SlideShare uma empresa Scribd logo
1 de 18
INTRODUCTION
  •   Almost all deep excavations are now associated with the removal of
      subsoil water for laying foundations of structures or underground
      construction. Most of the structures have deep foundations involving
      a substantial dewatering job. The overall land area around the world
      remaining constant, the development arrow has begun to point
      vertically upwards. Horizontal expansion has given way to
      vertical expansion. As a result, the importance of using dewatering
      equipment              has            increased            manifold.

  •   In many projects, dewatering of foundations plays the key role in
      deciding the overall completion period. Till the time the dewatering
      equipment is successfully installed and foundations come up,
      uncertainty prevails over the commissioning date of a project.
      completion schedule suffers a setback. Thus, it is very important to
      assess the quantum of dewatering work involved; choose the right
      dewatering equipment; and keep standby arrangements in place.
WELL POINT DEWATERING
      A method for draining permeable deposits around an
     excavation that requires small cones of depression. Tubes
     about 100 mm in diameter, with wire mesh screens, are
     sunk into the ground and connected by a header pipe to a
     suction pump at the top. Usually a series of well-points are
     connected to one header pipe. When these are used in a
     staged excavation a considerable depth can be drained and
     the drawdown restricted, because each well-point acts as a
     hydrogeologic boundary.
WELL POINT DEWATERING
   •
WELL POINT DEWATERING




               PICTURES     SHOWING
                WELL POINT
AREA OF APPLICATION
   1. Hydro projects
   2. Excavation of foundations for buildings
   3. Basement construction
   4. Laying of deep sewer lines
   5. Tunnel work
   6. Construction of subways
   7. Water supply projects
   8. Land reclamation projects
   9. Canal construction
   10.Thermal power project structures with not too deep foundations
       Underground tank construction
   11. Bridge construction
PRELIMANARY REQUIREMENTS
   •      Dimensional plan of area of excavation should be prepared.
       Proposed depth of foundation should be known and lowest depth of
       excavation should be ascertained.
   •      Geo-technical investigation data should be collected and position
       of subsoil water should be known.
   •       If river or stream is running in the vicinity of the site to be
       dewatered, its distance, discharge, direction and high flood level
       (HFL) should be known.
   •      Characteristics and type of soil to be dewatered should be
       ascertained. Thickness of various strata should be known.
   •      Permeability of porous strata should be determined. Coefficient of
       permeability may vary from 1 cm per second for very fine sands to even
       3,000 cm per second for gravel and coarse sands.
   •      Chemical properties of groundwater may be determined only if
       dewatering equipment has to remain in position for a considerably
       long period.
MULTI-STAGE WELL POINT SYSTEM
   •   Well-point system is suitable for depths up to 6 m if the
       pump is installed at ground level. Soils have to be coarser.
       If the sand content of soil is more than 20 per cent, the
       well-point system can work in it. For excavations deeper
       than 6 m, multi-staged dewatering equipment can be
       used. In this case, each stage has its own pump. Number of
       stages can vary but more than three stages of well points
       don't seem practical. More the number of stages, more is
       the excavation width required. Sometimes, a single-stage
       well-point system is attached with jet-eductor pump - this
       system allows dewatering up to 25 to 30 m depth. This is
       preferable over a multi-stage well-point system. In case of
       a multi-stage well-point system, care should be taken that
       the header of the lowermost stage is not more than 4 m
       above the excavation bed so that vacuum in the lines is not
       affected.
MULTI-STAGE WELL POINT SYSTEM
   •
EDUCTOR SYSTEM
       The eductor system is generally used in areas with soils of low
     permeability and to avoid using a multi-stage well-point system. In
     comparison to deep wells, it proves cost-effective too. It is well suited
     for deep excavations with stratified soils. The number of eductors in
     one system activated by a single pump is around 100. The volume of
     water pumped out by this system is normally low, in the range of 15 to
     20 litre per second. Under the system, a series of eductor wells are
     installed and connected to two parallel headers. One header is a high
     pressure water supply line and other is a low pressure return line. Both
     lines run to a central pumping station that feeds water under pressure
     to eductors located at the bottom of the wells. The system uses a
     venturi to draw groundwater into the screen of the well and further to
     the ground surface.
       While a large diameter pipe forms the well casing, a smaller
     diameter inner pipe forms the return line. Water is pumped under
     high pressure between the two pipes and forced through the venturi.
     The ground water is now recovered through the well and into the
     return pipe.
SYSTEM DETAILS
   •   Well points are about 1-m-deep slotted pipes carrying brass
       mesh screens over them. These act as filters or strainers and
       thus throw out only clear water. The diameter of well points is
       only 2 to 3 inch. Each well-point has a self-jetting nozzle at the
       bottom to help it drive into the ground to the desired depth.
       Sometimes, it takes minutes to sink the well points to the
       desired depth. Vertical riser pipes connected to the well points
       are of 2 to 2 ½ inch diameter. These are connected to the
       horizontal header with flexible swing joints. The header pipe
       has plug cocks to receive the flexible connections. These
       connections are equipped with non-return valves. The
       horizontal pipe connected to the vertical pipes is of 6 inch to 1 ft
       diameter. In certain cases, it may be of larger diameter. One
       well-point system has 50 to 60 well points. All the points and
       pipe system are connected to the pump. A 6 inch diameter
       header pipe provides a flow of 30 litre per second; a 8 inch
       diameter header gives 60 litre per second; a 10 inch diameter
       header gives 110 litre per second; and a 12 inch diameter header
       draws up to 190 litre per second.
WELL POINT PUPMS-1
   • The dewatering pumps are centrifugal pumps driven
     by electricity or diesel. The pumps are able to produce
     a high vacuum and have good air handling capacity.
     For this, self priming centrifugal pumps are attached
     with vacuum pumps. A diesel set is kept as a standby
     in case of power failure. A float- actuated air water
     separator tank is provided with the pump. A vacuum
     pump throws out the air separated by the separator
     from the water being removed. The location of the
     pump in the header line is governed by the fact that
     the pump is able to develop the required vacuum in
     the pipeline.
WELL POINT PUPMS-2
   • If the header pipeline is too long, i.e. more than 150
     m, the pump may have to be located at its centre. If
     the length is smaller, the pump may be located at its
     end. In any case, development of maximum vacuum
     can't be sacrificed. An effort should always be made to
     set the pump intake at the level of the header line. In
     any case, it shouldn't be kept more than 5 m above the
     level of the bottom of the excavation. The pump is
     equipped with a water discharge pipe that leads to a
     drain or basin at a sufficient distance from the
     excavation area to avoid its effect on the dewatering
     exercise.
WELL POINT PUPMS-3
   •    The spacing of well points depends upon the type of soil
       being dewatered. The more the permeability of soil, the
       less the spacing of well points as more discharge is
       required to be removed. Thus, spacing is less in sandy soils
       and more in silt soils. In sandy soils with gravel, spacing
       may be as less as only 1 ft. Generally, the spacing varies
       between 1 to 4 ft. The length of the header pipe and rate of
       discharge also matter in deciding the location and spacing
       of well points. Well-point systems may be in metal (steel
       or aluminium) or PVC. Earlier, metallic pipes, brass
       strainers and MS header pipes were used. Now, more and
       more manufacturers are switching over to PVC because of
       its flexibility, corrosion-proof quality and cost-
       effectiveness. Well-point system in PVC also has the
       advantage of being lightweight and easier to handle.
       Another advantage is low friction losses.
INSTALLATION
   •    Well points are equipped with self jetting tips and require
       water under pressure for self-installation. About 900 litre
       of water are specified in the IS code for each well-point.
       Water pressure has to be up to 14.5 kg per sq cm; if the
       pervious layer is underlain by a clay layer, jetting does not
       prove effective and augering of clay layer is first done. IS
       9759 advises an important safeguard of 'sanding in' of well
       points to avoid clogging of the system by fine materials
       from the ground. Under this process, the water pressure
       for jetting is reduced just to keep the hole around the
       point open, and coarse sand is filled around the annular
       space to act as a supplementary filter. Now, the jetting
       water supply can be safely closed.
MERITS AND DEMERITS
   •    The well-point system has the advantage of getting
       installed along any flexible line or shape. When a large
       area is to be dewatered, well points can be installed
       around the area. For long excavations for pipelines or
       cables, well points can be installed along a line and prove
       quite effective.

   •   In such a case, a continuous exercise of installing new well
       points in the area ahead and taking out well points from
       the area completed is on. Just one header pipe laid along
       the length of excavation connects the well points.
       However, the well-point system is not suitable for very
       deep areas. Excavation width becomes very large.
       Sometimes, air leakage into suction pipes is common and
       this adversely affects dewatering efficiency.
PLAYING SAFE
    Before beginning the dewatering operation, the well-point system
     should be checked to ensure it is leak-proof. All leakages, however
     minor, should be plugged by use of adhesives or paints available for
     the purpose. Always provide each well-point with a stop cock so that
     each individual well-point can be connected to or disconnected from
     the network. See that all vertical risers run full and air leakage is not
     allowed.
    Keep all the joints in the system airtight. Try to restrict the number of
     well points connected to a pumping unit to 50, maximum 60. Provide
     a solid base to the pump. See that the area of installation doesn't
     become slushy. Keep an eye on the vacuum gauge fitted to the pump.
     If any fluctuations are noted, these are an indication of trouble from
     well points. Discharge from well points may reduce in this case. This
     problem should be corrected by adjusting the plug cocks and
     checking the vacuum pump outlet.
    Always provide each well-point with a stop cock so that it can be
     connected or disconnected from the network.
QUICK BITES
     Deep excavations are associated with removal of subsoil
     water for laying foundations of structures.
    To complete the projects on time, it is very important to
     assess the quantum of dewatering work involved.
    Two types of dewatering equipment are used -
     well-point equipment and deep bore well equipment.
     Well-point equipment consists of a number of wells
     installed around the area of excavation.
    Well points are equipped with self jetting tips and require
     water      under      pressure       for    self-installation.
     The well-point system has the advantage of getting
     installed along any flexible line or shape but is not suitable
     for very deep areas.

Mais conteúdo relacionado

Mais procurados

Determination of co efficient of consolidation method
Determination of co efficient of consolidation methodDetermination of co efficient of consolidation method
Determination of co efficient of consolidation method
Parth Joshi
 
1)methods of exploration
1)methods of exploration1)methods of exploration
1)methods of exploration
jagadish108
 

Mais procurados (20)

Grouting
Grouting Grouting
Grouting
 
Slope stability
Slope stabilitySlope stability
Slope stability
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERING
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Embankment
EmbankmentEmbankment
Embankment
 
Subsurface exploration
Subsurface exploration  Subsurface exploration
Subsurface exploration
 
Determination of co efficient of consolidation method
Determination of co efficient of consolidation methodDetermination of co efficient of consolidation method
Determination of co efficient of consolidation method
 
Site investigation
Site investigationSite investigation
Site investigation
 
4. wbm roads 10 sep
4. wbm roads 10 sep4. wbm roads 10 sep
4. wbm roads 10 sep
 
Dynamic Pile Formulae
Dynamic Pile FormulaeDynamic Pile Formulae
Dynamic Pile Formulae
 
1)methods of exploration
1)methods of exploration1)methods of exploration
1)methods of exploration
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Dewatering
DewateringDewatering
Dewatering
 
IS Classification of Soils
IS Classification of SoilsIS Classification of Soils
IS Classification of Soils
 
Types of geosynthetics
Types of geosyntheticsTypes of geosynthetics
Types of geosynthetics
 

Semelhante a Presentation on well point system

Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
PriyaTalwar8
 

Semelhante a Presentation on well point system (20)

dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farming
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
Dewatering
DewateringDewatering
Dewatering
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
 
Drainage
DrainageDrainage
Drainage
 
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
 
Techniques of rain water harvesting in urban and rural areas
Techniques of rain water harvesting in urban and rural areasTechniques of rain water harvesting in urban and rural areas
Techniques of rain water harvesting in urban and rural areas
 
15 drainase bawah permukaan
15   drainase bawah permukaan15   drainase bawah permukaan
15 drainase bawah permukaan
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
 
Subsurface drainage
Subsurface drainageSubsurface drainage
Subsurface drainage
 
GWHMODULE5.pptx
GWHMODULE5.pptxGWHMODULE5.pptx
GWHMODULE5.pptx
 
A presentation on border irrigation system by Mostafijur Rahman
A presentation on border irrigation system by Mostafijur RahmanA presentation on border irrigation system by Mostafijur Rahman
A presentation on border irrigation system by Mostafijur Rahman
 
Tube wells and their design
Tube wells and their designTube wells and their design
Tube wells and their design
 
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSDEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
 
Tube-Wells and their Designs
Tube-Wells and their DesignsTube-Wells and their Designs
Tube-Wells and their Designs
 
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining EngineeringSpecial Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
 
Control of ground water in excavation
Control of ground water in excavation Control of ground water in excavation
Control of ground water in excavation
 

Mais de Anshuman Tyagi (6)

Guidebookforselectingacforlaymen
GuidebookforselectingacforlaymenGuidebookforselectingacforlaymen
Guidebookforselectingacforlaymen
 
Chimney one go
Chimney one goChimney one go
Chimney one go
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
 
Search engines
Search enginesSearch engines
Search engines
 
Metro presentation
Metro presentationMetro presentation
Metro presentation
 
Wagon tippler
Wagon tipplerWagon tippler
Wagon tippler
 

Último

Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
vineshkumarsajnani12
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 

Último (20)

SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 

Presentation on well point system

  • 1.
  • 2. INTRODUCTION • Almost all deep excavations are now associated with the removal of subsoil water for laying foundations of structures or underground construction. Most of the structures have deep foundations involving a substantial dewatering job. The overall land area around the world remaining constant, the development arrow has begun to point vertically upwards. Horizontal expansion has given way to vertical expansion. As a result, the importance of using dewatering equipment has increased manifold. • In many projects, dewatering of foundations plays the key role in deciding the overall completion period. Till the time the dewatering equipment is successfully installed and foundations come up, uncertainty prevails over the commissioning date of a project. completion schedule suffers a setback. Thus, it is very important to assess the quantum of dewatering work involved; choose the right dewatering equipment; and keep standby arrangements in place.
  • 3. WELL POINT DEWATERING A method for draining permeable deposits around an excavation that requires small cones of depression. Tubes about 100 mm in diameter, with wire mesh screens, are sunk into the ground and connected by a header pipe to a suction pump at the top. Usually a series of well-points are connected to one header pipe. When these are used in a staged excavation a considerable depth can be drained and the drawdown restricted, because each well-point acts as a hydrogeologic boundary.
  • 5. WELL POINT DEWATERING  PICTURES SHOWING WELL POINT
  • 6. AREA OF APPLICATION 1. Hydro projects 2. Excavation of foundations for buildings 3. Basement construction 4. Laying of deep sewer lines 5. Tunnel work 6. Construction of subways 7. Water supply projects 8. Land reclamation projects 9. Canal construction 10.Thermal power project structures with not too deep foundations Underground tank construction 11. Bridge construction
  • 7. PRELIMANARY REQUIREMENTS • Dimensional plan of area of excavation should be prepared. Proposed depth of foundation should be known and lowest depth of excavation should be ascertained. • Geo-technical investigation data should be collected and position of subsoil water should be known. • If river or stream is running in the vicinity of the site to be dewatered, its distance, discharge, direction and high flood level (HFL) should be known. • Characteristics and type of soil to be dewatered should be ascertained. Thickness of various strata should be known. • Permeability of porous strata should be determined. Coefficient of permeability may vary from 1 cm per second for very fine sands to even 3,000 cm per second for gravel and coarse sands. • Chemical properties of groundwater may be determined only if dewatering equipment has to remain in position for a considerably long period.
  • 8. MULTI-STAGE WELL POINT SYSTEM • Well-point system is suitable for depths up to 6 m if the pump is installed at ground level. Soils have to be coarser. If the sand content of soil is more than 20 per cent, the well-point system can work in it. For excavations deeper than 6 m, multi-staged dewatering equipment can be used. In this case, each stage has its own pump. Number of stages can vary but more than three stages of well points don't seem practical. More the number of stages, more is the excavation width required. Sometimes, a single-stage well-point system is attached with jet-eductor pump - this system allows dewatering up to 25 to 30 m depth. This is preferable over a multi-stage well-point system. In case of a multi-stage well-point system, care should be taken that the header of the lowermost stage is not more than 4 m above the excavation bed so that vacuum in the lines is not affected.
  • 10. EDUCTOR SYSTEM  The eductor system is generally used in areas with soils of low permeability and to avoid using a multi-stage well-point system. In comparison to deep wells, it proves cost-effective too. It is well suited for deep excavations with stratified soils. The number of eductors in one system activated by a single pump is around 100. The volume of water pumped out by this system is normally low, in the range of 15 to 20 litre per second. Under the system, a series of eductor wells are installed and connected to two parallel headers. One header is a high pressure water supply line and other is a low pressure return line. Both lines run to a central pumping station that feeds water under pressure to eductors located at the bottom of the wells. The system uses a venturi to draw groundwater into the screen of the well and further to the ground surface.  While a large diameter pipe forms the well casing, a smaller diameter inner pipe forms the return line. Water is pumped under high pressure between the two pipes and forced through the venturi. The ground water is now recovered through the well and into the return pipe.
  • 11. SYSTEM DETAILS • Well points are about 1-m-deep slotted pipes carrying brass mesh screens over them. These act as filters or strainers and thus throw out only clear water. The diameter of well points is only 2 to 3 inch. Each well-point has a self-jetting nozzle at the bottom to help it drive into the ground to the desired depth. Sometimes, it takes minutes to sink the well points to the desired depth. Vertical riser pipes connected to the well points are of 2 to 2 ½ inch diameter. These are connected to the horizontal header with flexible swing joints. The header pipe has plug cocks to receive the flexible connections. These connections are equipped with non-return valves. The horizontal pipe connected to the vertical pipes is of 6 inch to 1 ft diameter. In certain cases, it may be of larger diameter. One well-point system has 50 to 60 well points. All the points and pipe system are connected to the pump. A 6 inch diameter header pipe provides a flow of 30 litre per second; a 8 inch diameter header gives 60 litre per second; a 10 inch diameter header gives 110 litre per second; and a 12 inch diameter header draws up to 190 litre per second.
  • 12. WELL POINT PUPMS-1 • The dewatering pumps are centrifugal pumps driven by electricity or diesel. The pumps are able to produce a high vacuum and have good air handling capacity. For this, self priming centrifugal pumps are attached with vacuum pumps. A diesel set is kept as a standby in case of power failure. A float- actuated air water separator tank is provided with the pump. A vacuum pump throws out the air separated by the separator from the water being removed. The location of the pump in the header line is governed by the fact that the pump is able to develop the required vacuum in the pipeline.
  • 13. WELL POINT PUPMS-2 • If the header pipeline is too long, i.e. more than 150 m, the pump may have to be located at its centre. If the length is smaller, the pump may be located at its end. In any case, development of maximum vacuum can't be sacrificed. An effort should always be made to set the pump intake at the level of the header line. In any case, it shouldn't be kept more than 5 m above the level of the bottom of the excavation. The pump is equipped with a water discharge pipe that leads to a drain or basin at a sufficient distance from the excavation area to avoid its effect on the dewatering exercise.
  • 14. WELL POINT PUPMS-3 • The spacing of well points depends upon the type of soil being dewatered. The more the permeability of soil, the less the spacing of well points as more discharge is required to be removed. Thus, spacing is less in sandy soils and more in silt soils. In sandy soils with gravel, spacing may be as less as only 1 ft. Generally, the spacing varies between 1 to 4 ft. The length of the header pipe and rate of discharge also matter in deciding the location and spacing of well points. Well-point systems may be in metal (steel or aluminium) or PVC. Earlier, metallic pipes, brass strainers and MS header pipes were used. Now, more and more manufacturers are switching over to PVC because of its flexibility, corrosion-proof quality and cost- effectiveness. Well-point system in PVC also has the advantage of being lightweight and easier to handle. Another advantage is low friction losses.
  • 15. INSTALLATION • Well points are equipped with self jetting tips and require water under pressure for self-installation. About 900 litre of water are specified in the IS code for each well-point. Water pressure has to be up to 14.5 kg per sq cm; if the pervious layer is underlain by a clay layer, jetting does not prove effective and augering of clay layer is first done. IS 9759 advises an important safeguard of 'sanding in' of well points to avoid clogging of the system by fine materials from the ground. Under this process, the water pressure for jetting is reduced just to keep the hole around the point open, and coarse sand is filled around the annular space to act as a supplementary filter. Now, the jetting water supply can be safely closed.
  • 16. MERITS AND DEMERITS • The well-point system has the advantage of getting installed along any flexible line or shape. When a large area is to be dewatered, well points can be installed around the area. For long excavations for pipelines or cables, well points can be installed along a line and prove quite effective. • In such a case, a continuous exercise of installing new well points in the area ahead and taking out well points from the area completed is on. Just one header pipe laid along the length of excavation connects the well points. However, the well-point system is not suitable for very deep areas. Excavation width becomes very large. Sometimes, air leakage into suction pipes is common and this adversely affects dewatering efficiency.
  • 17. PLAYING SAFE  Before beginning the dewatering operation, the well-point system should be checked to ensure it is leak-proof. All leakages, however minor, should be plugged by use of adhesives or paints available for the purpose. Always provide each well-point with a stop cock so that each individual well-point can be connected to or disconnected from the network. See that all vertical risers run full and air leakage is not allowed.  Keep all the joints in the system airtight. Try to restrict the number of well points connected to a pumping unit to 50, maximum 60. Provide a solid base to the pump. See that the area of installation doesn't become slushy. Keep an eye on the vacuum gauge fitted to the pump. If any fluctuations are noted, these are an indication of trouble from well points. Discharge from well points may reduce in this case. This problem should be corrected by adjusting the plug cocks and checking the vacuum pump outlet.  Always provide each well-point with a stop cock so that it can be connected or disconnected from the network.
  • 18. QUICK BITES  Deep excavations are associated with removal of subsoil water for laying foundations of structures.  To complete the projects on time, it is very important to assess the quantum of dewatering work involved.  Two types of dewatering equipment are used - well-point equipment and deep bore well equipment. Well-point equipment consists of a number of wells installed around the area of excavation.  Well points are equipped with self jetting tips and require water under pressure for self-installation. The well-point system has the advantage of getting installed along any flexible line or shape but is not suitable for very deep areas.