BASEMENT SYSTEM
Concrete Diaphragm Wall Waterproofing Systems
PRECEDENT STUDY
Diaphragm walls are commonly used in the construction of large commercial
basement. Because of the way these types of wall are constructed, it is only
possible to position the waterproofing on the internal face of the wall.
Waterproofing solutions for these types of wall are therefore similar to those
used to waterproof internal basement walls although they are usually adapted
to take account of the higher levels of water ingress that might be expected in
larger basements.
SECTION A-A, indicates the floor
The Vue shopping mall comprises 7,800 sq.m GFA with 3,850 sq.m NSA with 1
level basement retail area and car parking; four floors retail area including
pedestrian circulation areas, footpaths seating areas. The construction Contract
was awarded mid December 2010 with completion planned 10 months later at
end of October 2011.
The basement works are 100% complete with the exception of the car
access/egress ramp nearing completion. The main M&E plant rooms, waste
water treatment, water storage tanks are complete with M&E works in progress.
Basement masonry walls and architectural works are 70% complete with M&E
works 35% complete.
The superstructure ground and second floor slabs and columns are complete
with third floor slabs 75% complete and forth floor 25% complete.
Lifts, aluminium, glazed windows and shop fronts are under fabrication. Lift
contract is awarded and delivery is due in September 2011.The Basement
Constructed with
Concrete diaphragm wall waterproofing system to maximize the car park
capacity and
prevent the inclement whether to drain out the rainwater efficiency.
VUE Boutique Shopping Mall ,Bangkok
Basement Construction
PREPAREDBY:ALEXCHUNGKAHSHENG
4
BASEMENT SYSTEM
APPLICATION METHOD
ADVANTAGES
- Can be Installed to considerable depth.
- Formation of walls with substantial thickness.
- Flexible system in plan layout.
- Easily incorporated into Permanent works.
- Designable to carry vertical loads.
- Construction time of Basement can be lowered considerably.
- Economic and Positive solution for large deep basement in saturated and
unstable soil profiles.
- Weakness Construction if in very unstable soil profiles below the water
table
- Limited construction time
- Where deeper than normal cantilever support may be required.
DISADVANTAGES
1. Diaphragm walls are constructed by excavating a series of rectangular
panels keyed into each other to form a continuous wall.
4. Panels are keyed into each other by using temporary formwork (stop
ends).
After that, pour in concrete to the formwork and form the basement
diaphragm wall. Finally apply waterproofing membrane to prevent
inclement whether.
3. Water bars (rubber membranes) can also be installed between panels by
casting
in place via the stop end. Excavation of the panels in soils and low
quality rock
are via either rope suspended or kelly bar mounted grabs.
2. Excavation in more competent rock requires mills. In almost all cases the
excavation is supported by drilling fluids such as bentonite or occasionally
polymer slurries. This enables diaphragm walls to be constructed through
almost any ground conditions.
PREPAREDBY:ALEXCHUNGKAHSHENG
5
BASEMENT SYSTEM
DETAIL WORKING DRAWING
WATERPROOFING SYSTEM FOR BASEMENT DETAIL
1. Insulation Membrane 35mm
2. Insulation 75mm
3. Brick Plug with Compression Seal
4. Plasterboard Dryling 50mm
5. Overseal Tape 75mm
6. Perimeter Drainage
7. Floor Screed- 50mm Min.
8. Insulation Membrane 15mm
9. Knauf Polyfam Floorboard 150mm
10. Membrane (Fill studs with Lean-Mix Concrete)
11. Vandex Super-Used As Lime Control Agent
DETAIL WORKING DRAWING
SEALED INTERNAL BASEMENT WATERPROOFING WITH
AQUADRAIN AND SENTRY SUMP SYSTEM
1. Safeguard Fastframe Dryling System Components
2. Plasterboard -12.5mm
3. Oldroyd Xv membrane 15mm
4. Oldroyd Overseal Tape 75mm
5. Skirting Board
6. Oldroyd Aquadrain
7. Pea Shingle
8. Oldroyd Xv Membrane 15mm
9. Oldroyd Flat Top Aquadrain
PREPAREDBY:ALEXCHUNGKAHSHENG
6
BASEMENT SYSTEM
DETAIL WORKING DRAWING
WATERPROOFING WITH INTERNAL INSULATION
1. Safeguard Fastframe Drylining System Components
2. Plasterboard 12.5mm
3. Closed Cell Insulation e.g.Knauf
4. Oldroyd Xv membrane
5. Oldroyd Brick Plug with compression seal
6. Oldroyd 75mm Overseal Tape
7. Skirting Board
8. Oldroyd Aquadrain Perimeter Drainage
9. Pea Shingle
10. Closed Cell Insulation e.g Knauf
11. Oldroyd Xv Membrane
12. Flooring Grade 18mm T&G Chipboard
PREPAREDBY:ALEXCHUNGKAHSHENG
7
RAFT FOUNDATION SYSTEM
RAFT FOUNDATION WITH REINFORCEMENT
PRECEDENT STUDY
A raft foundation consists of a raft of reinforced concrete under the whole of a
building. This type of foundation is described as a raft in the sense that the
concrete raft is cast on the surface of the ground which supports it, as water
does a raft, and the foundation is not fixed by foundations carried down into
the subsoil. Raft foundations may be used for buildings on compressible ground
such as very soft clay, alluvial deposits and compressible fill material where strip,
pad or pile foundations would not provide a stable foundation without
excessive excavation. The reinforced concrete raft is designed to transmit the
whole load of the building from the raft to the ground where the small spread
loads will cause little if any appreciable settlement.
SECTION, indicates the foundation
Tugendhat House
Details: Barn-style self build, Cambridge shire, November 2009-July 2010
Designer: PJT Design
The main contractor is currently preparing the site to begin casting foundations
for the house. Foundations are a very important part of building design, and the
choice of foundation depends on the soil, the site conditions and the type of
structure that will be built. Foundations carry the load of the entire building and
its contents and must be designed to limit excessive movement in the structure
that may result in it losing its integrity.
Due to the site conditions and the light steel frame structure we have designed
for Stand 47, the foundation type we will be using is a raft foundation. It varies
from the popular strip foundation (which uses unreinforced concrete ground
beams and light brick walls to distribute point loads), in that a raft foundation is
actually a two-way reinforced concrete slab resting on the ground. The raft
distributes pressure from the weight of the structure above to the ground
below, and provides a bound foundation system that reduces the risk of soil
collapse and cracks. The perimeter of the raft is usually turned down to prevent
storm-water from damaging the structure by causing channels below the slab.
Due to the building technology we are using at Stand 47, the raft foundation
offers an alternative to the usual masonry system used in residential
foundations.
8
PREPAREDBY:AZINESKANDARI
FOUNDATION SYSTEM
SUPPLIER
PEEL INDUSTRIAL ESTATE
CHAMBERHALL STREET
BURY
LANCASHIRE BL9 0LU
Tel: 0844 576 6726
Fax: 0161 447 8333
REINFORCEMENT DETAIL OF RAFT FOUNDATION
The extensive foundation (which is usually called raft foundation), is a unified
foundation that extends throughout the entire area of the columns.
As a rule, raft foundation is used as a building’s foundation when the soil has a
low bearing capacity.
The behavior of the raft foundation resembles the behavior of a strip
foundation grate.
The stresses applied upon the soil are larger in the columns’ area and lighter in
the intermediate areas. The presence of beams acting as stiffeners helps in a
more even distribution of the soil pressures between the columns’ areas and
the intermediate areas of the raft foundation.
The foundation slabs are reinforced with two wire meshes, one placed at the
lower fibers and one at the upper fibers, by following the reinforcement rules
that apply to slabs.
The beams are reinforced with strong stirrups and bars placed both at the
upper and lower fibers, by following the reinforcement rules that apply to
beams.
The slabs’ free edges are reinforced with common hairpin bars or with a wire
mesh folded like a hairpin, by following the reinforcement rules that apply to
slabs.
When the columns are subjected to large loads and the foundation slab’s
thickness is analogically small, it is obligatory to use punching shear
reinforcement. That reinforcement can be pro-vided by stirrup cages, as it is in
this example, by bundles of properly bent rebar or by special industrial
elements.
The column rebar are in grey color. The red color is reinforcement steel bar.
Reinforcement of a solid raft foundation Raft foundation with punching
shear reinforcement
9
PREPAREDBY:WONGSOONFOOK
FOUNDATION SYSTEM
APPLICATION METHOD
ADVANTAGES
1. A raft foundation consists of a raft of reinforced concrete under the whole of
a building. This type of foundation is described as a raft in the sense that the
concrete raft is cast on the surface of the ground which supports it, as water
does a raft, and the foundation is not fixed by foundations carried down into
the subsoil.
2. Raft foundations may be used for buildings on compressible ground such as
very soft clay, alluvial deposits and compressible fill material where strip, pad
or pile foundations would not provide a stable foundation without excessive
excavation. The reinforced concrete raft is designed to transmit the whole
load of the building from the raft to the ground where the small spread
loads will cause little if any appreciable settlement.
3. The concrete raft is reinforced top and bottom against both upward and
downward bending. Vegetable top soil is removed and a blinding layer of
concrete 50 mm thick is spread and levelled to provide a base on which to
cast the concrete raft. A waterproof membrane is laid, on the dry concrete
blinding, against moisture rising into the raft. The top and bottom
reinforcement is supported and spaced preparatory to placing the concrete
which is spread, consolidated and finished level.
1. Raft or mat foundation is economic
due to combination of foundation
and floor slab.
2. It requires little excavation.
3. It can cope with mixed or poor
ground condition.
4/ It reduces differential settlement.
Raft Doundation section diagram
Omkar Pune (2013). Architectural Presentation-RAFT FOUNDATION. [ONLINE] Available at: http://architecturalguidance.blogspot.com/2008/04/architectural-presentation-raft.html. [Last Accessed 29 September 14].
DISADVANTAGES
1. Mat foundation requires specific
treatment for point loads.
2. Edge erosion occurs if not treated
properly.
Samuel Lecthord (2011). Design Development. [ONLINE] Available at: http://tekvironment.weebly.com/stage-3-design-development.html. [Last Accessed 29 September 14].
10
PREPAREDBY:WONGSOONFOOK
FOUNDATION SYSTEM
DETAIL WORKING DRAWING
Step 1: Commonly used type of raft is the solid slab raft without downstand
beam. To begin constructing the solid slab raft foundation, the vegetative top
soil (original soil) is removed then the soil left behind is compressed.
Sometimes, hardcore (broken rocks or stones) maybe be added to raise the
ground floor level.
Step 2: To provide a level bed that will receive the reinforcement and concrete,
a layer of blinding (weak concrete) is added to the surface of the hardcore or
directly to the compacted soil.
Step 3: After the blinding has been allowed to cure for some days, then the
temporary formwork (wood) is then erected over it all around that will serve as
the support to for the reinforced steel bars and concrete work. Mould oil can be
used on the surfaces and sides of the formwork. This makes the finished
concrete work to have a clean look or surface by preventing the concrete from
sticking to the wood used.
Step 4: The reinforced steel bars will then be placed into the formwork
following the bending schedule the structural engineer has provided. After this
is done the concrete which is mixed to a given ratio is then poured in and
spread all over to cover the reinforcement.
When the concrete has been allowed to cure for some days. A layer of damp
proof membrane is spread around the entire area of the foundation and then
over it reinforced mesh wire is laid, which will receive the concrete for the main
floor slab (German floor). Before the concrete is poured all necessary plumbing
piping is done. After the concrete has been cured the main walling for the
building can begin.
STEPS OF RAFT FOUNDATION
Concrete blinding on hardcore Concrete blinding on the soil directly
Temporary frame work Reinforced steel bars Damp Proof Membrane and Mesh Wire Completed raft foundation Completed raft foundation
11
PREPAREDBY:WONGSOONFOOK
FOUNDATION SYSTEM
RAFT FOUNDATION SYSTEM DETAIL
12
FOUNDATION SYSTEM
RAFT FOUNDATION SYSTEM DETAIL
13
PREPAREDBY:WONGSOONFOOK
BEAM & BLOCK FLOOR SYSTEM
BEAM AND BLOCK SYSTEM
PRECEDENT STUDY
Beam and block is a flooring construction method where concrete blocks are
laid between supporting cast concrete beams. This method can be cost effective
and is also extremely durable. A number of firms specialize in making
components for beam and block flooring and some also provide installation.
One advantage of this technique is relative ease of installation, making it
possible for construction crews without prior experience to establish a sound
floor relatively quickly with some direction.
SECTION A-A, indicates the floor
SUTTERTON SURGERY MEDICAL CENTRE
The works comprise of a new single storey extension and
remodelling to an existing Surgery. Construction methods
include strip foundations, beam and block floors, traditional
cavity wall construction with face brickwork and flat roof.
Aluminum door and UPVC windows. External works include
tarmac to car park, concrete footpath to the perimeter of the
building and extending the existing drainage. New timber
fencing with concrete posts
Flooring Construction of Sutterton Surgery Medical Centre by using beam & block flooring.
PREPAREDBY:LINGTECKONG
14
BEAM & BLOCK FLOOR SYSTEM
APPLICATION METHOD
Installation
It is essential that the floor beams be handled and stacked the correct way up, they should be lifted as
close to the ends as possible and no damaged beams should be used in the installation. It is important
that all mortar in the preceding work is adequately cured, having enough strength to give support to the
floor being installed. Ensure that all mortar and debris is removed from the bearing points and they are
level and true.
PREPAREDBY:LINGTECKONG
15
Ventilation
Provision should be made for a void beneath the
floor, the depth of which should be at least 150mm
but may vary depending on site conditions. To meet
Local Authority and NHBC requirements, the void
should be ventilated. Ventilation openings should be
placed to enable the free flow of air to the complete
under floor area. Ventilators should be placed
frequently enough to the perimeter of the building to
give suitable ventilation. Supreme supply plastic
telescopic void ventilators with a range of colored
plastic air bricks.
BEAM & BLOCK FLOOR SYSTEM
Ground Floor (Application)
Supreme beams are 155mm deep, and
manufactured in two widths with the same side
profile. They are 120mm and 170mm wide. Note!
Wide beams are available at lengths over
4000mm only. They can be used with any
suitable infill block by any manufacturer, subject
to design requirements and specification. The
infill block may be selected to suit budget,
strength or thermal and sound recommendations
as required. Aerated blocks sometimes have a
larger face size than standard blocks. Care must
be taken when the infill block is bedded into a
load bearing wall as the floor blocks must be of
the same crushing strength, or stronger, than the
requirement of the wall.
Upper Floor (Application)
Supreme T Beams are also suitable for upper
floors in domestic dwellings where for example
a dense floor is required to create a "quiet
home" or the first floor partitions are to be of
block work, which can be supported by the
floor. Compartment Floors between Dwellings
Specific performance specifications are
required in accordance with the building
regulations in respect of infill blocks and
directly applied screeds.
-Quick and simple installation
-No specialist teams or skills
required.
-Minimal excavation of ground
surface, removing the requirement of
importing additional hardstanding
material.
-All weather construction – can be
installed in adverse weather
conditions.
-Flexibility of Design - the high load
carrying capacity allows complete
freedom of room design layouts.
Rigid Floor - without the bounce or
creaking associated with timber
joists.
-Suitable for brown field
developments and ideal on
developments with restricted site
access.
-Services pipe penetrations can be
easily accommodated.
-As soon as the flooring is installed,
the floor can safely be used as a
working platform, allowing the inner
leaf construction work to commence.
ADVANTAGES DISADVANTAGES
-The site measurement shall be
accurate other wise precast will not
fit in position
-require heavy lift machines
-the pipes and electric conduits
must be located accurately
PREPAREDBY:LINGTECKONG
16
BEAM & BLOCK FLOOR SYSTEM
DETAIL WORKING DRAWING
PREPAREDBY:LINGTECKONG
17
WALL SYSTEM
PRECEDENT STUDY / SRISUK VILLAGE, RAYANG
http://www.smartblock.in.th/download/manual/ManSiB_Eng.pdf Retrieved from 1 October 2014
ELEVATION, Indicates the Wall System
Manufacturer: Smart Concrete Co. Ltd
Website : www.smartblock.in.th
Material selection needed to be simple given the impermanence and relatively
Low Budget of the facility. Composite fiber reinforced cement board, a light
weight and economical concrete material, gives the building its clean, simple
planes and lines. It is an ideal material choice for this building given the desire
to create large, flat planes that are lightweight, easily dismantled and rebuilt.
The quality of its minimalist details is a tribute to the skill of the crafts people,
and proof that the relatively modest materials can be used to produce refined
result.
Lightweight aggregate concrete
Lightweight aggregate concrete can be produced using a variety of
lightweight aggregates. Lightweight aggregates originate from either:
• Natural materials, like volcanic pumice.
• The thermal treatment of natural raw materials like clay, slate or
shale i.e. Leca.
• Manufacture from industrial by-products such as fly ash, i.e. Lytag.
• Processing of industrial by-products like FBA or slag.
The benefits of using lightweight aggregate concrete include:
• Reduction in dead loads making savings in foundations and reinforcement.
• Improved thermal properties.
• Improved fire resistance.
• Savings in transporting and handling precast units on site.
• Reduction in formwork and propping.
4
21
3
1. Insert Tie Bar 2. Install the next row
3. Finish wall with one side plaster 4. Finished wall
PREPAREDBY:CELINETANJEANINN
18
WALL SYSTEM
Poli-Klinik Rüdersdorf bei Berlin
Material: TERRART- Large
Manufacturer: NBK Architectural Terracotta
TERRART® -LARGE is an ventilated curtain wall/ rain screen system whose
exposed components are made exclusively from terracotta. This system
components are manufactured so as to maximise shape, accuracy and
guarantee best fit. Terrart also provides large-format elements, which are
individually manufactured based on the project specification. Ideal for
projects where large-sized or oversized elements support wind load and
structural and design aesthetic are a consideration.
Length : max.1800mm. Length of ceramic element can be adjustable.
Height : max. 800mm. Height of the element can be adjustable.
Thickness : approx. 40mm Hollow chambers
Colors : Other colors are available on request.
Glazing according to customer wishes
or RAL specifications
Surface Finishes : Natural, Polished, Tetxured,
Peeled, Profiled, Glazed.
Curved Surface can not be polished
Mass per unit area : approx. 65kg/m2
NBK - Terrart Large. (n.d.). http://www.nbkterracotta.com/en-GB/products/terrart/large.jsp Retrieved October 1, 2014.
Figure: Poli-Klinik Rüdersdorf bei Berlin
Figure: Section dimension of
Terrart-Large
PREPAREDBY:CELINETANJEANINN
Figure: Elevation Drawing of
Polo-Klinik Rudersdort bei Berlin
Advantages:
• Strongest compressive strength
and the strongest break load
• Low percentage of water
absorption ensures that dirt
does not penetrate the tile
• Low maintenance material with
an inert material colour
• Outstanding colour consistency
• Recycle content that qualify for
LEEDs credit
• Large tiles enable faster
installation
• Lower labour costs
Key Features:
• Wide variety of machining
options available in our
production process
• Able to create individual
facades that meet the toughest
design
• Most common machining
options:
- Horizontal/Vertical/Diagonal
/Mitre Cutes/ Drilling
19
WALL SYSTEM
APPLICATION METHOD
ADVANTAGES
1. Combine half-blocks to add square or curved corners at the edges of a block
wall or pavement and use single or double corner bricks to smooth the
edges or corners.
2. The measurement for standard blocks is shown as 100mm .The half-inch gap
is made on purpose since the mortar between the blocks also takes some
space.
3. Pour the base concrete which will ground your wall strongly to the base.
4. Plan how you will lay concrete blocks for your project and prepare the site
before starting the main labour process.
5. Fix corner stakes firmly into the ground.
6. The length should be divisible by the types of blocks that you are using. Use
corner bricks or cut the concrete blocks if needed to complete the wall.
7. Start laying blocks from the corner or edge of the wall so you can work in
one direction.
8. Put the mortar 1 inch (2.5 cm) deep and the same width as the width of the
block that you are placing on top.
9. Apply mortar at the end of the block before you place the block adjacent to
it.
10. Try not to leave any gaps when applying mortar because this will weaken the
bond between blocks.
11. Check that your wall is flat intermittently during the construction project
using a masonry level.
• Lighter weight on building
structural load
• Easy and Fast Installation
• Greater Sound Absorption
• Better Vibration absorption
• Flexibility
• Compressive strength 80-100ksc
• Improved Insulation Values
• Environmental Friendly
• Paintable and plaster
Typical block work construction achieving U-value of at leaast 0.27W/m2K
Lyons, A. (2007). Materials for architects and builders (3rd ed.). Boston: Elsevier.
DISADVANTAGES
• Takes significantly longer time to
dry
• Optimize ambient conditions.
• RH levels and temperature able to
maximize the drying process.
• Test with relative humidity(RH)
testing
MIXING RATIO
PRODUCT FEATURE
Block 7.5 x 10 x 15cm
(half block)
Cavity wall fully filled with insulation
Method of applying Lightweight concrete block
PREPAREDBY:CELINETANJEANINN
20
WALL SYSTEM
TERRART LARGE SHADE SCREEN TO LIGHTWEIGHT CONCRETE WALL DETAIL DRAWING
PREPAREDBY:CELINETANJEANINN
21
ROOF SYSTEM
TPO ROOFING
PRECEDENT STUDY
Thermoplastic PolyOlefin (TPO) is a trade name that refers to polymer/filler
blends usually consisting of some fraction of PP (polypropylene), PE
(polyethylene), BCPP (block copolymer polypropylene), rubber, and a
reinforcing filler. Common fillers include, though are not restricted to talc,
fiberglass, carbon fiber, wollastonite, and MOS (Metal Oxy Sulfate). Common
rubbers include EPR (ethylene propylene rubber), EPDM (EP-diene rubber),
EO (ethylene-octene), EB (ethylbenzene), SEBS (styrene-ethylene-butadiene-
styrene). The process of manufacturing TPO requires no plasticizer or
chlorine.
SECTION A-A, indicates the roof
Architecture Lab (2011, March 29). Culloden Battlefield Visitor Centre, Scotland By Gareth Hoskins. Retrieved October 5, 2014, from website:
http://architecturelab.net/culloden-battlefield-visitor-centre-scotland-by-gareth-hoskins-architects/
CULLODEN BATTLEFIELD VISITOR CENTRE
Project Details:
Location: Culloden Moor, Inverness – Scotland
Type: Cultural - Public
Architects: Gareth Hoskins Architects
The building form, has a small surface:area ratio to minimize heat loss and
its low form reduces exposure to northerly winds. Orientation and roof form
are manipulated to maximize glare free daylight and natural ventilation. The
roof here functions as an viewing platform colonized by indigenous plants to
retain biodiversity. Roof access is achieved via an 80 metre inclined planted
berm/screen containing site spoil which would otherwise go to landfill.
The roof is a covered with a TPO membrane. More than 1000sqm are used
as a public viewing terrace and are covered with an intensive green roof
system. The under floor heating is powered by a bio fuel boiler fed from the
estates of the local forestry commission. Most of the building is natural
ventilated via roof lights, which also maximize the use of natural light or
high/low level grilles and stack vents.
PREPAREDBY:POHWEIKEAT
22
ROOF SYSTEM
APPLICATION METHOD
ADVANTAGES
Common Applications
• Fully adhered
• Mechanically fastened
• Ballasted
1. TPO is applied in large rolls that vary in both size and thickness.
2. TPO can be fully adhered, mechanically fastened, or ballasted.
3. The seams of the membrane are hot air-welded together to form a very
strong waterproof bond between sheets.
4. Sealing seams to prevent water from entering the welded area through
wicking or capillary action
5. TPO-coated metal flashing material is used to fasten some TPO membranes
at roof edges, walls, decks.
6. Fasteners and plates are used to held the membrane or insulation to the
roof deck.
7. Special screws simplify attachment of roof layers to steel, wood or concrete
decks.
8. Install all membrane flashing at the same time as the roof membrane. (Use
only fully adhered, mechanically attached or prefabricated flashings
depending on job circumstances.)
Method of applying TPO membrane
• Environmentally friendly
• Energy efficient
• Great flexibility even at extremely
low temperatures
• Strong puncture resistant material
• Cool roof Energy Star system UV
resistant, lowers heating and cooling
bills
• Reduces the heat island effect and
solar heat gain
• Resistant to chemicals, acid, salt, oil,
etc.
• Extremely strong seamsImage of material
DISADVANTAGES
• Questionable longevity
(Young roofing technology
which still finding the right
formula to make the product
durable and long lasting while
maintaining a competitive
price)
• Does not stand up well to heat
load
(TPO roofing membranes have
been noted to have an issue of
accelerated weathering when
subjected to high thermal or
solar loading.)
TPO SPECIAL-RESISTANT MEMBRANE
Ledegar Roofing (2014). Flat Roofing Systems for Commercial Buildings. Retrieved October 5, 2014, from Ledegar Roofing website:
https://www.ledegarroofing.com/commercial/flat-roofing
Godfrey Roofing (2013).TPO Roofing. Retrieved October 5, 2014, from Godfrey Roofing Inc website:
http://godfreyroofing.com/commercial/education/roofing-systems/tpo-thermoplastic-olefin/
3 4 5
6 7 8
PREPAREDBY:POHWEIKEAT
23
ROOF SYSTEM
BASE TIE IN WITH HD SEAM PLATE FASTENED TO DECK
GAF (2014). EverGuard® TPO. Retrieved October 5, 2014, from EverGuard website: http://www.gaf.com/Roofing/Commercial/Products/Single_Ply_Roofing/Self_Adhered/Double_Side_and_Strip_In
PREPAREDBY:POHWEIKEAT
24
ROOF SYSTEM
ROOF EDGE GUTTER WITH TPO COATED METAL
Firestone Building Product (2014). Roof Edge Gutter With Flange. Retrieved October 5, 2014, from Firestone website: http://us-fsbp.cbdmarketing.com/technical-information/all-drawings/detail-drawings/tpo-roof-
systems/ultrablend-roof-systems/
PREPAREDBY:POHWEIKEAT
25
ROOF SYSTEM
TPO ROOFING JOINED WITH LIGHT WEIGHT CONCRETE WALL
26
27
• Firestone Building Product (2014). Roof Edge Gutter With Flange. Retrieved October 5, 2014, from Firestone website: http://us-
fsbp.cbdmarketing.com/technical-information/all-drawings/detail-drawings/tpo-roof-systems/ultrablend-roof-systems/
• Ledegar Roofing (2014). Flat Roofing Systems for Commercial Buildings. Retrieved October 5, 2014, from Ledegar Roofing website:
https://www.ledegarroofing.com/commercial/flat-roofing
• Godfrey Roofing (2013).TPO Roofing. Retrieved October 5, 2014, from Godfrey Roofing Inc website:
http://godfreyroofing.com/commercial/education/roofing-systems/tpo-thermoplastic-olefin/
• Architecture Lab (2011, March 29). Culloden Battlefield Visitor Centre, Scotland By Gareth Hoskins. Retrieved October 5, 2014, from website:
http://architecturelab.net/culloden-battlefield-visitor-centre-scotland-by-gareth-hoskins-architects/
• Phillips, D., & Yamashita, M. (2012). Detail in contemporary concrete architecture. London: Laurence King Publishing.
• Ching, F. (1975). Building construction illustrated. New York: Van Nostrand Reinhold.
• NBK - Terrart Large. (n.d.). http://www.nbkterracotta.com/en-GB/products/terrart/large.jsp Retrieved October 1, 2014.
• http://www.smartblock.in.th/download/manual/ManSiB_Eng.pdf Retrieved from 1 October 2014
• Allen, E., & Iano, J. (2004). Fundamentals of building construction: Materials and methods(4th ed.). Hoboken, N.J.: J. Wiley & Sons.

Mais conteúdo relacionado

Mais procurados

CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18SANJEEV Wazir
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelBlake Johnson
 
04. superstructure
04. superstructure04. superstructure
04. superstructureThien Hee
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTIONRajesh Kolli
 
North Dakota Precast Concrete
North Dakota Precast ConcreteNorth Dakota Precast Concrete
North Dakota Precast ConcreteJenny Frost
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionMadan Mohan Jana
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slabPenny3688
 
04.chapter ii
04.chapter ii04.chapter ii
04.chapter iiGTVT
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...Bhaddin Al-Naqshabandi
 
Advantages of precast concrete
Advantages of precast concreteAdvantages of precast concrete
Advantages of precast concretebuiltify
 
Precast design (1)
Precast design (1)Precast design (1)
Precast design (1)Surya Singh
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wallkristenjames
 
house construction
house constructionhouse construction
house constructionAbhinav Saha
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concreteRajat Nainwal
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
7 building construction part 3 foundation - edit
7 building construction part 3   foundation - edit7 building construction part 3   foundation - edit
7 building construction part 3 foundation - editmuhammadumairallahdi
 

Mais procurados (19)

CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
 
Hollow Floor Slab
Hollow Floor SlabHollow Floor Slab
Hollow Floor Slab
 
04. superstructure
04. superstructure04. superstructure
04. superstructure
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
 
North Dakota Precast Concrete
North Dakota Precast ConcreteNorth Dakota Precast Concrete
North Dakota Precast Concrete
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slab
 
04.chapter ii
04.chapter ii04.chapter ii
04.chapter ii
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...
 
Advantages of precast concrete
Advantages of precast concreteAdvantages of precast concrete
Advantages of precast concrete
 
Precast design (1)
Precast design (1)Precast design (1)
Precast design (1)
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wall
 
house construction
house constructionhouse construction
house construction
 
Versaloc
VersalocVersaloc
Versaloc
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
 
Retaining Walls
Retaining WallsRetaining Walls
Retaining Walls
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
7 building construction part 3 foundation - edit
7 building construction part 3   foundation - edit7 building construction part 3   foundation - edit
7 building construction part 3 foundation - edit
 

Destaque

Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1KohSungJie
 
Enviroform Solutions Open Day
Enviroform Solutions Open DayEnviroform Solutions Open Day
Enviroform Solutions Open DayLiam Brown
 
Building Construction 1 Project 1
Building Construction 1 Project 1Building Construction 1 Project 1
Building Construction 1 Project 1dtan97
 
Ganaka Presentation Master
Ganaka Presentation MasterGanaka Presentation Master
Ganaka Presentation MasterGanesh Kamat
 
Specification Guide: Remember Its Waterproof (RIW Ltd)
Specification Guide: Remember Its Waterproof (RIW Ltd) Specification Guide: Remember Its Waterproof (RIW Ltd)
Specification Guide: Remember Its Waterproof (RIW Ltd) RIW Ltd
 
Building Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionBuilding Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionYung Kai
 
Lesson plan: HTML Formatting Texts and Paragraphs
Lesson plan: HTML Formatting Texts and ParagraphsLesson plan: HTML Formatting Texts and Paragraphs
Lesson plan: HTML Formatting Texts and ParagraphsKeith Borgonia Manatad
 
Design Portfolio by Aaron Kaira
Design Portfolio by Aaron KairaDesign Portfolio by Aaron Kaira
Design Portfolio by Aaron KairaAaron Kaira
 
Building Technology I - Project 2
Building Technology I - Project 2Building Technology I - Project 2
Building Technology I - Project 2jernjack
 
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline KH
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewateringShubham Parab
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailingAli Ishaqi
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 

Destaque (19)

Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1
 
Enviroform Solutions Open Day
Enviroform Solutions Open DayEnviroform Solutions Open Day
Enviroform Solutions Open Day
 
Building Construction 1 Project 1
Building Construction 1 Project 1Building Construction 1 Project 1
Building Construction 1 Project 1
 
Ganaka Presentation Master
Ganaka Presentation MasterGanaka Presentation Master
Ganaka Presentation Master
 
Specification Guide: Remember Its Waterproof (RIW Ltd)
Specification Guide: Remember Its Waterproof (RIW Ltd) Specification Guide: Remember Its Waterproof (RIW Ltd)
Specification Guide: Remember Its Waterproof (RIW Ltd)
 
Building Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionBuilding Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience Construction
 
Lesson plan: HTML Formatting Texts and Paragraphs
Lesson plan: HTML Formatting Texts and ParagraphsLesson plan: HTML Formatting Texts and Paragraphs
Lesson plan: HTML Formatting Texts and Paragraphs
 
Design Portfolio by Aaron Kaira
Design Portfolio by Aaron KairaDesign Portfolio by Aaron Kaira
Design Portfolio by Aaron Kaira
 
Building Technology I - Project 2
Building Technology I - Project 2Building Technology I - Project 2
Building Technology I - Project 2
 
BUILDERS FOUNDATION BOOK
BUILDERS FOUNDATION BOOKBUILDERS FOUNDATION BOOK
BUILDERS FOUNDATION BOOK
 
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
Shallow foundation
Shallow foundationShallow foundation
Shallow foundation
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 

Semelhante a Btech compile 6 oct 4am

How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APCkristenjames
 
BT5 ALTERNATIVE BUILDING CONSTRUCTION.pdf
BT5 ALTERNATIVE BUILDING CONSTRUCTION.pdfBT5 ALTERNATIVE BUILDING CONSTRUCTION.pdf
BT5 ALTERNATIVE BUILDING CONSTRUCTION.pdfLeymarJakeGandelaTam1
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology ReportShao Xun Sean Thun
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Luke D'Arcy
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardWriters Per Hour
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxsydneyaugust1
 
Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)Shane Ah
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
Raft Foundation b.arch 8th sem
Raft Foundation b.arch 8th semRaft Foundation b.arch 8th sem
Raft Foundation b.arch 8th semujjwal jharsi
 
Easy steps to build a besser block wall
Easy steps to build a besser block wallEasy steps to build a besser block wall
Easy steps to build a besser block wallkristenjames
 
u-boottechnology_122321.pptx
u-boottechnology_122321.pptxu-boottechnology_122321.pptx
u-boottechnology_122321.pptxArunPrasad249350
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinningOkwera David
 

Semelhante a Btech compile 6 oct 4am (20)

How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APC
 
BT5 ALTERNATIVE BUILDING CONSTRUCTION.pdf
BT5 ALTERNATIVE BUILDING CONSTRUCTION.pdfBT5 ALTERNATIVE BUILDING CONSTRUCTION.pdf
BT5 ALTERNATIVE BUILDING CONSTRUCTION.pdf
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Floors
FloorsFloors
Floors
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample Harvard
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Raft Foundation b.arch 8th sem
Raft Foundation b.arch 8th semRaft Foundation b.arch 8th sem
Raft Foundation b.arch 8th sem
 
Easy steps to build a besser block wall
Easy steps to build a besser block wallEasy steps to build a besser block wall
Easy steps to build a besser block wall
 
u-boottechnology_122321.pptx
u-boottechnology_122321.pptxu-boottechnology_122321.pptx
u-boottechnology_122321.pptx
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinning
 
pile wall
pile wallpile wall
pile wall
 

Mais de Celine Tan

Mais de Celine Tan (15)

Btech
BtechBtech
Btech
 
Btech plan and color
Btech plan and colorBtech plan and color
Btech plan and color
 
Celine 7
Celine 7Celine 7
Celine 7
 
Celine 6
Celine 6Celine 6
Celine 6
 
Celine 5
Celine 5Celine 5
Celine 5
 
Celine 4
Celine 4Celine 4
Celine 4
 
Celine 3
Celine 3Celine 3
Celine 3
 
Celine 2
Celine 2Celine 2
Celine 2
 
Celine 1
Celine 1Celine 1
Celine 1
 
Urban essay (1)
Urban essay (1)Urban essay (1)
Urban essay (1)
 
Content
ContentContent
Content
 
Tryst final
Tryst finalTryst final
Tryst final
 
Pinnacle sunway services
Pinnacle sunway services Pinnacle sunway services
Pinnacle sunway services
 
Asian Architecture
Asian ArchitectureAsian Architecture
Asian Architecture
 
MUAR STREET
MUAR STREETMUAR STREET
MUAR STREET
 

Último

Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Delhi Call girls
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfLars Albertsson
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一ffjhghh
 
04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationshipsccctableauusergroup
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfLars Albertsson
 
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
Data-Analysis for Chicago Crime Data 2023
Data-Analysis for Chicago Crime Data  2023Data-Analysis for Chicago Crime Data  2023
Data-Analysis for Chicago Crime Data 2023ymrp368
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAroojKhan71
 
Ravak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxRavak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxolyaivanovalion
 
VIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service Amravati
VIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service AmravatiVIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service Amravati
VIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service AmravatiSuhani Kapoor
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFxolyaivanovalion
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxolyaivanovalion
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfMarinCaroMartnezBerg
 

Último (20)

Sampling (random) method and Non random.ppt
Sampling (random) method and Non random.pptSampling (random) method and Non random.ppt
Sampling (random) method and Non random.ppt
 
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdf
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
 
04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
 
꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...
꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...
꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...
 
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdf
 
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Data-Analysis for Chicago Crime Data 2023
Data-Analysis for Chicago Crime Data  2023Data-Analysis for Chicago Crime Data  2023
Data-Analysis for Chicago Crime Data 2023
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
 
Ravak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxRavak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptx
 
VIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service Amravati
VIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service AmravatiVIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service Amravati
VIP Call Girls in Amravati Aarohi 8250192130 Independent Escort Service Amravati
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFx
 
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in  KishangarhDelhi 99530 vip 56974 Genuine Escort Service Call Girls in  Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptx
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdf
 

Btech compile 6 oct 4am

  • 1. 1
  • 2. 2
  • 3. 2
  • 4. BASEMENT SYSTEM Concrete Diaphragm Wall Waterproofing Systems PRECEDENT STUDY Diaphragm walls are commonly used in the construction of large commercial basement. Because of the way these types of wall are constructed, it is only possible to position the waterproofing on the internal face of the wall. Waterproofing solutions for these types of wall are therefore similar to those used to waterproof internal basement walls although they are usually adapted to take account of the higher levels of water ingress that might be expected in larger basements. SECTION A-A, indicates the floor The Vue shopping mall comprises 7,800 sq.m GFA with 3,850 sq.m NSA with 1 level basement retail area and car parking; four floors retail area including pedestrian circulation areas, footpaths seating areas. The construction Contract was awarded mid December 2010 with completion planned 10 months later at end of October 2011. The basement works are 100% complete with the exception of the car access/egress ramp nearing completion. The main M&E plant rooms, waste water treatment, water storage tanks are complete with M&E works in progress. Basement masonry walls and architectural works are 70% complete with M&E works 35% complete. The superstructure ground and second floor slabs and columns are complete with third floor slabs 75% complete and forth floor 25% complete. Lifts, aluminium, glazed windows and shop fronts are under fabrication. Lift contract is awarded and delivery is due in September 2011.The Basement Constructed with Concrete diaphragm wall waterproofing system to maximize the car park capacity and prevent the inclement whether to drain out the rainwater efficiency. VUE Boutique Shopping Mall ,Bangkok Basement Construction PREPAREDBY:ALEXCHUNGKAHSHENG 4
  • 5. BASEMENT SYSTEM APPLICATION METHOD ADVANTAGES - Can be Installed to considerable depth. - Formation of walls with substantial thickness. - Flexible system in plan layout. - Easily incorporated into Permanent works. - Designable to carry vertical loads. - Construction time of Basement can be lowered considerably. - Economic and Positive solution for large deep basement in saturated and unstable soil profiles. - Weakness Construction if in very unstable soil profiles below the water table - Limited construction time - Where deeper than normal cantilever support may be required. DISADVANTAGES 1. Diaphragm walls are constructed by excavating a series of rectangular panels keyed into each other to form a continuous wall. 4. Panels are keyed into each other by using temporary formwork (stop ends). After that, pour in concrete to the formwork and form the basement diaphragm wall. Finally apply waterproofing membrane to prevent inclement whether. 3. Water bars (rubber membranes) can also be installed between panels by casting in place via the stop end. Excavation of the panels in soils and low quality rock are via either rope suspended or kelly bar mounted grabs. 2. Excavation in more competent rock requires mills. In almost all cases the excavation is supported by drilling fluids such as bentonite or occasionally polymer slurries. This enables diaphragm walls to be constructed through almost any ground conditions. PREPAREDBY:ALEXCHUNGKAHSHENG 5
  • 6. BASEMENT SYSTEM DETAIL WORKING DRAWING WATERPROOFING SYSTEM FOR BASEMENT DETAIL 1. Insulation Membrane 35mm 2. Insulation 75mm 3. Brick Plug with Compression Seal 4. Plasterboard Dryling 50mm 5. Overseal Tape 75mm 6. Perimeter Drainage 7. Floor Screed- 50mm Min. 8. Insulation Membrane 15mm 9. Knauf Polyfam Floorboard 150mm 10. Membrane (Fill studs with Lean-Mix Concrete) 11. Vandex Super-Used As Lime Control Agent DETAIL WORKING DRAWING SEALED INTERNAL BASEMENT WATERPROOFING WITH AQUADRAIN AND SENTRY SUMP SYSTEM 1. Safeguard Fastframe Dryling System Components 2. Plasterboard -12.5mm 3. Oldroyd Xv membrane 15mm 4. Oldroyd Overseal Tape 75mm 5. Skirting Board 6. Oldroyd Aquadrain 7. Pea Shingle 8. Oldroyd Xv Membrane 15mm 9. Oldroyd Flat Top Aquadrain PREPAREDBY:ALEXCHUNGKAHSHENG 6
  • 7. BASEMENT SYSTEM DETAIL WORKING DRAWING WATERPROOFING WITH INTERNAL INSULATION 1. Safeguard Fastframe Drylining System Components 2. Plasterboard 12.5mm 3. Closed Cell Insulation e.g.Knauf 4. Oldroyd Xv membrane 5. Oldroyd Brick Plug with compression seal 6. Oldroyd 75mm Overseal Tape 7. Skirting Board 8. Oldroyd Aquadrain Perimeter Drainage 9. Pea Shingle 10. Closed Cell Insulation e.g Knauf 11. Oldroyd Xv Membrane 12. Flooring Grade 18mm T&G Chipboard PREPAREDBY:ALEXCHUNGKAHSHENG 7
  • 8. RAFT FOUNDATION SYSTEM RAFT FOUNDATION WITH REINFORCEMENT PRECEDENT STUDY A raft foundation consists of a raft of reinforced concrete under the whole of a building. This type of foundation is described as a raft in the sense that the concrete raft is cast on the surface of the ground which supports it, as water does a raft, and the foundation is not fixed by foundations carried down into the subsoil. Raft foundations may be used for buildings on compressible ground such as very soft clay, alluvial deposits and compressible fill material where strip, pad or pile foundations would not provide a stable foundation without excessive excavation. The reinforced concrete raft is designed to transmit the whole load of the building from the raft to the ground where the small spread loads will cause little if any appreciable settlement. SECTION, indicates the foundation Tugendhat House Details: Barn-style self build, Cambridge shire, November 2009-July 2010 Designer: PJT Design The main contractor is currently preparing the site to begin casting foundations for the house. Foundations are a very important part of building design, and the choice of foundation depends on the soil, the site conditions and the type of structure that will be built. Foundations carry the load of the entire building and its contents and must be designed to limit excessive movement in the structure that may result in it losing its integrity. Due to the site conditions and the light steel frame structure we have designed for Stand 47, the foundation type we will be using is a raft foundation. It varies from the popular strip foundation (which uses unreinforced concrete ground beams and light brick walls to distribute point loads), in that a raft foundation is actually a two-way reinforced concrete slab resting on the ground. The raft distributes pressure from the weight of the structure above to the ground below, and provides a bound foundation system that reduces the risk of soil collapse and cracks. The perimeter of the raft is usually turned down to prevent storm-water from damaging the structure by causing channels below the slab. Due to the building technology we are using at Stand 47, the raft foundation offers an alternative to the usual masonry system used in residential foundations. 8 PREPAREDBY:AZINESKANDARI
  • 9. FOUNDATION SYSTEM SUPPLIER PEEL INDUSTRIAL ESTATE CHAMBERHALL STREET BURY LANCASHIRE BL9 0LU Tel: 0844 576 6726 Fax: 0161 447 8333 REINFORCEMENT DETAIL OF RAFT FOUNDATION The extensive foundation (which is usually called raft foundation), is a unified foundation that extends throughout the entire area of the columns. As a rule, raft foundation is used as a building’s foundation when the soil has a low bearing capacity. The behavior of the raft foundation resembles the behavior of a strip foundation grate. The stresses applied upon the soil are larger in the columns’ area and lighter in the intermediate areas. The presence of beams acting as stiffeners helps in a more even distribution of the soil pressures between the columns’ areas and the intermediate areas of the raft foundation. The foundation slabs are reinforced with two wire meshes, one placed at the lower fibers and one at the upper fibers, by following the reinforcement rules that apply to slabs. The beams are reinforced with strong stirrups and bars placed both at the upper and lower fibers, by following the reinforcement rules that apply to beams. The slabs’ free edges are reinforced with common hairpin bars or with a wire mesh folded like a hairpin, by following the reinforcement rules that apply to slabs. When the columns are subjected to large loads and the foundation slab’s thickness is analogically small, it is obligatory to use punching shear reinforcement. That reinforcement can be pro-vided by stirrup cages, as it is in this example, by bundles of properly bent rebar or by special industrial elements. The column rebar are in grey color. The red color is reinforcement steel bar. Reinforcement of a solid raft foundation Raft foundation with punching shear reinforcement 9 PREPAREDBY:WONGSOONFOOK
  • 10. FOUNDATION SYSTEM APPLICATION METHOD ADVANTAGES 1. A raft foundation consists of a raft of reinforced concrete under the whole of a building. This type of foundation is described as a raft in the sense that the concrete raft is cast on the surface of the ground which supports it, as water does a raft, and the foundation is not fixed by foundations carried down into the subsoil. 2. Raft foundations may be used for buildings on compressible ground such as very soft clay, alluvial deposits and compressible fill material where strip, pad or pile foundations would not provide a stable foundation without excessive excavation. The reinforced concrete raft is designed to transmit the whole load of the building from the raft to the ground where the small spread loads will cause little if any appreciable settlement. 3. The concrete raft is reinforced top and bottom against both upward and downward bending. Vegetable top soil is removed and a blinding layer of concrete 50 mm thick is spread and levelled to provide a base on which to cast the concrete raft. A waterproof membrane is laid, on the dry concrete blinding, against moisture rising into the raft. The top and bottom reinforcement is supported and spaced preparatory to placing the concrete which is spread, consolidated and finished level. 1. Raft or mat foundation is economic due to combination of foundation and floor slab. 2. It requires little excavation. 3. It can cope with mixed or poor ground condition. 4/ It reduces differential settlement. Raft Doundation section diagram Omkar Pune (2013). Architectural Presentation-RAFT FOUNDATION. [ONLINE] Available at: http://architecturalguidance.blogspot.com/2008/04/architectural-presentation-raft.html. [Last Accessed 29 September 14]. DISADVANTAGES 1. Mat foundation requires specific treatment for point loads. 2. Edge erosion occurs if not treated properly. Samuel Lecthord (2011). Design Development. [ONLINE] Available at: http://tekvironment.weebly.com/stage-3-design-development.html. [Last Accessed 29 September 14]. 10 PREPAREDBY:WONGSOONFOOK
  • 11. FOUNDATION SYSTEM DETAIL WORKING DRAWING Step 1: Commonly used type of raft is the solid slab raft without downstand beam. To begin constructing the solid slab raft foundation, the vegetative top soil (original soil) is removed then the soil left behind is compressed. Sometimes, hardcore (broken rocks or stones) maybe be added to raise the ground floor level. Step 2: To provide a level bed that will receive the reinforcement and concrete, a layer of blinding (weak concrete) is added to the surface of the hardcore or directly to the compacted soil. Step 3: After the blinding has been allowed to cure for some days, then the temporary formwork (wood) is then erected over it all around that will serve as the support to for the reinforced steel bars and concrete work. Mould oil can be used on the surfaces and sides of the formwork. This makes the finished concrete work to have a clean look or surface by preventing the concrete from sticking to the wood used. Step 4: The reinforced steel bars will then be placed into the formwork following the bending schedule the structural engineer has provided. After this is done the concrete which is mixed to a given ratio is then poured in and spread all over to cover the reinforcement. When the concrete has been allowed to cure for some days. A layer of damp proof membrane is spread around the entire area of the foundation and then over it reinforced mesh wire is laid, which will receive the concrete for the main floor slab (German floor). Before the concrete is poured all necessary plumbing piping is done. After the concrete has been cured the main walling for the building can begin. STEPS OF RAFT FOUNDATION Concrete blinding on hardcore Concrete blinding on the soil directly Temporary frame work Reinforced steel bars Damp Proof Membrane and Mesh Wire Completed raft foundation Completed raft foundation 11 PREPAREDBY:WONGSOONFOOK
  • 13. FOUNDATION SYSTEM RAFT FOUNDATION SYSTEM DETAIL 13 PREPAREDBY:WONGSOONFOOK
  • 14. BEAM & BLOCK FLOOR SYSTEM BEAM AND BLOCK SYSTEM PRECEDENT STUDY Beam and block is a flooring construction method where concrete blocks are laid between supporting cast concrete beams. This method can be cost effective and is also extremely durable. A number of firms specialize in making components for beam and block flooring and some also provide installation. One advantage of this technique is relative ease of installation, making it possible for construction crews without prior experience to establish a sound floor relatively quickly with some direction. SECTION A-A, indicates the floor SUTTERTON SURGERY MEDICAL CENTRE The works comprise of a new single storey extension and remodelling to an existing Surgery. Construction methods include strip foundations, beam and block floors, traditional cavity wall construction with face brickwork and flat roof. Aluminum door and UPVC windows. External works include tarmac to car park, concrete footpath to the perimeter of the building and extending the existing drainage. New timber fencing with concrete posts Flooring Construction of Sutterton Surgery Medical Centre by using beam & block flooring. PREPAREDBY:LINGTECKONG 14
  • 15. BEAM & BLOCK FLOOR SYSTEM APPLICATION METHOD Installation It is essential that the floor beams be handled and stacked the correct way up, they should be lifted as close to the ends as possible and no damaged beams should be used in the installation. It is important that all mortar in the preceding work is adequately cured, having enough strength to give support to the floor being installed. Ensure that all mortar and debris is removed from the bearing points and they are level and true. PREPAREDBY:LINGTECKONG 15 Ventilation Provision should be made for a void beneath the floor, the depth of which should be at least 150mm but may vary depending on site conditions. To meet Local Authority and NHBC requirements, the void should be ventilated. Ventilation openings should be placed to enable the free flow of air to the complete under floor area. Ventilators should be placed frequently enough to the perimeter of the building to give suitable ventilation. Supreme supply plastic telescopic void ventilators with a range of colored plastic air bricks.
  • 16. BEAM & BLOCK FLOOR SYSTEM Ground Floor (Application) Supreme beams are 155mm deep, and manufactured in two widths with the same side profile. They are 120mm and 170mm wide. Note! Wide beams are available at lengths over 4000mm only. They can be used with any suitable infill block by any manufacturer, subject to design requirements and specification. The infill block may be selected to suit budget, strength or thermal and sound recommendations as required. Aerated blocks sometimes have a larger face size than standard blocks. Care must be taken when the infill block is bedded into a load bearing wall as the floor blocks must be of the same crushing strength, or stronger, than the requirement of the wall. Upper Floor (Application) Supreme T Beams are also suitable for upper floors in domestic dwellings where for example a dense floor is required to create a "quiet home" or the first floor partitions are to be of block work, which can be supported by the floor. Compartment Floors between Dwellings Specific performance specifications are required in accordance with the building regulations in respect of infill blocks and directly applied screeds. -Quick and simple installation -No specialist teams or skills required. -Minimal excavation of ground surface, removing the requirement of importing additional hardstanding material. -All weather construction – can be installed in adverse weather conditions. -Flexibility of Design - the high load carrying capacity allows complete freedom of room design layouts. Rigid Floor - without the bounce or creaking associated with timber joists. -Suitable for brown field developments and ideal on developments with restricted site access. -Services pipe penetrations can be easily accommodated. -As soon as the flooring is installed, the floor can safely be used as a working platform, allowing the inner leaf construction work to commence. ADVANTAGES DISADVANTAGES -The site measurement shall be accurate other wise precast will not fit in position -require heavy lift machines -the pipes and electric conduits must be located accurately PREPAREDBY:LINGTECKONG 16
  • 17. BEAM & BLOCK FLOOR SYSTEM DETAIL WORKING DRAWING PREPAREDBY:LINGTECKONG 17
  • 18. WALL SYSTEM PRECEDENT STUDY / SRISUK VILLAGE, RAYANG http://www.smartblock.in.th/download/manual/ManSiB_Eng.pdf Retrieved from 1 October 2014 ELEVATION, Indicates the Wall System Manufacturer: Smart Concrete Co. Ltd Website : www.smartblock.in.th Material selection needed to be simple given the impermanence and relatively Low Budget of the facility. Composite fiber reinforced cement board, a light weight and economical concrete material, gives the building its clean, simple planes and lines. It is an ideal material choice for this building given the desire to create large, flat planes that are lightweight, easily dismantled and rebuilt. The quality of its minimalist details is a tribute to the skill of the crafts people, and proof that the relatively modest materials can be used to produce refined result. Lightweight aggregate concrete Lightweight aggregate concrete can be produced using a variety of lightweight aggregates. Lightweight aggregates originate from either: • Natural materials, like volcanic pumice. • The thermal treatment of natural raw materials like clay, slate or shale i.e. Leca. • Manufacture from industrial by-products such as fly ash, i.e. Lytag. • Processing of industrial by-products like FBA or slag. The benefits of using lightweight aggregate concrete include: • Reduction in dead loads making savings in foundations and reinforcement. • Improved thermal properties. • Improved fire resistance. • Savings in transporting and handling precast units on site. • Reduction in formwork and propping. 4 21 3 1. Insert Tie Bar 2. Install the next row 3. Finish wall with one side plaster 4. Finished wall PREPAREDBY:CELINETANJEANINN 18
  • 19. WALL SYSTEM Poli-Klinik Rüdersdorf bei Berlin Material: TERRART- Large Manufacturer: NBK Architectural Terracotta TERRART® -LARGE is an ventilated curtain wall/ rain screen system whose exposed components are made exclusively from terracotta. This system components are manufactured so as to maximise shape, accuracy and guarantee best fit. Terrart also provides large-format elements, which are individually manufactured based on the project specification. Ideal for projects where large-sized or oversized elements support wind load and structural and design aesthetic are a consideration. Length : max.1800mm. Length of ceramic element can be adjustable. Height : max. 800mm. Height of the element can be adjustable. Thickness : approx. 40mm Hollow chambers Colors : Other colors are available on request. Glazing according to customer wishes or RAL specifications Surface Finishes : Natural, Polished, Tetxured, Peeled, Profiled, Glazed. Curved Surface can not be polished Mass per unit area : approx. 65kg/m2 NBK - Terrart Large. (n.d.). http://www.nbkterracotta.com/en-GB/products/terrart/large.jsp Retrieved October 1, 2014. Figure: Poli-Klinik Rüdersdorf bei Berlin Figure: Section dimension of Terrart-Large PREPAREDBY:CELINETANJEANINN Figure: Elevation Drawing of Polo-Klinik Rudersdort bei Berlin Advantages: • Strongest compressive strength and the strongest break load • Low percentage of water absorption ensures that dirt does not penetrate the tile • Low maintenance material with an inert material colour • Outstanding colour consistency • Recycle content that qualify for LEEDs credit • Large tiles enable faster installation • Lower labour costs Key Features: • Wide variety of machining options available in our production process • Able to create individual facades that meet the toughest design • Most common machining options: - Horizontal/Vertical/Diagonal /Mitre Cutes/ Drilling 19
  • 20. WALL SYSTEM APPLICATION METHOD ADVANTAGES 1. Combine half-blocks to add square or curved corners at the edges of a block wall or pavement and use single or double corner bricks to smooth the edges or corners. 2. The measurement for standard blocks is shown as 100mm .The half-inch gap is made on purpose since the mortar between the blocks also takes some space. 3. Pour the base concrete which will ground your wall strongly to the base. 4. Plan how you will lay concrete blocks for your project and prepare the site before starting the main labour process. 5. Fix corner stakes firmly into the ground. 6. The length should be divisible by the types of blocks that you are using. Use corner bricks or cut the concrete blocks if needed to complete the wall. 7. Start laying blocks from the corner or edge of the wall so you can work in one direction. 8. Put the mortar 1 inch (2.5 cm) deep and the same width as the width of the block that you are placing on top. 9. Apply mortar at the end of the block before you place the block adjacent to it. 10. Try not to leave any gaps when applying mortar because this will weaken the bond between blocks. 11. Check that your wall is flat intermittently during the construction project using a masonry level. • Lighter weight on building structural load • Easy and Fast Installation • Greater Sound Absorption • Better Vibration absorption • Flexibility • Compressive strength 80-100ksc • Improved Insulation Values • Environmental Friendly • Paintable and plaster Typical block work construction achieving U-value of at leaast 0.27W/m2K Lyons, A. (2007). Materials for architects and builders (3rd ed.). Boston: Elsevier. DISADVANTAGES • Takes significantly longer time to dry • Optimize ambient conditions. • RH levels and temperature able to maximize the drying process. • Test with relative humidity(RH) testing MIXING RATIO PRODUCT FEATURE Block 7.5 x 10 x 15cm (half block) Cavity wall fully filled with insulation Method of applying Lightweight concrete block PREPAREDBY:CELINETANJEANINN 20
  • 21. WALL SYSTEM TERRART LARGE SHADE SCREEN TO LIGHTWEIGHT CONCRETE WALL DETAIL DRAWING PREPAREDBY:CELINETANJEANINN 21
  • 22. ROOF SYSTEM TPO ROOFING PRECEDENT STUDY Thermoplastic PolyOlefin (TPO) is a trade name that refers to polymer/filler blends usually consisting of some fraction of PP (polypropylene), PE (polyethylene), BCPP (block copolymer polypropylene), rubber, and a reinforcing filler. Common fillers include, though are not restricted to talc, fiberglass, carbon fiber, wollastonite, and MOS (Metal Oxy Sulfate). Common rubbers include EPR (ethylene propylene rubber), EPDM (EP-diene rubber), EO (ethylene-octene), EB (ethylbenzene), SEBS (styrene-ethylene-butadiene- styrene). The process of manufacturing TPO requires no plasticizer or chlorine. SECTION A-A, indicates the roof Architecture Lab (2011, March 29). Culloden Battlefield Visitor Centre, Scotland By Gareth Hoskins. Retrieved October 5, 2014, from website: http://architecturelab.net/culloden-battlefield-visitor-centre-scotland-by-gareth-hoskins-architects/ CULLODEN BATTLEFIELD VISITOR CENTRE Project Details: Location: Culloden Moor, Inverness – Scotland Type: Cultural - Public Architects: Gareth Hoskins Architects The building form, has a small surface:area ratio to minimize heat loss and its low form reduces exposure to northerly winds. Orientation and roof form are manipulated to maximize glare free daylight and natural ventilation. The roof here functions as an viewing platform colonized by indigenous plants to retain biodiversity. Roof access is achieved via an 80 metre inclined planted berm/screen containing site spoil which would otherwise go to landfill. The roof is a covered with a TPO membrane. More than 1000sqm are used as a public viewing terrace and are covered with an intensive green roof system. The under floor heating is powered by a bio fuel boiler fed from the estates of the local forestry commission. Most of the building is natural ventilated via roof lights, which also maximize the use of natural light or high/low level grilles and stack vents. PREPAREDBY:POHWEIKEAT 22
  • 23. ROOF SYSTEM APPLICATION METHOD ADVANTAGES Common Applications • Fully adhered • Mechanically fastened • Ballasted 1. TPO is applied in large rolls that vary in both size and thickness. 2. TPO can be fully adhered, mechanically fastened, or ballasted. 3. The seams of the membrane are hot air-welded together to form a very strong waterproof bond between sheets. 4. Sealing seams to prevent water from entering the welded area through wicking or capillary action 5. TPO-coated metal flashing material is used to fasten some TPO membranes at roof edges, walls, decks. 6. Fasteners and plates are used to held the membrane or insulation to the roof deck. 7. Special screws simplify attachment of roof layers to steel, wood or concrete decks. 8. Install all membrane flashing at the same time as the roof membrane. (Use only fully adhered, mechanically attached or prefabricated flashings depending on job circumstances.) Method of applying TPO membrane • Environmentally friendly • Energy efficient • Great flexibility even at extremely low temperatures • Strong puncture resistant material • Cool roof Energy Star system UV resistant, lowers heating and cooling bills • Reduces the heat island effect and solar heat gain • Resistant to chemicals, acid, salt, oil, etc. • Extremely strong seamsImage of material DISADVANTAGES • Questionable longevity (Young roofing technology which still finding the right formula to make the product durable and long lasting while maintaining a competitive price) • Does not stand up well to heat load (TPO roofing membranes have been noted to have an issue of accelerated weathering when subjected to high thermal or solar loading.) TPO SPECIAL-RESISTANT MEMBRANE Ledegar Roofing (2014). Flat Roofing Systems for Commercial Buildings. Retrieved October 5, 2014, from Ledegar Roofing website: https://www.ledegarroofing.com/commercial/flat-roofing Godfrey Roofing (2013).TPO Roofing. Retrieved October 5, 2014, from Godfrey Roofing Inc website: http://godfreyroofing.com/commercial/education/roofing-systems/tpo-thermoplastic-olefin/ 3 4 5 6 7 8 PREPAREDBY:POHWEIKEAT 23
  • 24. ROOF SYSTEM BASE TIE IN WITH HD SEAM PLATE FASTENED TO DECK GAF (2014). EverGuard® TPO. Retrieved October 5, 2014, from EverGuard website: http://www.gaf.com/Roofing/Commercial/Products/Single_Ply_Roofing/Self_Adhered/Double_Side_and_Strip_In PREPAREDBY:POHWEIKEAT 24
  • 25. ROOF SYSTEM ROOF EDGE GUTTER WITH TPO COATED METAL Firestone Building Product (2014). Roof Edge Gutter With Flange. Retrieved October 5, 2014, from Firestone website: http://us-fsbp.cbdmarketing.com/technical-information/all-drawings/detail-drawings/tpo-roof- systems/ultrablend-roof-systems/ PREPAREDBY:POHWEIKEAT 25
  • 26. ROOF SYSTEM TPO ROOFING JOINED WITH LIGHT WEIGHT CONCRETE WALL 26
  • 27. 27 • Firestone Building Product (2014). Roof Edge Gutter With Flange. Retrieved October 5, 2014, from Firestone website: http://us- fsbp.cbdmarketing.com/technical-information/all-drawings/detail-drawings/tpo-roof-systems/ultrablend-roof-systems/ • Ledegar Roofing (2014). Flat Roofing Systems for Commercial Buildings. Retrieved October 5, 2014, from Ledegar Roofing website: https://www.ledegarroofing.com/commercial/flat-roofing • Godfrey Roofing (2013).TPO Roofing. Retrieved October 5, 2014, from Godfrey Roofing Inc website: http://godfreyroofing.com/commercial/education/roofing-systems/tpo-thermoplastic-olefin/ • Architecture Lab (2011, March 29). Culloden Battlefield Visitor Centre, Scotland By Gareth Hoskins. Retrieved October 5, 2014, from website: http://architecturelab.net/culloden-battlefield-visitor-centre-scotland-by-gareth-hoskins-architects/ • Phillips, D., & Yamashita, M. (2012). Detail in contemporary concrete architecture. London: Laurence King Publishing. • Ching, F. (1975). Building construction illustrated. New York: Van Nostrand Reinhold. • NBK - Terrart Large. (n.d.). http://www.nbkterracotta.com/en-GB/products/terrart/large.jsp Retrieved October 1, 2014. • http://www.smartblock.in.th/download/manual/ManSiB_Eng.pdf Retrieved from 1 October 2014 • Allen, E., & Iano, J. (2004). Fundamentals of building construction: Materials and methods(4th ed.). Hoboken, N.J.: J. Wiley & Sons.