SlideShare uma empresa Scribd logo
1 de 32
SUBSTATION OVERVIEW
-B. Prasad
Chartered Engineer
amieclub@gmail.com
TYPE OF SUBSTATION
 Classification based on voltage levels, e.g. : A.C.
Substation : EHV, HV, MV, LV; HVDC Substation.
 Classification based on OutdoororIndoor: Outdoor
substation is under open sky. Indoor substation is
inside a building.
 Classification based on configuration, e.g. :
 Conventional air insulated outdoor substation or
 SF6 Gas Insulated Substation (GIS)
 Composite substations having combination of the
above two
Classification based on application
 Step Up Substation : Associated with generating station as
the generating voltage is low.
 Primary Grid Substation : Created at suitable load centre
along Primary transmission lines.
 Secondary Substation : Along Secondary Transmission Line.
 Distribution Substation : Created where the transmission line
voltage is Step Down to supply voltage.
 Bulksupply and industrial substation : Similar to distribution
sub-station but created separately for each consumer.
 Mining Substation precaution for safety needed in the
operation of electric supply.
 Mobile Substation: Temporary requirement
PROMARY/SECONDARY/DISTRIBUTION
SUBSTATION
 Primary Substations receive power from EHV
lines at 400KV, 220KV, 132KV and transform the
voltage to 66KV, 33KV or 22KV (22KV is
uncommon) to suit the local requirements in
respect of both load and distance of ultimate
consumers. These are also referred to ‘EHV’
Substations.
 Secondary Substations receive power at 66/33KV
which is stepped down usually to 11KV.
 Distribution Substations receive power at 11KV,
6.6 KV and step down to a volt suitable for LV
distribution purposes, normally at 415 volts
SUBSTATION PARTSANDEQUIPMENTS
 OutdoorSwitchyard
 Incoming Lines
 Outgoing Lines
 Bus bar
 Transformers
 Bus post insulator & string insulators
 Substation Equipment such as Circuit-
beakers, Isolators, Earthing Switches, Surge
Arresters, CTs, VTs, Neutral Grounding
equipment.
SUBSTATION PARTS
….CONTD…
 Station Earthing system comprising ground mat, risers,
auxiliary mat, earthing strips, earthing spikes & earth
electrodes.
 Overhead earth wire shielding against lightening strokes.
 Galvanised steel structures for towers, gantries, equipment
supports.
 PLCC equipment including line trap, tuning unit, coupling
capacitor, etc.
 Power cables
 Control cables for protection and control
 Roads, Railway track, cable trenches
 Station illumination system
SINGLE LINE DIAGRAM
Transformer part
Batteries forindustrial orsubstation applications
 Vented /
Flooded Lead
Acid batteries
 Sealed
maintenance
free
batteries/Valve
Regulated Lead
Acid
 Nickel Cadmium
(Ni-cd) batteries
Battery AH
 LOAD CURRENT 10A for
3 hrs.
 Cell voltage =12V DC
 CALCULATION ,
AH=10X3
 CAPACITY =30/
(0.75X0.8)=50AH
 Discharge factor=0.7
 Ageing factor =0.8
 Drain capacity =C10
CHARGER
 Type of charger
 Input voltage
 output voltage
 Application
 Protection
 Metering
 Indication
 Alarms
 Auto operation
Clearance around an Indoorelectrical panel
(NES 110.26)
Description of Clearance Distance (min)
Left to Right the minimum clearance 0.9 Meter (3 Ft)
Distance between Panel and wall 1.0 Meter
Distance between Panel and Ceiling 0.9 Meter
Clear Height in front of Panel >480V 2.0 Meter
Clear Height in front of Panel <480V 0.9 Meter (3 Ft)
Clearance When Facing Other Electrical
Panels <480V
0.9 Meter (3 Ft)
The width of the working space in front of
the Panel
The width of Panel or 0.762 Meter which is
Greater.
Headroom of working spaces for panel
boards (Up to 200Amp)
Up to 2 Meter
Clearance between Bare Metal Busbarin
Panel (NES 408.5)
Voltage
Opposite
Polarity
Mounted on
Same
Surface
Opposite
Polarity
Where Held
Free in Air
Live Parts to
Ground
Up to 125 V 19.1 mm 12.7 mm 12.7 mm
125 V to 250 V 31.8 mm 19.1 mm 12.7 mm
250 V to 600 V 50.8 mm 25.4 mm 25.4 mm
Clearance of Outdoorelectrical panel to
Fence/Wall (NES 110.31)
Voltage Distance (min)
600 V to 13.8 KV 3.05 Meter
13.8 KV to 230 KV 4.57 Meter
Above 230 KV 5.49 Meter
GROUNDCLEARANCE
VOLTAGE LEVEL MINIMUM GROUND CLEARANCE
less than 66kV 6.1m
66kV - 110kV 6.4m
110kV - 165kV 6.7m
greater than 165kV 7.0m
Earth resistance value
 Major power station= 0.5
Ohm.
 Major Sub-stations= 1.0
Ohm
 Minor Sub-station = 2 Ohm
 Neutral Bushing. =2 Ohm
 Service connection = 4
Ohm
 Medium Voltage Network
=2 Ohm
 L.T.Lightening Arrestor= 4
Ohm
 L.T.Pole= 5 Ohm

Measurement of Earth Resistance
(Three point method)
Size of earth wire for motor
Sr. Capacity Size of earth wire Size Of Earth Electrode
Cu GI Cu GI
1 01- 10 HP 8 SWG 8 SWG 60cmX60cmX3.18
mm
60cmX60c
mX6.35mm
2 10 – 15 HP 8 SWG 6 SWG 60cmX60cmX3.18
mm
60cmX60c
mX6.35mm
3 15 – 30 HP 6 SWG 4SWG 60cmX60cmX3.18
mm
90cmX90c
mX6.35mm
4 30 – 50 HP 4SWG 25mmX3 mm 90cmX90cmX6.35
mm
90cmX90c
mX6.35mm
IRValue of Submersible Motor
IR Value of Submersible Motor
Motor Out off Well (Without Cable) IR Value
New Motor 20 MΩ
A used motor which can be reinstalled 10 MΩ
Motor Installed in Well (With Cable)
New Motor 2 MΩ
A used motor which can be reinstalled 0.5 MΩ
IRValue of Transformers:
Voltage Test Voltage
(DC) LV side
Test Voltage
(DC) HV side
Min IR
Value
415V 500V 2.5KV 100MΩ
Up to 6.6KV 500V 2.5KV 200MΩ
6.6KV to 11KV 500V 2.5KV 400MΩ
11KV to 33KV 1000V 5KV 500MΩ
33KV to 66KV 1000V 5KV 600MΩ
66KV to 132KV 1000V 5KV 600MΩ
132KV to 220KV 1000V 5KV 650MΩ
Standard voltage
Type Voltage
EXTRA LOW
VOLTAGE
Up to 50V AC/DC
LOW VOLTAGE 50-1000V AC/DC
MEDIUM VOLTAGE ABOVE 1000V AC/DC UPTO 6.6KV
AC
HIGH VOLTAGE ABOVE 6.6KV AC TO 33 KV AC
EXTRA HIGH
VOLTAGE
ABOVE 33KV AC TO 400 KV AC
ULTRA HIGH
VOLTAGE
ABOVE 400 KV AC TO 765 KV AC
Cable end termination
Breaker ACB/VCB/SF6/OCB
EARTHING
 The following steps, when put into practice, will ensure a
re liable , safe and tro uble -fre e  substatio n g ro unding  
syste m :
 Size conductors for anticipated faults
 Use the right connections
 Ground rod selection
 Soil preparation
 Grounding using building foundations
 Grounding the substation fence 
 Special attention to operating points 
 Surge arrestors must be grounded properly 
 Grounding of cable trays 
 Temporary grounding of normally energized parts 
Earthing .....contd
Cabling
 Depth of the trench 7 50
m m fo r cable s up to
1 . 1 KV
 Depth of the trench
1 20 0 m m fo r cable s up
to 1 . 1 KV
 Sand - covered with 150
mm
 Width of the trench -
350 mm minimum
 Loop –approximate -3
Cable laying
 Laying direct in ground
 In pipes,
 Closed or Open ducts,
 Cable trays and
 On surface of wall
BUILDING
 Administrative building
 Conference room etc.
 Battery Room
 Operator room
 Check and change room
 Adjacent maintenance room
 ECC room
Switchgearand Control Panel Building
 Low voltage AC. Switchgear
 High voltage AC. Switchgear
 Control Panels, Protection
Panels
 Capacitor panel room
Mechanical, Electrical and OtherAuxiliaries
 Fire fighting system
 D.G. Set
 Oil purification system
ACT FAST AND INITIATE
FIRST
 बड़ा    सोचो
        तेजी से सोचो व
    सबसे पहले सोचो
 िवचारो     पर िकसी का
      एकािधकार नही होता.
  ----  धीरभाई अमबानी
THANK YOU

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
SWITCHGEAR
SWITCHGEARSWITCHGEAR
SWITCHGEAR
 
132 kv
132 kv132 kv
132 kv
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Design of substation
Design of substationDesign of substation
Design of substation
 
132kv Substation
132kv Substation132kv Substation
132kv Substation
 
Switchyard
SwitchyardSwitchyard
Switchyard
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Reactors
ReactorsReactors
Reactors
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 

Destaque

Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurR-One Power
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Living Online
 
distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangementManjunath Ds
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis pptkarikalan123
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesLiving Online
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysiskirkusawi
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...Vikram Rawani
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2R.K. Mathuria
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthingNitesh Dash
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Conceptsmvrkprasad
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthingDenuka
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety Reliance
 

Destaque (20)

Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
A 220kV Substation
A 220kV SubstationA 220kV Substation
A 220kV Substation
 
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...
 
distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangement
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Earthing system
Earthing systemEarthing system
Earthing system
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety Rules
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthing
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Concepts
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthing
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Importance of industrial safety
Importance of industrial safetyImportance of industrial safety
Importance of industrial safety
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety
 

Semelhante a Substation overview

Lv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizingLv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizingAsif Eqbal
 
Substation structures
Substation structuresSubstation structures
Substation structuresJebitta Paul
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 
Pamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdsoPamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdsosonu200186
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authorityMahesh Chandra Manav
 
presentation national desaster management and JMV LPS Ltd
 presentation  national desaster management  and JMV LPS Ltd presentation  national desaster management  and JMV LPS Ltd
presentation national desaster management and JMV LPS LtdMahesh Chandra Manav
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authorityMahesh Chandra Manav
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
presentation defence and police and JMV LPS LTD
 presentation  defence and police  and JMV LPS LTD presentation  defence and police  and JMV LPS LTD
presentation defence and police and JMV LPS LTDMahesh Chandra Manav
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
Original High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 New
Original High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 NewOriginal High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 New
Original High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 NewAUTHELECTRONIC
 
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATIONHIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATIONSenthilVenkat2
 
2 u 650w single power supply
2 u 650w single power supply2 u 650w single power supply
2 u 650w single power supplykimminsu0216
 
1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptx1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptxTajmun1
 
1502957304lectrure_1.pptx
1502957304lectrure_1.pptx1502957304lectrure_1.pptx
1502957304lectrure_1.pptxTajmun1
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusDrCVMOHAN
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution ZunAib Ali
 

Semelhante a Substation overview (20)

Sub station over view
Sub station over view Sub station over view
Sub station over view
 
Lv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizingLv switchgear &amp; lv cable sizing
Lv switchgear &amp; lv cable sizing
 
Transmission network
Transmission  networkTransmission  network
Transmission network
 
Substation structures
Substation structuresSubstation structures
Substation structures
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
Pamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdsoPamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdso
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authority
 
presentation national desaster management and JMV LPS Ltd
 presentation  national desaster management  and JMV LPS Ltd presentation  national desaster management  and JMV LPS Ltd
presentation national desaster management and JMV LPS Ltd
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authority
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
presentation defence and police and JMV LPS LTD
 presentation  defence and police  and JMV LPS LTD presentation  defence and police  and JMV LPS LTD
presentation defence and police and JMV LPS LTD
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
Original High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 New
Original High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 NewOriginal High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 New
Original High Voltage Isolation IC ACS710T KLA-12CB 710T SOP-16 New
 
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATIONHIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
 
2 u 650w single power supply
2 u 650w single power supply2 u 650w single power supply
2 u 650w single power supply
 
High voltage module
High voltage moduleHigh voltage module
High voltage module
 
1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptx1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptx
 
1502957304lectrure_1.pptx
1502957304lectrure_1.pptx1502957304lectrure_1.pptx
1502957304lectrure_1.pptx
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabus
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution
 

Mais de BHAGWAN PRASAD

Mais de BHAGWAN PRASAD (20)

Emotion intelligence and project manger
Emotion intelligence and project manger Emotion intelligence and project manger
Emotion intelligence and project manger
 
Storage energy battery
Storage energy batteryStorage energy battery
Storage energy battery
 
Lightning protection oisd 180
Lightning protection oisd  180Lightning protection oisd  180
Lightning protection oisd 180
 
Cable termination tips
Cable termination tipsCable termination tips
Cable termination tips
 
Cable installation book
Cable installation bookCable installation book
Cable installation book
 
360 dgree
360 dgree 360 dgree
360 dgree
 
Strategic Petroleum Reserves India
Strategic Petroleum Reserves IndiaStrategic Petroleum Reserves India
Strategic Petroleum Reserves India
 
Led light panel board
Led light panel boardLed light panel board
Led light panel board
 
career ki Pathshala memory
career ki Pathshala memory career ki Pathshala memory
career ki Pathshala memory
 
Career ki pathshala
Career ki pathshalaCareer ki pathshala
Career ki pathshala
 
Energy conservation 2015
Energy  conservation 2015Energy  conservation 2015
Energy conservation 2015
 
Haryana know
Haryana  knowHaryana  know
Haryana know
 
Safety during construction
Safety during construction Safety during construction
Safety during construction
 
Carbon emission blog
Carbon emission blogCarbon emission blog
Carbon emission blog
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
Cable joint n end connector
Cable joint n end connectorCable joint n end connector
Cable joint n end connector
 
Power generation
Power generationPower generation
Power generation
 
Energy calculation
Energy calculationEnergy calculation
Energy calculation
 
Light
LightLight
Light
 
Battery
BatteryBattery
Battery
 

Último

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxnelietumpap1
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 

Último (20)

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 

Substation overview

  • 1. SUBSTATION OVERVIEW -B. Prasad Chartered Engineer amieclub@gmail.com
  • 2. TYPE OF SUBSTATION  Classification based on voltage levels, e.g. : A.C. Substation : EHV, HV, MV, LV; HVDC Substation.  Classification based on OutdoororIndoor: Outdoor substation is under open sky. Indoor substation is inside a building.  Classification based on configuration, e.g. :  Conventional air insulated outdoor substation or  SF6 Gas Insulated Substation (GIS)  Composite substations having combination of the above two
  • 3. Classification based on application  Step Up Substation : Associated with generating station as the generating voltage is low.  Primary Grid Substation : Created at suitable load centre along Primary transmission lines.  Secondary Substation : Along Secondary Transmission Line.  Distribution Substation : Created where the transmission line voltage is Step Down to supply voltage.  Bulksupply and industrial substation : Similar to distribution sub-station but created separately for each consumer.  Mining Substation precaution for safety needed in the operation of electric supply.  Mobile Substation: Temporary requirement
  • 4. PROMARY/SECONDARY/DISTRIBUTION SUBSTATION  Primary Substations receive power from EHV lines at 400KV, 220KV, 132KV and transform the voltage to 66KV, 33KV or 22KV (22KV is uncommon) to suit the local requirements in respect of both load and distance of ultimate consumers. These are also referred to ‘EHV’ Substations.  Secondary Substations receive power at 66/33KV which is stepped down usually to 11KV.  Distribution Substations receive power at 11KV, 6.6 KV and step down to a volt suitable for LV distribution purposes, normally at 415 volts
  • 5. SUBSTATION PARTSANDEQUIPMENTS  OutdoorSwitchyard  Incoming Lines  Outgoing Lines  Bus bar  Transformers  Bus post insulator & string insulators  Substation Equipment such as Circuit- beakers, Isolators, Earthing Switches, Surge Arresters, CTs, VTs, Neutral Grounding equipment.
  • 6. SUBSTATION PARTS ….CONTD…  Station Earthing system comprising ground mat, risers, auxiliary mat, earthing strips, earthing spikes & earth electrodes.  Overhead earth wire shielding against lightening strokes.  Galvanised steel structures for towers, gantries, equipment supports.  PLCC equipment including line trap, tuning unit, coupling capacitor, etc.  Power cables  Control cables for protection and control  Roads, Railway track, cable trenches  Station illumination system
  • 9. Batteries forindustrial orsubstation applications  Vented / Flooded Lead Acid batteries  Sealed maintenance free batteries/Valve Regulated Lead Acid  Nickel Cadmium (Ni-cd) batteries
  • 10. Battery AH  LOAD CURRENT 10A for 3 hrs.  Cell voltage =12V DC  CALCULATION , AH=10X3  CAPACITY =30/ (0.75X0.8)=50AH  Discharge factor=0.7  Ageing factor =0.8  Drain capacity =C10
  • 11. CHARGER  Type of charger  Input voltage  output voltage  Application  Protection  Metering  Indication  Alarms  Auto operation
  • 12. Clearance around an Indoorelectrical panel (NES 110.26) Description of Clearance Distance (min) Left to Right the minimum clearance 0.9 Meter (3 Ft) Distance between Panel and wall 1.0 Meter Distance between Panel and Ceiling 0.9 Meter Clear Height in front of Panel >480V 2.0 Meter Clear Height in front of Panel <480V 0.9 Meter (3 Ft) Clearance When Facing Other Electrical Panels <480V 0.9 Meter (3 Ft) The width of the working space in front of the Panel The width of Panel or 0.762 Meter which is Greater. Headroom of working spaces for panel boards (Up to 200Amp) Up to 2 Meter
  • 13. Clearance between Bare Metal Busbarin Panel (NES 408.5) Voltage Opposite Polarity Mounted on Same Surface Opposite Polarity Where Held Free in Air Live Parts to Ground Up to 125 V 19.1 mm 12.7 mm 12.7 mm 125 V to 250 V 31.8 mm 19.1 mm 12.7 mm 250 V to 600 V 50.8 mm 25.4 mm 25.4 mm
  • 14. Clearance of Outdoorelectrical panel to Fence/Wall (NES 110.31) Voltage Distance (min) 600 V to 13.8 KV 3.05 Meter 13.8 KV to 230 KV 4.57 Meter Above 230 KV 5.49 Meter
  • 15. GROUNDCLEARANCE VOLTAGE LEVEL MINIMUM GROUND CLEARANCE less than 66kV 6.1m 66kV - 110kV 6.4m 110kV - 165kV 6.7m greater than 165kV 7.0m
  • 16. Earth resistance value  Major power station= 0.5 Ohm.  Major Sub-stations= 1.0 Ohm  Minor Sub-station = 2 Ohm  Neutral Bushing. =2 Ohm  Service connection = 4 Ohm  Medium Voltage Network =2 Ohm  L.T.Lightening Arrestor= 4 Ohm  L.T.Pole= 5 Ohm 
  • 17. Measurement of Earth Resistance (Three point method)
  • 18. Size of earth wire for motor Sr. Capacity Size of earth wire Size Of Earth Electrode Cu GI Cu GI 1 01- 10 HP 8 SWG 8 SWG 60cmX60cmX3.18 mm 60cmX60c mX6.35mm 2 10 – 15 HP 8 SWG 6 SWG 60cmX60cmX3.18 mm 60cmX60c mX6.35mm 3 15 – 30 HP 6 SWG 4SWG 60cmX60cmX3.18 mm 90cmX90c mX6.35mm 4 30 – 50 HP 4SWG 25mmX3 mm 90cmX90cmX6.35 mm 90cmX90c mX6.35mm
  • 19. IRValue of Submersible Motor IR Value of Submersible Motor Motor Out off Well (Without Cable) IR Value New Motor 20 MΩ A used motor which can be reinstalled 10 MΩ Motor Installed in Well (With Cable) New Motor 2 MΩ A used motor which can be reinstalled 0.5 MΩ
  • 20. IRValue of Transformers: Voltage Test Voltage (DC) LV side Test Voltage (DC) HV side Min IR Value 415V 500V 2.5KV 100MΩ Up to 6.6KV 500V 2.5KV 200MΩ 6.6KV to 11KV 500V 2.5KV 400MΩ 11KV to 33KV 1000V 5KV 500MΩ 33KV to 66KV 1000V 5KV 600MΩ 66KV to 132KV 1000V 5KV 600MΩ 132KV to 220KV 1000V 5KV 650MΩ
  • 21. Standard voltage Type Voltage EXTRA LOW VOLTAGE Up to 50V AC/DC LOW VOLTAGE 50-1000V AC/DC MEDIUM VOLTAGE ABOVE 1000V AC/DC UPTO 6.6KV AC HIGH VOLTAGE ABOVE 6.6KV AC TO 33 KV AC EXTRA HIGH VOLTAGE ABOVE 33KV AC TO 400 KV AC ULTRA HIGH VOLTAGE ABOVE 400 KV AC TO 765 KV AC
  • 24. EARTHING  The following steps, when put into practice, will ensure a re liable , safe and tro uble -fre e  substatio n g ro unding   syste m :  Size conductors for anticipated faults  Use the right connections  Ground rod selection  Soil preparation  Grounding using building foundations  Grounding the substation fence   Special attention to operating points   Surge arrestors must be grounded properly   Grounding of cable trays   Temporary grounding of normally energized parts 
  • 26. Cabling  Depth of the trench 7 50 m m fo r cable s up to 1 . 1 KV  Depth of the trench 1 20 0 m m fo r cable s up to 1 . 1 KV  Sand - covered with 150 mm  Width of the trench - 350 mm minimum  Loop –approximate -3
  • 27. Cable laying  Laying direct in ground  In pipes,  Closed or Open ducts,  Cable trays and  On surface of wall
  • 28. BUILDING  Administrative building  Conference room etc.  Battery Room  Operator room  Check and change room  Adjacent maintenance room  ECC room
  • 29. Switchgearand Control Panel Building  Low voltage AC. Switchgear  High voltage AC. Switchgear  Control Panels, Protection Panels  Capacitor panel room
  • 30. Mechanical, Electrical and OtherAuxiliaries  Fire fighting system  D.G. Set  Oil purification system
  • 31. ACT FAST AND INITIATE FIRST  बड़ा    सोचो         तेजी से सोचो व     सबसे पहले सोचो  िवचारो     पर िकसी का       एकािधकार नही होता.   ----  धीरभाई अमबानी