SlideShare uma empresa Scribd logo
1 de 52
Baixar para ler offline
Automatic controlsAutomatic controls
CIBSE C i i i C d C 2001CIBSE Commissioning Code C: 2001
Presentation by N. A. Chazapis,
Commissioning Consultant AthensCommissioning Consultant, Athens -
Greece.
BMS Pre commissioningBMS Pre-commissioning
• Control Application
Software
General
• Control Panels
– Introduction
Panel tests (preliminaries)– General
– Set points
– Time schedules
– Panel tests (preliminaries)
– Panel tests (visual outside)
– Panel tests (Inside)
– Interlocks
– Control loops
( )
– Flash tests
– Function tests
– Sequencing
– Start up and shutdown
Plant changeover– Plant changeover
– Alarm functions
– User Interface software
BMS Pre commissioningBMS Pre-commissioning
• Wiring
– Cable type as specifiedyp p
– Cable identified at both ends
Cable cores identified at both ends– Cable cores identified at both ends
– Security of fixing/protection of cables to walls
– Cable carrier (tray, basket, conduit/trunking)
– Cable management according to specsg g p
– Screening continuity
BMS Pre commissioningBMS Pre-commissioning
• Communication networks
– Check that all network devices are inst correctlyy
– Check that all control devices can be addressed
All network data set up by the IT dept– All network data set up by the IT dept.
– Network testing comply with EN-50174-1
– Structured cabling: all outlets properly labeled
– Changes are reflected & updated ing p
documentation
BMS Pre commissioningBMS Pre-commissioning
• Sensors
– Correct location & orientation
– Adequate access for commissioning
Type of sensor as specified– Type of sensor as specified
– Appropriate sensor identification
– Sensor wired correctly
– Check sensors using a calibrated instrumentg
– Sensor replaced where the req. offset is high
BMS Pre commissioningBMS Pre-commissioning
• Actuators and valves
– Check correct location
– Check adequate access for Cx
Check type of actuator as specified– Check type of actuator as specified
– Check actuator linkage
– Check correct identification
– Check valve ported correctlyp y
– Drive the valve using control system
BMS Pre commissioningBMS Pre-commissioning
• Digital Inputs/Outputs
– Check that the signal DI is sensed correctlyg y
– Check that each contact assumes its correct
normally open or closed statenormally open or closed state
– Check that each DO switches the correct item
of plantof plant
– Ensure that each check is entered on the
l t h kli trelevant checklist
BMS Pre commissioning
Fi ld t l d i
BMS Pre-commissioning
• Field control devices
– Check size as specified
– Check enclosures as specified
– Check number and location as specifiedp
– Check adequate mechanical fixing
– Check identification by mnemonic labellingCheck identification by mnemonic labelling
– Check all cables terminated & identified
Check continuous power available– Check continuous power available
– Check fuse correct type/spares
BMS CommissioningBMS Commissioning
• Control strategy checking:
– Time schedules
• Check that time schedules enable the indented plant
• Check that any out-of-occupancy period, weekendCheck that any out of occupancy period, weekend
and holiday time schedules operate correctly
• Check that the spec routine to ensure unified timep
clocks throughout the complete control system opts
• Check that any specified summer/winter seasonal
changes to control strategies are enabled
BMS CommissioningBMS Commissioning
• Control strategy checking:
– Interlocks
• Check the correct operation of interlocks by
individually switching interlocked items of planty g p
• Check all safety interlocks
• Check the spec interl between different control sysp y
• Check the spec temper interlocks operate correctly
– Low inside air temp activates all duty heating plant
– Low inside air temp
BMS CommissioningBMS Commissioning
• Control strategy checking:
– Control loopsp
• Check attainment of desired set point
• Check above, within specified time following start-upCheck above, within specified time following start up
• Check stability of control loop (avoidance of hunting)
• Check minimal overshootCheck minimal overshoot
• Control loop should be tuned if the above
characteristics are not attained
• Data logging should be performed to proof.
• Check for satisfactory loop cycle/response lags.Check for satisfactory loop cycle/response lags.
BMS CommissioningBMS Commissioning
• Control strategy checking:
– Sequencingq g
• Check for correct sequencing control (in response
to varying plant loads) of items of plant such asy g p ) p
boilers and chillers.
• Check for operation in correct order and at the
desired set points.
BMS CommissioningBMS Commissioning
• Control strategy checking:
– Start-up and shutdownp
• Check for the correct control of plant on start-up
• Check for the correct status of plant items such asCheck for the correct status of plant items such as
dampers and valves on plant shut down.
• Check that the defined restart routine operatesp
correctly when power is rein started after a failure
• Check for any specified sequenced start-up to
accommodate high loads.
BMS CommissioningBMS Commissioning
• Control strategy checking:
– Plant Overrun
• Fan overrun: Check that the fans operate for the
specified period following a period of operation ofp p g p p
the vent.n system during which an electric heater
battery has been in operation.
• Pump overrun: Check that the pumps operate for
the specified period following a period of operation
of the boilers and chillers to allow temperatures toof the boilers and chillers to allow temperatures to
stabilize in order to prevent spurious tripping of
safety devices.safety devices.
BMS CommissioningBMS Commissioning
• Control strategy checking:
– Plant changeoverg
• Check automatic changeover of plant failure by
manually “failing” specific items of plant.y g p p
• Check automatic changeover of plant in response
to the specified number of run hours being
exceeded by manually increasing the run hours.
• Check the sequence of events following the failure
f th d t db it f l tof the second or standby item of plant.
BMS Commissioning
C t l t t h ki
BMS Commissioning
• Control strategy checking:
– Alarm functions
• Check operation of each alarm function by
triggering an alarm condition.
Ch k th t ti d l h l i il bl• Check that a time delay on each alarm is available
as specified.
• Check that any specific post-alarm controlCheck that any specific post alarm control
functions, operate correctly.
• Check that alarm masking is in place so that nog
spurious alarms are raised.
• Check the level or category of each alarm.
BMS CommissioningBMS Commissioning
• Checking Procedures for basic control
functions
– Optimizer
• Optimum start heating: check that the specified intl• Optimum start heating: check that the specified intl
temp is reached at the start of occupancy
• Check that the maximum pre-heat time isCheck that the maximum pre heat time is
incorporated
• Check that the compensator control is overriddenp
and maximum heat output achieved during tha pre-
heat period.
BMS Commissioning
Ch ki P d f b i t l
BMS Commissioning
• Checking Procedures for basic control
functions
– Compensation:
• Check that the compensator gives the specified
control function in response to changes in the
internal and external air temperatures.
• Check that each compensator control function is• Check that each compensator control function is
related to the correct internal temperature sensor
and heating plant zone.
• Check that the comp_cont_funct is overridden
during operation of the optimizer control function.
BMS CommissioningBMS Commissioning
• Checking Procedures for basic control
functions
– Mixed damper control:
• Check that the re-circ n damper is in the full re-• Check that the re-circ.n damper is in the full re-
circ.n position and the OA and EA dampers are
closed when the AHU is not in operation.p
• Check that the damper positions are such that the
specified req.d for min.m fresh air is met during
plant operation. Air flow measurement should be
performed by the mech services Cx engineer.
BMS Commissioning
Ch ki P d f b i t l
BMS Commissioning
• Checking Procedures for basic control
functions
– Mixed damper control:
• Free Cooling: Check that the OA & EA dampers
modulate towards fully open when the RA temp is
greater than the OA temp and cooling is requiered
• Free Cooling: Check that the dampers modulate to• Free Cooling: Check that the dampers modulate to
ensure the minimum OA flow rate is supplied when
the RA temp is greater than the OA and heating is
required or when the RA temp is less than the OA
temp and cooling is required.
BMS CommissioningBMS Commissioning
• Checking Procedures for basic control
functions
– Demand Controlled Ventilation (DCV)
• Check that the specified min fresh air requirem t is• Check that the specified min. fresh air requirem.t is
not compromised by the DCV control routine.
• Check that the plant operates and the dampersCheck that the plant operates and the dampers
modulate to allow an increase in ventilation rate
when the CO2 set point is exceeded.
• Check the highest demand priority, between DCV
and “free cooling”
BMS Commissioning
Ch ki P d f b i t l
BMS Commissioning
• Checking Procedures for basic control
functions
– Control of natural ventilation
• Check any specified manual overrides operate
• Check any specified automatic overrides operate
• Check prevention of ingress of cold OA
• Check prevention of vents opening if the OA temp
is above the IA temp and cooling vent/n is req/d
• Check prevention of rain ingress• Check prevention of rain ingress.
• Prevention of vents opening in the event of high
wind speeds.p
BMS CommissioningBMS Commissioning
• Lighting Controls
– Daylight-linked/lumen maintenancey g
• Check that the light sensor is located in a rep
location. Calibrate the sensor to give the spec/dg p
light levels.
• The calibration should take place at the lighting
controller, or operator workstation, not direct at the
sensor itself.
BMS Commissioning
Li hti C t l
BMS Commissioning
• Lighting Controls
– Occupancy sensors
• Check that the zone occupancy sensor is located
and oriented correctly in relation to occupants.
Ch k th t th iti it i• Check that the occupancy sensor sensitivity is
appropriate. Too low a sensitivity will result in
seated occupants not being detected, while toop g ,
high a sensitivity may result in movement outside
the zone activating the lights.
Ch k th ti d l tti i t ti f• Check the time delay settings is representative of
the occupant work/movement patterns.
BMS CommissioningBMS Commissioning
• Lighting Controls
– Manual dimmingg
• Check that the upper and lower limits of the
dimming range are as specified.g g p
BMS CommissioningBMS Commissioning
• Lighting Controls
– Sweep-offp
• Check that the start and stop times along with the
override control (e.g occupant or security staff( g p y
override) are as specified.
BMS Commissioning
O t W k t ti
BMS Commissioning
• Operator Workstations
– Check that the specified s/w release is installed
– Check that passwords and associated access
levels are set up correctly.
– Check that all outstations and unitary control
devices can be addressed and data sent and
retrieved.
– Check that any spec/d plant/bldg schematics are
displayed correctly on request.
– Check that data logging functions operate.
BMS CommissioningBMS Commissioning
• Occupant interfaces
– Check that the physical location of occupantp y p
control devices is correct
– Check that each occupant control deviceCheck that each occupant control device
controls the correct items of the plant
Check that the OCD / plant zoning– Check that the OCD / plant zoning
relationship is correct
Ch k th t th t l b d f th OCD i– Check that the control band of the OCD is as
specified
BMS CommissioningBMS Commissioning
• Communications networks
– Check that all control devices can be
addressed over the communications network
– Check that the speed of comm/s meets thatCheck that the speed of comm/s meets that
specified. It is important that this is assessed
when the network is under “normal” cond/swhen the network is under normal cond/s
– Check that the data comm/s are error-free
Ch k th t ti f d t– Check that no cross corruption of data occurs
– Check other devices: routers, bridges.
BMS CommissioningBMS Commissioning
• Integrated systems – gateways
– Check that the gateway drivers convertg y
between the two communications protocols.
– Check that the functionality of the gatewayCheck that the functionality of the gateway
meets the spec/s.
Check that the as specified transfer of data– Check that the as specified transfer of data
over the gateway occurs.
Ch k th t th ti d l i d i– Check that the time delays experienced in
transfer data do not exceed the spec/d max.
BMS CommissioningBMS Commissioning
• Integrated systems – direct
interoperabilityp y
– Check the degree of direct interoperability.
Check the functional profiles that define the– Check the functional profiles that define the
data which can be transferred for specific
items of plantitems of plant.
– Check that the data transferred between the
diff t f t t l d tdifferent manufacturers control products
meets the specified functional profiles.
BMS CommissioningBMS Commissioning
• Integration with fire detection systems
– Integration for monitoring (uni-directional)g g ( )
• Increasingly common (alarm status).
• Check the status info for each fire alarm detectorCheck the status info for each fire alarm detector
can be viewed on the BMS operator PC.
• Check that any spec/d bldg graphics indicating they p g g p g
location of detector heads can be viewed w. status
• Check that a fire alarm cond/n automatically
displays the appropriate bldg graphic.
• Check time delays receiving fire alarm data.
BMS CommissioningBMS Commissioning
• Integration with fire detection systems
– Integration for monitoring (bi-directional)g g ( )
• Check that the alteration of any fire alarm
parameter via the BMS has no adverse effect onp
the correct operation of the fire alarm system.
• Test re-setting of alarm sounders.
• Test changing thresholds on detector heads.
• Test isolating fire detection devices & sounders.
• Test partial system re-configuration.
• Check that loss of electrical power to the BMS hasp
no adverse effect on the fire detection system.
BMS Commissioning
I t ti ith fi d t ti t
BMS Commissioning
• Integration with fire detection systems
– Integration for control
• Control smoke protection plant such as smoke
vents, and fans for escape route pressurization
systemssystems.
• Check that the BMS can receive fire alarm data
originating from each detector and within time limitg g
• Check for correct control logic in response to a fire
alarm condition on a point-by-point basis.
• Confirm that the correct plant is activated in the
spec/d sequence.
BMS CommissioningBMS Commissioning
• Security systems – Intruder alarm
– Check that the status information for each
specified detector can be viewed on the W/S.
– Check that any specified graphics indicatingCheck that any specified graphics indicating
the location of detectors can be viewed.
Check that an alarm condition results in the– Check that an alarm condition results in the
automatic display of the appropriate graphic.
Ch k th t ti d l i i i– Check that any time delay in receiving an
alarm is within the specified maximum.
BMS Commissioning
S it t A t l
BMS Commissioning
• Security systems – Access control
– Check that the BMS operator W/S displays
the specified status information from the
access control system (ACS).
– Check that any time delay in receiving data
from the ACS system is within the spec/d max
– Check that any spec/d bldg services control
actions operate correctly in response to the
t t f th ACSstatus of the ACS.
– Check that ACS are correctly integr/d with
Lifts & EscalatorsLifts & Escalators.
BMS Commissioning
I t ti f l t i l l
BMS Commissioning
• Interruption of electrical power supply
– Check that the controllers preserve control
strategy configuration data for a spec/d periodstrategy configuration data for a spec/d period
when mains power is lost.
– Check that the condition of any volatile dataCheck that the condition of any volatile data
protection system is regularly and
automatically monitored.
– Check that an alarm is raised on loss of data
by any controller or other device and/or failure
of the monitoring systemof the monitoring system.
– Check that the control system operates
correctly under generator standby and UPScorrectly under generator standby and UPS
power.
BMS Commissioning
S ifi Pl t C V l
BMS Commissioning
• Specific Plant Cx – Valves
– Confirm that the valves have been correctly
selected, installed, and applied.
– Check the characteristic positioner, linear or
equal percentage.
– Under dynamic conditions:
• Drive the valve across the whole span.
• Check the max and min positions
• Check the rate of valve movement and whether it
meets that specified.
BMS CommissioningBMS Commissioning
• Specific pant Cx – Dampers
– Check that the dampers are correctly installedp y
and applied.
– Check that all damper sections & linkagesCheck that all damper sections & linkages
operate synchronously.
Check the max and min positions and rate of– Check the max and min positions and rate of
movement.
Ch k /d i t l ki ith th f– Check any spec/d interlocking with other fans.
– On receipt of a fire signal check the spec.pos.
BMS Commissioning
S ifi l t C F ( i l d)
BMS Commissioning
• Specific plant Cx – Fans (single speed)
– Panel controls (power, fan run/trip, fuses, )
– Hardware:
• Check the fan rotates in correct direction.
• Check start/stop by the application s/w.
• Check correct fan status & mnemonic.
– Interlocks:
• Appropriate interlocks and overrides, with plant in
ffmanual, off, auto modes.
• Check the fans operate as spec/d under fire alarm.
BMS CommissioningBMS Commissioning
• Specific plant Cx – Fans (single speed)
– Alarms:
• Set the fan air flow failure device to the desired
value and simulate a no flow condition.
• Check an alarm is initiated and fans are shutdown.
• Set the alarm inhibit time for the air flow failure
device to a time consistent with the fan start.
• Check that on fan failure the corresponding supply
or extract fan switches off.
BMS CommissioningBMS Commissioning
• Specific plant Cx – Fans (variable speed)
BMS CommissioningBMS Commissioning
• Specific plant Cx – Pumps and Inverter
banks (batteries).( )
BMS CommissioningBMS Commissioning
• Specific plant Cx- Terminal units – FCU
and VAV units.
BMS CommissioningBMS Commissioning
• Specific plant Cx – Heating and Cooling
coils.
BMS CommissioningBMS Commissioning
• Specific plant Cx – CHW dehumidification
coils
BMS CommissioningBMS Commissioning
• Specific plant Cx – Humidifier steam &
sprayp y
BMS CommissioningBMS Commissioning
• System Handover - Witnessing
BMS CommissioningBMS Commissioning
• System Handover – Documentation
Operations and Maintenance Manualp
BMS CommissioningBMS Commissioning
• System Handover – Operator Training
BMS CommissioningBMS Commissioning
• Post-occupancy checks – Complete
performance checking – global checksp g g
BMS CommissioningBMS Commissioning
• Post-occupancy checks - Complete
performance checking – system level checksp g y

Mais conteúdo relacionado

Mais procurados

Practical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & TechniciansPractical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & TechniciansLiving Online
 
day 3: Control Concepts & BMS
day 3: Control Concepts & BMS day 3: Control Concepts & BMS
day 3: Control Concepts & BMS RCREEE
 
Building management-system power point
Building management-system power pointBuilding management-system power point
Building management-system power pointazharbang
 
DCS PRESENTATION
DCS PRESENTATIONDCS PRESENTATION
DCS PRESENTATIONbvent2005
 
Optimizing Building Performance with Building Management Systems (BMS): Benef...
Optimizing Building Performance with Building Management Systems (BMS): Benef...Optimizing Building Performance with Building Management Systems (BMS): Benef...
Optimizing Building Performance with Building Management Systems (BMS): Benef...Ashraf El Desoky
 
Basic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryBasic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryHassanulHadiZakaria
 
Scada systems automating electrical distribution
Scada systems automating electrical distributionScada systems automating electrical distribution
Scada systems automating electrical distributionSHUBHAM SAINI
 
Building management system
Building management systemBuilding management system
Building management systemcharan malyala
 
VARIABLE REFRIGERATE FLOW
VARIABLE REFRIGERATE FLOWVARIABLE REFRIGERATE FLOW
VARIABLE REFRIGERATE FLOWRIDDHESH VARIK
 
Basics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaBasics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaJitendra Jha
 
Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)
Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)
Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)Dimple Poddar
 
Variable refrigerant flow systems
Variable refrigerant flow systemsVariable refrigerant flow systems
Variable refrigerant flow systemsVAHAB ABDUL
 

Mais procurados (20)

Practical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & TechniciansPractical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & Technicians
 
day 3: Control Concepts & BMS
day 3: Control Concepts & BMS day 3: Control Concepts & BMS
day 3: Control Concepts & BMS
 
Building management-system power point
Building management-system power pointBuilding management-system power point
Building management-system power point
 
BMS-System
BMS-SystemBMS-System
BMS-System
 
BUILDING MEP SYSTEM
BUILDING MEP SYSTEMBUILDING MEP SYSTEM
BUILDING MEP SYSTEM
 
DCS PRESENTATION
DCS PRESENTATIONDCS PRESENTATION
DCS PRESENTATION
 
Optimizing Building Performance with Building Management Systems (BMS): Benef...
Optimizing Building Performance with Building Management Systems (BMS): Benef...Optimizing Building Performance with Building Management Systems (BMS): Benef...
Optimizing Building Performance with Building Management Systems (BMS): Benef...
 
Basic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryBasic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction Industry
 
Scada systems automating electrical distribution
Scada systems automating electrical distributionScada systems automating electrical distribution
Scada systems automating electrical distribution
 
Building management system
Building management systemBuilding management system
Building management system
 
VARIABLE REFRIGERATE FLOW
VARIABLE REFRIGERATE FLOWVARIABLE REFRIGERATE FLOW
VARIABLE REFRIGERATE FLOW
 
Basics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra JhaBasics of HVAC by Jitendra Jha
Basics of HVAC by Jitendra Jha
 
Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)
Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)
Building management system (LINK IN DESCRIPTION FOR DOWNLOAD)
 
Bms overview
Bms overviewBms overview
Bms overview
 
Variable refrigerant flow systems
Variable refrigerant flow systemsVariable refrigerant flow systems
Variable refrigerant flow systems
 
BMSOverview
BMSOverviewBMSOverview
BMSOverview
 
DCS Introduction
DCS IntroductionDCS Introduction
DCS Introduction
 
CHILLER PLANT MANAGER
CHILLER PLANT MANAGERCHILLER PLANT MANAGER
CHILLER PLANT MANAGER
 
Dcs
DcsDcs
Dcs
 
Panel check-list
Panel check-listPanel check-list
Panel check-list
 

Destaque

Optimised Buildings
Optimised BuildingsOptimised Buildings
Optimised BuildingsGary Bark
 
Bms activities 2015-16
Bms activities 2015-16Bms activities 2015-16
Bms activities 2015-16bmspune
 
Final building service (assignment)
Final   building service (assignment)Final   building service (assignment)
Final building service (assignment)Chee Lee
 
CCTV Camera Presentation
CCTV Camera PresentationCCTV Camera Presentation
CCTV Camera PresentationBasith JM
 

Destaque (6)

Optimised Buildings
Optimised BuildingsOptimised Buildings
Optimised Buildings
 
Bms activities 2015-16
Bms activities 2015-16Bms activities 2015-16
Bms activities 2015-16
 
Vkat product information
Vkat product informationVkat product information
Vkat product information
 
Final building service (assignment)
Final   building service (assignment)Final   building service (assignment)
Final building service (assignment)
 
CCTV Camera Presentation
CCTV Camera PresentationCCTV Camera Presentation
CCTV Camera Presentation
 
Cctv presentation
Cctv presentationCctv presentation
Cctv presentation
 

Semelhante a BMS COMMISSIONING CODE C_CIBSE

Inst maint practices
Inst maint practicesInst maint practices
Inst maint practicesPrem Baboo
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practicesPrem Baboo
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
Jomaray Pulp Packaging, Ana's breeders.ppt
Jomaray Pulp Packaging, Ana's breeders.pptJomaray Pulp Packaging, Ana's breeders.ppt
Jomaray Pulp Packaging, Ana's breeders.pptBenjoDelaCuadra
 
Bmssystem basic-141229052438-conversion-gate02
Bmssystem basic-141229052438-conversion-gate02Bmssystem basic-141229052438-conversion-gate02
Bmssystem basic-141229052438-conversion-gate02manjunatha appaiah
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdfAnithaSyam
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintananceAnasMirza10
 
AUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMAUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMkumarswamy927
 
GridPoint\’s Energy Management System Intelligent Controllers
GridPoint\’s Energy Management System Intelligent ControllersGridPoint\’s Energy Management System Intelligent Controllers
GridPoint\’s Energy Management System Intelligent ControllersMichele_Zambrano333
 
computerized-microprocessor-controlled-dv-test-bench.pptx
computerized-microprocessor-controlled-dv-test-bench.pptxcomputerized-microprocessor-controlled-dv-test-bench.pptx
computerized-microprocessor-controlled-dv-test-bench.pptxNeometrix_Engineering_Pvt_Ltd
 
CENTRALIZED MONITORED COOLING SYSTEM
CENTRALIZED MONITORED COOLING SYSTEMCENTRALIZED MONITORED COOLING SYSTEM
CENTRALIZED MONITORED COOLING SYSTEMmoehassan
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.pptssuser9e9be71
 
VAV Controls_NEP 2017_Rev1.pptx
VAV Controls_NEP 2017_Rev1.pptxVAV Controls_NEP 2017_Rev1.pptx
VAV Controls_NEP 2017_Rev1.pptxKartikPrabhakar2
 

Semelhante a BMS COMMISSIONING CODE C_CIBSE (20)

Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
Jomaray Pulp Packaging, Ana's breeders.ppt
Jomaray Pulp Packaging, Ana's breeders.pptJomaray Pulp Packaging, Ana's breeders.ppt
Jomaray Pulp Packaging, Ana's breeders.ppt
 
Bmssystem basic-141229052438-conversion-gate02
Bmssystem basic-141229052438-conversion-gate02Bmssystem basic-141229052438-conversion-gate02
Bmssystem basic-141229052438-conversion-gate02
 
C&i systems
C&i systemsC&i systems
C&i systems
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdf
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintanance
 
AUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMAUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEM
 
GridPoint\’s Energy Management System Intelligent Controllers
GridPoint\’s Energy Management System Intelligent ControllersGridPoint\’s Energy Management System Intelligent Controllers
GridPoint\’s Energy Management System Intelligent Controllers
 
Ks%20 eng
Ks%20 engKs%20 eng
Ks%20 eng
 
updated_ashishmalhotra
updated_ashishmalhotraupdated_ashishmalhotra
updated_ashishmalhotra
 
jayakumarcv
jayakumarcvjayakumarcv
jayakumarcv
 
Oil production3
Oil production3Oil production3
Oil production3
 
bms-the-basics-explained.pptx
bms-the-basics-explained.pptxbms-the-basics-explained.pptx
bms-the-basics-explained.pptx
 
bms-the-basics-explained.pptx
bms-the-basics-explained.pptxbms-the-basics-explained.pptx
bms-the-basics-explained.pptx
 
computerized-microprocessor-controlled-dv-test-bench.pptx
computerized-microprocessor-controlled-dv-test-bench.pptxcomputerized-microprocessor-controlled-dv-test-bench.pptx
computerized-microprocessor-controlled-dv-test-bench.pptx
 
CENTRALIZED MONITORED COOLING SYSTEM
CENTRALIZED MONITORED COOLING SYSTEMCENTRALIZED MONITORED COOLING SYSTEM
CENTRALIZED MONITORED COOLING SYSTEM
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
VAV Controls_NEP 2017_Rev1.pptx
VAV Controls_NEP 2017_Rev1.pptxVAV Controls_NEP 2017_Rev1.pptx
VAV Controls_NEP 2017_Rev1.pptx
 

Mais de Nicholas Chazapis

Predictive maintenance of an intelligent FCU
Predictive maintenance of an intelligent FCUPredictive maintenance of an intelligent FCU
Predictive maintenance of an intelligent FCUNicholas Chazapis
 
HVAC equipment and systems optimization for efficiency
HVAC equipment and systems optimization for efficiencyHVAC equipment and systems optimization for efficiency
HVAC equipment and systems optimization for efficiencyNicholas Chazapis
 
17.11.2016 fm design chazapis presentation
17.11.2016 fm design chazapis presentation17.11.2016 fm design chazapis presentation
17.11.2016 fm design chazapis presentationNicholas Chazapis
 
Chazapis cx for better buildings rev2
Chazapis cx for better buildings   rev2Chazapis cx for better buildings   rev2
Chazapis cx for better buildings rev2Nicholas Chazapis
 
2016 chazapis energy - efficiency - comfort - iso 50001
2016 chazapis   energy - efficiency - comfort - iso 500012016 chazapis   energy - efficiency - comfort - iso 50001
2016 chazapis energy - efficiency - comfort - iso 50001Nicholas Chazapis
 
Chazapis cx for better buildings rev
Chazapis cx for better buildings   revChazapis cx for better buildings   rev
Chazapis cx for better buildings revNicholas Chazapis
 
Chazapis cx for better buildings
Chazapis cx for better buildingsChazapis cx for better buildings
Chazapis cx for better buildingsNicholas Chazapis
 
Chazapis Commissioning: are you interested in?
Chazapis Commissioning: are you interested in?Chazapis Commissioning: are you interested in?
Chazapis Commissioning: are you interested in?Nicholas Chazapis
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Nicholas Chazapis
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Nicholas Chazapis
 
Cx a activities flow diagram en
Cx a activities flow diagram enCx a activities flow diagram en
Cx a activities flow diagram enNicholas Chazapis
 
EMPATHY IN PROJECT MANAGEMENT EL V20100915
EMPATHY IN PROJECT MANAGEMENT EL   V20100915EMPATHY IN PROJECT MANAGEMENT EL   V20100915
EMPATHY IN PROJECT MANAGEMENT EL V20100915Nicholas Chazapis
 
Chazapis elot en 15232 the impact of bacs - preso
Chazapis   elot en 15232 the impact of bacs - presoChazapis   elot en 15232 the impact of bacs - preso
Chazapis elot en 15232 the impact of bacs - presoNicholas Chazapis
 
Chazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOL
Chazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOLChazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOL
Chazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOLNicholas Chazapis
 
Commissioning for energy saving nha
Commissioning for energy saving nhaCommissioning for energy saving nha
Commissioning for energy saving nhaNicholas Chazapis
 

Mais de Nicholas Chazapis (19)

Chazapis the automated bldg
Chazapis the automated bldgChazapis the automated bldg
Chazapis the automated bldg
 
Systems trg syllabus
Systems trg syllabusSystems trg syllabus
Systems trg syllabus
 
Predictive maintenance of an intelligent FCU
Predictive maintenance of an intelligent FCUPredictive maintenance of an intelligent FCU
Predictive maintenance of an intelligent FCU
 
Chazapis cx management
Chazapis cx managementChazapis cx management
Chazapis cx management
 
HVAC equipment and systems optimization for efficiency
HVAC equipment and systems optimization for efficiencyHVAC equipment and systems optimization for efficiency
HVAC equipment and systems optimization for efficiency
 
17.11.2016 fm design chazapis presentation
17.11.2016 fm design chazapis presentation17.11.2016 fm design chazapis presentation
17.11.2016 fm design chazapis presentation
 
Chazapis cx for better buildings rev2
Chazapis cx for better buildings   rev2Chazapis cx for better buildings   rev2
Chazapis cx for better buildings rev2
 
2016 chazapis energy - efficiency - comfort - iso 50001
2016 chazapis   energy - efficiency - comfort - iso 500012016 chazapis   energy - efficiency - comfort - iso 50001
2016 chazapis energy - efficiency - comfort - iso 50001
 
Chazapis cx for better buildings rev
Chazapis cx for better buildings   revChazapis cx for better buildings   rev
Chazapis cx for better buildings rev
 
Chazapis cx for better buildings
Chazapis cx for better buildingsChazapis cx for better buildings
Chazapis cx for better buildings
 
Chazapis Commissioning: are you interested in?
Chazapis Commissioning: are you interested in?Chazapis Commissioning: are you interested in?
Chazapis Commissioning: are you interested in?
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.
 
Chazapis pm basics
Chazapis pm basicsChazapis pm basics
Chazapis pm basics
 
Cx a activities flow diagram en
Cx a activities flow diagram enCx a activities flow diagram en
Cx a activities flow diagram en
 
EMPATHY IN PROJECT MANAGEMENT EL V20100915
EMPATHY IN PROJECT MANAGEMENT EL   V20100915EMPATHY IN PROJECT MANAGEMENT EL   V20100915
EMPATHY IN PROJECT MANAGEMENT EL V20100915
 
Chazapis elot en 15232 the impact of bacs - preso
Chazapis   elot en 15232 the impact of bacs - presoChazapis   elot en 15232 the impact of bacs - preso
Chazapis elot en 15232 the impact of bacs - preso
 
Chazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOL
Chazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOLChazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOL
Chazapis HVAC SYSTEMS COMMISSIONING A PROJECT MANAGEMENT TOOL
 
Commissioning for energy saving nha
Commissioning for energy saving nhaCommissioning for energy saving nha
Commissioning for energy saving nha
 

Último

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Último (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

BMS COMMISSIONING CODE C_CIBSE

  • 1. Automatic controlsAutomatic controls CIBSE C i i i C d C 2001CIBSE Commissioning Code C: 2001 Presentation by N. A. Chazapis, Commissioning Consultant AthensCommissioning Consultant, Athens - Greece.
  • 2. BMS Pre commissioningBMS Pre-commissioning • Control Application Software General • Control Panels – Introduction Panel tests (preliminaries)– General – Set points – Time schedules – Panel tests (preliminaries) – Panel tests (visual outside) – Panel tests (Inside) – Interlocks – Control loops ( ) – Flash tests – Function tests – Sequencing – Start up and shutdown Plant changeover– Plant changeover – Alarm functions – User Interface software
  • 3. BMS Pre commissioningBMS Pre-commissioning • Wiring – Cable type as specifiedyp p – Cable identified at both ends Cable cores identified at both ends– Cable cores identified at both ends – Security of fixing/protection of cables to walls – Cable carrier (tray, basket, conduit/trunking) – Cable management according to specsg g p – Screening continuity
  • 4. BMS Pre commissioningBMS Pre-commissioning • Communication networks – Check that all network devices are inst correctlyy – Check that all control devices can be addressed All network data set up by the IT dept– All network data set up by the IT dept. – Network testing comply with EN-50174-1 – Structured cabling: all outlets properly labeled – Changes are reflected & updated ing p documentation
  • 5. BMS Pre commissioningBMS Pre-commissioning • Sensors – Correct location & orientation – Adequate access for commissioning Type of sensor as specified– Type of sensor as specified – Appropriate sensor identification – Sensor wired correctly – Check sensors using a calibrated instrumentg – Sensor replaced where the req. offset is high
  • 6. BMS Pre commissioningBMS Pre-commissioning • Actuators and valves – Check correct location – Check adequate access for Cx Check type of actuator as specified– Check type of actuator as specified – Check actuator linkage – Check correct identification – Check valve ported correctlyp y – Drive the valve using control system
  • 7. BMS Pre commissioningBMS Pre-commissioning • Digital Inputs/Outputs – Check that the signal DI is sensed correctlyg y – Check that each contact assumes its correct normally open or closed statenormally open or closed state – Check that each DO switches the correct item of plantof plant – Ensure that each check is entered on the l t h kli trelevant checklist
  • 8. BMS Pre commissioning Fi ld t l d i BMS Pre-commissioning • Field control devices – Check size as specified – Check enclosures as specified – Check number and location as specifiedp – Check adequate mechanical fixing – Check identification by mnemonic labellingCheck identification by mnemonic labelling – Check all cables terminated & identified Check continuous power available– Check continuous power available – Check fuse correct type/spares
  • 9. BMS CommissioningBMS Commissioning • Control strategy checking: – Time schedules • Check that time schedules enable the indented plant • Check that any out-of-occupancy period, weekendCheck that any out of occupancy period, weekend and holiday time schedules operate correctly • Check that the spec routine to ensure unified timep clocks throughout the complete control system opts • Check that any specified summer/winter seasonal changes to control strategies are enabled
  • 10. BMS CommissioningBMS Commissioning • Control strategy checking: – Interlocks • Check the correct operation of interlocks by individually switching interlocked items of planty g p • Check all safety interlocks • Check the spec interl between different control sysp y • Check the spec temper interlocks operate correctly – Low inside air temp activates all duty heating plant – Low inside air temp
  • 11. BMS CommissioningBMS Commissioning • Control strategy checking: – Control loopsp • Check attainment of desired set point • Check above, within specified time following start-upCheck above, within specified time following start up • Check stability of control loop (avoidance of hunting) • Check minimal overshootCheck minimal overshoot • Control loop should be tuned if the above characteristics are not attained • Data logging should be performed to proof. • Check for satisfactory loop cycle/response lags.Check for satisfactory loop cycle/response lags.
  • 12. BMS CommissioningBMS Commissioning • Control strategy checking: – Sequencingq g • Check for correct sequencing control (in response to varying plant loads) of items of plant such asy g p ) p boilers and chillers. • Check for operation in correct order and at the desired set points.
  • 13. BMS CommissioningBMS Commissioning • Control strategy checking: – Start-up and shutdownp • Check for the correct control of plant on start-up • Check for the correct status of plant items such asCheck for the correct status of plant items such as dampers and valves on plant shut down. • Check that the defined restart routine operatesp correctly when power is rein started after a failure • Check for any specified sequenced start-up to accommodate high loads.
  • 14. BMS CommissioningBMS Commissioning • Control strategy checking: – Plant Overrun • Fan overrun: Check that the fans operate for the specified period following a period of operation ofp p g p p the vent.n system during which an electric heater battery has been in operation. • Pump overrun: Check that the pumps operate for the specified period following a period of operation of the boilers and chillers to allow temperatures toof the boilers and chillers to allow temperatures to stabilize in order to prevent spurious tripping of safety devices.safety devices.
  • 15. BMS CommissioningBMS Commissioning • Control strategy checking: – Plant changeoverg • Check automatic changeover of plant failure by manually “failing” specific items of plant.y g p p • Check automatic changeover of plant in response to the specified number of run hours being exceeded by manually increasing the run hours. • Check the sequence of events following the failure f th d t db it f l tof the second or standby item of plant.
  • 16. BMS Commissioning C t l t t h ki BMS Commissioning • Control strategy checking: – Alarm functions • Check operation of each alarm function by triggering an alarm condition. Ch k th t ti d l h l i il bl• Check that a time delay on each alarm is available as specified. • Check that any specific post-alarm controlCheck that any specific post alarm control functions, operate correctly. • Check that alarm masking is in place so that nog spurious alarms are raised. • Check the level or category of each alarm.
  • 17. BMS CommissioningBMS Commissioning • Checking Procedures for basic control functions – Optimizer • Optimum start heating: check that the specified intl• Optimum start heating: check that the specified intl temp is reached at the start of occupancy • Check that the maximum pre-heat time isCheck that the maximum pre heat time is incorporated • Check that the compensator control is overriddenp and maximum heat output achieved during tha pre- heat period.
  • 18. BMS Commissioning Ch ki P d f b i t l BMS Commissioning • Checking Procedures for basic control functions – Compensation: • Check that the compensator gives the specified control function in response to changes in the internal and external air temperatures. • Check that each compensator control function is• Check that each compensator control function is related to the correct internal temperature sensor and heating plant zone. • Check that the comp_cont_funct is overridden during operation of the optimizer control function.
  • 19. BMS CommissioningBMS Commissioning • Checking Procedures for basic control functions – Mixed damper control: • Check that the re-circ n damper is in the full re-• Check that the re-circ.n damper is in the full re- circ.n position and the OA and EA dampers are closed when the AHU is not in operation.p • Check that the damper positions are such that the specified req.d for min.m fresh air is met during plant operation. Air flow measurement should be performed by the mech services Cx engineer.
  • 20. BMS Commissioning Ch ki P d f b i t l BMS Commissioning • Checking Procedures for basic control functions – Mixed damper control: • Free Cooling: Check that the OA & EA dampers modulate towards fully open when the RA temp is greater than the OA temp and cooling is requiered • Free Cooling: Check that the dampers modulate to• Free Cooling: Check that the dampers modulate to ensure the minimum OA flow rate is supplied when the RA temp is greater than the OA and heating is required or when the RA temp is less than the OA temp and cooling is required.
  • 21. BMS CommissioningBMS Commissioning • Checking Procedures for basic control functions – Demand Controlled Ventilation (DCV) • Check that the specified min fresh air requirem t is• Check that the specified min. fresh air requirem.t is not compromised by the DCV control routine. • Check that the plant operates and the dampersCheck that the plant operates and the dampers modulate to allow an increase in ventilation rate when the CO2 set point is exceeded. • Check the highest demand priority, between DCV and “free cooling”
  • 22. BMS Commissioning Ch ki P d f b i t l BMS Commissioning • Checking Procedures for basic control functions – Control of natural ventilation • Check any specified manual overrides operate • Check any specified automatic overrides operate • Check prevention of ingress of cold OA • Check prevention of vents opening if the OA temp is above the IA temp and cooling vent/n is req/d • Check prevention of rain ingress• Check prevention of rain ingress. • Prevention of vents opening in the event of high wind speeds.p
  • 23. BMS CommissioningBMS Commissioning • Lighting Controls – Daylight-linked/lumen maintenancey g • Check that the light sensor is located in a rep location. Calibrate the sensor to give the spec/dg p light levels. • The calibration should take place at the lighting controller, or operator workstation, not direct at the sensor itself.
  • 24. BMS Commissioning Li hti C t l BMS Commissioning • Lighting Controls – Occupancy sensors • Check that the zone occupancy sensor is located and oriented correctly in relation to occupants. Ch k th t th iti it i• Check that the occupancy sensor sensitivity is appropriate. Too low a sensitivity will result in seated occupants not being detected, while toop g , high a sensitivity may result in movement outside the zone activating the lights. Ch k th ti d l tti i t ti f• Check the time delay settings is representative of the occupant work/movement patterns.
  • 25. BMS CommissioningBMS Commissioning • Lighting Controls – Manual dimmingg • Check that the upper and lower limits of the dimming range are as specified.g g p
  • 26. BMS CommissioningBMS Commissioning • Lighting Controls – Sweep-offp • Check that the start and stop times along with the override control (e.g occupant or security staff( g p y override) are as specified.
  • 27. BMS Commissioning O t W k t ti BMS Commissioning • Operator Workstations – Check that the specified s/w release is installed – Check that passwords and associated access levels are set up correctly. – Check that all outstations and unitary control devices can be addressed and data sent and retrieved. – Check that any spec/d plant/bldg schematics are displayed correctly on request. – Check that data logging functions operate.
  • 28. BMS CommissioningBMS Commissioning • Occupant interfaces – Check that the physical location of occupantp y p control devices is correct – Check that each occupant control deviceCheck that each occupant control device controls the correct items of the plant Check that the OCD / plant zoning– Check that the OCD / plant zoning relationship is correct Ch k th t th t l b d f th OCD i– Check that the control band of the OCD is as specified
  • 29. BMS CommissioningBMS Commissioning • Communications networks – Check that all control devices can be addressed over the communications network – Check that the speed of comm/s meets thatCheck that the speed of comm/s meets that specified. It is important that this is assessed when the network is under “normal” cond/swhen the network is under normal cond/s – Check that the data comm/s are error-free Ch k th t ti f d t– Check that no cross corruption of data occurs – Check other devices: routers, bridges.
  • 30. BMS CommissioningBMS Commissioning • Integrated systems – gateways – Check that the gateway drivers convertg y between the two communications protocols. – Check that the functionality of the gatewayCheck that the functionality of the gateway meets the spec/s. Check that the as specified transfer of data– Check that the as specified transfer of data over the gateway occurs. Ch k th t th ti d l i d i– Check that the time delays experienced in transfer data do not exceed the spec/d max.
  • 31. BMS CommissioningBMS Commissioning • Integrated systems – direct interoperabilityp y – Check the degree of direct interoperability. Check the functional profiles that define the– Check the functional profiles that define the data which can be transferred for specific items of plantitems of plant. – Check that the data transferred between the diff t f t t l d tdifferent manufacturers control products meets the specified functional profiles.
  • 32. BMS CommissioningBMS Commissioning • Integration with fire detection systems – Integration for monitoring (uni-directional)g g ( ) • Increasingly common (alarm status). • Check the status info for each fire alarm detectorCheck the status info for each fire alarm detector can be viewed on the BMS operator PC. • Check that any spec/d bldg graphics indicating they p g g p g location of detector heads can be viewed w. status • Check that a fire alarm cond/n automatically displays the appropriate bldg graphic. • Check time delays receiving fire alarm data.
  • 33. BMS CommissioningBMS Commissioning • Integration with fire detection systems – Integration for monitoring (bi-directional)g g ( ) • Check that the alteration of any fire alarm parameter via the BMS has no adverse effect onp the correct operation of the fire alarm system. • Test re-setting of alarm sounders. • Test changing thresholds on detector heads. • Test isolating fire detection devices & sounders. • Test partial system re-configuration. • Check that loss of electrical power to the BMS hasp no adverse effect on the fire detection system.
  • 34. BMS Commissioning I t ti ith fi d t ti t BMS Commissioning • Integration with fire detection systems – Integration for control • Control smoke protection plant such as smoke vents, and fans for escape route pressurization systemssystems. • Check that the BMS can receive fire alarm data originating from each detector and within time limitg g • Check for correct control logic in response to a fire alarm condition on a point-by-point basis. • Confirm that the correct plant is activated in the spec/d sequence.
  • 35. BMS CommissioningBMS Commissioning • Security systems – Intruder alarm – Check that the status information for each specified detector can be viewed on the W/S. – Check that any specified graphics indicatingCheck that any specified graphics indicating the location of detectors can be viewed. Check that an alarm condition results in the– Check that an alarm condition results in the automatic display of the appropriate graphic. Ch k th t ti d l i i i– Check that any time delay in receiving an alarm is within the specified maximum.
  • 36. BMS Commissioning S it t A t l BMS Commissioning • Security systems – Access control – Check that the BMS operator W/S displays the specified status information from the access control system (ACS). – Check that any time delay in receiving data from the ACS system is within the spec/d max – Check that any spec/d bldg services control actions operate correctly in response to the t t f th ACSstatus of the ACS. – Check that ACS are correctly integr/d with Lifts & EscalatorsLifts & Escalators.
  • 37. BMS Commissioning I t ti f l t i l l BMS Commissioning • Interruption of electrical power supply – Check that the controllers preserve control strategy configuration data for a spec/d periodstrategy configuration data for a spec/d period when mains power is lost. – Check that the condition of any volatile dataCheck that the condition of any volatile data protection system is regularly and automatically monitored. – Check that an alarm is raised on loss of data by any controller or other device and/or failure of the monitoring systemof the monitoring system. – Check that the control system operates correctly under generator standby and UPScorrectly under generator standby and UPS power.
  • 38. BMS Commissioning S ifi Pl t C V l BMS Commissioning • Specific Plant Cx – Valves – Confirm that the valves have been correctly selected, installed, and applied. – Check the characteristic positioner, linear or equal percentage. – Under dynamic conditions: • Drive the valve across the whole span. • Check the max and min positions • Check the rate of valve movement and whether it meets that specified.
  • 39. BMS CommissioningBMS Commissioning • Specific pant Cx – Dampers – Check that the dampers are correctly installedp y and applied. – Check that all damper sections & linkagesCheck that all damper sections & linkages operate synchronously. Check the max and min positions and rate of– Check the max and min positions and rate of movement. Ch k /d i t l ki ith th f– Check any spec/d interlocking with other fans. – On receipt of a fire signal check the spec.pos.
  • 40. BMS Commissioning S ifi l t C F ( i l d) BMS Commissioning • Specific plant Cx – Fans (single speed) – Panel controls (power, fan run/trip, fuses, ) – Hardware: • Check the fan rotates in correct direction. • Check start/stop by the application s/w. • Check correct fan status & mnemonic. – Interlocks: • Appropriate interlocks and overrides, with plant in ffmanual, off, auto modes. • Check the fans operate as spec/d under fire alarm.
  • 41. BMS CommissioningBMS Commissioning • Specific plant Cx – Fans (single speed) – Alarms: • Set the fan air flow failure device to the desired value and simulate a no flow condition. • Check an alarm is initiated and fans are shutdown. • Set the alarm inhibit time for the air flow failure device to a time consistent with the fan start. • Check that on fan failure the corresponding supply or extract fan switches off.
  • 42. BMS CommissioningBMS Commissioning • Specific plant Cx – Fans (variable speed)
  • 43. BMS CommissioningBMS Commissioning • Specific plant Cx – Pumps and Inverter banks (batteries).( )
  • 44. BMS CommissioningBMS Commissioning • Specific plant Cx- Terminal units – FCU and VAV units.
  • 45. BMS CommissioningBMS Commissioning • Specific plant Cx – Heating and Cooling coils.
  • 46. BMS CommissioningBMS Commissioning • Specific plant Cx – CHW dehumidification coils
  • 47. BMS CommissioningBMS Commissioning • Specific plant Cx – Humidifier steam & sprayp y
  • 48. BMS CommissioningBMS Commissioning • System Handover - Witnessing
  • 49. BMS CommissioningBMS Commissioning • System Handover – Documentation Operations and Maintenance Manualp
  • 50. BMS CommissioningBMS Commissioning • System Handover – Operator Training
  • 51. BMS CommissioningBMS Commissioning • Post-occupancy checks – Complete performance checking – global checksp g g
  • 52. BMS CommissioningBMS Commissioning • Post-occupancy checks - Complete performance checking – system level checksp g y