Pipeline Safety: Control Room Management /Human Factors                                                  “Final Rule December 3, 2009” Pipeliners Club of Atlanta January 11, 2010
Presentation Objectives Provide background information on development of the rule. Present elements of “new” control room management rule. Comment on ways to comply with rule, and go beyond compliance.
Background on Rule Development Pipeline and Hazardous Materials Safety Administration has been examining and evaluating and advising on Control Room operations for at least 14 years. (1996) NTSB has been making recommendations about “human factors” for at least 12 years. (1998) Pipeline Safety Improvement Act of 2002 Pipeline Inspection, Protection, Enforcement, and Safety Act of 2006 (PIPES Act)
Safety Rec. P-05-001 (NTSB)  Recommends that PHMSA: Require operators of hazardous liquids pipelines to follow the API Recommended Practice 1165 for the use of graphics on the SCADA* screens. NTSB had performed a safety study due to leaks going undetected after indications of a leak on the SCADA interface. New rule addresses this recommendation. *SCADA = Supervisory Control and Data Acquisition
Safety Rec. P-05-002 (NTSB) Recommends that PHMSA: Require pipeline companies to have a policy for the review/audit of alarms. New rule addresses this recommendation.
Safety Rec. P-05-003 (NTSB) Recommends that PHMSA: Require controller training to include simulator or non-computerized simulations for controller recognition of abnormal operating conditions, in particular, leak events. New rule addresses this recommendation.
Safety Rec. P-05-004 (NTSB) Recommends that PHMSA: Change the liquid accident reporting form and require operators to provide data related to controller fatigue. This recommendation is being addressed in a change to accident reporting requirements for gas and liquids pipelines.
Safety Rec. P-99-12 (NTSB) Urges PHMSA, to: “establish within two years scientifically based hours of service regulations… that set limits on hours of service,… provide predictable work and rest schedules… and consider circadian rhythms and human sleep and rest requirements.” New rule may or may not address this recommendation, depending on whether you are NTSB or PHMSA.
Safety Rec. P-98-30 (NTSB) Urges PHMSA, to: “assess the potential safety risks associated with rotating pipeline controller shifts and… establish industry guidelines for the development and implementation of pipeline controller work schedules…  that reduce the likelihood of accidents attributable to controller fatigue.” Closed May 3, 2006, due to P-99-12 being issued.
Reasons for NTSB Bulletins The NTSB noted that scientific research has shown that certain sleep factors can affect fatigue and performance, such as insufficient sleep, irregular schedules, and unpredictable schedules.
Reasons for NTSB Bulletins Recommendations resulted from the NTSB’s review of all transportation accidents reported to U.S. Department of Transportation (DOT) modal administrations over a 10 year period.  NTSB noted that it had issued over 70 fatigue-related safety recommendations that resulted from its investigations of major accidents, special investigations, or safety studies that identified operator fatigue as a causal factor.
Reasons for NTSB Bulletins Were there any pipeline accidents where Control Room issues could have contributed to the accident? Several examples cited: Colonial Pipeline      1996 (Controller fatigue) Marathon Pipeline    1998 (SCADA & alarms) Olympic Pipeline      1999 (SCADA maintenance) Marathon-Ashland    2000 (Controller fatigue) NTSB study “10 of 18 hazardous liquids accidents have potential Control Room involvement”
Federal Most Wanted Transportation Safety Improvements Reduce Pipeline Accidents Caused by Human Fatigue
NTSB Most Wanted No Federal hours-of-service regulations exist for controllers of pipeline systems Regulations exist in other transportation modes. Set working hour limits for pipeline controllers based on fatigue research, circadian rhythms, and sleep and rest requirements.  “Acceptable Response – Progressing Slowly”
PHMSA Bulletins  “Pipeline Safety:  Countermeasures to Prevent Human Fatigue in the Control Room”  ADB-05-06 “Potential Service Disruptions in SCADA Systems”  ADB-03-09 “Potential Service Interruptions in Supervisory Control and Data Acquisition Systems”  ADB-99-03
PHMSA & Industry Activities Controller Certification Study Participation with industry associations API 1165 RP SCADA displays API 1167 RP Alarm Mgt.(in progress) API 1168 RP Control Room Mgt. Battelle Human Factors Analysis API Control Room Forums SGA Gas Control Framework Document AGA White Papers
Congress Pipeline Safety Improvement Act of 2002 Study control room operations Operator Qualification Requirements PIPES Act of 2006 “Reduce risks associated with human factors, including fatigue, for pipeline controllers and other employees.” NTSB recommendations on display, alarms, and training Issue regulations
Notice of Proposed Rulemaking PHMSA issued NPRM PHMSA-2007-27954 on September 12, 2008. Received 144 comments, mostly from liquids and gas pipeline industry groups and companies. Majority of comments said “withdraw the proposed rule and start over.” Rule was not withdrawn, but PHMSA did take some comments into consideration before issuing the final rule.
Initial Summary Statements Must define the roles and responsibilities of controllers… And provide controllers with the necessary information, training, and processes to fulfill these responsibilities. …must also implement methods to prevent controller fatigue
Initial Summary (continued) …manage SCADA alarms …assure control room considerations are taken into account when changing pipeline equipment or configurations… …review reportable incidents or accidents to determine whether control room actions contributed to the event.
Effective Dates Final rule is effective February 1, 2010. Develop control room management procedures by August 1, 2011. Implement the procedures by February 1, 2012. Plenty of time for compliance? Most companies still have questions about what parts of the rule “really mean.”
Definitions in Parts 192 & 195 Important for determining if rule applies: Alarm Controller Control Room Supervisory Control and Data Acquisition System
Definitions in Parts 192 & 195 Alarm means an audible or visible means of indicating to the controller that equipment or processes are outside operator-defined, safety-related parameters. Control Room means an operations center staffed by personnel charged with the responsibility for remotely monitoring and controlling a pipeline facility.
Definitions in Parts 192 & 195 Controller means a qualified individual who remotely monitors and controls the safety-related operations of a pipeline facility via a SCADA system from a control room, and who has operational authority and accountability for the remote operational functions of the pipeline facility.
Definitions in Parts 192 & 195 Supervisory Control and Data Acquisition (SCADA) system means a computer-based system or systems used by a controller in a control room that collects and displays information about a pipeline facility and may have the ability to send commands back to the pipeline facility.
Rule for Parts 192 & 195 If you have controller(s) in a control room monitoring and controlling with a SCADA system; Applies to natural gas pipelines, except Distribution with less than 250,000 services, or Transmission without a compressor station Must still implement sections about fatigue, compliance validation, compliance and deviations. Applies to hazardous liquids pipelines.
Control Room Mgt. Section Written control room management plan Define controller roles and responsibilities: Normal, abnormal, and emergency operations Authority to make decisions and take actions Controller’s role during abnormal operating conditions Controller’s role during emergency operating conditions Method of recording shift-changes and hand-over of responsibility. I would also define roles and responsibilities of other jobs in relation to controllers so that every person understands roles and responsibilities.
“Provide adequate information” Implement API 1165 (partially for gas) whenever SCADA is changed. Conduct point-to-point verification between SCADA displays and field equipment whenever something is changed. Test and verify internal communication plan for manual operation of the pipeline. Test any backup SCADA systems. Implement section 5 of API RP 1168 to establish procedures for when different controller assumes responsibility. Very specific in this section, because it is easier to be specific about SCADA systems & equipment.
“Fatigue mitigation” Establish shift lengths and schedule rotations that…provide time…to achieve 8 hours of continuous sleep.  Work time + commute time Educate controllers and supervisors in fatigue mitigation strategies and how off-duty activities contribute to fatigue.  Regular, ongoing Train controllers and supervisors to recognize the effects of fatigue.  Recognize signs and risks Establish a maximum limit on controller hours of service.   Day, week, dayshift, nightshift Less specific in “socio-technical” system.
“Alarm Management” Written alarm management plan Review SCADA safety-related alarm operations using a process that ensures alarms are accurate… Monthly identification of alarms that are off-scan, inhibited, false, etc.  Verify correct safety-related alarm set-point values and alarm descriptions annually. Review alarm management plan annually. Monitor content and volume of general activity directed to controller annually to ensure alarm response. Address deficiencies in any of these items. Specific again
“Change Management” Establish communications between control room representatives, management, and field personnel when planning and implementing changes.   Document your plans and practices Require field personnel to contact control room during emergency conditions or when making field changes.   How will you “require?” Seek control room or control room management participation in planning prior to implementation of significant pipeline hydraulic or configuration changes.   What is “significant?” Less specific, due to more “socio-technical” elements
“Operating Experience” Incorporate lessons learned from operating experience into procedures and training. Review incidents that meet reporting requirements for contributions/deficiencies: Controller fatigue Field equipment Operation of any safety device Procedures SCADA system configuration & performance. Do you have operating experience system?
“Training” Establish, then review annually and improve training program. Responding to abnormal operating conditions likely to occur. Use of simulator or tabletop method for training controllers to recognize abnormal operating conditions. Working knowledge of pipeline system… Infrequently used setups and procedures. Most companies have a training program.
“Compliance Validation” Submit procedures, when requested, to PHMSA or appropriate State agency.
“Compliance & Deviations” Maintain records for review: Records that demonstrate compliance Documentation to demonstrate that any deviations from requirements was necessary for the safe operation of a pipeline facility.
Summary Was this rule necessary?   Can this rule help improve pipeline operations? Incidents and near misses are caused by any and all of the areas in the rule. Most organizations are averse to learning. Most organizations have a change management process, but sometimes do not manage changes well. Is the final rule the “final” rule? Believe SCADA and alarm management are. Do not believe fatigue mitigation will be.
2010 Pipeliners Club Crm Final Rule

Mais conteúdo relacionado

Mais procurados

In Apc Training Presentation
In  Apc Training PresentationIn  Apc Training Presentation
In Apc Training Presentationahmad bassiouny
 
Media Object File Flt Ops Sop Seq05
Media Object File Flt Ops Sop Seq05Media Object File Flt Ops Sop Seq05
Media Object File Flt Ops Sop Seq05syed viquar
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyDesign World
 
20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_final20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_finaltwevans
 
Utilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control PerformanceUtilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control PerformanceEmerson Exchange
 
Aging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectAging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectUkrainian Nuclear Society
 
Effects of Macrocycle Time and Sampling Rates on Control Loop Performance
Effects of Macrocycle Time and Sampling Rates on Control Loop PerformanceEffects of Macrocycle Time and Sampling Rates on Control Loop Performance
Effects of Macrocycle Time and Sampling Rates on Control Loop PerformanceJim Cahill
 
aa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processesaa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processesDavid Lyon
 
Emergency Shutdown System - Worldwide Oilfield Machine
Emergency Shutdown System - Worldwide Oilfield MachineEmergency Shutdown System - Worldwide Oilfield Machine
Emergency Shutdown System - Worldwide Oilfield Machinewomgroup
 
Nfpa process safety and osha, seven keys to surviving a chem nep audi
Nfpa process safety and osha, seven keys to surviving a chem nep audiNfpa process safety and osha, seven keys to surviving a chem nep audi
Nfpa process safety and osha, seven keys to surviving a chem nep audivtsiri
 

Mais procurados (16)

In Apc Training Presentation
In  Apc Training PresentationIn  Apc Training Presentation
In Apc Training Presentation
 
HIPPS
HIPPSHIPPS
HIPPS
 
Media Object File Flt Ops Sop Seq05
Media Object File Flt Ops Sop Seq05Media Object File Flt Ops Sop Seq05
Media Object File Flt Ops Sop Seq05
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
 
Lp2007 216
Lp2007 216Lp2007 216
Lp2007 216
 
20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_final20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_final
 
Fault finding in mechatronics
Fault finding in mechatronicsFault finding in mechatronics
Fault finding in mechatronics
 
Sil 1 (1)1
Sil 1 (1)1Sil 1 (1)1
Sil 1 (1)1
 
Utilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control PerformanceUtilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control Performance
 
Aging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectAging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR Project
 
Aging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectAging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR Project
 
Effects of Macrocycle Time and Sampling Rates on Control Loop Performance
Effects of Macrocycle Time and Sampling Rates on Control Loop PerformanceEffects of Macrocycle Time and Sampling Rates on Control Loop Performance
Effects of Macrocycle Time and Sampling Rates on Control Loop Performance
 
aa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processesaa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processes
 
Emergency Shutdown System - Worldwide Oilfield Machine
Emergency Shutdown System - Worldwide Oilfield MachineEmergency Shutdown System - Worldwide Oilfield Machine
Emergency Shutdown System - Worldwide Oilfield Machine
 
Airmen Certification Standards by Dr. Janeen Kochan
Airmen Certification Standards by Dr. Janeen KochanAirmen Certification Standards by Dr. Janeen Kochan
Airmen Certification Standards by Dr. Janeen Kochan
 
Nfpa process safety and osha, seven keys to surviving a chem nep audi
Nfpa process safety and osha, seven keys to surviving a chem nep audiNfpa process safety and osha, seven keys to surviving a chem nep audi
Nfpa process safety and osha, seven keys to surviving a chem nep audi
 

Semelhante a 2010 Pipeliners Club Crm Final Rule

[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation Training
[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation Training[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation Training
[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation TrainingSchneider Electric
 
[Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management [Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management Schneider Electric
 
Conoco on Path to Reliability Centered Loop Management: Enhancing ROA on the Way
Conoco on Path to Reliability Centered Loop Management: Enhancing ROA on the WayConoco on Path to Reliability Centered Loop Management: Enhancing ROA on the Way
Conoco on Path to Reliability Centered Loop Management: Enhancing ROA on the WayARC Advisory Group
 
A straightforward approach using DeltaV SIS for typical BMS systems
 A straightforward approach using DeltaV SIS for typical BMS systems A straightforward approach using DeltaV SIS for typical BMS systems
A straightforward approach using DeltaV SIS for typical BMS systemsDavid Sheppard
 
Autonomous Industry Feedback
Autonomous Industry Feedback Autonomous Industry Feedback
Autonomous Industry Feedback amitgangwar2010
 
Real time monitoring proposal 2011
Real time monitoring proposal 2011Real time monitoring proposal 2011
Real time monitoring proposal 2011Eduardo Carvajal
 
Terminal Automation - Evolution & challenges
Terminal Automation - Evolution & challengesTerminal Automation - Evolution & challenges
Terminal Automation - Evolution & challengesNaimish Raval
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS Julian Kalac P.Eng
 
An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...MARIO524285
 
Check interval escalation
Check interval escalation Check interval escalation
Check interval escalation Mohammed Awad
 
Application of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented SystemsApplication of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented SystemsBelilove Company-Engineers
 
ECAST Meeting - 04 Jun 2013 - Reliability Data Sharing
ECAST Meeting - 04 Jun 2013 - Reliability Data SharingECAST Meeting - 04 Jun 2013 - Reliability Data Sharing
ECAST Meeting - 04 Jun 2013 - Reliability Data SharingCranfield University
 
Asco Safety Systems Solenoid Valve Selection Guide
Asco Safety Systems Solenoid Valve Selection GuideAsco Safety Systems Solenoid Valve Selection Guide
Asco Safety Systems Solenoid Valve Selection GuideMiller Energy, Inc.
 
Transition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operationsTransition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operationsEmerson Exchange
 

Semelhante a 2010 Pipeliners Club Crm Final Rule (20)

[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation Training
[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation Training[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation Training
[Oil & Gas White Paper] Liquids Pipeline Leak Detection and Simulation Training
 
[Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management [Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management
 
Conoco on Path to Reliability Centered Loop Management: Enhancing ROA on the Way
Conoco on Path to Reliability Centered Loop Management: Enhancing ROA on the WayConoco on Path to Reliability Centered Loop Management: Enhancing ROA on the Way
Conoco on Path to Reliability Centered Loop Management: Enhancing ROA on the Way
 
Minimal Requirements for Relief Systems Documentation
Minimal Requirements for Relief Systems DocumentationMinimal Requirements for Relief Systems Documentation
Minimal Requirements for Relief Systems Documentation
 
A straightforward approach using DeltaV SIS for typical BMS systems
 A straightforward approach using DeltaV SIS for typical BMS systems A straightforward approach using DeltaV SIS for typical BMS systems
A straightforward approach using DeltaV SIS for typical BMS systems
 
HUMS-Final-PPT.pptx
HUMS-Final-PPT.pptxHUMS-Final-PPT.pptx
HUMS-Final-PPT.pptx
 
Autonomous Industry Feedback
Autonomous Industry Feedback Autonomous Industry Feedback
Autonomous Industry Feedback
 
Real time monitoring proposal 2011
Real time monitoring proposal 2011Real time monitoring proposal 2011
Real time monitoring proposal 2011
 
Plant Operation System
Plant Operation SystemPlant Operation System
Plant Operation System
 
Cmr
CmrCmr
Cmr
 
Terminal Automation - Evolution & challenges
Terminal Automation - Evolution & challengesTerminal Automation - Evolution & challenges
Terminal Automation - Evolution & challenges
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
 
Rams 2007 paper pdf
Rams 2007 paper pdfRams 2007 paper pdf
Rams 2007 paper pdf
 
An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...
 
Check interval escalation
Check interval escalation Check interval escalation
Check interval escalation
 
Application of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented SystemsApplication of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented Systems
 
ECAST Meeting - 04 Jun 2013 - Reliability Data Sharing
ECAST Meeting - 04 Jun 2013 - Reliability Data SharingECAST Meeting - 04 Jun 2013 - Reliability Data Sharing
ECAST Meeting - 04 Jun 2013 - Reliability Data Sharing
 
Asco Safety Systems Solenoid Valve Selection Guide
Asco Safety Systems Solenoid Valve Selection GuideAsco Safety Systems Solenoid Valve Selection Guide
Asco Safety Systems Solenoid Valve Selection Guide
 
Transition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operationsTransition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operations
 
hdbk1101.pdf
hdbk1101.pdfhdbk1101.pdf
hdbk1101.pdf
 

Mais de calday

AGA Assessing Controller Workload Final May 10
AGA Assessing Controller Workload Final May 10AGA Assessing Controller Workload Final May 10
AGA Assessing Controller Workload Final May 10calday
 
Professionalism In Communications
Professionalism In CommunicationsProfessionalism In Communications
Professionalism In Communicationscalday
 
Theres An Elephant In The Control Room V4
Theres An Elephant In The Control Room V4Theres An Elephant In The Control Room V4
Theres An Elephant In The Control Room V4calday
 
API 2010 Pipeline Conference
API 2010 Pipeline ConferenceAPI 2010 Pipeline Conference
API 2010 Pipeline Conferencecalday
 
Dirty Dozen 2010 Client Presentation 97 03
Dirty Dozen 2010 Client Presentation 97 03Dirty Dozen 2010 Client Presentation 97 03
Dirty Dozen 2010 Client Presentation 97 03calday
 
Leadership Course PetroChina
Leadership Course PetroChinaLeadership Course PetroChina
Leadership Course PetroChinacalday
 
API 2009 Rule Implcations Fatigue Alday
API 2009 Rule Implcations Fatigue AldayAPI 2009 Rule Implcations Fatigue Alday
API 2009 Rule Implcations Fatigue Aldaycalday
 

Mais de calday (7)

AGA Assessing Controller Workload Final May 10
AGA Assessing Controller Workload Final May 10AGA Assessing Controller Workload Final May 10
AGA Assessing Controller Workload Final May 10
 
Professionalism In Communications
Professionalism In CommunicationsProfessionalism In Communications
Professionalism In Communications
 
Theres An Elephant In The Control Room V4
Theres An Elephant In The Control Room V4Theres An Elephant In The Control Room V4
Theres An Elephant In The Control Room V4
 
API 2010 Pipeline Conference
API 2010 Pipeline ConferenceAPI 2010 Pipeline Conference
API 2010 Pipeline Conference
 
Dirty Dozen 2010 Client Presentation 97 03
Dirty Dozen 2010 Client Presentation 97 03Dirty Dozen 2010 Client Presentation 97 03
Dirty Dozen 2010 Client Presentation 97 03
 
Leadership Course PetroChina
Leadership Course PetroChinaLeadership Course PetroChina
Leadership Course PetroChina
 
API 2009 Rule Implcations Fatigue Alday
API 2009 Rule Implcations Fatigue AldayAPI 2009 Rule Implcations Fatigue Alday
API 2009 Rule Implcations Fatigue Alday
 

2010 Pipeliners Club Crm Final Rule

  • 1.
  • 2. Pipeline Safety: Control Room Management /Human Factors “Final Rule December 3, 2009” Pipeliners Club of Atlanta January 11, 2010
  • 3. Presentation Objectives Provide background information on development of the rule. Present elements of “new” control room management rule. Comment on ways to comply with rule, and go beyond compliance.
  • 4. Background on Rule Development Pipeline and Hazardous Materials Safety Administration has been examining and evaluating and advising on Control Room operations for at least 14 years. (1996) NTSB has been making recommendations about “human factors” for at least 12 years. (1998) Pipeline Safety Improvement Act of 2002 Pipeline Inspection, Protection, Enforcement, and Safety Act of 2006 (PIPES Act)
  • 5. Safety Rec. P-05-001 (NTSB) Recommends that PHMSA: Require operators of hazardous liquids pipelines to follow the API Recommended Practice 1165 for the use of graphics on the SCADA* screens. NTSB had performed a safety study due to leaks going undetected after indications of a leak on the SCADA interface. New rule addresses this recommendation. *SCADA = Supervisory Control and Data Acquisition
  • 6. Safety Rec. P-05-002 (NTSB) Recommends that PHMSA: Require pipeline companies to have a policy for the review/audit of alarms. New rule addresses this recommendation.
  • 7. Safety Rec. P-05-003 (NTSB) Recommends that PHMSA: Require controller training to include simulator or non-computerized simulations for controller recognition of abnormal operating conditions, in particular, leak events. New rule addresses this recommendation.
  • 8. Safety Rec. P-05-004 (NTSB) Recommends that PHMSA: Change the liquid accident reporting form and require operators to provide data related to controller fatigue. This recommendation is being addressed in a change to accident reporting requirements for gas and liquids pipelines.
  • 9. Safety Rec. P-99-12 (NTSB) Urges PHMSA, to: “establish within two years scientifically based hours of service regulations… that set limits on hours of service,… provide predictable work and rest schedules… and consider circadian rhythms and human sleep and rest requirements.” New rule may or may not address this recommendation, depending on whether you are NTSB or PHMSA.
  • 10. Safety Rec. P-98-30 (NTSB) Urges PHMSA, to: “assess the potential safety risks associated with rotating pipeline controller shifts and… establish industry guidelines for the development and implementation of pipeline controller work schedules… that reduce the likelihood of accidents attributable to controller fatigue.” Closed May 3, 2006, due to P-99-12 being issued.
  • 11. Reasons for NTSB Bulletins The NTSB noted that scientific research has shown that certain sleep factors can affect fatigue and performance, such as insufficient sleep, irregular schedules, and unpredictable schedules.
  • 12. Reasons for NTSB Bulletins Recommendations resulted from the NTSB’s review of all transportation accidents reported to U.S. Department of Transportation (DOT) modal administrations over a 10 year period. NTSB noted that it had issued over 70 fatigue-related safety recommendations that resulted from its investigations of major accidents, special investigations, or safety studies that identified operator fatigue as a causal factor.
  • 13. Reasons for NTSB Bulletins Were there any pipeline accidents where Control Room issues could have contributed to the accident? Several examples cited: Colonial Pipeline 1996 (Controller fatigue) Marathon Pipeline 1998 (SCADA & alarms) Olympic Pipeline 1999 (SCADA maintenance) Marathon-Ashland 2000 (Controller fatigue) NTSB study “10 of 18 hazardous liquids accidents have potential Control Room involvement”
  • 14. Federal Most Wanted Transportation Safety Improvements Reduce Pipeline Accidents Caused by Human Fatigue
  • 15. NTSB Most Wanted No Federal hours-of-service regulations exist for controllers of pipeline systems Regulations exist in other transportation modes. Set working hour limits for pipeline controllers based on fatigue research, circadian rhythms, and sleep and rest requirements. “Acceptable Response – Progressing Slowly”
  • 16. PHMSA Bulletins “Pipeline Safety: Countermeasures to Prevent Human Fatigue in the Control Room” ADB-05-06 “Potential Service Disruptions in SCADA Systems” ADB-03-09 “Potential Service Interruptions in Supervisory Control and Data Acquisition Systems” ADB-99-03
  • 17. PHMSA & Industry Activities Controller Certification Study Participation with industry associations API 1165 RP SCADA displays API 1167 RP Alarm Mgt.(in progress) API 1168 RP Control Room Mgt. Battelle Human Factors Analysis API Control Room Forums SGA Gas Control Framework Document AGA White Papers
  • 18. Congress Pipeline Safety Improvement Act of 2002 Study control room operations Operator Qualification Requirements PIPES Act of 2006 “Reduce risks associated with human factors, including fatigue, for pipeline controllers and other employees.” NTSB recommendations on display, alarms, and training Issue regulations
  • 19. Notice of Proposed Rulemaking PHMSA issued NPRM PHMSA-2007-27954 on September 12, 2008. Received 144 comments, mostly from liquids and gas pipeline industry groups and companies. Majority of comments said “withdraw the proposed rule and start over.” Rule was not withdrawn, but PHMSA did take some comments into consideration before issuing the final rule.
  • 20. Initial Summary Statements Must define the roles and responsibilities of controllers… And provide controllers with the necessary information, training, and processes to fulfill these responsibilities. …must also implement methods to prevent controller fatigue
  • 21. Initial Summary (continued) …manage SCADA alarms …assure control room considerations are taken into account when changing pipeline equipment or configurations… …review reportable incidents or accidents to determine whether control room actions contributed to the event.
  • 22. Effective Dates Final rule is effective February 1, 2010. Develop control room management procedures by August 1, 2011. Implement the procedures by February 1, 2012. Plenty of time for compliance? Most companies still have questions about what parts of the rule “really mean.”
  • 23. Definitions in Parts 192 & 195 Important for determining if rule applies: Alarm Controller Control Room Supervisory Control and Data Acquisition System
  • 24. Definitions in Parts 192 & 195 Alarm means an audible or visible means of indicating to the controller that equipment or processes are outside operator-defined, safety-related parameters. Control Room means an operations center staffed by personnel charged with the responsibility for remotely monitoring and controlling a pipeline facility.
  • 25. Definitions in Parts 192 & 195 Controller means a qualified individual who remotely monitors and controls the safety-related operations of a pipeline facility via a SCADA system from a control room, and who has operational authority and accountability for the remote operational functions of the pipeline facility.
  • 26. Definitions in Parts 192 & 195 Supervisory Control and Data Acquisition (SCADA) system means a computer-based system or systems used by a controller in a control room that collects and displays information about a pipeline facility and may have the ability to send commands back to the pipeline facility.
  • 27. Rule for Parts 192 & 195 If you have controller(s) in a control room monitoring and controlling with a SCADA system; Applies to natural gas pipelines, except Distribution with less than 250,000 services, or Transmission without a compressor station Must still implement sections about fatigue, compliance validation, compliance and deviations. Applies to hazardous liquids pipelines.
  • 28. Control Room Mgt. Section Written control room management plan Define controller roles and responsibilities: Normal, abnormal, and emergency operations Authority to make decisions and take actions Controller’s role during abnormal operating conditions Controller’s role during emergency operating conditions Method of recording shift-changes and hand-over of responsibility. I would also define roles and responsibilities of other jobs in relation to controllers so that every person understands roles and responsibilities.
  • 29. “Provide adequate information” Implement API 1165 (partially for gas) whenever SCADA is changed. Conduct point-to-point verification between SCADA displays and field equipment whenever something is changed. Test and verify internal communication plan for manual operation of the pipeline. Test any backup SCADA systems. Implement section 5 of API RP 1168 to establish procedures for when different controller assumes responsibility. Very specific in this section, because it is easier to be specific about SCADA systems & equipment.
  • 30. “Fatigue mitigation” Establish shift lengths and schedule rotations that…provide time…to achieve 8 hours of continuous sleep. Work time + commute time Educate controllers and supervisors in fatigue mitigation strategies and how off-duty activities contribute to fatigue. Regular, ongoing Train controllers and supervisors to recognize the effects of fatigue. Recognize signs and risks Establish a maximum limit on controller hours of service. Day, week, dayshift, nightshift Less specific in “socio-technical” system.
  • 31. “Alarm Management” Written alarm management plan Review SCADA safety-related alarm operations using a process that ensures alarms are accurate… Monthly identification of alarms that are off-scan, inhibited, false, etc. Verify correct safety-related alarm set-point values and alarm descriptions annually. Review alarm management plan annually. Monitor content and volume of general activity directed to controller annually to ensure alarm response. Address deficiencies in any of these items. Specific again
  • 32. “Change Management” Establish communications between control room representatives, management, and field personnel when planning and implementing changes. Document your plans and practices Require field personnel to contact control room during emergency conditions or when making field changes. How will you “require?” Seek control room or control room management participation in planning prior to implementation of significant pipeline hydraulic or configuration changes. What is “significant?” Less specific, due to more “socio-technical” elements
  • 33. “Operating Experience” Incorporate lessons learned from operating experience into procedures and training. Review incidents that meet reporting requirements for contributions/deficiencies: Controller fatigue Field equipment Operation of any safety device Procedures SCADA system configuration & performance. Do you have operating experience system?
  • 34. “Training” Establish, then review annually and improve training program. Responding to abnormal operating conditions likely to occur. Use of simulator or tabletop method for training controllers to recognize abnormal operating conditions. Working knowledge of pipeline system… Infrequently used setups and procedures. Most companies have a training program.
  • 35. “Compliance Validation” Submit procedures, when requested, to PHMSA or appropriate State agency.
  • 36. “Compliance & Deviations” Maintain records for review: Records that demonstrate compliance Documentation to demonstrate that any deviations from requirements was necessary for the safe operation of a pipeline facility.
  • 37. Summary Was this rule necessary? Can this rule help improve pipeline operations? Incidents and near misses are caused by any and all of the areas in the rule. Most organizations are averse to learning. Most organizations have a change management process, but sometimes do not manage changes well. Is the final rule the “final” rule? Believe SCADA and alarm management are. Do not believe fatigue mitigation will be.