SlideShare uma empresa Scribd logo
1 de 50
Presented By:-
Navajyoti Martha
 Incentivise efficiency improvement
 Obviate regulatory uncertainty – reduce regulatory
risk
 Less intrusive and avoids tendency to micro
manage
 Assists the utility to plan its business
 Determine framework for regulating the utilities for a period of
time,
◦ Principles of regulation of returns/profits of utilities
◦ Principles of regulating individual cost and revenue elements
◦ Degree of regulation on an on-going basis
 Incentivise utilities to become more efficient in operations
 Mitigate risks that are external to the utilities
 Make the sector financially sound
 Introduce efficient tariff design
 Separates costs into controllable and uncontrollable
components and treats them separately
 Section 61 states that the appropriate commissions, for
determining the terms and conditions for the determination of
tariffs shall be guided by multi-year tariff principles
 MYT framework to be adopted for any tariffs from 1 April 2006
 The framework should feature a five year control period
 The initial control period can be of 3 years for transmission &
distribution if deemed necessary on account of data
inadequacies and other practical considerations
 ERC can state assumptions in first control period and then as
more reliable data becomes available, a fresh control period may
be started
 Where operations are below norms for several
years, improvement trajectories may be
recognized at “relaxed” levels and not “desired”
levels
 Suitable benchmarking studies must be conducted
to establish “desired” performance standards
 Separate studies may be carried out by each
utility to assess the capital expenditure necessary
to meet minimum service standards
 Once revenue requirements are established at the
beginning of the control period, the ERC should focus
on regulation of outputs and not the input cost elements
 Uncontrollable costs should be recovered speedily to
ensure that future consumers are not burdened with
past costs
 Uncontrollable costs would include (but not limited to):
◦ Fuel costs, cost on account of inflation, taxes and cess,
variation in power purchase unit costs including on
account of hydel thermal mix in case of adverse natural
events
 Supply of electricity by a Generating Co to a Discom
 Intra-state transmission of Electricity
 Intra-state wheeling of electricity
 Retail supply of electricity
◦ If there are two or more distribution licensees, GERC can
prescribe a tariff ceiling or cap
 General framework for tariff determination and the
Commission reserves a right to vary the parameters
and procedures when facts and/or circumstances so
warrant
 ARR and expected revenue from tariff and
charges for Genco, Transmission Licensee,
Distribution wires and retail supply business
 All the companies would file the MYT petition/
applications separately
 The MYT Petition comprises:
◦ Truing up for the year for 2009-10 for which audited results
are available under GERC (Terms & Conditions)
Regulations and GERC (MYT) Regulations
◦ Annual Performance Review for 2010-11
◦ Multi-year ARR for the entire control period (2011-12 to
2015-16) with year wise details
◦ Revenue from the sale of power at existing tariffs and
charges & projected revenue gap for the first year of the
control period
◦ Application for determination of tariff for the first year of the
control period
 All MYT Applications would be filed along with a Business
Plan for the control period
 Business Plan shall comprise (but not limited to) in
accordance with the guidelines & formats as prescribed by
the ERC:
◦ Detailed category wise sales & demand projections
◦ Power procurement plan
◦ Capital investment plan
◦ Financing plan
◦ Physical targets
 Capital investment plan shall show on-going projects to be
completed in the control period and new projects that will spill
beyond the control period
 ERC will approve the capital investment plan
 Discom will project the power procurement plan
based on merit order despatch principles, RPPO,
DSM, Energy Efficiency etc.
 The Business Plan has to be approved by the
ERC
 The MYT Application shall necessarily contain the
trajectories for the following variables for the
control period:
◦ O & M expenses
◦ Target Plant Load Factor
◦ Distribution Losses
 The companies may seek a mid-term review of
the trajectory at the time of the mid-term review of
the Business Plan
 From the first year of the Control Period and
onward, the Petition will comprise:
◦ Truing up for FY 2010-11
◦ Revenue from the sale of power at existing tariffs and
charges for the ensuing year
◦ Revenue gap for the ensuing year calculated based on
ARR approved in the Tariff Order or MYT Order and
truing up for the previous year
◦ Application for determination of tariff for the ensuing year
◦ Truing up for previous year
◦ Modification of the ARR for the remaining years of the
control period with justification
◦ Revenue from the sale of power at existing tariffs and the
changes for the ensuing year
◦ Revenue gap for the ensuring year calculated based on
the ARR approved in the MYT Order and Truing up for
the previous year
◦ Application for the determination of tariff for the ensuing
year
 True up is of expenses and revenue during the control period
 The approved forecast of ARR and Expected revenue from
tariff is compared with the audited performance including
pass through of uncontrollable factors
 Review of compliance with ERC directives
 ERC will then pass an order recording the approved
aggregate gain and loss – components of costs related to
uncontrollable factors will be pass through
 Once ERC notifies the regulations for submission of
regulatory accounts, the application for tariff determination
and truing up shall be based on the Regulatory Accounts
 Costs are categorised as controllable & uncontrollable
 Uncontrollable factors include:
◦ Force Majeure events
◦ Change in law/ judicial pronouncements by govts or commission
◦ Fuel price variation
◦ Power purchase in accordance with FPPPA formula
◦ Variation in consumer number or mix or quantities of electricity
supplied to consumers/ under open access
◦ Transmission loss
◦ Variation in market interest rate
◦ Taxes & statutory levies
◦ Taxes on income
 Variation in capitalization on account of time or cost
overruns or inefficiencies in implementation
 Variation in interest & financial charges on account of
the above
 Variation in technical an commercial losses of discoms
 Variations in performance parameters
 Variations in working capital requirements
 Failure to meet performance standards
 Variation in labour productivity
 Variation in O&M expenses
 Variation in wires availability
 Uncontrollable Factors:
◦ Aggregate gain or loss on account of uncontrollable
factors is a pass through in the next year’s ARR
 Controllable Factors:
◦ In case of gain, one third is passed onto consumers and
the remaining to be utilised at the discretion of the utility
◦ In case of loss, one third of the loss may be passed on
as additional charge over tariffs and balance absorbed
by the utility
 In accordance with the GERC (Conduct of
Business Regulations) 2004
 GERC can suo moto or on basis of a petition
determine the tariff including terms and conditions
thereof
 Existing arrangements would continue but these
arrangements would be converted to PPAs to be
approved by ERC
 PPAs must be signed with new generating
stations
 Where Discom has own generation, transfer price
shall be determined by ERC
 Process as specified in the regualtion
◦ Filing of tariff
◦ Notification in papers
◦ Call for objections
◦ Public Hearing
◦ Tariff Order
◦ Process of judicial review – APTEL/ Supreme Court
 Govt has to pay in advance the amount to
compensate the DISCOM/ affected party
 No such direction of state govt would be operative
if payment is not made in advance
 Debt equity ratio is 70:30
 Where equity is more than 30 the amount of equity for
the purpose of tariff shall be 30% and the balance
considered a loan
 When equity is less than 30%, actual equity is
considered
 In case of retirement or replacement of assets, the
equity capital approved as mentioned above, shall be
reduced to the extent of 30% (or actual if less than 30)
of the original cost of the retired or replaced asset
 Capital cost is expenditure incurred or projected to be
incurred including
◦ Interest during construction and financing charges
◦ Forex variations on the loan during construction upto
commercial operation of project
◦ Capitalized initial spares subject to ceiling rates
 Capital expenditure will undergo a prudency check by
ERC
 Replacement of assets, R&M, extension of life will be
treated as follows:
◦ Net value of replaced assets = OCFA – AD – CC where
 OCFA – Original capital cost of replaced assets
 AD – accumulated depreciation pertaining to replaced assets
 CC – Total consumer contribution pertaining to the replaced asset
 The capital cost may include capitalised initial
spares:
◦ upto 2.5% of original capital cost in case of coal
based/lignite fired generating stations;
◦ upto 4.0% of original capital cost in case of gas
turbine/combined cycle generating stations;
◦ upto 1.5% of original capital cost in case of hydro-
generating stations; and
◦ upto 1.5% of original capital cost in case of Transmission
Licensee and Distribution Licensee.
 Additional capitalisation is allowed on account of:
 Un discharged liabilities within the original scope of work;
 On works within the original scope of work, deferred for execution
 To meet award of arbitration and compliance of final and
unappealable order or decree of a court arising out of original
scope of works;
 On account of change in law;
 On procurement of initial spares included in the original project
costs subject to the ceiling norm laid down in Regulation 35.6;
 Any additional works/services, which have become necessary for
efficient and successful operation of a generating station or a
transmission system or a distribution system but not included in the
original capital cost:
 Provided that original scope of work is submitted in the
Business Line
 Works after obtaining a part or all of the funds
from the users in the context of deposit works;
 Capital works undertaken by utilising grants
received from the State and Central Governments,
including funds under RGGVY, APDRP, etc;
 Any other grant of similar nature and such amount
received without any obligation to return the same
and with no interest costs attached to such
subvention
 Return on equity shall be computed on the paid up equity capital - the rate of 14%
for Generating Companies, including hydro generation stations above 25 MW,
Transmission Licensee, and Distribution Licensee:
 Provided that for Genco, Tranco, and Discoms, ROE shall be allowed on the
amount of allowed equity capital for the assets put to use at the commencement of
each financial year and on 50% of equity capital portion of the allowable capital cost
for the investments put to use during the financial year:
 For the purpose of truing up for the utilites, ROE shall be allowed on pro-rata basis
based on documentary evidence provided for the assets put to use during the year.
 The premium raised by the utilities while issuing share capital and investment of
internal resources created out of free reserve, if any, shall also be reckoned as paid
up capital for the purpose of computing return on equity, provided such premium
amount and internal resources are actually utilised for meeting capital expenditure.
 Equity invested in foreign currency shall be converted to rupee currency based on
the exchange rate prevailing on the date(s) it is subscribed.
 The loans arrived at shall be considered as gross normative
loan for calculation of interest on loan:
 Provided that interest and finance charges on capital works
in progress shall be excluded:
 Provided further that in case of retirement or replacement of
assets, the loan capital approved as mentioned above, shall
be reduced to the extent of outstanding loan component of
the original cost of the retired or replaced assets, based on
documentary evidence.
 The repayment for the year during the tariff period from FY
2011-12 to FY 2015-16 shall be deemed to be equal to the
depreciation allowed for that year.
 The rate of interest shall be the weighted average rate of interest calculated on
the basis of the actual loan portfolio at the beginning of each year applicable to
the Generating Company or the Transmission Licensee or the Distribution
Licensee:
 Provided that if there is no actual loan for a particular year but normative loan
is still outstanding, the last available weighted average rate of interest shall be
considered:
 The above interest computation shall exclude interest on loan amount,
normative or otherwise, to the extent of capital cost funded by Consumer
Contribution, Grants or Deposit Works carried out by Transmission Licensee
or Distribution Licensee or Generating Company, as the case may be.
 The utilities shall make every effort to re-finance the loan as long as it results
in net savings on interest and in that event the costs associated with such re-
financing shall be borne by the beneficiaries and the net savings shall be shared
between the beneficiaries and the utilities in the ratio of 2:1.
 Interest shall be allowed on the amount held as security deposit held in cash
from Transmission System Users, Distribution System Users and Retail
consumers at the Bank Rate as on 1stApril of the financial year in which the
Petition is filed
 The approved original cost of the project/fixed assets shall be the value
base for calculation of depreciation;
 Depreciation shall be computed annually based on the straight line
method at the rates specified by ERC
 The remaining depreciable value as on 31st March of the year closing
after a period of 12 years from date of commercial operation shall be
spread over the balance useful life of the assets:
 Specifies that the utilities formed as part of transfer scheme shall be
charged as per rates specified in these Regulations for a period of 12
years from the date of the Transfer Scheme, and thereafter depreciation
will be spread over the balance useful life of the assets:
 The salvage value of the asset shall be considered at 10 per cent of the
allowable capital cost and depreciation shall be allowed upto a
maximum of 90 per cent of the allowable capital cost of the asset:
 Provided that in the case of hydro generating station, the salvage value shall be
as provided in the agreement, if any, signed by the developers with the State
Government.
 Land other than the land held under lease and the land for reservoir in case of
hydro generating station shall not be a depreciable asset and its cost shall be
excluded from the capital cost while computing depreciable value of the asset.
 In case of the existing projects, the balance depreciable value as on April 1,
2011, shall be worked out by deducting the cumulative depreciation as
admitted by the Commission upto March 31, 2011, from the gross value of the
assets.
 In case of projected commercial operation of the asset for part of the year,
depreciation shall be calculated based on the average of opening and closing
value of asset, approved by the Commission:
 Provided that depreciation will be re-calculated during truing-up for assets
capitalised at the time of Truing Up of each year of the Control Period, based
on documentary evidence of asset capitalised by the applicant, subject to the
prudence check of the Commission, such that the depreciation is calculated
proportionately from the date of capitalisation.
 Working capital is defined separately for:
◦ Generation
 Coal/ lignite/ oil fired plants
 Gas Turbine/ combined cycle plants
 Hydro plants
 Transmission
 Distribution Wires Business
 Retail Supply Business
 Interest on working capital shall be allowed at a rate
equal to the State Bank Advance Rate (SBAR) as on
1stApril of the financial year in which the Petition is
filed.
Working capital shall shall cover:
 Cost of coal or lignite for one (1) month for pit-head generating stations and
one and a half (1½) months for non-pit-head generating stations, corresponding
to target availability; plus
 Cost of oil for one (1) month corresponding to target availability; plus
 Cost of secondary fuel oil for two (2) months corresponding to target
availability; plus
 Operation and Maintenance expenses for one (1) month; plus
 Maintenance spares at one (1) per cent of the historical cost escalated at 6%
from the date of commercial operation; plus
 Receivables for sale of electricity equivalent to one (1) month of the sum of
annual fixed charges and energy charges calculated on target availability:
 In case of own generating stations, no amount shall be allowed towards
receivables, to the extent of supply of power by the Generation Business to the
Retail Supply Business
 Fuel cost for one (1) month corresponding to target availability factor,
duly taking into account the mode of operation of the generating
station on gas fuel and /or liquid fuel; plus
 Liquid fuel stock for fifteen (15) days corresponding to target
availability; plus
 Operation and maintenance expenses for one (1) month; plus
 Maintenance spares at one (1) per cent of the historical cost escalated
at 6% from the date of commercial operation; plus
 Receivables equivalent to one (1) month of capacity charge and energy
charge for sale of electricity equivalent calculated on normative plant
availability factor, duly taking into account mode of operation of the
generating station on gas fuel and liquid fuel:
 In case of own generating stations, no amount shall be allowed towards
receivables, to the extent of supply of power by the Generation
Business to the Retail Supply Business
 Operation and maintenance expenses for one (1)
month;
 Maintenance spares at one (1) per cent of the historical
cost escalated at 6% from the date of commercial
operation; and
 Receivables equivalent to one (1) month of fixed cost:
 Provided that in case of own generating stations, no
amount shall be allowed towards receivables, to the
extent of supply of power by the Generation Business
to the Retail Supply Business, in the computation of
working capital in accordance with these Regulations.
 Operation and maintenance expenses for one month; plus
 Maintenance spares at one (1) per cent of the historical cost
escalated at 6% from the date of commercial operation; plus
 Receivables equivalent to one (1) month of transmission
charges calculated on target availability level;
 minus
 Amount, if any, held as security deposits except the security
deposits held in the form of Bank Guarantee from
Transmission System Users.
 Operation and maintenance expenses for one month; plus
 Maintenance spares at one (1) per cent of the historical cost
escalated at 6% from the date of commercial operation; plus
 Receivables equivalent to one (1) month of the expected
revenue from charges for use of Distribution Wires at the
prevailing tariffs;
 minus
 Amount, if any, held as security deposits under clause (b) of
sub-section (1) of Section 47 of the Act from Distribution
System Users except the security deposits held in the form
of Bank Guarantees.
 Operation and maintenance expenses for one month; plus
 Maintenance spares at one (1) per cent of the historical cost
escalated at 6% from the date of commercial operation; plus
 Receivables equivalent to one (1) month of the expected
revenue from sale of electricity at the prevailing tariffs;
 minus
 Amount held as security deposits under clause (a) and
clause (b) of sub-section (1) of Section 47 of the Act from
consumers except the security deposits held in the form of
Bank Guarantees;
 Tax on income: provisionally allow for the
control period and then actuals after audited
results are available
 Rebate:
 Delayed Payment surcharge:
 Forex Rate Variation: Utilities will be encouraged
to hedge; cost of hedging will be allowed
 Tariffs for Generation, Transmission and
Distribution dealt with in separate session
 Certain specific norms etc as spelt out in GERC
MYT regulations follows:
 Annual Fixed Charge
 Energy (variable charges) for recovery of primary
and secondary fuel cost
 Depreciation;
 Operation & Maintenance Expenses;
 Return on Equity;
 Interest and Finance Charges on Loan Capital;
 Interest on Working Capital;
 minus:
 Non-Tariff Income:
Capital costs as specified in the MYT regulations
 Indicative list of various heads to be considered for Non-Tariff Income
shall be as under:
◦ Income from rent of land or buildings;
◦ Income from sale of scrap;
◦ Income from statutory investments;
◦ Income from sale of Ash/rejected coal;
◦ Interest on delayed or deferred payment on bills;
◦ Interest on advances to suppliers/contractors;
◦ Rental from staff quarters;
◦ Rental from contractors;
◦ Income from hire charges from contactors and others;
◦ Income from advertisements, etc.:
 Provided that the interest earned from investments made out of Return on
Equity corresponding to the regulated business of the Generating Company
shall not be included in Non-Tariff Income.
 Norms are specified for:
◦ Plant Availability – 85% for full fixed cost recovery
◦ Gross station Heat rate – Existing and new stations
◦ Secondary Fuel oil consumption - Existing and new stations
 Coal-based generating stations: 1.00 ml/kWh;
 Lignite-Fired generating stations except stations based on CFBC technology:
2.00 ml/kWh;
 Lignite-Fired generating stations based on CFBC technology: 1.25 ml/kWh;
 Trajectory determined separately for GSECL stations
◦ Auxiliary Energy consumption - Existing and new stations
◦ Transit and Handling losses
◦ O&M expenses
◦ Norms for Hydro stations
◦ Norms specified are ceiling norms
 The target Wires Network Availability for full recovery of Return on
Equity for Wires Business shall be as under:
◦ Rural Areas 90 percent;
◦ Towns and cities 95 percent;
 Provided that the Commission may stipulate a trajectory for achieving
the target Availability for Wires Business of the Distribution licensee
as part of the Order on the Business Plan filed by the Distribution
Licensee
 Provided further that for every 1 percent under-achievement in Wires
Availability vis-a-vis target availability, Rate of Return on Equity shall
be reduced by 0.1%:
 Provided further that for every 1 percent over-achievement in Wires
Availability vis-a-vis target availability, Rate of Return on Equity shall
be increased by 0.1%.
 Components of Tariffs (will be dealt with in ARR
session)
 Amount received as cross subsidy surcharge will
be deducted from ARR
Thank you

Mais conteúdo relacionado

Mais procurados

ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)shyamies11
 
Electricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market DesignElectricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market DesignLeonardo ENERGY
 
Transmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operationsTransmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operationsWriteKraft Dissertations
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)Munira Abubakari
 
Solar PPA Presentation
Solar PPA PresentationSolar PPA Presentation
Solar PPA Presentationmatt_UCI
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
Deviation Settlement Mechanism (DSM)
Deviation Settlement Mechanism (DSM)Deviation Settlement Mechanism (DSM)
Deviation Settlement Mechanism (DSM)Shishir Kumar Pradhan
 
The power purchase agreement (ppa) presentation
The power purchase agreement (ppa) presentationThe power purchase agreement (ppa) presentation
The power purchase agreement (ppa) presentationAudrey Mwala
 
Ancillary Service market
Ancillary Service marketAncillary Service market
Ancillary Service marketIPPAI
 
Captive power Policy
Captive power PolicyCaptive power Policy
Captive power PolicyPRIYANK JAIN
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in Indiamohkab1
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and TechnologyBushveld Energy
 

Mais procurados (20)

IEGC.pptx
IEGC.pptxIEGC.pptx
IEGC.pptx
 
Grid code
Grid codeGrid code
Grid code
 
Open access ppt
Open access pptOpen access ppt
Open access ppt
 
ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)
 
Electricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market DesignElectricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market Design
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Power Markets & Trading in India
Power Markets & Trading in IndiaPower Markets & Trading in India
Power Markets & Trading in India
 
Open access
Open accessOpen access
Open access
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
Transmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operationsTransmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operations
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)POWER PURCHASE AGREEMENTS(PPA)
POWER PURCHASE AGREEMENTS(PPA)
 
Solar PPA Presentation
Solar PPA PresentationSolar PPA Presentation
Solar PPA Presentation
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
Deviation Settlement Mechanism (DSM)
Deviation Settlement Mechanism (DSM)Deviation Settlement Mechanism (DSM)
Deviation Settlement Mechanism (DSM)
 
The power purchase agreement (ppa) presentation
The power purchase agreement (ppa) presentationThe power purchase agreement (ppa) presentation
The power purchase agreement (ppa) presentation
 
Ancillary Service market
Ancillary Service marketAncillary Service market
Ancillary Service market
 
Captive power Policy
Captive power PolicyCaptive power Policy
Captive power Policy
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in India
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and Technology
 

Destaque

Tariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEATariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEAAshish Verma
 
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...Harish Sharma
 
Tariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorTariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorIPPAI
 
Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?IPPAI
 
Ppt on Conflict
Ppt on Conflict Ppt on Conflict
Ppt on Conflict Aman Kumar
 
Nuclear Overview of India
Nuclear Overview of India Nuclear Overview of India
Nuclear Overview of India Aman Kumar
 
MREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market PotentialMREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market PotentialCUSP | Univ of Guelph
 
Mcc tariff models dr harish ahuja
Mcc tariff models dr harish ahujaMcc tariff models dr harish ahuja
Mcc tariff models dr harish ahujamcci175
 
Day-3, Mr. Ajay Kumar contract sanctity case 1 case 2
Day-3, Mr. Ajay Kumar contract sanctity case 1  case 2Day-3, Mr. Ajay Kumar contract sanctity case 1  case 2
Day-3, Mr. Ajay Kumar contract sanctity case 1 case 2IPPAI
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGRAVI PAL SINGH
 
Effect of Primary Fuels on the Availability and Cost of Power in India
Effect of Primary Fuels on the Availability and Cost of Power in IndiaEffect of Primary Fuels on the Availability and Cost of Power in India
Effect of Primary Fuels on the Availability and Cost of Power in IndiaIPPAI
 
Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?IPPAI
 
Financial & operational opportunities for disco ms under uday
Financial & operational opportunities for disco ms under udayFinancial & operational opportunities for disco ms under uday
Financial & operational opportunities for disco ms under udaySakshi Saini
 
Power distribution tariff in india 2016 discom wise and consumer wise compre...
Power distribution tariff in india 2016  discom wise and consumer wise compre...Power distribution tariff in india 2016  discom wise and consumer wise compre...
Power distribution tariff in india 2016 discom wise and consumer wise compre...Sakshi Saini
 
Operational challenges in India's power sector
Operational challenges  in India's power sectorOperational challenges  in India's power sector
Operational challenges in India's power sectorpradhansushil
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reformsPSPCL
 

Destaque (20)

Power tariffs-2014-15
Power tariffs-2014-15Power tariffs-2014-15
Power tariffs-2014-15
 
Tariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEATariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEA
 
Availability based tariff
Availability based tariffAvailability based tariff
Availability based tariff
 
Tarif based comp_bidding
Tarif based comp_biddingTarif based comp_bidding
Tarif based comp_bidding
 
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
 
Tariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorTariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power Sector
 
Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?
 
Ppt on Conflict
Ppt on Conflict Ppt on Conflict
Ppt on Conflict
 
Nuclear Overview of India
Nuclear Overview of India Nuclear Overview of India
Nuclear Overview of India
 
MREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market PotentialMREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market Potential
 
Mcc tariff models dr harish ahuja
Mcc tariff models dr harish ahujaMcc tariff models dr harish ahuja
Mcc tariff models dr harish ahuja
 
Day-3, Mr. Ajay Kumar contract sanctity case 1 case 2
Day-3, Mr. Ajay Kumar contract sanctity case 1  case 2Day-3, Mr. Ajay Kumar contract sanctity case 1  case 2
Day-3, Mr. Ajay Kumar contract sanctity case 1 case 2
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDING
 
Effect of Primary Fuels on the Availability and Cost of Power in India
Effect of Primary Fuels on the Availability and Cost of Power in IndiaEffect of Primary Fuels on the Availability and Cost of Power in India
Effect of Primary Fuels on the Availability and Cost of Power in India
 
Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?
 
Financial & operational opportunities for disco ms under uday
Financial & operational opportunities for disco ms under udayFinancial & operational opportunities for disco ms under uday
Financial & operational opportunities for disco ms under uday
 
Power distribution tariff in india 2016 discom wise and consumer wise compre...
Power distribution tariff in india 2016  discom wise and consumer wise compre...Power distribution tariff in india 2016  discom wise and consumer wise compre...
Power distribution tariff in india 2016 discom wise and consumer wise compre...
 
Operational challenges in India's power sector
Operational challenges  in India's power sectorOperational challenges  in India's power sector
Operational challenges in India's power sector
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reforms
 
Uday Ujjwal
Uday UjjwalUday Ujjwal
Uday Ujjwal
 

Semelhante a Multi year tariffs and regulations

CESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.pptCESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.pptMdSazibMollik
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access MaharashtraJay Ranvir
 
Edison International Business Update - July 2018
Edison International Business Update - July 2018Edison International Business Update - July 2018
Edison International Business Update - July 2018EdisonInternational
 
Edison International Business Update - May 2018
Edison International Business Update - May 2018Edison International Business Update - May 2018
Edison International Business Update - May 2018EdisonInternational
 
Distribution In India for better understanding.pptx
Distribution In India for better understanding.pptxDistribution In India for better understanding.pptx
Distribution In India for better understanding.pptxkarikalcholanmayavan1
 
Electric Ratemaking in Texas
Electric Ratemaking in Texas Electric Ratemaking in Texas
Electric Ratemaking in Texas aectnet
 
PPTTR2024 for public release presentation.pdf
PPTTR2024 for public release presentation.pdfPPTTR2024 for public release presentation.pdf
PPTTR2024 for public release presentation.pdfMukeshKr19
 
Edison International - Business Update November 2016
Edison International - Business Update November 2016Edison International - Business Update November 2016
Edison International - Business Update November 2016EdisonInternational
 
Edison International Business Update
Edison International Business UpdateEdison International Business Update
Edison International Business UpdateEdisonInternational
 
Edison International Business Update - February 2018
Edison International Business Update - February 2018Edison International Business Update - February 2018
Edison International Business Update - February 2018EdisonInternational
 
Edison International October 2017 Business Update
Edison International October 2017 Business UpdateEdison International October 2017 Business Update
Edison International October 2017 Business UpdateEdisonInternational
 
Wis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentationWis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentationwispolitics
 

Semelhante a Multi year tariffs and regulations (20)

Tariff
TariffTariff
Tariff
 
CESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.pptCESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.ppt
 
Rotating.ppt
Rotating.pptRotating.ppt
Rotating.ppt
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access Maharashtra
 
Edison International Business Update - July 2018
Edison International Business Update - July 2018Edison International Business Update - July 2018
Edison International Business Update - July 2018
 
Edison International Business Update - May 2018
Edison International Business Update - May 2018Edison International Business Update - May 2018
Edison International Business Update - May 2018
 
Distribution In India for better understanding.pptx
Distribution In India for better understanding.pptxDistribution In India for better understanding.pptx
Distribution In India for better understanding.pptx
 
Electric Ratemaking in Texas
Electric Ratemaking in Texas Electric Ratemaking in Texas
Electric Ratemaking in Texas
 
PPTTR2024 for public release presentation.pdf
PPTTR2024 for public release presentation.pdfPPTTR2024 for public release presentation.pdf
PPTTR2024 for public release presentation.pdf
 
Edison International - Business Update November 2016
Edison International - Business Update November 2016Edison International - Business Update November 2016
Edison International - Business Update November 2016
 
Edison International Business Update
Edison International Business UpdateEdison International Business Update
Edison International Business Update
 
tester
testertester
tester
 
Edison International Business Update - February 2018
Edison International Business Update - February 2018Edison International Business Update - February 2018
Edison International Business Update - February 2018
 
Edison International October 2017 Business Update
Edison International October 2017 Business UpdateEdison International October 2017 Business Update
Edison International October 2017 Business Update
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Business Update October 2018
Business Update October 2018Business Update October 2018
Business Update October 2018
 
PSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptxPSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptx
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Ppt nep n ntp
Ppt nep n ntpPpt nep n ntp
Ppt nep n ntp
 
Wis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentationWis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentation
 

Último

Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseribangash
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 

Último (20)

Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 

Multi year tariffs and regulations

  • 2.  Incentivise efficiency improvement  Obviate regulatory uncertainty – reduce regulatory risk  Less intrusive and avoids tendency to micro manage  Assists the utility to plan its business
  • 3.  Determine framework for regulating the utilities for a period of time, ◦ Principles of regulation of returns/profits of utilities ◦ Principles of regulating individual cost and revenue elements ◦ Degree of regulation on an on-going basis  Incentivise utilities to become more efficient in operations  Mitigate risks that are external to the utilities  Make the sector financially sound  Introduce efficient tariff design  Separates costs into controllable and uncontrollable components and treats them separately
  • 4.  Section 61 states that the appropriate commissions, for determining the terms and conditions for the determination of tariffs shall be guided by multi-year tariff principles  MYT framework to be adopted for any tariffs from 1 April 2006  The framework should feature a five year control period  The initial control period can be of 3 years for transmission & distribution if deemed necessary on account of data inadequacies and other practical considerations  ERC can state assumptions in first control period and then as more reliable data becomes available, a fresh control period may be started
  • 5.  Where operations are below norms for several years, improvement trajectories may be recognized at “relaxed” levels and not “desired” levels  Suitable benchmarking studies must be conducted to establish “desired” performance standards  Separate studies may be carried out by each utility to assess the capital expenditure necessary to meet minimum service standards
  • 6.  Once revenue requirements are established at the beginning of the control period, the ERC should focus on regulation of outputs and not the input cost elements  Uncontrollable costs should be recovered speedily to ensure that future consumers are not burdened with past costs  Uncontrollable costs would include (but not limited to): ◦ Fuel costs, cost on account of inflation, taxes and cess, variation in power purchase unit costs including on account of hydel thermal mix in case of adverse natural events
  • 7.
  • 8.  Supply of electricity by a Generating Co to a Discom  Intra-state transmission of Electricity  Intra-state wheeling of electricity  Retail supply of electricity ◦ If there are two or more distribution licensees, GERC can prescribe a tariff ceiling or cap  General framework for tariff determination and the Commission reserves a right to vary the parameters and procedures when facts and/or circumstances so warrant
  • 9.  ARR and expected revenue from tariff and charges for Genco, Transmission Licensee, Distribution wires and retail supply business  All the companies would file the MYT petition/ applications separately
  • 10.  The MYT Petition comprises: ◦ Truing up for the year for 2009-10 for which audited results are available under GERC (Terms & Conditions) Regulations and GERC (MYT) Regulations ◦ Annual Performance Review for 2010-11 ◦ Multi-year ARR for the entire control period (2011-12 to 2015-16) with year wise details ◦ Revenue from the sale of power at existing tariffs and charges & projected revenue gap for the first year of the control period ◦ Application for determination of tariff for the first year of the control period
  • 11.  All MYT Applications would be filed along with a Business Plan for the control period  Business Plan shall comprise (but not limited to) in accordance with the guidelines & formats as prescribed by the ERC: ◦ Detailed category wise sales & demand projections ◦ Power procurement plan ◦ Capital investment plan ◦ Financing plan ◦ Physical targets  Capital investment plan shall show on-going projects to be completed in the control period and new projects that will spill beyond the control period  ERC will approve the capital investment plan
  • 12.  Discom will project the power procurement plan based on merit order despatch principles, RPPO, DSM, Energy Efficiency etc.  The Business Plan has to be approved by the ERC
  • 13.  The MYT Application shall necessarily contain the trajectories for the following variables for the control period: ◦ O & M expenses ◦ Target Plant Load Factor ◦ Distribution Losses  The companies may seek a mid-term review of the trajectory at the time of the mid-term review of the Business Plan
  • 14.  From the first year of the Control Period and onward, the Petition will comprise: ◦ Truing up for FY 2010-11 ◦ Revenue from the sale of power at existing tariffs and charges for the ensuing year ◦ Revenue gap for the ensuing year calculated based on ARR approved in the Tariff Order or MYT Order and truing up for the previous year ◦ Application for determination of tariff for the ensuing year
  • 15. ◦ Truing up for previous year ◦ Modification of the ARR for the remaining years of the control period with justification ◦ Revenue from the sale of power at existing tariffs and the changes for the ensuing year ◦ Revenue gap for the ensuring year calculated based on the ARR approved in the MYT Order and Truing up for the previous year ◦ Application for the determination of tariff for the ensuing year
  • 16.  True up is of expenses and revenue during the control period  The approved forecast of ARR and Expected revenue from tariff is compared with the audited performance including pass through of uncontrollable factors  Review of compliance with ERC directives  ERC will then pass an order recording the approved aggregate gain and loss – components of costs related to uncontrollable factors will be pass through  Once ERC notifies the regulations for submission of regulatory accounts, the application for tariff determination and truing up shall be based on the Regulatory Accounts
  • 17.  Costs are categorised as controllable & uncontrollable  Uncontrollable factors include: ◦ Force Majeure events ◦ Change in law/ judicial pronouncements by govts or commission ◦ Fuel price variation ◦ Power purchase in accordance with FPPPA formula ◦ Variation in consumer number or mix or quantities of electricity supplied to consumers/ under open access ◦ Transmission loss ◦ Variation in market interest rate ◦ Taxes & statutory levies ◦ Taxes on income
  • 18.  Variation in capitalization on account of time or cost overruns or inefficiencies in implementation  Variation in interest & financial charges on account of the above  Variation in technical an commercial losses of discoms  Variations in performance parameters  Variations in working capital requirements  Failure to meet performance standards  Variation in labour productivity  Variation in O&M expenses  Variation in wires availability
  • 19.  Uncontrollable Factors: ◦ Aggregate gain or loss on account of uncontrollable factors is a pass through in the next year’s ARR  Controllable Factors: ◦ In case of gain, one third is passed onto consumers and the remaining to be utilised at the discretion of the utility ◦ In case of loss, one third of the loss may be passed on as additional charge over tariffs and balance absorbed by the utility
  • 20.  In accordance with the GERC (Conduct of Business Regulations) 2004  GERC can suo moto or on basis of a petition determine the tariff including terms and conditions thereof
  • 21.  Existing arrangements would continue but these arrangements would be converted to PPAs to be approved by ERC  PPAs must be signed with new generating stations  Where Discom has own generation, transfer price shall be determined by ERC
  • 22.  Process as specified in the regualtion ◦ Filing of tariff ◦ Notification in papers ◦ Call for objections ◦ Public Hearing ◦ Tariff Order ◦ Process of judicial review – APTEL/ Supreme Court
  • 23.  Govt has to pay in advance the amount to compensate the DISCOM/ affected party  No such direction of state govt would be operative if payment is not made in advance
  • 24.  Debt equity ratio is 70:30  Where equity is more than 30 the amount of equity for the purpose of tariff shall be 30% and the balance considered a loan  When equity is less than 30%, actual equity is considered  In case of retirement or replacement of assets, the equity capital approved as mentioned above, shall be reduced to the extent of 30% (or actual if less than 30) of the original cost of the retired or replaced asset
  • 25.  Capital cost is expenditure incurred or projected to be incurred including ◦ Interest during construction and financing charges ◦ Forex variations on the loan during construction upto commercial operation of project ◦ Capitalized initial spares subject to ceiling rates  Capital expenditure will undergo a prudency check by ERC  Replacement of assets, R&M, extension of life will be treated as follows: ◦ Net value of replaced assets = OCFA – AD – CC where  OCFA – Original capital cost of replaced assets  AD – accumulated depreciation pertaining to replaced assets  CC – Total consumer contribution pertaining to the replaced asset
  • 26.  The capital cost may include capitalised initial spares: ◦ upto 2.5% of original capital cost in case of coal based/lignite fired generating stations; ◦ upto 4.0% of original capital cost in case of gas turbine/combined cycle generating stations; ◦ upto 1.5% of original capital cost in case of hydro- generating stations; and ◦ upto 1.5% of original capital cost in case of Transmission Licensee and Distribution Licensee.
  • 27.  Additional capitalisation is allowed on account of:  Un discharged liabilities within the original scope of work;  On works within the original scope of work, deferred for execution  To meet award of arbitration and compliance of final and unappealable order or decree of a court arising out of original scope of works;  On account of change in law;  On procurement of initial spares included in the original project costs subject to the ceiling norm laid down in Regulation 35.6;  Any additional works/services, which have become necessary for efficient and successful operation of a generating station or a transmission system or a distribution system but not included in the original capital cost:  Provided that original scope of work is submitted in the Business Line
  • 28.  Works after obtaining a part or all of the funds from the users in the context of deposit works;  Capital works undertaken by utilising grants received from the State and Central Governments, including funds under RGGVY, APDRP, etc;  Any other grant of similar nature and such amount received without any obligation to return the same and with no interest costs attached to such subvention
  • 29.  Return on equity shall be computed on the paid up equity capital - the rate of 14% for Generating Companies, including hydro generation stations above 25 MW, Transmission Licensee, and Distribution Licensee:  Provided that for Genco, Tranco, and Discoms, ROE shall be allowed on the amount of allowed equity capital for the assets put to use at the commencement of each financial year and on 50% of equity capital portion of the allowable capital cost for the investments put to use during the financial year:  For the purpose of truing up for the utilites, ROE shall be allowed on pro-rata basis based on documentary evidence provided for the assets put to use during the year.  The premium raised by the utilities while issuing share capital and investment of internal resources created out of free reserve, if any, shall also be reckoned as paid up capital for the purpose of computing return on equity, provided such premium amount and internal resources are actually utilised for meeting capital expenditure.  Equity invested in foreign currency shall be converted to rupee currency based on the exchange rate prevailing on the date(s) it is subscribed.
  • 30.  The loans arrived at shall be considered as gross normative loan for calculation of interest on loan:  Provided that interest and finance charges on capital works in progress shall be excluded:  Provided further that in case of retirement or replacement of assets, the loan capital approved as mentioned above, shall be reduced to the extent of outstanding loan component of the original cost of the retired or replaced assets, based on documentary evidence.  The repayment for the year during the tariff period from FY 2011-12 to FY 2015-16 shall be deemed to be equal to the depreciation allowed for that year.
  • 31.  The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio at the beginning of each year applicable to the Generating Company or the Transmission Licensee or the Distribution Licensee:  Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered:  The above interest computation shall exclude interest on loan amount, normative or otherwise, to the extent of capital cost funded by Consumer Contribution, Grants or Deposit Works carried out by Transmission Licensee or Distribution Licensee or Generating Company, as the case may be.  The utilities shall make every effort to re-finance the loan as long as it results in net savings on interest and in that event the costs associated with such re- financing shall be borne by the beneficiaries and the net savings shall be shared between the beneficiaries and the utilities in the ratio of 2:1.  Interest shall be allowed on the amount held as security deposit held in cash from Transmission System Users, Distribution System Users and Retail consumers at the Bank Rate as on 1stApril of the financial year in which the Petition is filed
  • 32.  The approved original cost of the project/fixed assets shall be the value base for calculation of depreciation;  Depreciation shall be computed annually based on the straight line method at the rates specified by ERC  The remaining depreciable value as on 31st March of the year closing after a period of 12 years from date of commercial operation shall be spread over the balance useful life of the assets:  Specifies that the utilities formed as part of transfer scheme shall be charged as per rates specified in these Regulations for a period of 12 years from the date of the Transfer Scheme, and thereafter depreciation will be spread over the balance useful life of the assets:  The salvage value of the asset shall be considered at 10 per cent of the allowable capital cost and depreciation shall be allowed upto a maximum of 90 per cent of the allowable capital cost of the asset:
  • 33.  Provided that in the case of hydro generating station, the salvage value shall be as provided in the agreement, if any, signed by the developers with the State Government.  Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall be excluded from the capital cost while computing depreciable value of the asset.  In case of the existing projects, the balance depreciable value as on April 1, 2011, shall be worked out by deducting the cumulative depreciation as admitted by the Commission upto March 31, 2011, from the gross value of the assets.  In case of projected commercial operation of the asset for part of the year, depreciation shall be calculated based on the average of opening and closing value of asset, approved by the Commission:  Provided that depreciation will be re-calculated during truing-up for assets capitalised at the time of Truing Up of each year of the Control Period, based on documentary evidence of asset capitalised by the applicant, subject to the prudence check of the Commission, such that the depreciation is calculated proportionately from the date of capitalisation.
  • 34.  Working capital is defined separately for: ◦ Generation  Coal/ lignite/ oil fired plants  Gas Turbine/ combined cycle plants  Hydro plants  Transmission  Distribution Wires Business  Retail Supply Business  Interest on working capital shall be allowed at a rate equal to the State Bank Advance Rate (SBAR) as on 1stApril of the financial year in which the Petition is filed.
  • 35. Working capital shall shall cover:  Cost of coal or lignite for one (1) month for pit-head generating stations and one and a half (1½) months for non-pit-head generating stations, corresponding to target availability; plus  Cost of oil for one (1) month corresponding to target availability; plus  Cost of secondary fuel oil for two (2) months corresponding to target availability; plus  Operation and Maintenance expenses for one (1) month; plus  Maintenance spares at one (1) per cent of the historical cost escalated at 6% from the date of commercial operation; plus  Receivables for sale of electricity equivalent to one (1) month of the sum of annual fixed charges and energy charges calculated on target availability:  In case of own generating stations, no amount shall be allowed towards receivables, to the extent of supply of power by the Generation Business to the Retail Supply Business
  • 36.  Fuel cost for one (1) month corresponding to target availability factor, duly taking into account the mode of operation of the generating station on gas fuel and /or liquid fuel; plus  Liquid fuel stock for fifteen (15) days corresponding to target availability; plus  Operation and maintenance expenses for one (1) month; plus  Maintenance spares at one (1) per cent of the historical cost escalated at 6% from the date of commercial operation; plus  Receivables equivalent to one (1) month of capacity charge and energy charge for sale of electricity equivalent calculated on normative plant availability factor, duly taking into account mode of operation of the generating station on gas fuel and liquid fuel:  In case of own generating stations, no amount shall be allowed towards receivables, to the extent of supply of power by the Generation Business to the Retail Supply Business
  • 37.  Operation and maintenance expenses for one (1) month;  Maintenance spares at one (1) per cent of the historical cost escalated at 6% from the date of commercial operation; and  Receivables equivalent to one (1) month of fixed cost:  Provided that in case of own generating stations, no amount shall be allowed towards receivables, to the extent of supply of power by the Generation Business to the Retail Supply Business, in the computation of working capital in accordance with these Regulations.
  • 38.  Operation and maintenance expenses for one month; plus  Maintenance spares at one (1) per cent of the historical cost escalated at 6% from the date of commercial operation; plus  Receivables equivalent to one (1) month of transmission charges calculated on target availability level;  minus  Amount, if any, held as security deposits except the security deposits held in the form of Bank Guarantee from Transmission System Users.
  • 39.  Operation and maintenance expenses for one month; plus  Maintenance spares at one (1) per cent of the historical cost escalated at 6% from the date of commercial operation; plus  Receivables equivalent to one (1) month of the expected revenue from charges for use of Distribution Wires at the prevailing tariffs;  minus  Amount, if any, held as security deposits under clause (b) of sub-section (1) of Section 47 of the Act from Distribution System Users except the security deposits held in the form of Bank Guarantees.
  • 40.  Operation and maintenance expenses for one month; plus  Maintenance spares at one (1) per cent of the historical cost escalated at 6% from the date of commercial operation; plus  Receivables equivalent to one (1) month of the expected revenue from sale of electricity at the prevailing tariffs;  minus  Amount held as security deposits under clause (a) and clause (b) of sub-section (1) of Section 47 of the Act from consumers except the security deposits held in the form of Bank Guarantees;
  • 41.  Tax on income: provisionally allow for the control period and then actuals after audited results are available  Rebate:  Delayed Payment surcharge:  Forex Rate Variation: Utilities will be encouraged to hedge; cost of hedging will be allowed
  • 42.
  • 43.  Tariffs for Generation, Transmission and Distribution dealt with in separate session  Certain specific norms etc as spelt out in GERC MYT regulations follows:
  • 44.  Annual Fixed Charge  Energy (variable charges) for recovery of primary and secondary fuel cost
  • 45.  Depreciation;  Operation & Maintenance Expenses;  Return on Equity;  Interest and Finance Charges on Loan Capital;  Interest on Working Capital;  minus:  Non-Tariff Income: Capital costs as specified in the MYT regulations
  • 46.  Indicative list of various heads to be considered for Non-Tariff Income shall be as under: ◦ Income from rent of land or buildings; ◦ Income from sale of scrap; ◦ Income from statutory investments; ◦ Income from sale of Ash/rejected coal; ◦ Interest on delayed or deferred payment on bills; ◦ Interest on advances to suppliers/contractors; ◦ Rental from staff quarters; ◦ Rental from contractors; ◦ Income from hire charges from contactors and others; ◦ Income from advertisements, etc.:  Provided that the interest earned from investments made out of Return on Equity corresponding to the regulated business of the Generating Company shall not be included in Non-Tariff Income.
  • 47.  Norms are specified for: ◦ Plant Availability – 85% for full fixed cost recovery ◦ Gross station Heat rate – Existing and new stations ◦ Secondary Fuel oil consumption - Existing and new stations  Coal-based generating stations: 1.00 ml/kWh;  Lignite-Fired generating stations except stations based on CFBC technology: 2.00 ml/kWh;  Lignite-Fired generating stations based on CFBC technology: 1.25 ml/kWh;  Trajectory determined separately for GSECL stations ◦ Auxiliary Energy consumption - Existing and new stations ◦ Transit and Handling losses ◦ O&M expenses ◦ Norms for Hydro stations ◦ Norms specified are ceiling norms
  • 48.  The target Wires Network Availability for full recovery of Return on Equity for Wires Business shall be as under: ◦ Rural Areas 90 percent; ◦ Towns and cities 95 percent;  Provided that the Commission may stipulate a trajectory for achieving the target Availability for Wires Business of the Distribution licensee as part of the Order on the Business Plan filed by the Distribution Licensee  Provided further that for every 1 percent under-achievement in Wires Availability vis-a-vis target availability, Rate of Return on Equity shall be reduced by 0.1%:  Provided further that for every 1 percent over-achievement in Wires Availability vis-a-vis target availability, Rate of Return on Equity shall be increased by 0.1%.
  • 49.  Components of Tariffs (will be dealt with in ARR session)  Amount received as cross subsidy surcharge will be deducted from ARR