You have done risk analysis and determine the following risks and their probabilities could affect your project. Based on these risks, what should you contingency reserve be? Risk 1: 50% chance of a weather delay costing $5,000 Risk 2: 20% chance of a worker strike costing $10,000 Risk 3: 10% chance of catastrophic failure costing $50,000 .