Brian D. Rich, AIA, NCARB, LEED AP, CDT, CCCA, PMP*
Richaven PLLC
HISTORIC PRESERVATION
IN KING COUNTY
THE REGULATORY AND REVIEW PROCESS
OFTHE
KING COUNTY LANDMARKS COMMISSION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
PART I – A BRIEF HISTORY OF HISTORIC PRESERVATION
PART II - WHAT ARETHE ELEMENTS OFTHE KING COUNTY HISTORIC PRESERVATION
PROGRAM?
PART III – SECRETARY OFTHE INTERIOR’S STANDARDS FORTHETREATMENT OF
HISTORIC PROPERTIES BYTHE NATIONAL PARK SERVICE
PART IV - CULTURAL LANDSCAPES PART I – A BRIEF HISTORY OF HISTORIC
PRESERVATION
PART V - WHAT IS A COA AND HOW DOES IT WORK?
PART VI – APPLICATION OF SECRETARY OFTHE INTERIOR’S STANDARDS – CASE
STUDIES
PART VII – WHAT HAVE WE LEARNED?
PART VIII - WHAT CAN CSI MEMBERS DOTO BE MORE AWARE OF HISTORIC
PRESERVATION ISSUES FORTHEIR PROJECTS?
OUTLINE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
WHAT ARE THE STANDARDS, RULES, AND REGULATIONSTHAT APPLYTO KING
COUNTY LANDMARKS?
HOW DOESTHE KING COUNTY LANDMARKS COMMISSION MAKE IT’S
DECISIONS ON PROJECTS?
HOW ARE THESE DECISIONS COMMUNICATEDTO
OWNERS, PRACTITIONERS, AND CONTRACTORS?
HISTORIC PRESERVATION IN KING
COUNTY
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
1966 NATIONAL HISTORIC PRESERVATION ACT AND
FLOWED FROMTHERE…
NHPA enabled states to create legislation and
established the SHPO
Local jurisdictions passed their own ordinances
Historic Preservation in King County originates in the
King County Planning Policies
King County created the Historic Preservation Program
in 1978 with KCC 20.62.
FORMAL HISTORIC PRESERVATION IN
THE US STARTED IN…
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
King County Code Section 20.62
Administrative Rules and Regulations
King County Landmarks Commission
King County Historic Preservation Program
4 CULTURE
PART II - WHAT ARETHE ELEMENTS
OFTHE KING COUNTY HISTORIC
PRESERVATION PROGRAM?
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
King County Historic Preservation Program
Criteria for nomination and designation of landmarks
Procedures for Certificates of Appropriateness (COAs)
Procedures for evaluation of economic impact
Procedures for appeals, penalties, and funding
Enabled creation of administrative rules
WHAT DOES KCC 20.62 INCLUDE?
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
CRITERION A: Is associated with events that have made a significant contribution
to the broad patterns of national, state or local history
CRITERION B: Is associated with the lives of persons significant in national, state
or local history
CRITERION C: Embodies the distinctive characteristics of a type, period, style or
method of design or construction, or that represents a significant and
distinguishable entity whose components may lack individual distinction
CRITERION D: Has yielded, or may be likely to yield, information important to
prehistory or history
CRITERION E: Is an outstanding work of a designer or builder who has made a
substantial contribution to the art
LANDMARK DESIGNATION CRITERIA
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
In many ways they repeat a lot of the provisions of KCC 20.62
Most importantly, KC Landmarks Commissions Rules and Regulations refer
us to the Secretary of the Interior’s Standards for evaluation of alterations to
designated landmarks.
What are the Standards and how do they work?
KCLC RULES AND REGULATIONS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Formally known as….
PART III –THE STANDARDS
OR…
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
… IS NOT THE HYPOCRITIC OATH!
THE ESSENCE OFTHE STANDARDS…
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
THE ESSENCE OFTHE STANDARDS…
… IS THE HIPPOCRATIC OATH!
• “…I will follow that system of regimen
which, according to my ability and
judgment, I consider for the benefit of my
patients, and abstain from whatever is
deleterious and mischievous…”
• Or, in other words…
FIRST , DO NO HARM.
• Second, preserve the nature of the
original entity
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
PRESERVATION is defined as the act
or process of applying measures
necessary to sustain the existing
form, integrity, and materials of an
historic property.
PRESERVATION – DEFINITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
a) A property will be used as it was historically, or be given a new use
that maximizes the retention of distinctive materials, features, spaces, and
spatial relationships. Where a treatment and use have not been identified, a
property will be protected and, if necessary, stabilized until additional work
may be undertaken.
b) The historic character of a property will be retained and preserved.
The replacement of intact or repairable historic materials or alteration of
features, spaces, and spatial relationships that characterize a property will
be avoided.
PRESERVATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
c) Each property will be recognized as a physical record of its
time, place, and use. Work needed to stabilize, consolidate, and conserve
existing historic materials and features will be physically and visually
compatible, identifiable upon close inspection, and properly documented for
future research.
d) Changes to a property that have acquired historic significance in
their own right will be retained and preserved.
e) Distinctive materials, features, finishes, and construction
techniques or examples of craftsmanship that characterize a property will be
preserved.
PRESERVATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
f) The existing condition of historic features will be evaluated to
determine the appropriate level of intervention needed. Where the severity
of deterioration requires repair or limited replacement of a distinctive
feature, the new material will match the old in
composition, design, color, and texture.
g) Chemical or physical treatments, if appropriate, will be undertaken
using the gentlest means possible.Treatments that cause damage to historic
materials will not be used.
h) Archeological resources will be protected and preserved in place. If
such resources must be disturbed, mitigation measures will be undertaken.
PRESERVATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
REHABILITATION is defined as the act
or process of making possible a
compatible use for a property through
repair, alterations, and additions while
preserving those portions or features
which convey its historical, cultural, or
architectural values.
REHABILITATION – DEFINITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
a) A property will be used as it was historically or be given a new use
that requires minimal change to its distinctive
materials, features, spaces, and spatial relationships.
b) The historic character of a property will be retained and preserved.
The removal of distinctive materials or alteration of features, spaces, and
spatial relationships that characterize a property will be avoided.
c) Each property will be recognized as a physical record of its
time, place, and use. Changes that create a false sense of historical
development, such as adding conjectural features or elements from other
historic properties, will not be undertaken.
REHABILITATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
d) Changes to a property that have acquired historic significance in
their own right will be retained and preserved.
e) Distinctive materials, features, finishes, and construction
techniques or examples of craftsmanship that characterize a property will be
preserved.
f) Deteriorated historic features will be repaired rather than replaced.
Where the severity of deterioration requires replacement of a distinctive
feature, the new feature will match the old in
design, color, texture, and, where possible, materials. Replacement of
missing features will be substantiated by documentary and physical
evidence.
REHABILITATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
g) Chemical or physical treatments, if appropriate, will be undertaken
using the gentlest means possible.Treatments that cause damage to historic
materials will not be used.
h) Archeological resources will be protected and preserved in place. If
such resources must be disturbed, mitigation measures will be undertaken.
REHABILITATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
i) New additions, exterior alterations, or related new construction
will not destroy historic materials, features, and spatial relationships that
characterize the property.The new work shall be differentiated from the old
and will be compatible with the historic materials, features, size, scale and
proportion, and massing to protect the integrity of the property and its
environment.
j) New additions and adjacent or related new construction will be
undertaken in a such a manner that, if removed in the future, the essential
form and integrity of the historic property and its environment would be
unimpaired.
REHABILITATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
RESTORATION is defined as the act or process of
accurately depicting the form, features, and
character of a property as it appeared at a
particular period of time by means of the removal
of features from other periods in its history and
reconstruction of missing features from the
restoration period.The limited and sensitive
upgrading of mechanical, electrical, and
plumbing systems and other code-required work
to make properties functional is appropriate
within a restoration project.
RESTORATION – DEFINITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
a) A property will be used as it was historically or be given a new use
which reflects the property's restoration period.
b) Materials and features from the restoration period will be retained
and preserved.The removal of materials or alteration of
features, spaces, and spatial relationships that characterize the period will
not be undertaken.
c) Each property will be recognized as a physical record of its
time, place, and use. Work needed to stabilize, consolidate and conserve
materials and features from the restoration period will be physically and
visually compatible, identifiable upon close inspection, and properly
documented for future research.
RESTORATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
d) Materials, features, spaces, and finishes that characterize other
historical periods will be documented prior to their alteration or removal.
e) Distinctive materials, features, finishes, and construction
techniques or examples of craftsmanship that characterize the restoration
period will be preserved.
f) Deteriorated features from the restoration period will be repaired
rather than replaced. Where the severity of deterioration requires
replacement of a distinctive feature, the new feature will match the old in
design, color, texture, and, where possible, materials.
RESTORATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
g) Replacement of missing features from the restoration period will be
substantiated by documentary and physical evidence. A false sense of history will
not be created by adding conjectural features, features from other properties, or
by combining features that never existed together historically.
h) Chemical or physical treatments, if appropriate, will be undertaken using
the gentlest means possible.Treatments that cause damage to historic materials
will not be used.
i) Archeological resources affected by a project will be protected and
preserved in place. If such resources must be disturbed, mitigation measures will
be undertaken.
j) Designs that were never executed historically will not be constructed.
RESTORATION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
RECONSTRUCTION is defined as the
act or process of depicting, by means
of new construction, the
form, features, and detailing of a
non-surviving
site, landscape, building, structure, or
object for the purpose of replicating
its appearance at a specific period of
time and in its historic location
RECONSTRUCTION – DEFINITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
a) Reconstruction will be used to depict vanished or non-surviving
portions of a property when documentary and physical evidence is available
to permit accurate reconstruction with minimal conjecture, and such
reconstruction is essential to the public understanding of the property.
b) Reconstruction of a landscape, building, structure, or object in its
historic location will be preceded by a thorough archeological investigation
to identify and evaluate those features and artifacts which are essential to
an accurate reconstruction. If such resources must be disturbed, mitigation
measures will be undertaken.
c) Reconstruction will include measures to preserve any remaining
historic materials, features, and spatial relationships.
RECONSTRUCTION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
d) Reconstruction will be based on the accurate duplication of historic
features and elements substantiated by documentary or physical evidence
rather than on conjectural designs or the availability of different features
from other historic properties. A reconstructed property will re-create the
appearance of the non-surviving historic property in
materials, design, color, and texture.
e) A reconstruction will be clearly identified as a contemporary re-
creation.
f) Designs that were never executed historically will not be
constructed.
RECONSTRUCTION – STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
A CULTURAL LANDSCAPE is defined as "a geographic area, including both cultural
and natural resources and the wildlife or domestic animals therein, associated with
a historic event, activity, or person or exhibiting other cultural or aesthetic values."
There are four general types of cultural landscapes, not mutually exclusive: historic
sites, historic designed landscapes, historic vernacular landscapes, and
ethnographic landscapes.
PART IV - CULTURAL LANDSCAPES
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
A landscape that was consciously designed or laid out by a landscape
architect, master gardener, architect, or horticulturist according to design
principles, or an amateur gardener working in a recognized style or tradition.
HISTORIC DESIGNED LANDSCAPE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
A landscape that evolved through use by the people whose activities or
occupancy shaped that landscape.
Through social or cultural attitudes of an individual, family or a
community, the landscape reflects the physical, biological, and cultural
character of those everyday lives.
HISTORICVERNACULAR LANDSCAPE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
A landscape significant for its association with a historic event, activity, or
person.
Examples include battlefields and president's house properties.
HISTORIC SITE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
A landscape containing a variety of
natural and cultural resources that
associated people define as heritage
resources.
Examples are contemporary
settlements, religious sacred sites and
massive geological structures.
Small plant
communities, animals, subsistence and
ceremonial grounds are often
components.
ETHNOGRAPHIC LANDSCAPE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
• COA = Certificate Of Appropriateness
• Application to the Landmarks Commission for approval of alterations to be done to a
landmark.
• A COA can contain the application form, drawings, narrative descriptions, material
samples, specifications, or any combination of the above items.
• There are 3 types of COAs
• Type I
• Type II
• Type III
PARTV - WHAT IS A C.O.A.?
HOW DOES ITWORK?
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Projects that involve restoration of historic
features and major repairs using the same type
of materials originally found on the building
require a Type I COA.
An example of a project that requires a Type I
COA is replacing a deteriorated shingle roof
with a new shingle roof. Or replacing old
cartilage with newly grown cartilage.
TYPE I COAs
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Projects that involve alterations in the appearance
of the property requireType II COAs.
Examples of projects requiringType II COA are
building an addition on a landmark
building, adding a new building within the
boundary of a landmark property or district, or
replacing a joint with a metal ball and socket.
TYPE II COAs
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Projects that propose the
demolition or relocation of
landmark properties or the
excavation of archaeological
sites requireType III COA’s.
These types of projects have an
irreversible effect on a landmark
property, and therefore require
the most stringent review.
TYPE III COAs
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
TYPICALTYPE II COA PROCESS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
CASE STUDIES
PARTVI – APPLICATION OF
SECRETARY OFTHE INTERIOR’S
STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
MARY OLSON FARM
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Built in 1897 through 1902
In Auburn, Washington
Designated a King County Landmark in 1995
Farmstead includes an 1897 hay barn, a 1902 farm house, and several
outbuildings constructed in the late 19th and early 20th centuries including a
weaving house, smokehouse, garage / ice house, and chicken coop.
Mission Statement/Preservation Philosophy
HISTORY
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
It is listed on the National Register of Historic Places under Category A as a
Locally Significant place associated with events that have made a significant
contribution to the broad patterns of our history.
It is listed as a King County Landmark, designated under Criterion A1 and
A3, for its strong association with the evolving agricultural history of King
County and as an intact cultural landscape complete with a late 19th century
working farm including a farmhouse, several
outbuildings, road, creek, fence, orchard, forest, and field features.
Features of Significance include all exterior portions of the contributing
buildings, interior of the barn, all fences, orchard trees…
The Period of Significance is from 1897 to 1940, encompassing the major
physical development of the farm.
SIGNIFICANCE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Siding, which runs the full height of the 30’ walls, is rotting
Doors deteriorating, and a code and ADA compliant floor were non-existent
Roof needed to be replaced on barn
Several other structures on property that had collapsed
CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Barn restoration – siding & roof
Barn restoration – flooring, doors, and siding
These projects at Mary Olson Farm are the best of preservation where
original building fabric is carefully duplicated in material and even method of
fabrication and installation
TYPE II COAs SUBMITTED
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
TYPE II COA’S SUBMITTED
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Standards for Rehabilitation were applied
APPLICATION OFTHE SECRETARY OF
THE INTERIOR’S STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
All applications for Type II COAs have been approved and work is in progress
Auburn School District uses the farm as an educational tool for their children
demonstrating our heritage and old farming techniques
CONCLUSION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
QUAALE LOG CABIN
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Built circa 1903 to 1905
West edge of the SnoqualmieValley, near Carnation
Designated a King County Landmark in 1990
HISTORY
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
One of the earliest and best extant examples of log cabin construction in the
Snoqualmie River Valley and King County.
Designated under Criterion A3 as an excellent example of alternating hewn
log construction
with full dovetail cornering with
no overlap.
Features of Significance include
all exterior portions of the house.
One of two remaining log houses
in King County retaining its
physical integrity.
SIGNIFICANCE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Roof needed reworking
Windows and doors did not seal completely
Deteriorating due to water infiltration
BUILDING CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
COA included in-kind replacement of all original windows with new wood
framed windows
TYPE II COA APPLICATION
SUBMITTED
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Standards for Rehabilitation were
applied
APPLICATION OFTHE SECRETARY OF
THE INTERIOR’S STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
KCLC approved the application for a Type 2 COA
Window installation was completed in Mid-2005.
CONCLUSION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
TOLT BRIDGE DEMOLITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Built in 1922
Second bridge at this location on
Tolt Hill Road, crossing the
Snoqualmie River
PrattTruss (Parker Sub-type)
Designed and built at a time when
fully riveted trusses were gaining
favor with the introduction of the
pneumatic riveter.
HISTORY
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Designated less than 10 years ago, in
1997
Designated under Criterion A3 due to
its design as one of only two
remaining fully riveted Pratt (Parker
sub-type) trusses in King County
Features of Significance include: All
components of the bridge and their
associated approaches.
SIGNIFICANCE
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Severely rusted members
Corrosion was in areas where it could not be arrested
Bridge was in danger of collapse
CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
CONDITION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
New bridge to be built adjacent to old
bridge
New bridge was downstream of old
bridge
Could not keep old bridge for several
reasons
Old bridge had to be
removed, therefore the Type III COA
application was required.
TYPE III COA SUBMITTED
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Secretary of the Interior’s Standards
were NOT applied
APPLICATION OFTHE SECRETARY OF
THE INTERIOR’S STANDARDS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
KCLC Rules and Regulations allow for demolition of a Designated Landmark
on the basis of a threat to public health and safety
KCLC Rules and Regulations allow for leniency in alterations to landmarks on
the basis of Economic Hardship
Washington State and Federal Laws do not allow for increasing the water
level during a flood
APPLICATION OFWASHINGTON
STATE LAW AND KCLC RULES AND
REGULATIONS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
APPLICATION OFWASHINGTON
STATE LAW AND KCLC RULES AND
REGULATIONS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
KCLC approved the application for a Type III COA
King County Roads and Bridges Department presented a carefully outlined
case for why the bridge had to be removed, including all of the County, State
and Federal laws and economic implications supporting their decisions.
KC Roads & Bridges worked with the Commission to provide the information
which provided the key to allowing the demolition of the bridge. They
worked the KC Code.
King County lost one of the finest examples of the early 20th Century bridges
Mitigation Efforts
CONCLUSION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Landmarks Commissions are here to
ensure we do not destroy our cultural
heritage with a balance of using and
preserving the resource
The Secretary of the Interior’s Standards
intentionally allow for flexibility
Make your case!
PARTVII –WHAT HAVEWE LEARNED?
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
WHAT CANYOU DO TO BE MORE AWARE OF HISTORIC PRESERVATION
ISSUES ONYOUR PROJECTS?
PARTVIII -WHAT CANYOU DO?
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Why is keeping any building or site valuable?
What does Preservation mean to the Owner?
What does Preservation meant to the user?
UNDERSTANDTHE CONCEPT OF
PRESERVATION
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Use caution when calling for any
procedure which may damage the
historic fabric of a site or building or
material
Remember the Hippocratic Oath
(not the Hypocritic Oath!)
UNDERSTANDTHE CONCEPT OF
REVERSIBILITY
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Understand what the preservation philosophy and approach is for each
project, client, design team.
Make sure all Team Members understand what the Preservation Philosophy
is.
Landmark Designation forms are the key to documenting this philosophy.
Use Historic Resources Survey/Inventory information if it’s not designated!
DEVELOP A PRESERVATION
PHILOSOPHY
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Exercise and require caution when designing
new construction to go within an existing
historic structure
Material compatibility
Design/aesthetic compatibility
Does it meet the preservation philosophy?
Be sensitive to not only the appearance, but the
substance of the materials being altered.
DESIGN APPROPRIATELY
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
Call for large scale tests and mockups of procedures prior to implementation
on all different substrates.
Monitor your construction
Contractor be aware of what you are doing – we only get one chance.
TESTYOUR HYPOTHESES
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
The design team and Owner should understand that a restoration project
will only be the first of many.
Hopefully, one alteration project will keep the structure around long enough
for someone to want to do another one in the future.
ANTICIPATE FUTURE REHABILITATIONS
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
There is no magic silver bullet for all sets of
conditions
Multiple choices for each situation
All projects are constrained by
budget, time, and quality criteria
What we do is make decisions and choices.
MAKE A DECISION AND
DOCUMENT IT
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
THANKYOU!
QUESTIONS?
SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866

Mais conteúdo relacionado

Semelhante a Preservation in King County

Semelhante a Preservation in King County (20)

2008 01 09 H D C Kidorf Farmington Hills H D C
2008 01 09  H D C  Kidorf Farmington  Hills  H D C2008 01 09  H D C  Kidorf Farmington  Hills  H D C
2008 01 09 H D C Kidorf Farmington Hills H D C
 
Architectural conservation
Architectural conservationArchitectural conservation
Architectural conservation
 
casestudy on conservation of historic township (leh)
casestudy on conservation of historic township (leh)casestudy on conservation of historic township (leh)
casestudy on conservation of historic township (leh)
 
Downtown Kankakee Historic District Public Hearing 8-31-16
Downtown Kankakee Historic District Public Hearing 8-31-16Downtown Kankakee Historic District Public Hearing 8-31-16
Downtown Kankakee Historic District Public Hearing 8-31-16
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
 
Architectural_conservation_Guidelines_no.pdf
Architectural_conservation_Guidelines_no.pdfArchitectural_conservation_Guidelines_no.pdf
Architectural_conservation_Guidelines_no.pdf
 
Zahran heritage design guidelines
Zahran heritage design guidelines Zahran heritage design guidelines
Zahran heritage design guidelines
 
Integrated Urban Conservation, MURP.pptx
Integrated Urban Conservation, MURP.pptxIntegrated Urban Conservation, MURP.pptx
Integrated Urban Conservation, MURP.pptx
 
Icomos principles
Icomos principlesIcomos principles
Icomos principles
 
Lecture 3 Degree of Intervention.ppt
Lecture 3 Degree of Intervention.pptLecture 3 Degree of Intervention.ppt
Lecture 3 Degree of Intervention.ppt
 
Historic Buildings and Sustainability
Historic Buildings and SustainabilityHistoric Buildings and Sustainability
Historic Buildings and Sustainability
 
3.Finding New Uses for Former Military Land: Military Land in the Planning Pr...
3.Finding New Uses for Former Military Land: Military Land in the Planning Pr...3.Finding New Uses for Former Military Land: Military Land in the Planning Pr...
3.Finding New Uses for Former Military Land: Military Land in the Planning Pr...
 
Planning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil StichertPlanning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil Stichert
 
Local heritage and planning policy- Pete Boland, RTPI CPD
Local heritage and planning policy- Pete Boland, RTPI CPDLocal heritage and planning policy- Pete Boland, RTPI CPD
Local heritage and planning policy- Pete Boland, RTPI CPD
 
Cadw, planning and the historic environment of wales / Cynllunio ac Amgylched...
Cadw, planning and the historic environment of wales / Cynllunio ac Amgylched...Cadw, planning and the historic environment of wales / Cynllunio ac Amgylched...
Cadw, planning and the historic environment of wales / Cynllunio ac Amgylched...
 
Ar6017 urban housing unit 04 no copy
Ar6017 urban housing unit 04 no copyAr6017 urban housing unit 04 no copy
Ar6017 urban housing unit 04 no copy
 
Optimising Existing Structures Through Retrofitting
Optimising Existing Structures Through RetrofittingOptimising Existing Structures Through Retrofitting
Optimising Existing Structures Through Retrofitting
 
Optimising Existing Structures Through Retrofitting
Optimising Existing Structures Through  RetrofittingOptimising Existing Structures Through  Retrofitting
Optimising Existing Structures Through Retrofitting
 
2008 Historic Districts
2008 Historic Districts2008 Historic Districts
2008 Historic Districts
 
Conservation slide show
Conservation slide showConservation slide show
Conservation slide show
 

Mais de Brian Rich

Future-Proofing and Panarchy in the Historic Built Environment
Future-Proofing and Panarchy in the Historic Built EnvironmentFuture-Proofing and Panarchy in the Historic Built Environment
Future-Proofing and Panarchy in the Historic Built Environment
Brian Rich
 

Mais de Brian Rich (19)

Technical Issues in Historic Preservation: Brick & Clay Masonry - Materials ...
Technical Issues in Historic Preservation:  Brick & Clay Masonry - Materials ...Technical Issues in Historic Preservation:  Brick & Clay Masonry - Materials ...
Technical Issues in Historic Preservation: Brick & Clay Masonry - Materials ...
 
Panarchy & The Principles of Future-Proofing
Panarchy & The Principles of Future-ProofingPanarchy & The Principles of Future-Proofing
Panarchy & The Principles of Future-Proofing
 
Mid-Century Modern - Modern Philosophies & Materials
Mid-Century Modern - Modern Philosophies & MaterialsMid-Century Modern - Modern Philosophies & Materials
Mid-Century Modern - Modern Philosophies & Materials
 
Principles of Future-Proofing - APTI Ottowa 2017
Principles of Future-Proofing - APTI Ottowa 2017Principles of Future-Proofing - APTI Ottowa 2017
Principles of Future-Proofing - APTI Ottowa 2017
 
APT Northwest - Mid-century Modern Panel Discussion
APT Northwest - Mid-century Modern Panel DiscussionAPT Northwest - Mid-century Modern Panel Discussion
APT Northwest - Mid-century Modern Panel Discussion
 
Future-proofing Water Infrastructure - ACSA Seattle 2016
Future-proofing Water Infrastructure - ACSA Seattle 2016Future-proofing Water Infrastructure - ACSA Seattle 2016
Future-proofing Water Infrastructure - ACSA Seattle 2016
 
Future-Proofing and Panarchy in the Historic Built Environment
Future-Proofing and Panarchy in the Historic Built EnvironmentFuture-Proofing and Panarchy in the Historic Built Environment
Future-Proofing and Panarchy in the Historic Built Environment
 
Future-Proofing Historic Buildings - A Proposed Rating System
Future-Proofing Historic Buildings - A Proposed Rating SystemFuture-Proofing Historic Buildings - A Proposed Rating System
Future-Proofing Historic Buildings - A Proposed Rating System
 
The 10 Principles of Future-Proofing and the Arctic Building
The 10 Principles of Future-Proofing and the Arctic BuildingThe 10 Principles of Future-Proofing and the Arctic Building
The 10 Principles of Future-Proofing and the Arctic Building
 
10 Principles of Future Proofing Historic Buildings
10 Principles of Future Proofing Historic Buildings10 Principles of Future Proofing Historic Buildings
10 Principles of Future Proofing Historic Buildings
 
Sustainability Through Preservation
Sustainability Through PreservationSustainability Through Preservation
Sustainability Through Preservation
 
Preservation basics wood-stone-brick by richaven
Preservation basics   wood-stone-brick by richavenPreservation basics   wood-stone-brick by richaven
Preservation basics wood-stone-brick by richaven
 
Conduct of Public Hearings for Landmark Commissions
Conduct of Public Hearings for Landmark CommissionsConduct of Public Hearings for Landmark Commissions
Conduct of Public Hearings for Landmark Commissions
 
Preservation & Sustainability - City of Redmond
Preservation & Sustainability - City of RedmondPreservation & Sustainability - City of Redmond
Preservation & Sustainability - City of Redmond
 
Brian Rich's Resume & Portfolio
Brian Rich's Resume & PortfolioBrian Rich's Resume & Portfolio
Brian Rich's Resume & Portfolio
 
Stone Restoration Workshop
Stone Restoration WorkshopStone Restoration Workshop
Stone Restoration Workshop
 
Wood Preservation Presentation
Wood Preservation PresentationWood Preservation Presentation
Wood Preservation Presentation
 
Exposed Concrete Floors
Exposed Concrete FloorsExposed Concrete Floors
Exposed Concrete Floors
 
The Future of LEED and Historic Preservation
The Future of LEED and Historic PreservationThe Future of LEED and Historic Preservation
The Future of LEED and Historic Preservation
 

Preservation in King County

  • 1. Brian D. Rich, AIA, NCARB, LEED AP, CDT, CCCA, PMP* Richaven PLLC HISTORIC PRESERVATION IN KING COUNTY THE REGULATORY AND REVIEW PROCESS OFTHE KING COUNTY LANDMARKS COMMISSION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 2. PART I – A BRIEF HISTORY OF HISTORIC PRESERVATION PART II - WHAT ARETHE ELEMENTS OFTHE KING COUNTY HISTORIC PRESERVATION PROGRAM? PART III – SECRETARY OFTHE INTERIOR’S STANDARDS FORTHETREATMENT OF HISTORIC PROPERTIES BYTHE NATIONAL PARK SERVICE PART IV - CULTURAL LANDSCAPES PART I – A BRIEF HISTORY OF HISTORIC PRESERVATION PART V - WHAT IS A COA AND HOW DOES IT WORK? PART VI – APPLICATION OF SECRETARY OFTHE INTERIOR’S STANDARDS – CASE STUDIES PART VII – WHAT HAVE WE LEARNED? PART VIII - WHAT CAN CSI MEMBERS DOTO BE MORE AWARE OF HISTORIC PRESERVATION ISSUES FORTHEIR PROJECTS? OUTLINE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 3. WHAT ARE THE STANDARDS, RULES, AND REGULATIONSTHAT APPLYTO KING COUNTY LANDMARKS? HOW DOESTHE KING COUNTY LANDMARKS COMMISSION MAKE IT’S DECISIONS ON PROJECTS? HOW ARE THESE DECISIONS COMMUNICATEDTO OWNERS, PRACTITIONERS, AND CONTRACTORS? HISTORIC PRESERVATION IN KING COUNTY SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 4. 1966 NATIONAL HISTORIC PRESERVATION ACT AND FLOWED FROMTHERE… NHPA enabled states to create legislation and established the SHPO Local jurisdictions passed their own ordinances Historic Preservation in King County originates in the King County Planning Policies King County created the Historic Preservation Program in 1978 with KCC 20.62. FORMAL HISTORIC PRESERVATION IN THE US STARTED IN… SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 5. King County Code Section 20.62 Administrative Rules and Regulations King County Landmarks Commission King County Historic Preservation Program 4 CULTURE PART II - WHAT ARETHE ELEMENTS OFTHE KING COUNTY HISTORIC PRESERVATION PROGRAM? SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 6. King County Historic Preservation Program Criteria for nomination and designation of landmarks Procedures for Certificates of Appropriateness (COAs) Procedures for evaluation of economic impact Procedures for appeals, penalties, and funding Enabled creation of administrative rules WHAT DOES KCC 20.62 INCLUDE? SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 7. CRITERION A: Is associated with events that have made a significant contribution to the broad patterns of national, state or local history CRITERION B: Is associated with the lives of persons significant in national, state or local history CRITERION C: Embodies the distinctive characteristics of a type, period, style or method of design or construction, or that represents a significant and distinguishable entity whose components may lack individual distinction CRITERION D: Has yielded, or may be likely to yield, information important to prehistory or history CRITERION E: Is an outstanding work of a designer or builder who has made a substantial contribution to the art LANDMARK DESIGNATION CRITERIA SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 8. In many ways they repeat a lot of the provisions of KCC 20.62 Most importantly, KC Landmarks Commissions Rules and Regulations refer us to the Secretary of the Interior’s Standards for evaluation of alterations to designated landmarks. What are the Standards and how do they work? KCLC RULES AND REGULATIONS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 9. Formally known as…. PART III –THE STANDARDS OR… SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 10. … IS NOT THE HYPOCRITIC OATH! THE ESSENCE OFTHE STANDARDS… SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 11. THE ESSENCE OFTHE STANDARDS… … IS THE HIPPOCRATIC OATH! • “…I will follow that system of regimen which, according to my ability and judgment, I consider for the benefit of my patients, and abstain from whatever is deleterious and mischievous…” • Or, in other words… FIRST , DO NO HARM. • Second, preserve the nature of the original entity SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 12. PRESERVATION is defined as the act or process of applying measures necessary to sustain the existing form, integrity, and materials of an historic property. PRESERVATION – DEFINITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 13. a) A property will be used as it was historically, or be given a new use that maximizes the retention of distinctive materials, features, spaces, and spatial relationships. Where a treatment and use have not been identified, a property will be protected and, if necessary, stabilized until additional work may be undertaken. b) The historic character of a property will be retained and preserved. The replacement of intact or repairable historic materials or alteration of features, spaces, and spatial relationships that characterize a property will be avoided. PRESERVATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 14. c) Each property will be recognized as a physical record of its time, place, and use. Work needed to stabilize, consolidate, and conserve existing historic materials and features will be physically and visually compatible, identifiable upon close inspection, and properly documented for future research. d) Changes to a property that have acquired historic significance in their own right will be retained and preserved. e) Distinctive materials, features, finishes, and construction techniques or examples of craftsmanship that characterize a property will be preserved. PRESERVATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 15. f) The existing condition of historic features will be evaluated to determine the appropriate level of intervention needed. Where the severity of deterioration requires repair or limited replacement of a distinctive feature, the new material will match the old in composition, design, color, and texture. g) Chemical or physical treatments, if appropriate, will be undertaken using the gentlest means possible.Treatments that cause damage to historic materials will not be used. h) Archeological resources will be protected and preserved in place. If such resources must be disturbed, mitigation measures will be undertaken. PRESERVATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 16. REHABILITATION is defined as the act or process of making possible a compatible use for a property through repair, alterations, and additions while preserving those portions or features which convey its historical, cultural, or architectural values. REHABILITATION – DEFINITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 17. a) A property will be used as it was historically or be given a new use that requires minimal change to its distinctive materials, features, spaces, and spatial relationships. b) The historic character of a property will be retained and preserved. The removal of distinctive materials or alteration of features, spaces, and spatial relationships that characterize a property will be avoided. c) Each property will be recognized as a physical record of its time, place, and use. Changes that create a false sense of historical development, such as adding conjectural features or elements from other historic properties, will not be undertaken. REHABILITATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 18. d) Changes to a property that have acquired historic significance in their own right will be retained and preserved. e) Distinctive materials, features, finishes, and construction techniques or examples of craftsmanship that characterize a property will be preserved. f) Deteriorated historic features will be repaired rather than replaced. Where the severity of deterioration requires replacement of a distinctive feature, the new feature will match the old in design, color, texture, and, where possible, materials. Replacement of missing features will be substantiated by documentary and physical evidence. REHABILITATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 19. g) Chemical or physical treatments, if appropriate, will be undertaken using the gentlest means possible.Treatments that cause damage to historic materials will not be used. h) Archeological resources will be protected and preserved in place. If such resources must be disturbed, mitigation measures will be undertaken. REHABILITATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 20. i) New additions, exterior alterations, or related new construction will not destroy historic materials, features, and spatial relationships that characterize the property.The new work shall be differentiated from the old and will be compatible with the historic materials, features, size, scale and proportion, and massing to protect the integrity of the property and its environment. j) New additions and adjacent or related new construction will be undertaken in a such a manner that, if removed in the future, the essential form and integrity of the historic property and its environment would be unimpaired. REHABILITATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 21. RESTORATION is defined as the act or process of accurately depicting the form, features, and character of a property as it appeared at a particular period of time by means of the removal of features from other periods in its history and reconstruction of missing features from the restoration period.The limited and sensitive upgrading of mechanical, electrical, and plumbing systems and other code-required work to make properties functional is appropriate within a restoration project. RESTORATION – DEFINITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 22. a) A property will be used as it was historically or be given a new use which reflects the property's restoration period. b) Materials and features from the restoration period will be retained and preserved.The removal of materials or alteration of features, spaces, and spatial relationships that characterize the period will not be undertaken. c) Each property will be recognized as a physical record of its time, place, and use. Work needed to stabilize, consolidate and conserve materials and features from the restoration period will be physically and visually compatible, identifiable upon close inspection, and properly documented for future research. RESTORATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 23. d) Materials, features, spaces, and finishes that characterize other historical periods will be documented prior to their alteration or removal. e) Distinctive materials, features, finishes, and construction techniques or examples of craftsmanship that characterize the restoration period will be preserved. f) Deteriorated features from the restoration period will be repaired rather than replaced. Where the severity of deterioration requires replacement of a distinctive feature, the new feature will match the old in design, color, texture, and, where possible, materials. RESTORATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 24. g) Replacement of missing features from the restoration period will be substantiated by documentary and physical evidence. A false sense of history will not be created by adding conjectural features, features from other properties, or by combining features that never existed together historically. h) Chemical or physical treatments, if appropriate, will be undertaken using the gentlest means possible.Treatments that cause damage to historic materials will not be used. i) Archeological resources affected by a project will be protected and preserved in place. If such resources must be disturbed, mitigation measures will be undertaken. j) Designs that were never executed historically will not be constructed. RESTORATION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 25. RECONSTRUCTION is defined as the act or process of depicting, by means of new construction, the form, features, and detailing of a non-surviving site, landscape, building, structure, or object for the purpose of replicating its appearance at a specific period of time and in its historic location RECONSTRUCTION – DEFINITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 26. a) Reconstruction will be used to depict vanished or non-surviving portions of a property when documentary and physical evidence is available to permit accurate reconstruction with minimal conjecture, and such reconstruction is essential to the public understanding of the property. b) Reconstruction of a landscape, building, structure, or object in its historic location will be preceded by a thorough archeological investigation to identify and evaluate those features and artifacts which are essential to an accurate reconstruction. If such resources must be disturbed, mitigation measures will be undertaken. c) Reconstruction will include measures to preserve any remaining historic materials, features, and spatial relationships. RECONSTRUCTION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 27. d) Reconstruction will be based on the accurate duplication of historic features and elements substantiated by documentary or physical evidence rather than on conjectural designs or the availability of different features from other historic properties. A reconstructed property will re-create the appearance of the non-surviving historic property in materials, design, color, and texture. e) A reconstruction will be clearly identified as a contemporary re- creation. f) Designs that were never executed historically will not be constructed. RECONSTRUCTION – STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 28. A CULTURAL LANDSCAPE is defined as "a geographic area, including both cultural and natural resources and the wildlife or domestic animals therein, associated with a historic event, activity, or person or exhibiting other cultural or aesthetic values." There are four general types of cultural landscapes, not mutually exclusive: historic sites, historic designed landscapes, historic vernacular landscapes, and ethnographic landscapes. PART IV - CULTURAL LANDSCAPES SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 29. A landscape that was consciously designed or laid out by a landscape architect, master gardener, architect, or horticulturist according to design principles, or an amateur gardener working in a recognized style or tradition. HISTORIC DESIGNED LANDSCAPE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 30. A landscape that evolved through use by the people whose activities or occupancy shaped that landscape. Through social or cultural attitudes of an individual, family or a community, the landscape reflects the physical, biological, and cultural character of those everyday lives. HISTORICVERNACULAR LANDSCAPE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 31. A landscape significant for its association with a historic event, activity, or person. Examples include battlefields and president's house properties. HISTORIC SITE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 32. A landscape containing a variety of natural and cultural resources that associated people define as heritage resources. Examples are contemporary settlements, religious sacred sites and massive geological structures. Small plant communities, animals, subsistence and ceremonial grounds are often components. ETHNOGRAPHIC LANDSCAPE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 33. • COA = Certificate Of Appropriateness • Application to the Landmarks Commission for approval of alterations to be done to a landmark. • A COA can contain the application form, drawings, narrative descriptions, material samples, specifications, or any combination of the above items. • There are 3 types of COAs • Type I • Type II • Type III PARTV - WHAT IS A C.O.A.? HOW DOES ITWORK? SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 34. Projects that involve restoration of historic features and major repairs using the same type of materials originally found on the building require a Type I COA. An example of a project that requires a Type I COA is replacing a deteriorated shingle roof with a new shingle roof. Or replacing old cartilage with newly grown cartilage. TYPE I COAs SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 35. Projects that involve alterations in the appearance of the property requireType II COAs. Examples of projects requiringType II COA are building an addition on a landmark building, adding a new building within the boundary of a landmark property or district, or replacing a joint with a metal ball and socket. TYPE II COAs SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 36. Projects that propose the demolition or relocation of landmark properties or the excavation of archaeological sites requireType III COA’s. These types of projects have an irreversible effect on a landmark property, and therefore require the most stringent review. TYPE III COAs SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 37. TYPICALTYPE II COA PROCESS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 38. CASE STUDIES PARTVI – APPLICATION OF SECRETARY OFTHE INTERIOR’S STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 39. MARY OLSON FARM SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 40. Built in 1897 through 1902 In Auburn, Washington Designated a King County Landmark in 1995 Farmstead includes an 1897 hay barn, a 1902 farm house, and several outbuildings constructed in the late 19th and early 20th centuries including a weaving house, smokehouse, garage / ice house, and chicken coop. Mission Statement/Preservation Philosophy HISTORY SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 41. It is listed on the National Register of Historic Places under Category A as a Locally Significant place associated with events that have made a significant contribution to the broad patterns of our history. It is listed as a King County Landmark, designated under Criterion A1 and A3, for its strong association with the evolving agricultural history of King County and as an intact cultural landscape complete with a late 19th century working farm including a farmhouse, several outbuildings, road, creek, fence, orchard, forest, and field features. Features of Significance include all exterior portions of the contributing buildings, interior of the barn, all fences, orchard trees… The Period of Significance is from 1897 to 1940, encompassing the major physical development of the farm. SIGNIFICANCE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 42. Siding, which runs the full height of the 30’ walls, is rotting Doors deteriorating, and a code and ADA compliant floor were non-existent Roof needed to be replaced on barn Several other structures on property that had collapsed CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 43. CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 44. CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 45. CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 46. Barn restoration – siding & roof Barn restoration – flooring, doors, and siding These projects at Mary Olson Farm are the best of preservation where original building fabric is carefully duplicated in material and even method of fabrication and installation TYPE II COAs SUBMITTED SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 47. TYPE II COA’S SUBMITTED SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 48. Standards for Rehabilitation were applied APPLICATION OFTHE SECRETARY OF THE INTERIOR’S STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 49. All applications for Type II COAs have been approved and work is in progress Auburn School District uses the farm as an educational tool for their children demonstrating our heritage and old farming techniques CONCLUSION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 50. QUAALE LOG CABIN SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 51. Built circa 1903 to 1905 West edge of the SnoqualmieValley, near Carnation Designated a King County Landmark in 1990 HISTORY SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 52. One of the earliest and best extant examples of log cabin construction in the Snoqualmie River Valley and King County. Designated under Criterion A3 as an excellent example of alternating hewn log construction with full dovetail cornering with no overlap. Features of Significance include all exterior portions of the house. One of two remaining log houses in King County retaining its physical integrity. SIGNIFICANCE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 53. Roof needed reworking Windows and doors did not seal completely Deteriorating due to water infiltration BUILDING CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 54. COA included in-kind replacement of all original windows with new wood framed windows TYPE II COA APPLICATION SUBMITTED SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 55. Standards for Rehabilitation were applied APPLICATION OFTHE SECRETARY OF THE INTERIOR’S STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 56. KCLC approved the application for a Type 2 COA Window installation was completed in Mid-2005. CONCLUSION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 57. TOLT BRIDGE DEMOLITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 58. Built in 1922 Second bridge at this location on Tolt Hill Road, crossing the Snoqualmie River PrattTruss (Parker Sub-type) Designed and built at a time when fully riveted trusses were gaining favor with the introduction of the pneumatic riveter. HISTORY SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 59. Designated less than 10 years ago, in 1997 Designated under Criterion A3 due to its design as one of only two remaining fully riveted Pratt (Parker sub-type) trusses in King County Features of Significance include: All components of the bridge and their associated approaches. SIGNIFICANCE SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 60. Severely rusted members Corrosion was in areas where it could not be arrested Bridge was in danger of collapse CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 61. CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 62. CONDITION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 63. New bridge to be built adjacent to old bridge New bridge was downstream of old bridge Could not keep old bridge for several reasons Old bridge had to be removed, therefore the Type III COA application was required. TYPE III COA SUBMITTED SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 64. Secretary of the Interior’s Standards were NOT applied APPLICATION OFTHE SECRETARY OF THE INTERIOR’S STANDARDS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 65. KCLC Rules and Regulations allow for demolition of a Designated Landmark on the basis of a threat to public health and safety KCLC Rules and Regulations allow for leniency in alterations to landmarks on the basis of Economic Hardship Washington State and Federal Laws do not allow for increasing the water level during a flood APPLICATION OFWASHINGTON STATE LAW AND KCLC RULES AND REGULATIONS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 66. APPLICATION OFWASHINGTON STATE LAW AND KCLC RULES AND REGULATIONS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 67. KCLC approved the application for a Type III COA King County Roads and Bridges Department presented a carefully outlined case for why the bridge had to be removed, including all of the County, State and Federal laws and economic implications supporting their decisions. KC Roads & Bridges worked with the Commission to provide the information which provided the key to allowing the demolition of the bridge. They worked the KC Code. King County lost one of the finest examples of the early 20th Century bridges Mitigation Efforts CONCLUSION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 68. Landmarks Commissions are here to ensure we do not destroy our cultural heritage with a balance of using and preserving the resource The Secretary of the Interior’s Standards intentionally allow for flexibility Make your case! PARTVII –WHAT HAVEWE LEARNED? SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 69. WHAT CANYOU DO TO BE MORE AWARE OF HISTORIC PRESERVATION ISSUES ONYOUR PROJECTS? PARTVIII -WHAT CANYOU DO? SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 70. Why is keeping any building or site valuable? What does Preservation mean to the Owner? What does Preservation meant to the user? UNDERSTANDTHE CONCEPT OF PRESERVATION SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 71. Use caution when calling for any procedure which may damage the historic fabric of a site or building or material Remember the Hippocratic Oath (not the Hypocritic Oath!) UNDERSTANDTHE CONCEPT OF REVERSIBILITY SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 72. Understand what the preservation philosophy and approach is for each project, client, design team. Make sure all Team Members understand what the Preservation Philosophy is. Landmark Designation forms are the key to documenting this philosophy. Use Historic Resources Survey/Inventory information if it’s not designated! DEVELOP A PRESERVATION PHILOSOPHY SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 73. Exercise and require caution when designing new construction to go within an existing historic structure Material compatibility Design/aesthetic compatibility Does it meet the preservation philosophy? Be sensitive to not only the appearance, but the substance of the materials being altered. DESIGN APPROPRIATELY SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 74. Call for large scale tests and mockups of procedures prior to implementation on all different substrates. Monitor your construction Contractor be aware of what you are doing – we only get one chance. TESTYOUR HYPOTHESES SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 75. The design team and Owner should understand that a restoration project will only be the first of many. Hopefully, one alteration project will keep the structure around long enough for someone to want to do another one in the future. ANTICIPATE FUTURE REHABILITATIONS SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 76. There is no magic silver bullet for all sets of conditions Multiple choices for each situation All projects are constrained by budget, time, and quality criteria What we do is make decisions and choices. MAKE A DECISION AND DOCUMENT IT SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866
  • 77. THANKYOU! QUESTIONS? SUSTAINABLE PRESERVATION ARCHITECTURE & CONSTRUCTION MANAGEMENT WWW.RICHAVEN.COM 206.909.9866