Carroll, CTC Engineering Supervisor
                                     Spartanburg County Public Works
U.S. Bridge




       • Founded as American
         Culvert in 1936 by
         brothers Herman &
         Ted Rogovin
History


• Designing & Building Truss
  Bridges for over 60 years
Location


 • Cambridge, Ohio
 • Juncture of I-70 & I-77
 • 21 shops covering 250,000
   sq ft. in 11 buildings
How We Work With You

• Feasibility Assessments
• Programming Costs
• Specifications
• Schematic Details
• Preliminary Engineering
• Supplemental Contract
  Documents
• Modeling & Rendering
• Hard Bid Quotes & Information
• Engineering Design & Plan
  Submittals
How We Work With You …


• Construction Submittals
• Installation Assistance
• Engineering Department
  •   4 Professional Engineers
  •   2 EIT’s
  •   4 Detailers
Coordination

•   Preliminary Engineering
    •   Loads & Substructure Reactions
    •   Structure Depths & Low Steel Clearance
•   Final Engineering
    •   Abutment Seat Elevations
    •   Plan Submittals & Reviews




                                                  Adam Stout, EIT
                                                 Estimating Engineer
Bridge Truss Design


•    Final Design
    • Stringer Beams & Connections
    • Floor Beams & Connections
    • Truss Members & Connections
    • Truss Stability
    • Gusset Plates
    • Bearings
    • Deck Slab & SIP Forms
    • Misc.
                                     Scott Flaten, PE
                                     Project Engineer
Bridge Design Criteria

Span:                          104’-4” c/c Bearing
Roadway Width:                 29’-0” curb/curb + 6” curbs
Sidewalk:                      N/A
Skew:                          24o-0’-0” RF (right fwd.)
Design Live Load:              HL-93
Expansion:                     N/A (jointless bridge)
Connections:                   Shop & Field Bolted

Design Loads:
     SIP Forms & Fill:         15 psf
     Utility Loading:          100 plf
     8 ¼” Concrete Slab:       105 psf
     Future Wearing Surface:   15 psf

Truss Reactions:
     Dead Load, DC:            120.4k
     Dead Load, DW:             17.0k
     Live Load:                125.7k
     Impact:                    27.4k
     Braking (Horiz.):          20.8k
     Wind (Horiz.):             15.6k
Member Calculations

•   Non-Composite Stringers sized for       •   Connections are sized for
    Strength I Flexure                          Strength I and Service Load II
                                                Shear (Slip Critical) and
•   Composite Floor Beams sized by              checked against block shear
    Strength I Flexure
                                            •   Floor beam-to-truss connection
•   Top Chords sized using truss                is also checked against Service
    analysis and checked U-Frame                Load III (Wind on structure)
    Stability to confirm axial capacity
    can be developed                        •   Gusset Plates are designed in
                                                accordance with FHWA
•   Bottom Chords sized using truss             Publication FHWA-IF-09-014
    analysis and checked against
    fatigue allowable stress

•   Truss tension members checked for
    gross section yielding and net
    section fracture (shear lag and block
    shear) and bolt shear
Calculations
Plan Development

•   Model Creation (Smart Solids)   Software
•   Connection Design(s)                 AutoCAD Structural
•   3D Solid Additions (Dumb             Detailing 2012 (ASD)
    Solids)
•   Groups & Views
•   Detailing
•   Sheet Creation
Plan Development




•   Design Criteria, General Notes, Sheet Index
•   Framing & Geometry, Section Views, Field Splices, Bearing Details
•   SIP Forms, Deck Slab Layout, Railing Installation
•   Bill of Materials (BOM)
•   Shop Assemblies
•   Shop Drawings (Piece Details)
Fabrication


•   AISC Certifications
    • Simple Bridge
    • Major Bridge
    • Fracture Critical Endorsement
    • Sophisticated Paint Systems
      Endorsement
Processing Equipment




•   CNC 3-Axis Drill Line for
    Shape Processing
•   CNC Plasma Arc/Drill for
    Plate Processing
•   Shot Blaster
Finish & Corrosion
                   Protection

•   Hand Grinding
•   Brush Blasting
•   Hot-Dip Galvanizing
•   2-Coat Paint System
    (Paint on Galvanizing)
•   3-Coat Paint System
    (DOT Specifications)
Shop Assembly



                     Bolt Tightening




Shop Layout
Shipping
Construction

•    Overhead Bridge Road Bridge
    •   Constructed by Taylor & Murphy Construction
        Company
•    Ezell Road Bridge
    •   Constructed by Saddlebrook Construction Inc.
Overhead Bridge Road
                Construction
Stepped Truss & Stringer Abutment Seat with Integral Abutments
Overhead Bridge Road
    Construction
      Staging area
Overhead Bridge Road
    Construction
   Two field splices complete
Overhead Bridge Road
    Construction
Lifting first truss and walks to abutment
Overhead Bridge Road
    Construction
    First truss is in position
Overhead Bridge Road
    Construction
     Stabilized by cables
Overhead Bridge Road
    Construction
 Lifting the second truss into place
Overhead Bridge Road
    Construction
   Erecting first floor beam
Overhead Bridge Road
    Construction
   Floor beams being erected
Overhead Bridge Road
    Construction
     SIP forms in place
Overhead Bridge Road
    Construction
      Open for traffic
Ezell Road

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Civil pre engennerd structure
Civil pre engennerd structureCivil pre engennerd structure
Civil pre engennerd structure
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
 
Peb
PebPeb
Peb
 
Slip formwork technique
Slip formwork techniqueSlip formwork technique
Slip formwork technique
 
telecommunication Towers
telecommunication Towerstelecommunication Towers
telecommunication Towers
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Parkingembedfont
ParkingembedfontParkingembedfont
Parkingembedfont
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge System
 
Bobby's Resume
Bobby's ResumeBobby's Resume
Bobby's Resume
 
Structure analysis and design
Structure analysis and designStructure analysis and design
Structure analysis and design
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)
 
Impact of new codes in silos design
Impact of new codes in silos designImpact of new codes in silos design
Impact of new codes in silos design
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
Steel structures
Steel structuresSteel structures
Steel structures
 
Peb ss
Peb ssPeb ss
Peb ss
 
BOMA BTO Final Parking Structure Maintenance
BOMA BTO Final Parking Structure MaintenanceBOMA BTO Final Parking Structure Maintenance
BOMA BTO Final Parking Structure Maintenance
 
Kavya12
Kavya12Kavya12
Kavya12
 
Load dev-silo-design
Load dev-silo-designLoad dev-silo-design
Load dev-silo-design
 
Overhead Cranes, Jib Cranes, Commercial Doors & Loading Dock Equipment - O'Br...
Overhead Cranes, Jib Cranes, Commercial Doors & Loading Dock Equipment - O'Br...Overhead Cranes, Jib Cranes, Commercial Doors & Loading Dock Equipment - O'Br...
Overhead Cranes, Jib Cranes, Commercial Doors & Loading Dock Equipment - O'Br...
 
Horseshoe Casino Construction
Horseshoe Casino ConstructionHorseshoe Casino Construction
Horseshoe Casino Construction
 

Destaque

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Halcrow
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Piyush Kumar Santhalia
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
AELC
 
project report on truss bridge
project report on truss bridgeproject report on truss bridge
project report on truss bridge
rajdutt1111
 
Shear Force And Bending Moment In Beams
Shear Force And Bending Moment In BeamsShear Force And Bending Moment In Beams
Shear Force And Bending Moment In Beams
Amr Hamed
 

Destaque (13)

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Truss bridge final presentation
Truss bridge final presentationTruss bridge final presentation
Truss bridge final presentation
 
Cantilever bridge
Cantilever bridgeCantilever bridge
Cantilever bridge
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
 
Design of Precast Elements
Design of Precast ElementsDesign of Precast Elements
Design of Precast Elements
 
Truss Bridge Report
Truss Bridge ReportTruss Bridge Report
Truss Bridge Report
 
Bridge
BridgeBridge
Bridge
 
project report on truss bridge
project report on truss bridgeproject report on truss bridge
project report on truss bridge
 
Progressive collapse analysis
Progressive collapse analysisProgressive collapse analysis
Progressive collapse analysis
 
Shear Force And Bending Moment In Beams
Shear Force And Bending Moment In BeamsShear Force And Bending Moment In Beams
Shear Force And Bending Moment In Beams
 
Shear wall
Shear wallShear wall
Shear wall
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 

Semelhante a SynTerra / US Bridge Presentation (10 24 11)

Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...
mecocca5
 
2013 11 21-walterdale_csce
2013 11 21-walterdale_csce2013 11 21-walterdale_csce
2013 11 21-walterdale_csce
DIALOGdesign
 

Semelhante a SynTerra / US Bridge Presentation (10 24 11) (20)

Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...
 
Chapter1
Chapter1Chapter1
Chapter1
 
Company profile
Company profileCompany profile
Company profile
 
Airport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation ProjectAirport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation Project
 
Bridges by span
Bridges by spanBridges by span
Bridges by span
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
M.Tech PPT.pptx
M.Tech PPT.pptxM.Tech PPT.pptx
M.Tech PPT.pptx
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design Review
 
Bridge facts
Bridge factsBridge facts
Bridge facts
 
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
 
Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End Treatments
 
Experimental study of shear capacity of reinforced concrete slabs
Experimental study of shear capacity of reinforced concrete slabsExperimental study of shear capacity of reinforced concrete slabs
Experimental study of shear capacity of reinforced concrete slabs
 
Nace barker presentation
Nace barker presentationNace barker presentation
Nace barker presentation
 
2013 11 21-walterdale_csce
2013 11 21-walterdale_csce2013 11 21-walterdale_csce
2013 11 21-walterdale_csce
 
MULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKINGMULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKING
 
Basic R C C structurs
Basic R C C structursBasic R C C structurs
Basic R C C structurs
 
50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear Structures
 
07 AASHTO Bridge Committee Awards Presentation
07 AASHTO Bridge Committee Awards Presentation07 AASHTO Bridge Committee Awards Presentation
07 AASHTO Bridge Committee Awards Presentation
 
CE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
CE72.52 - Lecture 3b - Section Behavior - Shear and TorsionCE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
CE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
 

Mais de dgonano

Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...
Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...
Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...
dgonano
 
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
dgonano
 
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
dgonano
 
Today's Bridge Company (04-07-14)
Today's Bridge Company (04-07-14)Today's Bridge Company (04-07-14)
Today's Bridge Company (04-07-14)
dgonano
 
CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...
CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...
CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...
dgonano
 
Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)
dgonano
 

Mais de dgonano (7)

Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...
Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...
Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, N...
 
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
 
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
 
Today's Bridge Company (04-07-14)
Today's Bridge Company (04-07-14)Today's Bridge Company (04-07-14)
Today's Bridge Company (04-07-14)
 
CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...
CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...
CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03...
 
Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)
 
Engineers Club Of Memphis V2
Engineers Club Of Memphis V2Engineers Club Of Memphis V2
Engineers Club Of Memphis V2
 

SynTerra / US Bridge Presentation (10 24 11)

  • 1. Innovation in Design Using Pre-fabricated Truss Bridges Presented By: Petrina Butler, P.E. SynTerra Corporation Dennis Gonano, P.E. U.S. Bridge
  • 2.
  • 3. Ezell Road Before • Low structural rating • Single lane • Blind curves on approach roadway
  • 4. Ezell Road Alignment 2009 and 2011 aerials provided by USDA NCRS
  • 6. Overhead Bridge Road Alignment 2009 and 2011 aerials provided by USDA NCRS
  • 7. Design Criteria • Increase Safety • Increase Capacity • Minimize Railroad Interference • Economic Solution
  • 8. Bridge Replacement Options • Prestressed Concrete Girder Bridge • Steel Plate Girder Bridge • Pre-fabricated Truss Bridge
  • 9. Advantages of Pre-fabricated Bridge • Shallowest structure depth • Reduced construction activity within railroad right-of-way • Significant cost savings
  • 10. Shallowest Structure Depth Prestressed Steel Plate Pre-fabricated Girder Girder Truss Deck = 8¼” Deck = 8¼” Deck = 8¼” Cross Slope = 2¾” Cross Slope = 2¾” Cross Slope = 3½” Haunch = 1½” Haunch = 1½” Bottom Chord = 31” Beam = 54” Beam = 42” TOTAL = 42¾” TOTAL = 66½” TOTAL = 54½” DEPTH IS UP TO 2 FEET LESS
  • 13. Reduced Construction Activity Within Railroad Right of Way • Accelerate construction schedule • Smaller footprint for staging area • Increase Safety • Reduce road closure duration
  • 14. Significant Cost Savings $1,690,000 Total Cost of Plate Girder Option - $400,000 Savings for Superstructure - $110,000 Savings for Roadway Items - $40,000 Savings for Railroad Flagman $1,140,000 Total Cost of US Bridge Option TOTAL COST SAVINGS = $550,000 OVER 30% COST REDUCTION Cost basis - bid unit cost from actual construction
  • 15. Advantages of Pre-fabricated Bridge • Shallowest structure depth • Less fill for approaches • Smaller footprint • Same loading capacity • Reduced construction activity within railroad right-of-way • Accelerate construction schedule • Smaller footprint for staging area • Increase safety • Reduce delay
  • 16. Advantages of Pre-fabricated Bridge Significant cost savings • Savings of $550,000 for both projects • 30% cost reduction
  • 17. “... the bridges are great. They provided an economical and aesthetically pleasing solution to obtaining adequate clearance over CSXT.” Todd Carroll, CTC Engineering Supervisor Spartanburg County Public Works
  • 18. U.S. Bridge • Founded as American Culvert in 1936 by brothers Herman & Ted Rogovin
  • 19. History • Designing & Building Truss Bridges for over 60 years
  • 20. Location • Cambridge, Ohio • Juncture of I-70 & I-77 • 21 shops covering 250,000 sq ft. in 11 buildings
  • 21. How We Work With You • Feasibility Assessments • Programming Costs • Specifications • Schematic Details • Preliminary Engineering • Supplemental Contract Documents • Modeling & Rendering • Hard Bid Quotes & Information • Engineering Design & Plan Submittals
  • 22. How We Work With You … • Construction Submittals • Installation Assistance • Engineering Department • 4 Professional Engineers • 2 EIT’s • 4 Detailers
  • 23. Coordination • Preliminary Engineering • Loads & Substructure Reactions • Structure Depths & Low Steel Clearance • Final Engineering • Abutment Seat Elevations • Plan Submittals & Reviews Adam Stout, EIT Estimating Engineer
  • 24. Bridge Truss Design • Final Design • Stringer Beams & Connections • Floor Beams & Connections • Truss Members & Connections • Truss Stability • Gusset Plates • Bearings • Deck Slab & SIP Forms • Misc. Scott Flaten, PE Project Engineer
  • 25. Bridge Design Criteria Span: 104’-4” c/c Bearing Roadway Width: 29’-0” curb/curb + 6” curbs Sidewalk: N/A Skew: 24o-0’-0” RF (right fwd.) Design Live Load: HL-93 Expansion: N/A (jointless bridge) Connections: Shop & Field Bolted Design Loads: SIP Forms & Fill: 15 psf Utility Loading: 100 plf 8 ¼” Concrete Slab: 105 psf Future Wearing Surface: 15 psf Truss Reactions: Dead Load, DC: 120.4k Dead Load, DW: 17.0k Live Load: 125.7k Impact: 27.4k Braking (Horiz.): 20.8k Wind (Horiz.): 15.6k
  • 26. Member Calculations • Non-Composite Stringers sized for • Connections are sized for Strength I Flexure Strength I and Service Load II Shear (Slip Critical) and • Composite Floor Beams sized by checked against block shear Strength I Flexure • Floor beam-to-truss connection • Top Chords sized using truss is also checked against Service analysis and checked U-Frame Load III (Wind on structure) Stability to confirm axial capacity can be developed • Gusset Plates are designed in accordance with FHWA • Bottom Chords sized using truss Publication FHWA-IF-09-014 analysis and checked against fatigue allowable stress • Truss tension members checked for gross section yielding and net section fracture (shear lag and block shear) and bolt shear
  • 28. Plan Development • Model Creation (Smart Solids) Software • Connection Design(s) AutoCAD Structural • 3D Solid Additions (Dumb Detailing 2012 (ASD) Solids) • Groups & Views • Detailing • Sheet Creation
  • 29. Plan Development • Design Criteria, General Notes, Sheet Index • Framing & Geometry, Section Views, Field Splices, Bearing Details • SIP Forms, Deck Slab Layout, Railing Installation • Bill of Materials (BOM) • Shop Assemblies • Shop Drawings (Piece Details)
  • 30. Fabrication • AISC Certifications • Simple Bridge • Major Bridge • Fracture Critical Endorsement • Sophisticated Paint Systems Endorsement
  • 31. Processing Equipment • CNC 3-Axis Drill Line for Shape Processing • CNC Plasma Arc/Drill for Plate Processing • Shot Blaster
  • 32. Finish & Corrosion Protection • Hand Grinding • Brush Blasting • Hot-Dip Galvanizing • 2-Coat Paint System (Paint on Galvanizing) • 3-Coat Paint System (DOT Specifications)
  • 33. Shop Assembly Bolt Tightening Shop Layout
  • 35. Construction • Overhead Bridge Road Bridge • Constructed by Taylor & Murphy Construction Company • Ezell Road Bridge • Constructed by Saddlebrook Construction Inc.
  • 36. Overhead Bridge Road Construction Stepped Truss & Stringer Abutment Seat with Integral Abutments
  • 37. Overhead Bridge Road Construction Staging area
  • 38. Overhead Bridge Road Construction Two field splices complete
  • 39. Overhead Bridge Road Construction Lifting first truss and walks to abutment
  • 40. Overhead Bridge Road Construction First truss is in position
  • 41. Overhead Bridge Road Construction Stabilized by cables
  • 42. Overhead Bridge Road Construction Lifting the second truss into place
  • 43. Overhead Bridge Road Construction Erecting first floor beam
  • 44. Overhead Bridge Road Construction Floor beams being erected
  • 45. Overhead Bridge Road Construction SIP forms in place
  • 46. Overhead Bridge Road Construction Open for traffic