Secondary Containment
           Beth Powell
         Managing Director
    Well Pad Containment Division
     www.newpig.com/shalegas
Secondary Containment
 Safeguarding method in addition to the primary containment system


Specific/Sized
   – Indoor: Sump capacity should contain 10% of the volume of
     total containers or the total volume of the largest container,
     whichever is greater
   – Outdoor: Plus sufficient freeboard to contain precipitation


General
   – Address typical failure mode and the most likely quantity
   – Passive or Active
Regulations
           and Best Practices
     EPA                    PA DEP




                Liquids

STRONGER                    Advisory
API                         Commissions
MSC                         & Boards
EPA
Oil & Gas Extraction Point Source
   – 40 CFR 435.32

   – There shall be no discharge of waste water pollutants into
     navigable waters from any source associated with production,
     field exploration, drilling, well completion, or well treatment
     (i.e., produced water, drilling muds, drill cuttings, and produced
     sand).
SPCC
Spill Prevention, Control, and Countermeasure (SPCC)
   – 40 CFR 112
   – Monitors plans to prevent oil spills at facilities
       • 1320 gallons of above-ground storage capacity
       • Potential to reach “navigable waters”
       • Oil, oil-like and oil/water mixtures
   – Clarifies “facility”; can be considered mobile or portable
   – Sets compliance date of November 10, 2011 for facilities that

      came into operation after August 12, 2002

   http://www.epa.gov/osweroe1/docs/oil/spcc/spcc_101_prod.pdf
SPCC 40CFR112.7(c)
The entire containment system, including walls and floor, must be capable of
containing oil and must be constructed so that any discharge from a primary
containment system, such as a tank or pipe, will not escape the
containment system before cleanup occurs.

At a minimum, you must use one of the following prevention systems or its
   equivalent:
     (1) For onshore facilities:
          (i) Dikes, berms, or retaining walls sufficiently impervious to contain oil;
          (ii) Curbing;
          (iii) Culverting, gutters, or other drainage systems;
          (iv) Weirs, booms, or other barriers;
          (v) Spill diversion ponds;
          (vi) Retention ponds; or
          (vii) Sorbent materials.
SPCC Examples
            Methods                                  Description of Secondary Containment Examples

Dikes, berms, or retaining walls         Raised earth embankments or concrete containment walls used in areas with potential for large
sufficiently impervious to contain oil   discharges, such as single or multiple aboveground storage tanks and certain piping.
Curbing                                  Permanent concrete or asphalt apron surrounded by a curb. Can be used where only small spills
                                         are expected and also used to direct spills to drains or catchment areas.
Culverting, gutters, or other drainage   Types of permanent drainage systems designed to direct spills to remote containment or
systems                                  treatment areas.
Weirs                                    Dam-like structures with a notch through which oil may flow to be collected.
                                         Used in combination with skimmers to remove oil from the surface of water.
Booms                                    Form a continuous barrier placed as a precautionary measure to contain/collect oil. Typically used
                                         for the containment, exclusion, or deflection of oil floating on water, and is usually used to
                                         address oil spills that have reached surface waters.
Barriers                                 Spill mats, storm drain covers, and dams used to block or prevent the flow of oil.

Spill diversion and retention ponds      Designed for long-term or permanent containment of storm water capable to capture and hold oil
                                         or runoff and prevent it from entering surface water bodies.
Sorbent materials                        Materials include spill pads, pillows, socks, mats, clay, vermiculite, and diatomaceous earth. Used
                                         to isolate and contain small drips or leaks until the source of the leak is repaired.
                                         Used to isolate and contain small drips or leaks until the source of the leak is repaired. Drip pans
Drip pans
                                         are commonly used with product dispensing containers (usually drums), uncoupling of hoses
                                         during bulk transfer operations, and for pumps, valves, and fittings.

Sumps and collection systems             A permanent pit or reservoir and the troughs/trenches connected to it that collect oil.
SPCC Provisions
Type of Facility                         Secondary Containment                    Rule Section(s)

All Facilities                           General containment (areas with          112.7(c)
                                         potential for discharge, e.g., piping,
                                         oil-filled operating and
                                         manufacturing equipment, and non-
                                         rack related transfer areas)
Onshore Storage                          Bulk storage containers                  112.8(c)(2) or 112.12(c)(2)

                                         Mobile or portable oil containers*       112.8(c)(11) or 112.12(c)(11)


Onshore Production                       Bulk storage containers, including       112.9(c)(2)
                                         tank batteries, separation, and
                                         treating facility installations*

Onshore Oil Drilling and Workover        Mobile drilling or workover              112.10(c)
                                         equipment

Offshore Oil Drilling, Production, and   Oil drilling, production, or workover    112.7(c)
Workover                                 equipment



  SPCC Guidance for Regional Inspectors
  http://www.epa.gov/oem/docs/oil/spcc/guidance/4_SecondaryContainment_Impracticability.pdf
SPCC § 112.10 Provisions
•   If you are the owner or operator of an onshore oil drilling and workover
    facility, you must:
•   (a) Meet the general requirements listed under §112.7, and also meet the
    specific discharge prevention and containment procedures listed under this
    section.
•   (b) Position or locate mobile drilling or workover equipment so as to prevent
    a discharge as described in §112.1(b).
•   (c) Provide catchment basins or diversion structures to intercept and
    contain discharges of fuel, crude oil, or oily drilling fluids.
•   (d) Install a blowout prevention (BOP) assembly and well control system
    before drilling below any casing string or during workover operations. The
    BOP assembly and well control system must be capable of controlling any
    well-head pressure that may be encountered while that BOP assembly and
    well control system are on the well.
RCRA
Resource Conservation & Recovery Act (RCRA)
  – 40 CFR 260-265 (generator standards)
  – Restricts hazardous waste collection and storage
  – Defines “characteristic” and “listed” hazardous wastes
     • Ignitability
     • Corrosivity
     • Reactivity
     • Toxicity
  – Exempts flowback fluids at federal level (state laws may apply)
  – May not exempt fracturing fluids at federal level
NPDES
National Pollutant Discharge Elimination System
  (NPDES)
   – 40 CFR 122
   – Limits water pollution through permits
   – Defines oil pollution as a “sheen” on the water
   – Regulates stormwater discharges from construction sites
     (1 acre plus), industrial facilities and municipalities
   – Considers sediment to be the most common pollutant
   – Requires E&P sites to have sediment controls
   – Delegates permitting to states; all Marcellus Shale states have
     received delegation
Hydraulic Fracturing Study

Section 6.4.4
•   EPA is interested in gathering information relating to the current
    on-site management practices that are used to prevent and/or
    contain accidental releases of flowback and produced water to
    drinking water resources.
PA DEP
Oil & Gas Act
Clean Streams Law
Solid Waste Management Act


Prevention, Preparedness and Contingency (PPC) Plan
•   25 Pa. Code §§ 78.55 Control and Disposal Plan
•   25 Pa. Code §§ 91.34 Activities Utilizing Pollutants
•   Spills of 5 gallons or greater are reportable
Oil & Gas Spill Policy Draft
•   Report a spill or release regardless of the quantity spilled

•   If secondary containment is in place, notify if the quantity of material
    exceeds 42 gallons

•   Remove the spilled material from the secondary containment within
    24 hours

•   When spilled onto the ground, the material is usually either residual
    waste or hazardous waste
STRONGER
Pennsylvania Hydraulic Fracturing State Review—September 2010


Recommendation 9.2.1.10.
   – The review team recommends that secondary containment
     requirements be established for tanks used in hydraulic
     fracturing operations.
Act 13 of 2012
•   The environmental protection provisions are effective April 16, 2012.
•   Unconventional well sites must be designed and constructed to prevent
    spills to the ground surface or off the well site. Containment practices must
    be in place during both drilling and hydraulic fracturing operations and
    must be sufficiently impervious and able to contain spilled materials, and
    be compatible with the waste material or waste stored within the
    containment. Containment plans must be submitted to the department
    and describe any equipment that is to be kept onsite to prevent a spill from
    leaving the well pad.
•   Containment systems shall be used wherever drilling mud, hydraulic oil,
    diesel fuel, drilling mud additives, hydraulic fracturing additives,
    and/or hydraulic fracturing flowback are stored. Containment areas must
    be sufficient to hold the volume of the largest container stored in the area
    plus ten percent. (§3218.2 of the Act)


    http://files.dep.state.pa.us/OilGas/OilGasLandingPageFiles/Act13/Act_13_FAQ.pdf
API Recommend Practice
Environmental Protection for Onshore Oil and Gas
     Production Operations and Leases (51R)
– Containment should be constructed so spilled fuels or chemicals do not
  reach the ground

– Control the spread to the smallest possible area

    • Drip pans under equipment and storage containers

    • Retaining walls or dikes around tanks and other spill prone equipment

    • Secondary catchment basins

    • Permanent booms in the adjoining water basin

    • Temporary booms deployed after the spill occurs

    • Cleanup materials sufficient to handle small spills stocked on site
API Guidance Document
Practices for Mitigating Surface Impacts Associated
           with Hydraulic Fracturing (HF3)
 – Spill prevention, response and cleanup procedures as part of SOP
   manual for storing oil, chemicals or other fluids

 – Installation of containment, BMPs, barriers and response equipment

     • Sloping well location away from surface water

     • Retaining walls or dikes around tanks

     • Secondary catchment basins

     • Absorbent between sites and surface waters

     • Temporary containment and liners during drilling and completions
Marcellus Shale Coalition
    Best Practices for Drilling and Well Construction
                               &
Best Practices Well Completion and Work-over Operations

– Waste management strategy should include storage containment, spill
  contingency plans, transfer and disposal procedures

– Fuel storage should include secondary containment

– Drilling fluid tanks and manifolds should be considered for placement
  inside lined secondary containment areas

– Drilling fluid containment and catchment systems should be
  considered
Appalachian Shale
Recommended Practices Group
            Recommended Standards and Practices

 – The use of an impermeable material (natural or manmade) under
   critical well pad areas.

 – The use of secondary containment for tanks (excluding freshwater).

 – Store liquid additives with secondary containment

 – Appropriate amounts of sorbent materials (spill kits)
Commissions & Boards
Secretary of Energy Advisory Board
   Incidents causing problems have been unrelated to fracking itself but
   have arisen from surface spills, poor cementing jobs in wellbores and
   other operational failures


Governor’s Marcellus Shale Advisory Commission
8.1.1The primary concerns regarding hydraulic fracturing relate to surface
   spills of fluids, well control and lost containment of production and
   flowback water on the surface


Citizen’s Marcellus Shale Commission
2.2 Well pads should be impervious and tanks should be surrounded by
   secondary containment to capture any spillage
Energy Institute
           University of Texas at Austin
•   Surface spills of fracturing fluids appear to pose greater risks to
    groundwater sources than from hydraulic fracturing itself

•   Gaps remain in the regulation of well casing and cementing,
    water withdrawal and usage, and waste storage and disposal

•   Regulations should focus on the most urgent issues, such as spill
    prevention — which may pose greater risk than hydraulic fracturing itself

•   Enforcement actions tend to emphasize surface incidents more than
    subsurface contaminant releases, perhaps because they are easier to
    observe
Shale Containments
Pad
  – Large square footage, typically centered off the wellheads
  – 6 to 8 inch high berms

Tank
  – 110% (150% in WV) of the largest tank
  – 2 to 3 foot high berms

Equipment
  – Placed under equipment that is leak prone
  – 6 to 8 inch high berms
Pad Containment

        Work surfaces should be as clean
        and dry as possible to prevent
        slips and falls.

        Tip: Polyethylene liners should be
        covered in felt to increase the
        coefficient of friction.

        Tip: Limit wrinkled, loose layers of
        material to reduce tripping hazards.


        OSHA 29 CFR 1910.22
        SPCC 40 CFR 112.7
        NPDES 40 CFR 122.26
        RCRA 40 CFR 264.175
Composite Pad Liners

                          Composite liners are slip resistant
                          and 4X more puncture resistant.

                          Tip: Withstands rigging up and down.

                          Tip: Doesn’t crack when cold.

                          Tip: Holes are readily detectable and
                          easily repairable.

                          Tip: Recyclable to reduce 93% of
                          landfill burden.
                          OSHA 29 CFR 1910.22
                          SPCC 40 CFR 112.7
New Pig Patents Pending   NPDES 40 CFR 122.26
                          RCRA 40 CFR 264.175
Pad Subbase

      Avoid mud.

      Tip: Cement dirt should be capped
      with at least 2 inches of stone.

      Tip: Stone should firm
      (no rolling or pumping) and rolled.

      Tip: Stone should be 2 inches or
      less in diameter. 2A Modified is
      preferred. River rock may develop
      rutts.
Soft Subbase
Resulting Rutts
Pad Layout

     Start square to end square.
     This is important when using rig mats.

     Tip: Square off of the main wellhead.

     Tip: Mark side and account for
     berming width.

     Tip: Use sand bags to keep panels
     in place.

     Tip: Starting and stopping lines
     reduce wasted material.
Seam Welding

      Automated wedge welders should
      be used for all liners to join large
      panels together.

      Tip: Set to correct temperature and
      speed depending on material and
      site conditions.

      Tip: Avoid “walking the dog”.
      Use a handle to guide the welder.


      OSHA 29 CFR 1910.22
      SPCC 40 CFR 112.7
      NPDES 40 CFR 122.26
      RCRA 40 CFR 264.175
Leak Testing

      Split welder seams can be tested
      by pressure.

      Solid wedge welder seams can be
      tested by vacuum.

      Tip: Vacuum tester can be moved
      30 inches every 10 seconds




      OSHA 29 CFR 1910.22
      SPCC 40 CFR 112.7
      NPDES 40 CFR 122.26
Patching

     Plastic Liner:
     2)Dry surface
     3)Heat tack patch
     4)Grind edge
     5)Extrusion weld

     Composite Liner:
     8)Dry surface
     9)Surround with sealant
     10)Heat tack patch


     OSHA 29 CFR 1910.22
     SPCC 40 CFR 112.7
     NPDES 40 CFR 122.26
     RCRA 40 CFR 264.175
Attachment to Cellar

          Prevents leak in cellar from backing
          up under the liner.

          Tip: Can be mechanically attached
          or spray coated with polyurea.




          OSHA 29 CFR 1910.22
          SPCC 40 CFR 112.7
          NPDES 40 CFR 122.26
          RCRA 40 CFR 264.175
Traffic Control

        Control access to either ramps
        or foam berms.
         
        Tip: Plastic barricades seem to have
        the most success in limiting traffic.




        OSHA 29 CFR 1910.22
        SPCC 40 CFR 112.7
        NPDES 40 CFR 122.26
        RCRA 40 CFR 264.175
Low-Wall Berming

        Most common materials are railroad
        ties, corrugated pipe or foam.

        Tip: Tie corrugated pipe corners
        together to prevent kick out.

        Tip: Folds should reach the top
        of the berm to maintain sump
        capacity.


        OSHA 29 CFR 1910.22
        SPCC 40 CFR 112.7
        NPDES 40 CFR 122.26
        RCRA 40 CFR 264.175
Grounding Rods

       Ideally grounding rods should be
       outside of the pad containment.

       Tip: Use a boot with standing pipe.
       Pipe should be as tall as the berm.




       OSHA 29 CFR 1910.22
       SPCC 40 CFR 112.7
       NPDES 40 CFR 122.26
       RCRA 40 CFR 264.175
Hole Prone Areas
Pipe Racks
  – Use rig mats or outrigger pads
     OR
  – Keep liner tight to catwalk


Backyard
  – Use rig mats for trackhoe path to drilling cutting bins


Outriggers
  – Use outrigger pads when positioning heavy equipment
Frac Tank Containment

           110% of largest tank. Berm walls
           are typically metal, concrete or
           plastic barricades.

           Tip: Subtract out tank
           displacement when calculating
           capacity.

           Tip: Keep separate from pad
           containment. Berm should terminate,
           meaning no hats.

           Tip: Higher sidewalls increase sump
           capacity for smaller footprints.
Brine Tank Containment

           Brine tanks are permanent
           structures and should have
           permanent secondary containment.

           Tip: Install a ladder to prevent falls.




           OSHA 29 CFR 1910.22
           SPCC 40 CFR 112.7
           NPDES 40 CFR 122.26
           RCRA 40 CFR 264.175
Fuel Tank Containment

           Fuel tanks should be double wall
           construction so that secondary
           containment travels with the tank.

           Tip: Tertiary containment

           Tip: Quaternary containment




           OSHA 29 CFR 1910.22
           SPCC 40 CFR 112.7
           NPDES 40 CFR 122.26
           RCRA 40 CFR 264.175
Equipment Containment

           Typically used under generators,
           light posts, and sewer treaters.

           Tip: Can be reused from site to site.




           OSHA 29 CFR 1910.22
           SPCC 40 CFR 112.7
           NPDES 40 CFR 122.26
           RCRA 40 CFR 264.175
Collapsible Storage

          Lightweight and reusable spot
          containment can be used for tanks,
          separators and vehicles.

          Tip: Float-up walls reduce
          impalement and tripping concerns.

          Tip: Drive-through options
          eliminate need to drop and raise
          walls.



          SPCC 40 CFR 112.7
          NPDES 40 CFR 122.26
          RCRA 40 CFR 264.175
Perimeter Control

         Sediment and oil are the two
         largest stormwater pollutants.

         Remember, it only takes a sheen
         for a spill to be reportable.

         Tip: Compost-filled sock does not
         fall over.

         Tip: Can be treated to remove oil
         and heavy metals.

         NPDES 40 CFR 122.26
         25 Pa. Code §§ 78.55
         25 Pa. Code §§ 91.34
Fluid Dispensing

        Fluid dispensing is a high-risk
        area for spills.

        Tip: Place quick-throw berms
        under hose connections.




        OSHA 29 CFR 1910.106
        SPCC 40 CFR 112.7
        NPDES 40 CFR 122.26
Universal Spill Removal

            Surround spill with booms
            to prevent spreading.

            Tip: Choose socks filled with
            earthen materials to create
            stronger containment dikes.

            Tip: Absorbent mats cover large
            surface areas to soak up spills.




            NPDES 40 CFR 122.26
            25 Pa. Code §§ 78.55
            25 Pa. Code §§ 91.34
Oil/Diesel Spill Removal

            Oil-only absorbents will not
            pick up water, which reduces
            disposal costs.

            Tip: Place booms at an angle in
            water basins as a preventative
            measure.

            Tip: Select UV-resistant
            absorbents if installed in the field
            for more than 3 months.

            SPCC 40 CFR 112.7
            NPDES 40 CFR 122.26
            25 Pa. Code §§ 78.55
            25 Pa. Code §§ 91.34
Response Trailers

         Equipment available for cleanup
         of a given spill must be listed.

         Tip: Use GPS coordinates to mark
         locations of the off-site trailers.

         Tip: Keep first responder boom
         supplies on site to surround
         perimeter.



         OSHA 29 CFR 1910.120
         SPCC 40 CFR 112.7
         25 Pa. Code §§ 78.55
         25 Pa. Code §§ 91.34
Truck Kits

     Address the typical failure mode
     and the most likely quantity.

     Tip: 5- to 8-gallon kits fit inside cabs.

     Tip: Consider pop-up pools for
     fuel tank damage and shovels for
     spills to soil.




     OSHA 29 CFR 1910.120
     SPCC 40 CFR 112.7
     25 Pa. Code §§ 78.55
     25 Pa. Code §§ 91.34
Drain Covers

      Storm drains are a major entry
      point into U.S. waters, which can
      trigger multiple violations.

      Tip: Cover drains during bulk
      transfer as a precaution.




      SPCC 40 CFR 112.7
      NPDES 40 CFR 122.26
Waste Collection – Solid

            Reduce air pollutant emissions
            from storage containers with
            continuous gaskets.

            Tip: Latching lids provide easy
            access for frequently opened
            and closed containers.




            RCRA 40 CFR 262.34
            RCRA 40 CFR 264.1086
Waste Collection – Liquid

             Hazardous waste can be
             collected in satellite accumulation
             drums in quantities of 55 gallons
             or less.

             Tip: Use a funnel with integral
             venting and overflow prevention
             to reduce spills.




             OSHA 29 CFR 264.1086
             RCRA 40 CFR 262.34
             RCRA 40 CFR 264.173
Contaminated Soil

         Keep spill waste separate from
         drill cuttings.

         Tip: Stock bags with the highest
         weight capacity and UN rating
         needed.
Questions?

Mais conteúdo relacionado

Mais procurados

Particularly Sensitive Sea Areas
Particularly Sensitive Sea AreasParticularly Sensitive Sea Areas
Particularly Sensitive Sea AreasEzra Dave Ignacio
 
ISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdf
ISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdfISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdf
ISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdfAustinAgbolo
 
Reece scba ppt
Reece scba pptReece scba ppt
Reece scba pptReece Mas
 
Ongc mumbai high accident
Ongc mumbai high accidentOngc mumbai high accident
Ongc mumbai high accidentMuzahid Khan
 
Operational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss PreventionOperational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss PreventionMichael Marshall, PE
 
Innoregio techn audits
Innoregio techn auditsInnoregio techn audits
Innoregio techn auditsjayanne07
 
Marine Diesel Engine Exhaust Gas Emissions Control Technologies
Marine Diesel Engine Exhaust Gas Emissions Control TechnologiesMarine Diesel Engine Exhaust Gas Emissions Control Technologies
Marine Diesel Engine Exhaust Gas Emissions Control TechnologiesMohammud Hanif Dewan M.Phil.
 
Amoco Drilling Fluid Manual
Amoco Drilling Fluid ManualAmoco Drilling Fluid Manual
Amoco Drilling Fluid ManualVyan Persad
 
Rigging safety 7
Rigging safety 7Rigging safety 7
Rigging safety 7vtsiri
 
Flammability Testing Of Plastics Jinish Doshi
Flammability Testing Of Plastics Jinish DoshiFlammability Testing Of Plastics Jinish Doshi
Flammability Testing Of Plastics Jinish DoshiJinish Doshi
 
Marine fire safety
Marine fire safetyMarine fire safety
Marine fire safetykmsu
 
SMCP security messages essay
SMCP security messages essaySMCP security messages essay
SMCP security messages essayborjaf4e
 
LIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdfLIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdfNanangArief2
 
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputCrane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputGaurav Singh Rajput
 
Fundamentals of Melt Flow Testing
Fundamentals of Melt Flow TestingFundamentals of Melt Flow Testing
Fundamentals of Melt Flow TestingInstron
 

Mais procurados (20)

Particularly Sensitive Sea Areas
Particularly Sensitive Sea AreasParticularly Sensitive Sea Areas
Particularly Sensitive Sea Areas
 
ISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdf
ISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdfISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdf
ISM_CODE_SHIPBOARD_TRAINING_FAMILIARIZAT.pdf
 
Reece scba ppt
Reece scba pptReece scba ppt
Reece scba ppt
 
Ongc mumbai high accident
Ongc mumbai high accidentOngc mumbai high accident
Ongc mumbai high accident
 
Operational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss PreventionOperational Excellence in Oil and Gas Loss Prevention
Operational Excellence in Oil and Gas Loss Prevention
 
Innoregio techn audits
Innoregio techn auditsInnoregio techn audits
Innoregio techn audits
 
2
22
2
 
Motor operations manual
Motor operations manualMotor operations manual
Motor operations manual
 
Ladder safety
Ladder safetyLadder safety
Ladder safety
 
Marine Diesel Engine Exhaust Gas Emissions Control Technologies
Marine Diesel Engine Exhaust Gas Emissions Control TechnologiesMarine Diesel Engine Exhaust Gas Emissions Control Technologies
Marine Diesel Engine Exhaust Gas Emissions Control Technologies
 
Amoco Drilling Fluid Manual
Amoco Drilling Fluid ManualAmoco Drilling Fluid Manual
Amoco Drilling Fluid Manual
 
Rigging safety 7
Rigging safety 7Rigging safety 7
Rigging safety 7
 
Flammability Testing Of Plastics Jinish Doshi
Flammability Testing Of Plastics Jinish DoshiFlammability Testing Of Plastics Jinish Doshi
Flammability Testing Of Plastics Jinish Doshi
 
Marine fire safety
Marine fire safetyMarine fire safety
Marine fire safety
 
Incinerator and MARPOL Requirements
Incinerator and MARPOL RequirementsIncinerator and MARPOL Requirements
Incinerator and MARPOL Requirements
 
FORKLIFT SAFETY
FORKLIFT SAFETYFORKLIFT SAFETY
FORKLIFT SAFETY
 
SMCP security messages essay
SMCP security messages essaySMCP security messages essay
SMCP security messages essay
 
LIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdfLIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdf
 
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputCrane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
 
Fundamentals of Melt Flow Testing
Fundamentals of Melt Flow TestingFundamentals of Melt Flow Testing
Fundamentals of Melt Flow Testing
 

Semelhante a Secondary Containment for Oil & Gas Well Pads

Spurlin spc cshortversfinal mb
Spurlin spc cshortversfinal mbSpurlin spc cshortversfinal mb
Spurlin spc cshortversfinal mbmacmanblue121
 
Oil Spill Prevention, Control & Countermeasure by Morehead State University
Oil Spill Prevention, Control & Countermeasure by Morehead State UniversityOil Spill Prevention, Control & Countermeasure by Morehead State University
Oil Spill Prevention, Control & Countermeasure by Morehead State UniversityAtlantic Training, LLC.
 
Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015
Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015
Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015Marcellus Drilling News
 
Subsea field development
Subsea field developmentSubsea field development
Subsea field developmentHamid S
 
Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27
Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27
Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27UTCIS
 
An introduction to oil and gas production
An introduction to oil and gas productionAn introduction to oil and gas production
An introduction to oil and gas productionAndi Anriansyah
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5Paulo P
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5Paulo P
 
Revised/New Pennsylvania Drilling Regulations - Chapter 78 & 78a
Revised/New Pennsylvania Drilling Regulations - Chapter 78 & 78aRevised/New Pennsylvania Drilling Regulations - Chapter 78 & 78a
Revised/New Pennsylvania Drilling Regulations - Chapter 78 & 78aMarcellus Drilling News
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overviewminh nguyễn
 
WY Offshore segments
WY Offshore segmentsWY Offshore segments
WY Offshore segmentsAlfred Hong
 
Draft Final Changes to Pennsylvania's Oil & Gas Well Drilling Rules
Draft Final Changes to Pennsylvania's Oil & Gas Well Drilling RulesDraft Final Changes to Pennsylvania's Oil & Gas Well Drilling Rules
Draft Final Changes to Pennsylvania's Oil & Gas Well Drilling RulesMarcellus Drilling News
 
Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?
Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?
Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?Triumvirate Environmental
 
IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004Abdulla Wanis
 
Best Practices for Leak & Spill Control
Best Practices for Leak & Spill ControlBest Practices for Leak & Spill Control
Best Practices for Leak & Spill ControlNew Pig Corporation
 
Shale HVHF Technique & Chemicals Used
Shale  HVHF Technique & Chemicals UsedShale  HVHF Technique & Chemicals Used
Shale HVHF Technique & Chemicals UsedWalden Associates
 
Oilspills 121205234057-phpapp02
Oilspills 121205234057-phpapp02Oilspills 121205234057-phpapp02
Oilspills 121205234057-phpapp02mohammed almahdi
 

Semelhante a Secondary Containment for Oil & Gas Well Pads (20)

SPCC 2015
SPCC 2015SPCC 2015
SPCC 2015
 
Spurlin spc cshortversfinal mb
Spurlin spc cshortversfinal mbSpurlin spc cshortversfinal mb
Spurlin spc cshortversfinal mb
 
Spcc training
Spcc trainingSpcc training
Spcc training
 
Oil Spill Prevention, Control & Countermeasure by Morehead State University
Oil Spill Prevention, Control & Countermeasure by Morehead State UniversityOil Spill Prevention, Control & Countermeasure by Morehead State University
Oil Spill Prevention, Control & Countermeasure by Morehead State University
 
Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015
Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015
Draft Final Rules for PA Oil & Gas Chapter 78 & 78a - August 2015
 
Subsea field development
Subsea field developmentSubsea field development
Subsea field development
 
Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27
Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27
Spill Prevention, Control and Countermeasure Plans (SPCC) - Kingsport, Sep 27
 
An introduction to oil and gas production
An introduction to oil and gas productionAn introduction to oil and gas production
An introduction to oil and gas production
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5
 
Revised/New Pennsylvania Drilling Regulations - Chapter 78 & 78a
Revised/New Pennsylvania Drilling Regulations - Chapter 78 & 78aRevised/New Pennsylvania Drilling Regulations - Chapter 78 & 78a
Revised/New Pennsylvania Drilling Regulations - Chapter 78 & 78a
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overview
 
WY Offshore segments
WY Offshore segmentsWY Offshore segments
WY Offshore segments
 
Draft Final Changes to Pennsylvania's Oil & Gas Well Drilling Rules
Draft Final Changes to Pennsylvania's Oil & Gas Well Drilling RulesDraft Final Changes to Pennsylvania's Oil & Gas Well Drilling Rules
Draft Final Changes to Pennsylvania's Oil & Gas Well Drilling Rules
 
SPCC Training .pptx
SPCC Training                       .pptxSPCC Training                       .pptx
SPCC Training .pptx
 
Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?
Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?
Is Your Spill Prevention, Control, and Countermeasure Plan EPA Compliant?
 
IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004
 
Best Practices for Leak & Spill Control
Best Practices for Leak & Spill ControlBest Practices for Leak & Spill Control
Best Practices for Leak & Spill Control
 
Shale HVHF Technique & Chemicals Used
Shale  HVHF Technique & Chemicals UsedShale  HVHF Technique & Chemicals Used
Shale HVHF Technique & Chemicals Used
 
Oilspills 121205234057-phpapp02
Oilspills 121205234057-phpapp02Oilspills 121205234057-phpapp02
Oilspills 121205234057-phpapp02
 

Secondary Containment for Oil & Gas Well Pads

  • 1. Secondary Containment Beth Powell Managing Director Well Pad Containment Division www.newpig.com/shalegas
  • 2. Secondary Containment Safeguarding method in addition to the primary containment system Specific/Sized – Indoor: Sump capacity should contain 10% of the volume of total containers or the total volume of the largest container, whichever is greater – Outdoor: Plus sufficient freeboard to contain precipitation General – Address typical failure mode and the most likely quantity – Passive or Active
  • 3. Regulations and Best Practices EPA PA DEP Liquids STRONGER Advisory API Commissions MSC & Boards
  • 4. EPA Oil & Gas Extraction Point Source – 40 CFR 435.32 – There shall be no discharge of waste water pollutants into navigable waters from any source associated with production, field exploration, drilling, well completion, or well treatment (i.e., produced water, drilling muds, drill cuttings, and produced sand).
  • 5. SPCC Spill Prevention, Control, and Countermeasure (SPCC) – 40 CFR 112 – Monitors plans to prevent oil spills at facilities • 1320 gallons of above-ground storage capacity • Potential to reach “navigable waters” • Oil, oil-like and oil/water mixtures – Clarifies “facility”; can be considered mobile or portable – Sets compliance date of November 10, 2011 for facilities that came into operation after August 12, 2002 http://www.epa.gov/osweroe1/docs/oil/spcc/spcc_101_prod.pdf
  • 6. SPCC 40CFR112.7(c) The entire containment system, including walls and floor, must be capable of containing oil and must be constructed so that any discharge from a primary containment system, such as a tank or pipe, will not escape the containment system before cleanup occurs. At a minimum, you must use one of the following prevention systems or its equivalent: (1) For onshore facilities: (i) Dikes, berms, or retaining walls sufficiently impervious to contain oil; (ii) Curbing; (iii) Culverting, gutters, or other drainage systems; (iv) Weirs, booms, or other barriers; (v) Spill diversion ponds; (vi) Retention ponds; or (vii) Sorbent materials.
  • 7. SPCC Examples Methods Description of Secondary Containment Examples Dikes, berms, or retaining walls Raised earth embankments or concrete containment walls used in areas with potential for large sufficiently impervious to contain oil discharges, such as single or multiple aboveground storage tanks and certain piping. Curbing Permanent concrete or asphalt apron surrounded by a curb. Can be used where only small spills are expected and also used to direct spills to drains or catchment areas. Culverting, gutters, or other drainage Types of permanent drainage systems designed to direct spills to remote containment or systems treatment areas. Weirs Dam-like structures with a notch through which oil may flow to be collected. Used in combination with skimmers to remove oil from the surface of water. Booms Form a continuous barrier placed as a precautionary measure to contain/collect oil. Typically used for the containment, exclusion, or deflection of oil floating on water, and is usually used to address oil spills that have reached surface waters. Barriers Spill mats, storm drain covers, and dams used to block or prevent the flow of oil. Spill diversion and retention ponds Designed for long-term or permanent containment of storm water capable to capture and hold oil or runoff and prevent it from entering surface water bodies. Sorbent materials Materials include spill pads, pillows, socks, mats, clay, vermiculite, and diatomaceous earth. Used to isolate and contain small drips or leaks until the source of the leak is repaired. Used to isolate and contain small drips or leaks until the source of the leak is repaired. Drip pans Drip pans are commonly used with product dispensing containers (usually drums), uncoupling of hoses during bulk transfer operations, and for pumps, valves, and fittings. Sumps and collection systems A permanent pit or reservoir and the troughs/trenches connected to it that collect oil.
  • 8. SPCC Provisions Type of Facility Secondary Containment Rule Section(s) All Facilities General containment (areas with 112.7(c) potential for discharge, e.g., piping, oil-filled operating and manufacturing equipment, and non- rack related transfer areas) Onshore Storage Bulk storage containers 112.8(c)(2) or 112.12(c)(2) Mobile or portable oil containers* 112.8(c)(11) or 112.12(c)(11) Onshore Production Bulk storage containers, including 112.9(c)(2) tank batteries, separation, and treating facility installations* Onshore Oil Drilling and Workover Mobile drilling or workover 112.10(c) equipment Offshore Oil Drilling, Production, and Oil drilling, production, or workover 112.7(c) Workover equipment SPCC Guidance for Regional Inspectors http://www.epa.gov/oem/docs/oil/spcc/guidance/4_SecondaryContainment_Impracticability.pdf
  • 9. SPCC § 112.10 Provisions • If you are the owner or operator of an onshore oil drilling and workover facility, you must: • (a) Meet the general requirements listed under §112.7, and also meet the specific discharge prevention and containment procedures listed under this section. • (b) Position or locate mobile drilling or workover equipment so as to prevent a discharge as described in §112.1(b). • (c) Provide catchment basins or diversion structures to intercept and contain discharges of fuel, crude oil, or oily drilling fluids. • (d) Install a blowout prevention (BOP) assembly and well control system before drilling below any casing string or during workover operations. The BOP assembly and well control system must be capable of controlling any well-head pressure that may be encountered while that BOP assembly and well control system are on the well.
  • 10. RCRA Resource Conservation & Recovery Act (RCRA) – 40 CFR 260-265 (generator standards) – Restricts hazardous waste collection and storage – Defines “characteristic” and “listed” hazardous wastes • Ignitability • Corrosivity • Reactivity • Toxicity – Exempts flowback fluids at federal level (state laws may apply) – May not exempt fracturing fluids at federal level
  • 11. NPDES National Pollutant Discharge Elimination System (NPDES) – 40 CFR 122 – Limits water pollution through permits – Defines oil pollution as a “sheen” on the water – Regulates stormwater discharges from construction sites (1 acre plus), industrial facilities and municipalities – Considers sediment to be the most common pollutant – Requires E&P sites to have sediment controls – Delegates permitting to states; all Marcellus Shale states have received delegation
  • 12. Hydraulic Fracturing Study Section 6.4.4 • EPA is interested in gathering information relating to the current on-site management practices that are used to prevent and/or contain accidental releases of flowback and produced water to drinking water resources.
  • 13. PA DEP Oil & Gas Act Clean Streams Law Solid Waste Management Act Prevention, Preparedness and Contingency (PPC) Plan • 25 Pa. Code §§ 78.55 Control and Disposal Plan • 25 Pa. Code §§ 91.34 Activities Utilizing Pollutants • Spills of 5 gallons or greater are reportable
  • 14. Oil & Gas Spill Policy Draft • Report a spill or release regardless of the quantity spilled • If secondary containment is in place, notify if the quantity of material exceeds 42 gallons • Remove the spilled material from the secondary containment within 24 hours • When spilled onto the ground, the material is usually either residual waste or hazardous waste
  • 15. STRONGER Pennsylvania Hydraulic Fracturing State Review—September 2010 Recommendation 9.2.1.10. – The review team recommends that secondary containment requirements be established for tanks used in hydraulic fracturing operations.
  • 16. Act 13 of 2012 • The environmental protection provisions are effective April 16, 2012. • Unconventional well sites must be designed and constructed to prevent spills to the ground surface or off the well site. Containment practices must be in place during both drilling and hydraulic fracturing operations and must be sufficiently impervious and able to contain spilled materials, and be compatible with the waste material or waste stored within the containment. Containment plans must be submitted to the department and describe any equipment that is to be kept onsite to prevent a spill from leaving the well pad. • Containment systems shall be used wherever drilling mud, hydraulic oil, diesel fuel, drilling mud additives, hydraulic fracturing additives, and/or hydraulic fracturing flowback are stored. Containment areas must be sufficient to hold the volume of the largest container stored in the area plus ten percent. (§3218.2 of the Act) http://files.dep.state.pa.us/OilGas/OilGasLandingPageFiles/Act13/Act_13_FAQ.pdf
  • 17. API Recommend Practice Environmental Protection for Onshore Oil and Gas Production Operations and Leases (51R) – Containment should be constructed so spilled fuels or chemicals do not reach the ground – Control the spread to the smallest possible area • Drip pans under equipment and storage containers • Retaining walls or dikes around tanks and other spill prone equipment • Secondary catchment basins • Permanent booms in the adjoining water basin • Temporary booms deployed after the spill occurs • Cleanup materials sufficient to handle small spills stocked on site
  • 18. API Guidance Document Practices for Mitigating Surface Impacts Associated with Hydraulic Fracturing (HF3) – Spill prevention, response and cleanup procedures as part of SOP manual for storing oil, chemicals or other fluids – Installation of containment, BMPs, barriers and response equipment • Sloping well location away from surface water • Retaining walls or dikes around tanks • Secondary catchment basins • Absorbent between sites and surface waters • Temporary containment and liners during drilling and completions
  • 19. Marcellus Shale Coalition Best Practices for Drilling and Well Construction & Best Practices Well Completion and Work-over Operations – Waste management strategy should include storage containment, spill contingency plans, transfer and disposal procedures – Fuel storage should include secondary containment – Drilling fluid tanks and manifolds should be considered for placement inside lined secondary containment areas – Drilling fluid containment and catchment systems should be considered
  • 20. Appalachian Shale Recommended Practices Group Recommended Standards and Practices – The use of an impermeable material (natural or manmade) under critical well pad areas. – The use of secondary containment for tanks (excluding freshwater). – Store liquid additives with secondary containment – Appropriate amounts of sorbent materials (spill kits)
  • 21. Commissions & Boards Secretary of Energy Advisory Board Incidents causing problems have been unrelated to fracking itself but have arisen from surface spills, poor cementing jobs in wellbores and other operational failures Governor’s Marcellus Shale Advisory Commission 8.1.1The primary concerns regarding hydraulic fracturing relate to surface spills of fluids, well control and lost containment of production and flowback water on the surface Citizen’s Marcellus Shale Commission 2.2 Well pads should be impervious and tanks should be surrounded by secondary containment to capture any spillage
  • 22. Energy Institute University of Texas at Austin • Surface spills of fracturing fluids appear to pose greater risks to groundwater sources than from hydraulic fracturing itself • Gaps remain in the regulation of well casing and cementing, water withdrawal and usage, and waste storage and disposal • Regulations should focus on the most urgent issues, such as spill prevention — which may pose greater risk than hydraulic fracturing itself • Enforcement actions tend to emphasize surface incidents more than subsurface contaminant releases, perhaps because they are easier to observe
  • 23. Shale Containments Pad – Large square footage, typically centered off the wellheads – 6 to 8 inch high berms Tank – 110% (150% in WV) of the largest tank – 2 to 3 foot high berms Equipment – Placed under equipment that is leak prone – 6 to 8 inch high berms
  • 24. Pad Containment Work surfaces should be as clean and dry as possible to prevent slips and falls. Tip: Polyethylene liners should be covered in felt to increase the coefficient of friction. Tip: Limit wrinkled, loose layers of material to reduce tripping hazards. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 25. Composite Pad Liners Composite liners are slip resistant and 4X more puncture resistant. Tip: Withstands rigging up and down. Tip: Doesn’t crack when cold. Tip: Holes are readily detectable and easily repairable. Tip: Recyclable to reduce 93% of landfill burden. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 New Pig Patents Pending NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 26. Pad Subbase Avoid mud. Tip: Cement dirt should be capped with at least 2 inches of stone. Tip: Stone should firm (no rolling or pumping) and rolled. Tip: Stone should be 2 inches or less in diameter. 2A Modified is preferred. River rock may develop rutts.
  • 29. Pad Layout Start square to end square. This is important when using rig mats. Tip: Square off of the main wellhead. Tip: Mark side and account for berming width. Tip: Use sand bags to keep panels in place. Tip: Starting and stopping lines reduce wasted material.
  • 30. Seam Welding Automated wedge welders should be used for all liners to join large panels together. Tip: Set to correct temperature and speed depending on material and site conditions. Tip: Avoid “walking the dog”. Use a handle to guide the welder. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 31. Leak Testing Split welder seams can be tested by pressure. Solid wedge welder seams can be tested by vacuum. Tip: Vacuum tester can be moved 30 inches every 10 seconds OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26
  • 32. Patching Plastic Liner: 2)Dry surface 3)Heat tack patch 4)Grind edge 5)Extrusion weld Composite Liner: 8)Dry surface 9)Surround with sealant 10)Heat tack patch OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 33. Attachment to Cellar Prevents leak in cellar from backing up under the liner. Tip: Can be mechanically attached or spray coated with polyurea. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 34. Traffic Control Control access to either ramps or foam berms.   Tip: Plastic barricades seem to have the most success in limiting traffic. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 35. Low-Wall Berming Most common materials are railroad ties, corrugated pipe or foam. Tip: Tie corrugated pipe corners together to prevent kick out. Tip: Folds should reach the top of the berm to maintain sump capacity. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 36. Grounding Rods Ideally grounding rods should be outside of the pad containment. Tip: Use a boot with standing pipe. Pipe should be as tall as the berm. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 37. Hole Prone Areas Pipe Racks – Use rig mats or outrigger pads OR – Keep liner tight to catwalk Backyard – Use rig mats for trackhoe path to drilling cutting bins Outriggers – Use outrigger pads when positioning heavy equipment
  • 38. Frac Tank Containment 110% of largest tank. Berm walls are typically metal, concrete or plastic barricades. Tip: Subtract out tank displacement when calculating capacity. Tip: Keep separate from pad containment. Berm should terminate, meaning no hats. Tip: Higher sidewalls increase sump capacity for smaller footprints.
  • 39. Brine Tank Containment Brine tanks are permanent structures and should have permanent secondary containment. Tip: Install a ladder to prevent falls. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 40. Fuel Tank Containment Fuel tanks should be double wall construction so that secondary containment travels with the tank. Tip: Tertiary containment Tip: Quaternary containment OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 41. Equipment Containment Typically used under generators, light posts, and sewer treaters. Tip: Can be reused from site to site. OSHA 29 CFR 1910.22 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 42. Collapsible Storage Lightweight and reusable spot containment can be used for tanks, separators and vehicles. Tip: Float-up walls reduce impalement and tripping concerns. Tip: Drive-through options eliminate need to drop and raise walls. SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 RCRA 40 CFR 264.175
  • 43. Perimeter Control Sediment and oil are the two largest stormwater pollutants. Remember, it only takes a sheen for a spill to be reportable. Tip: Compost-filled sock does not fall over. Tip: Can be treated to remove oil and heavy metals. NPDES 40 CFR 122.26 25 Pa. Code §§ 78.55 25 Pa. Code §§ 91.34
  • 44. Fluid Dispensing Fluid dispensing is a high-risk area for spills. Tip: Place quick-throw berms under hose connections. OSHA 29 CFR 1910.106 SPCC 40 CFR 112.7 NPDES 40 CFR 122.26
  • 45. Universal Spill Removal Surround spill with booms to prevent spreading. Tip: Choose socks filled with earthen materials to create stronger containment dikes. Tip: Absorbent mats cover large surface areas to soak up spills. NPDES 40 CFR 122.26 25 Pa. Code §§ 78.55 25 Pa. Code §§ 91.34
  • 46. Oil/Diesel Spill Removal Oil-only absorbents will not pick up water, which reduces disposal costs. Tip: Place booms at an angle in water basins as a preventative measure. Tip: Select UV-resistant absorbents if installed in the field for more than 3 months. SPCC 40 CFR 112.7 NPDES 40 CFR 122.26 25 Pa. Code §§ 78.55 25 Pa. Code §§ 91.34
  • 47. Response Trailers Equipment available for cleanup of a given spill must be listed. Tip: Use GPS coordinates to mark locations of the off-site trailers. Tip: Keep first responder boom supplies on site to surround perimeter. OSHA 29 CFR 1910.120 SPCC 40 CFR 112.7 25 Pa. Code §§ 78.55 25 Pa. Code §§ 91.34
  • 48. Truck Kits Address the typical failure mode and the most likely quantity. Tip: 5- to 8-gallon kits fit inside cabs. Tip: Consider pop-up pools for fuel tank damage and shovels for spills to soil. OSHA 29 CFR 1910.120 SPCC 40 CFR 112.7 25 Pa. Code §§ 78.55 25 Pa. Code §§ 91.34
  • 49. Drain Covers Storm drains are a major entry point into U.S. waters, which can trigger multiple violations. Tip: Cover drains during bulk transfer as a precaution. SPCC 40 CFR 112.7 NPDES 40 CFR 122.26
  • 50. Waste Collection – Solid Reduce air pollutant emissions from storage containers with continuous gaskets. Tip: Latching lids provide easy access for frequently opened and closed containers. RCRA 40 CFR 262.34 RCRA 40 CFR 264.1086
  • 51. Waste Collection – Liquid Hazardous waste can be collected in satellite accumulation drums in quantities of 55 gallons or less. Tip: Use a funnel with integral venting and overflow prevention to reduce spills. OSHA 29 CFR 264.1086 RCRA 40 CFR 262.34 RCRA 40 CFR 264.173
  • 52. Contaminated Soil Keep spill waste separate from drill cuttings. Tip: Stock bags with the highest weight capacity and UN rating needed.

Notas do Editor

  1. The specific secondary containment requirements are intended to address a major container failure (the entire contents of the container and/or compartment) associated with a bulk storage container; single compartment of a tank car or tank truck at a loading/unloading rack; mobile/portable containers; and production tank batteries, treatment, and separation installations. These specific provisions (see Table 4.1 in Section 4.2) explicitly provide requirements for sizing, design, and freeboard that need to be addressed in the SPCC Plan. The general secondary containment requirements are intended to address the most likely oil discharge from bulk storage containers; mobile/portable containers; production tank battery, treatment, and separation installations; a particular piece of oil-filled operational or process equipment; (non-rack) transfer activity; or piping in accordance with good engineering practice. SPCC 40CFR112.7(c) The entire containment system, including walls and floor, must be capable of containing oil and must be constructed so that any discharge from a primary containment system, such as a tank or pipe, will not escape the containment system before cleanup occurs. At a minimum, you must use one of the following prevention systems or its equivalent: (1) For onshore facilities: (i) Dikes, berms, or retaining walls sufficiently impervious to contain oil; (ii) Curbing; (iii) Culverting, gutters, or other drainage systems; (iv) Weirs, booms, or other barriers; (v) Spill diversion ponds; (vi) Retention ponds; or (vii) Sorbent materials .
  2. Environmental Protection Agency State Departments of Environmental Protection Occupational Safety & Health Administration American Petroleum Institute Marcellus Shale Coalition S tate R eview of O il & N atural G as E nvironmental R egulations
  3. EPA jurisdiction is provided for under the Clean Water Act
  4. Onshore Production Bulk storage containers, including tank batteries, separation, and treating facility installations 112.9(c)(2) Onshore Oil Drilling and Workover Mobile drilling or workover equipment 112.10(c)
  5. Among the wastes covered by the 1978 proposal were “gas and oil drilling muds and oil production brines.” The oil and gas exemption was expanded in the 1980 legislative amendments to RCRA to include “drilling fluids, produced water, and other wastes associated with the exploration, development, or production of crude oil or natural gas. . . .” The following simple rule of thumb can be used to determine if an E&P waste is exempt or non-exempt from RCRA Subtitle C regulations: 1) Has the waste come from down-hole, i.e., was it brought to the surface during oil and gas E&P operations? 2) Has the waste otherwise been generated by contact with the oil and gas production stream during the removal of produced water or other contaminants from the product? If the answer to either question is yes, then the waste is likely considered exempt from RCRA Subtitle C regulations. It is important to remember that all E&P wastes require proper management to ensure protection of human health and the environment. Non-Exempt Wastes Unused fracturing fluids or acids Waste solvents Service company wastes such spent solvents, spilled chemicals, and waste acids Used equipment lubricating oils Waste compressor oil, filters, and blowdown Used hydraulic fluids Caustic or acid cleaners
  6. Section 6.4.4
  7. Oil and Gas Act (Act 223) Any well operator who affects a public or private water supply by pollution or diminution shall restore or replace the affected water supply…(Sec. 601.208) Clean Streams Law (P.L. 1987, Act 394 or 1937) Discharge of industrial waste or any substance into the waters which causes pollution is against public policy (Section 3) Permits are required to discharge industrial waste (Section 303, 307) If impounding, handling, storage, transportation, processing or disposing of materials creates a danger of pollution, DEP may establish the conditions under which such activity may be conducted (Section 402) Solid Waste Management Act § 78.55. Control and disposal plan.   (a)  Prior to generation of waste, the well operator shall prepare and implement a plan under §  91.34 (relating to activities utilizing pollutants) for the control and disposal of fluids, residual waste and drill cuttings, including tophole water, brines, drilling fluids, additives, drilling muds, stimulation fluids, well servicing fluids, oil, production fluids and drill cuttings from the drilling, alteration, production, plugging or other activity associated with oil and gas wells.   (b)  The plan shall identify the control and disposal methods and practices utilized by the well operator and be consistent with the act, The Clean Streams Law (35 P. S. § §  691.1—691.1001), the Solid Waste Management Act (35 P. S. § §  6018.101—6018.1003) and § §  78.54, 78.56—78.58 and 78.60—78.63.   (c)  The operator shall revise the plan prior to implementing a change to the practices identified in the plan.   (d)  A copy of the plan shall be provided to the Department upon request. § 91.34. Activities utilizing pollutants.   (a)  Persons engaged in an activity which includes the impoundment, production, processing, transportation, storage, use, application or disposal of pollutants shall take necessary measures to prevent the substances from directly or indirectly reaching waters of this Commonwealth, through accident, carelessness, maliciousness, hazards of weather or from another cause.   (b)  The Department may require a person to submit a report or plan for activities described in subsection (a). Upon notice from the Department and within the time specified in the notice, the person shall submit to the Department the report or plan setting forth the nature of the activity and the nature of the preventative measures taken to comply with subsection (a). The Department will encourage the use of pollution prevention measures that minimize or eliminate the generation of the pollutant over measures which involve pollutant handling or treatment. The Department will encourage consideration of the following pollution prevention measures, in descending order of preference, for environmental management of wastes: reuse, recycling, treatment and disposal. http://apps.sos.wv.gov/adlaw/files/rulespdf/35-01.pdf
  8. S tate R eview of O il & N atural G as E nvironmental R egulations (independent body of state, industry and environmental stakeholders) IN PA, secondary containment liners are recommended but not required.
  9. Best Practices for Drilling and Well Co nstruction Waste management strategy should include storage containment, spill contingency plan, transfer and disposal procedures (3.8) Fuel storage should include secondary containment (6.3) Drilling fluid tanks and manifolds should be considered for placement inside lined secondary containment areas. (10.6) Drilling fluid containment and catchment systems should be considered. (10.7) Best Practices for Well Completion and Work-over Operations Waste management strategy should include storage containment, spill contingency plan, transfer and disposal procedures (3.8) Fuel storage should include secondary containment (6.3) Work-over fluid tanks and manifolds should be considered for placement inside lined secondary containment areas. (10.5) Work-over fluid containment and catchment systems should be considered. (10.6)
  10. Secretary of Energy Advisory Board:
  11. Secretary of Energy Advisory Board:
  12. Pad Containment --This is the main liner that is placed over a large square footage, typically centered off the wellheads. This is the first liner installed before a rig move. Highly suggest attaching the liner directly to the cellar walls, either mechanically or with a coating, to prevent any back up at the well head from pushing under the liner. Berming is typically 6" to 8" high. Although some operators tie into plastic barricades (to control traffic to designated areas), the entrance ways are typically only 6" to 8".   Tank Farm Containment --This is the containment under the battery of frac tanks and may or may not be on top of Pad Containment.  Plastic, metal or concrete barricades are used to provide high walls to meet the 110% containment of the largest tank or 10% of the total volume in a small footprint.  If walls are 3' or higher, use a bridge ladder to enter/exit since you cannot step over them easily.   Equipment Containment --This liner that is placed directly under equipment that is leak prone.  It may be on the Pad Containment to limit spread (mud tanks, pump house) or it could be under a generator, light post, sewer treater, etc. that is off the Pad Containment.  Berming is typically 6" to 8" high.   Containment Recommended Practices: 1. Large panels should be seamed together with a wedge welder, not a hot air gun or extrusion welder, to ensure good seam contact over long lengths. The hot air gun and extrusion welder should only be used for spot repairs or detail work around obstacles.  2. Fuel tanks should be double-walled. Some operators place them on two liners (Pad and Equipment/Tank Containment), with the second cut to fit around them specifically. This provides four levels of containment.  3. If secondary containment walls are higher than 3', use a bridge ladder to enter and exit the area.  4. If you have designated entrance areas, string flag the rest or place plastic barricades around the perimeter. Avoid posts that could be impalement hazards.  5. Do not use metal L-brackets to build spot containment. They are an impalement hazard.  6. Vacuum off standing water before it freezes. If over an inch, it takes a long time to melt off.  7. Use dark colored liner in the winter. The sunlight in the morning will quickly melt ice and evaporate water.  8. Do not place pipe racks directly on the containment liner. This is one of the most hole prone areas. Use rig mats on the liner or keep the liner tight to the catwalk.  9. Use rig mats for the drill cutting bins and trackhoe path on the liner. This is one of the most hole prone areas.  10. Use outrigger pads when positioning heavy equipment on the containment liner. This is one of the most hole prone areas.  11. Use liners with high coefficients of friction to limit slips and falls when wet. Avoid ones with smooth seams. There is a large change in the coefficient of friction between the two areas.  12. Limit loose layers and wrinkles in the containment liner. Wrinkles should be pulled out during installation. The edges should be sandbagged until the berm is in place or berm at least two sides before equipment moves in.  13. Do not place grounding rods in high traffic areas. They are an impalement hazard. Cover exposed ends with buckets, tennis balls or other protective cushioning. If placed through the liner, boots or gaskets must be used. 14. Place a liner sleeve into the cellar and bond the liner edges to it to conform to the opening. This should then be mechanically fastened to prevent spills in the cellar from spreading under the liner.  15. Clean up hydrocarbon spills as quickly as possible, such as drilling mud and pipe dope. Place catch basins where this is likely to happen (i.e. valves).  16. Make frac tank containment a stand-alone containment. The base liner should wrap and terminate at the berm. Patching a berm over the top is suspect for leaks.  17. Test field suspect seams for water tightness. A vacuum tester is non-destructive.   18. The subbase has a large effect on the number of patches required throughout the liner lifetime. A gravel base will shift to disperse load; 2A Modified is recommended.  2B has rounded stones and results in few punctures--but may develops ruts.  Avoid a hard surface (cement dirt) with scattered loose stones since the forces will be concentrated on the scattered stones. A covering of dust/screening over larger rocks will work—but may turn into mud as operations progress. All pads should be rolled before the liner is installed.   19.  If corrugated pipe is used to make the berm, the sections that meet to establish a corner should strapped together to prevent kick out.        
  13. Pad Containment --This is the main liner that is placed over a large square footage, typically centered off the wellheads. This is the first liner installed before a rig move. Highly suggest attaching the liner directly to the cellar walls, either mechanically or with a coating, to prevent any back up at the well head from pushing under the liner. Berming is typically 6" to 8" high. Although some operators tie into plastic barricades (to control traffic to designated areas), the entrance ways are typically only 6" to 8".   Tank Farm Containment --This is the containment under the battery of frac tanks and may or may not be on top of Pad Containment.  Plastic, metal or concrete barricades are used to provide high walls to meet the 110% containment of the largest tank or 10% of the total volume in a small footprint.  If walls are 3' or higher, use a bridge ladder to enter/exit since you cannot step over them easily.   Equipment Containment --This liner that is placed directly under equipment that is leak prone.  It may be on the Pad Containment to limit spread (mud tanks, pump house) or it could be under a generator, light post, sewer treater, etc. that is off the Pad Containment.  Berming is typically 6" to 8" high.   Containment Recommended Practices: 1. Large panels should be seamed together with a wedge welder, not a hot air gun or extrusion welder, to ensure good seam contact over long lengths. The hot air gun and extrusion welder should only be used for spot repairs or detail work around obstacles.  2. Fuel tanks should be double-walled. Some operators place them on two liners (Pad and Equipment/Tank Containment), with the second cut to fit around them specifically. This provides four levels of containment.  3. If secondary containment walls are higher than 3', use a bridge ladder to enter and exit the area.  4. If you have designated entrance areas, string flag the rest or place plastic barricades around the perimeter. Avoid posts that could be impalement hazards.  5. Do not use metal L-brackets to build spot containment. They are an impalement hazard.  6. Vacuum off standing water before it freezes. If over an inch, it takes a long time to melt off.  7. Use dark colored liner in the winter. The sunlight in the morning will quickly melt ice and evaporate water.  8. Do not place pipe racks directly on the containment liner. This is one of the most hole prone areas. Use rig mats on the liner or keep the liner tight to the catwalk.  9. Use rig mats for the drill cutting bins and trackhoe path on the liner. This is one of the most hole prone areas.  10. Use outrigger pads when positioning heavy equipment on the containment liner. This is one of the most hole prone areas.  11. Use liners with high coefficients of friction to limit slips and falls when wet. Avoid ones with smooth seams. There is a large change in the coefficient of friction between the two areas.  12. Limit loose layers and wrinkles in the containment liner. Wrinkles should be pulled out during installation. The edges should be sandbagged until the berm is in place or berm at least two sides before equipment moves in.  13. Do not place grounding rods in high traffic areas. They are an impalement hazard. Cover exposed ends with buckets, tennis balls or other protective cushioning. If placed through the liner, boots or gaskets must be used. 14. Place a liner sleeve into the cellar and bond the liner edges to it to conform to the opening. This should then be mechanically fastened to prevent spills in the cellar from spreading under the liner.  15. Clean up hydrocarbon spills as quickly as possible, such as drilling mud and pipe dope. Place catch basins where this is likely to happen (i.e. valves).  16. Make frac tank containment a stand-alone containment. The base liner should wrap and terminate at the berm. Patching a berm over the top is suspect for leaks.  17. Test field suspect seams for water tightness. A vacuum tester is non-destructive.   18. The subbase has a large effect on the number of patches required throughout the liner lifetime. A gravel base will shift to disperse load; 2A Modified is recommended.  2B has rounded stones and results in few punctures--but may develops ruts.  Avoid a hard surface (cement dirt) with scattered loose stones since the forces will be concentrated on the scattered stones. A covering of dust/screening over larger rocks will work—but may turn into mud as operations progress. All pads should be rolled before the liner is installed.   19.  If corrugated pipe is used to make the berm, the sections that meet to establish a corner should strapped together to prevent kick out.        
  14. It may be on the Pad Containment to limit spread (mud tanks, pump house) or it could be under a generator, light post, sewer treater, etc. that is off the Pad Containment.  Berming is typically 6" to 8" high.