Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
1 | P a g e
RISK ASSESSMENT PROCEDURE
DISCLAIM ER:
 This document is the sole property of Urban Landscapes, No part of this document shall be re-
created, copied, Referenced or translated without the written prior consent and approval of the
Management Representative.
 This document has been prepared in accordance with the requirements of the OHSAS 18001:2007
standard & QCS 2014
 Where applicable, to be stamped "Controlled" in red color ink, indicating that the document is a
COPY of the MASTER, and is verified and approved by the Management Representative of Urban
Landscapes.
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
2 | P a g e
Document Title RISK ASSESSMENT PROCEDURE
Prepared by
Name Arun Gangadharan
Position HSSE Manager
Date 28/5/2020
Signature
Audited & reviewed by
Name Jodman
Position QA/QC MANAGER
Date 28/5/2020
Signature
Approved by
Name Chadi
Position Managing partner
Date 28/5/2020
Signature
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
3 | P a g e
CONTENTS Pge No.
01 AMENDMENT SHEET 04
02 OBJECTIVE 05
03 SCOPE OF IMPLEMENTATION 05
04 DEFINITIONS 05
05 CROSS REFRENCES 05
06 RESPONSIBILITIES 05
07 PROCESS/ REQUIREMENTS 06
08 RECORDS RETENTION 10
09 DOCUMENT FILING 10
10 FORMS 11
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
4 | P a g e
01. AMENDMENT SHEET
Description of Amendment Issue Rev Date Amended Pages
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
5 | P a g e
02. OBJECTIVE
To identify the hazards associated with all work activities of company and quantification of associated
risk to place best possible operational controls to bring risk at As Low As Reasonably Practicable
(ALARP) level.
The main aim throughout this procedure and guidance is to follow the principles of (Prevention -
Protection- information - Monitoring - Review)
03. SCOPE
To determine measures required for eliminating hazards and reducing the risk for provision safe
workplace.This procedure covers all Landscapes Projects and locations under the control of
Landscapes.
04. DEFINITIONS
4.1 ALARP As Low As Reasonably Practicable
4.2 Company Urban Landscapes
4.3 Contractor The person(s) / firm(s) whose services, supply or product has
been accepted by the company
4.4 Hazard Source, situation or act with a potential for harm in terms of
human injury or ill health or combination of these
4.5 HIRAC Hazard Identification, Risk Assessment and Control
4.6 HSE Health Safety and Environment
4.7 May The use of may indicated – to be considered
4.8 PBG Project Business Group
4.9 PPE Personal Protective Equipment
4.10 Risk Combination of the likelihood and consequence(s) of a specified
hazardous event occurring
4.11 Risk
Assessment
Overall process of estimating the magnitude of risk and deciding
whether or not the risk is tolerable
4.12 Shall The use of ‘Shall’ indicates mandatory requirement
4.13 Tolerable
Risk
The risk that has been reduced to a level that can be endured by
the organization having regard to its legal obligations and its own
HSE Policy
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
6 | P a g e
4.14 Probability The likelihood of a specific outcome, measured by the ratio
of specific outcome to the total number of possible outcomes.
4.15 Severity The outcome of an event or situations expressed qualitatively
or quantitatively, being a loss, injury, disadvantage or gain.
05. REFRENCES
QCS 2014, Section 11Part 2.4.1
06. RESPONSIBILITIES
PROJECT MANAGER
 To ensure that a sufficient resources for carrying out risk assessments are in place and the
risk assessment findings are being applied as part of the hazard control and analysis strategy
 To review the effectiveness of the system to ensure that a safe system of work is in place.
CONSTRUCTIONMANAGERS/ ENGINEER
 To ensure that the requirements of this procedure are known to all employees and understood
by Subcontractors at the kick-off meeting stage or at workplace.
 To provide technical input into the formulation of the risk assessments and shall review prior
to its distribution.
 To supply information relevant to the scope of works.
SUPERVISORS
 To assist in developing work risk assessments.
 To liaise with other disciplines I task supervision to ensure that conflicts of interest are
accommodated.
 To ensure that the requirements identified during the development of the Risk assessment is
adequate in terms of detail and are being effectively communicated to all personnel involved
with the task.
PROJECT HSSE MANAGER/ INCHARGE
 To associate with the Construction Team and ensure that the requirements outlined in this
procedure are understood and are being implemented.
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
7 | P a g e
 To audit the task against the requirements specified to ensure compliance.
 To carry out reviews of risk assessments on a periodic basis. Generally once in a year.
 Review after any incident.
 To train urban landscapes Field personnel in the requirements of the HSSE details in the
risk assessment.
SUBCONTRACTORS
 To coordinate, develop and implement safe systems of work that includes the requirements of
this procedure.
 To ensure that sufficient resources are available to address the requirements of this procedure
competently and efficiently.
 To train their personnel in the requirements of the HSSE details in the risk assessment.
07. PROCESS / REQUIREMENTS
7.1 RISK ASSESSMENT TEAM
Based in project specific job requirement and complexity of operations, Risk assessment team
members shall be selected. Ideally the team members shall consist of various disciples viz: Civil,
Mechanical, Electrical, Process, commissioning, HSE etc.
7.2 TRAINING
Familiarization training shall be conducted on Hazard Identification Risk Assessment and control
prior to start of study.
7.3 RISK ASSESSMENT PROCESS
The following six elements shall be considered during the HIRAC process
 Hazard Identification
 Persons / Environment / Asset / Reputation of Risk
 Evaluation of Risk level
 Risk controls (existing and additional)
 Record of risk assessment findings
 Monitoring and Review
7.3.1 Hazard Identification is performed considering the following consequences
 Personal Injury
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
8 | P a g e
 Asset Damage
 Environmental Impact
 Reputation
7.3.2 The purpose of this study is to identify the hazard, access the risks associated with these
identified hazards and suggest risk reducing measures.
7.3.3 The first step of the HIRAC is to identify the activity of a department for which you want to
access the risk involved.
7.3.4 After selecting the particular work activity list down the sub activities looks to each sub activity
from all perspective to find out both major and minor hazards associated with that activity of
work.
7.3.5 The next step after determining the hazard is to note down all the existing control measures
which are being followed currently. The control measures is of THREE types.
 Engineering Control (ex. Access, Excess)
 Administration Control (ex. Permit to work, supervision)
 Personal Protective Equipment (ex. Full body harness)
7.3.6 Evaluation of Risk: For evaluation of hazard the following criteria can be used.
7.3.6.1 Likelihood: In the below table we have to choose the chances of the occurrence of the
hazards
Assessments can be done either Quantitative or Qualitative:
Quantitative Assessment:
Frequency
of Failure
(F)
Probability (Frequency)
1 Improbable: Less than once in 10years or more
2 Remote: Unlikely to occur during life cycle of the system (once in 6-10 years)
3 Rare: At least once in life cycle system (typically) once in SIX years
4 Reasonably Probable: Several times during life cycle of the system or at least
once in THREE years
5 Frequent: Repeatedly during life cycle of the system or at least once in a year.
Table 1
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
9 | P a g e
7.3.6.2 Possible Consequence (Severity): In the below table the consequence of hazards is to be
noted.
Severity
(C)
People Asset (Amount
in INR)
Environment Reputation
1 Minor injury
illness (first aid)
Ten Thousand Minor spills or
fugitive emission
Individual concern
2 Medical aid
injury
ONE Lakh Controlled
Environment
Release (with in
limit)
Local / community
attention
3 Disabling
injury(s)
TEN Lakh Major sustained
Environmental
release
Provincial attention
4 Single Fatality ONE Crore Some permanent
ecological
damage
Industry wide
attention
5 Multiple
Fatalities
TEN Crore Widespread –
Permanent
ecological
damage
National and
International
attention
Table 2
7.3.6.3 RISK MATRIX
Once each hazard is ranked in terms of likelihood and consequences, it can be plotted on a risk
matrix and associated risk level can be determined.
Consequence levels are determined with reference to loss of people, asset damage, Environment
and reputation.
The risk level defines three areas:
 Low: Either the evaluated risk is negligible or the corresponding system / item are acceptable as
they are.
 Medium: Risk falls in ALARP region and risk control options are then to be proposed and assed
in accordance with safety objectives.
 High: Risk is found unacceptable and corresponding source of risk is to be removed.
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
10 | P a g e
Shown in Below Grid Hazard Ranking Risk Level (r)
Unacceptable High
ALARP Medium
Acceptable Low
Table 3
5
4
3
2
1
1 2 3 4 5
Quatitative assessment.
The principle is the same as for Qualitative assessments, but numerical scores rather than a grade
are assigned to probability and consequences.
The probability or likelihood of the event is rated on a scale of 1 to 5 as follows:
Level 1 Very unlikely to happen
Level 2 Unlikely to happen, but not by any means impossible
Level 3 likely to happen, and would not be totally unexpected.
Level 4 It is very likely to happen, and would not be at all unusual
Level 5 It is certain to happen.
The consequences or the severity of the event, should it happen, are also then rated on a scale
of 1to 5 as follows:
Level 1 No injury. It would be a 'near miss'. Minor property damage.
Consequence
F
R
E
Q
U
E
N
C
Y
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
11 | P a g e
Level 2
Minor injury. Less than three days' work time lost. Property damage more
than just minor likely to happen, and would not be totally unexpected.
Level 3
Reportable injury to the HSE with over three days' time lost, but not a
major injury. Substantial property damage or something causing
environmental damage
Level 4 Major injury, long term absence. Major damage, serious environmental
impact.
Level 5
Fatal accident or multiple major injuries. Public or others could be involved
as well.
All possible resulting numbers are calculated by multiplying all the probability figures by all the
consequence figures. These are included in the matrix, as shown below. This means that once a risk
assessment has been made on a particular activity, and the probability factor is multiplied by the
consequence factor, the number produced indicates where the assessment places the risk associated
with the activity on the matrix.
Clearly, the higher the resulting number, the less acceptable the level of risk. The matrix shows
where actions need to be taken to reduce either the probability or the consequences in order to
reduce the risks to an acceptable level.
Probability
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
Consequences
Risks with a rating above 1 6 are unacceptable and the work will not be undertaken until the risk
has been reduced.
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
12 | P a g e
RECORD YOUR FINDINGS AND IMPLEMENT THEM
Putting the results of your risk assessment into practice will make a difference when looking after
people and your business.
Writing down the results of your risk assessment, and sharing them with your staff, encourages
you to do this. If you have fewer than five employees you do not have to write anything down,
though it is useful so that you can review it at a later date if, for example, something changes.
When writing down your results, keep it simple, for example, 'Tripping over rubbish: bins provided,
staff instructed, weekly housekeeping checks', or 'Fume from welding: local exhaust ventilation used
and regularly checked'.
We do not expect a risk assessment to be perfect, but it must be suitable and sufficient. You need
to be able to show that:
 a proper check was made;
 you asked who might be affected;
 you dealt with all the significant hazards, taking into account the number of people
who could be involved;
 the precautions are reasonable, and the remaining risk is low; and.
 You involved your staff or their representatives in the process.
A good plan of action often includes a mixture of different things such as;
 a few cheap or easy improvements that can be done quickly, perhaps as a temporary
solution until more reliable controls are in place;
 long-term solutions to those risks most likely to cause accidents or ill health;
 long-term solutions to those risks with the worst potential consequences;
 arrangements for training employees on the main risks that remain and how they are to be
controlled;
 regular checks to make sure that the control measures stay in place; and
 Clear responsibilities - who will lead on what action, and by when
Remember, prioritize and tackle the most important things first. As you complete each action,
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
13 | P a g e
tick it off your plan.
Review your risk assessment and update if necessary
Few workplaces stay the same. Sooner or later, you will bring in new equipment, substances and
procedures that could lead to new hazards. It makes sense, therefore, to review what you are doing
on an ongoing basis. Every year or so formally review where you are, to make sure you are still
improving, or at least not sliding back.
Look at your risk assessment again. Have there been any changes? Are there improvements you
still need to make? Have your workers spotted a problem? Have you learnt anything from accidents
or near misses? Make sure your risk assessment stays up to date.
During the year, if there is a significant change, don't wait. Check your risk assessment and,
where necessary, amend it. If possible, it is best to think about the risk assessment when you're
planning your change - that way you leave yourself more flexibility.
08. RECORDS
Records necessary to implement this procedure shall be kept with the HSSE Senior Manager for a
period not less than 3 years.
09. DOCUMENT FILING
The original version of this procedure along with the rest of the procedures shall be maintained
with the HSSE Senior Manager and the procedure shall have a reference number: OHSP- RA –
UL- 001 Rev 00.
10. FORMS
Risk Assessment Form OHSF-RA-UL-RA-01 Rev 00
Risk Assessment INDEX OHSF-RA-UL-RA-02Rev 00
Document Reference OHSP- RA – UL- 001 Rev00.
Revision 00
Issue Date 01 June 2020
14 | P a g e

Mais conteúdo relacionado

Mais procurados

Functional safety certification guide
Functional safety certification guideFunctional safety certification guide
Functional safety certification guideMohammed Majid Khan
 
Layer of protection analysis
Layer of protection analysisLayer of protection analysis
Layer of protection analysisSandip Sonawane
 
Knowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementKnowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementAmr El-Ganainy
 
Lecture 4-_hazard_analysis_prevention_and_safety_management
Lecture  4-_hazard_analysis_prevention_and_safety_managementLecture  4-_hazard_analysis_prevention_and_safety_management
Lecture 4-_hazard_analysis_prevention_and_safety_managementShahbani Laa
 
Applying IEC 62304 Risk Management in Aligned Elements - the medical device ALM
Applying IEC 62304 Risk Management in Aligned Elements - the medical device ALMApplying IEC 62304 Risk Management in Aligned Elements - the medical device ALM
Applying IEC 62304 Risk Management in Aligned Elements - the medical device ALMAligned AG
 
Contingency%20planning%20lecture%205
Contingency%20planning%20lecture%205Contingency%20planning%20lecture%205
Contingency%20planning%20lecture%205Magdalena Anna Fas
 
(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)
(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)
(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)Paul Reese
 
Psm guide 4th edition
Psm guide 4th editionPsm guide 4th edition
Psm guide 4th editionArul Arasu K
 
Ten tips on hazop quality control
Ten tips on hazop quality controlTen tips on hazop quality control
Ten tips on hazop quality controlPaul Baybutt
 
Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...
Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...
Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...Thorne & Derrick UK
 
PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1Process Safety Culture
 
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...PECB
 
Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management SystemACM Facility Safety
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 
Risk assessment techniques a critical success factor
Risk assessment techniques a critical success factorRisk assessment techniques a critical success factor
Risk assessment techniques a critical success factorPECB
 
Risk assessment presentation
Risk assessment presentationRisk assessment presentation
Risk assessment presentationmmagario
 

Mais procurados (20)

Functional safety certification guide
Functional safety certification guideFunctional safety certification guide
Functional safety certification guide
 
Resume jan2016
Resume jan2016Resume jan2016
Resume jan2016
 
Layer of protection analysis
Layer of protection analysisLayer of protection analysis
Layer of protection analysis
 
Knowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementKnowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & Management
 
Lecture 4-_hazard_analysis_prevention_and_safety_management
Lecture  4-_hazard_analysis_prevention_and_safety_managementLecture  4-_hazard_analysis_prevention_and_safety_management
Lecture 4-_hazard_analysis_prevention_and_safety_management
 
Safety Integrity Levels
Safety Integrity LevelsSafety Integrity Levels
Safety Integrity Levels
 
Applying IEC 62304 Risk Management in Aligned Elements - the medical device ALM
Applying IEC 62304 Risk Management in Aligned Elements - the medical device ALMApplying IEC 62304 Risk Management in Aligned Elements - the medical device ALM
Applying IEC 62304 Risk Management in Aligned Elements - the medical device ALM
 
Contingency%20planning%20lecture%205
Contingency%20planning%20lecture%205Contingency%20planning%20lecture%205
Contingency%20planning%20lecture%205
 
(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)
(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)
(Baxter_P.Reese)_Instrument_Adjustement_Policies_14_(2015_NCSLI)
 
Psm guide 4th edition
Psm guide 4th editionPsm guide 4th edition
Psm guide 4th edition
 
Ten tips on hazop quality control
Ten tips on hazop quality controlTen tips on hazop quality control
Ten tips on hazop quality control
 
Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...
Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...
Drager Fixed Gas Detector - Functional Safety & Gas Detection Systems - SIL B...
 
PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1
 
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
 
Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management System
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 
Risk assessment techniques a critical success factor
Risk assessment techniques a critical success factorRisk assessment techniques a critical success factor
Risk assessment techniques a critical success factor
 
Risk assessment presentation
Risk assessment presentationRisk assessment presentation
Risk assessment presentation
 
LAYER OF PROTECTION ANALYSIS
LAYER OF PROTECTION ANALYSISLAYER OF PROTECTION ANALYSIS
LAYER OF PROTECTION ANALYSIS
 
Pma adv technique hazard & risk management
Pma   adv technique hazard & risk managementPma   adv technique hazard & risk management
Pma adv technique hazard & risk management
 

Semelhante a Risk Assessment

IRJET- Assessing the Workplace Risk in Food Industry
IRJET-  	  Assessing the Workplace Risk in Food IndustryIRJET-  	  Assessing the Workplace Risk in Food Industry
IRJET- Assessing the Workplace Risk in Food IndustryIRJET Journal
 
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...IRJET Journal
 
HIRA TATA Projects construction of solar plant
HIRA TATA Projects construction of solar plantHIRA TATA Projects construction of solar plant
HIRA TATA Projects construction of solar plantvenkataramireddykamu1
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectIRJET Journal
 
HIRA TRAINING PPT.pptx
HIRA  TRAINING PPT.pptxHIRA  TRAINING PPT.pptx
HIRA TRAINING PPT.pptxMoolRaj3
 
ISO 31000 risk management process
ISO 31000 risk management processISO 31000 risk management process
ISO 31000 risk management processMuizz Anibire
 
Practical Application Of System Safety For Performance Improvement
Practical Application Of System Safety For Performance ImprovementPractical Application Of System Safety For Performance Improvement
Practical Application Of System Safety For Performance ImprovementAlbert V. Condello III CSP CHMM
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Risk Analysis and.pdf
Risk Analysis and.pdfRisk Analysis and.pdf
Risk Analysis and.pdfCesarPuma10
 
Bizsafe Risk Assessment
Bizsafe Risk AssessmentBizsafe Risk Assessment
Bizsafe Risk Assessmentsearchgeeksg
 
Bizsafe risk assessment
Bizsafe risk assessmentBizsafe risk assessment
Bizsafe risk assessmentsearchgeeksg
 
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and CommunicationSession 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and CommunicationMuizz Anibire
 
Session 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis ISession 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis IMuizz Anibire
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfmohamed Ismail
 
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment ProcessSession 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment ProcessMuizz Anibire
 

Semelhante a Risk Assessment (20)

IRJET- Assessing the Workplace Risk in Food Industry
IRJET-  	  Assessing the Workplace Risk in Food IndustryIRJET-  	  Assessing the Workplace Risk in Food Industry
IRJET- Assessing the Workplace Risk in Food Industry
 
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
 
Risk management
Risk managementRisk management
Risk management
 
HIRA TATA Projects construction of solar plant
HIRA TATA Projects construction of solar plantHIRA TATA Projects construction of solar plant
HIRA TATA Projects construction of solar plant
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure project
 
QMRS OSH 06 RISK MANUAL
QMRS OSH 06 RISK MANUALQMRS OSH 06 RISK MANUAL
QMRS OSH 06 RISK MANUAL
 
HIRA TRAINING PPT.pptx
HIRA  TRAINING PPT.pptxHIRA  TRAINING PPT.pptx
HIRA TRAINING PPT.pptx
 
ISO 31000 risk management process
ISO 31000 risk management processISO 31000 risk management process
ISO 31000 risk management process
 
Practical Application Of System Safety For Performance Improvement
Practical Application Of System Safety For Performance ImprovementPractical Application Of System Safety For Performance Improvement
Practical Application Of System Safety For Performance Improvement
 
HIRA Manual
HIRA ManualHIRA Manual
HIRA Manual
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Risk Analysis and.pdf
Risk Analysis and.pdfRisk Analysis and.pdf
Risk Analysis and.pdf
 
Task Risk Assessment .pdf
Task Risk Assessment .pdfTask Risk Assessment .pdf
Task Risk Assessment .pdf
 
Bizsafe Risk Assessment
Bizsafe Risk AssessmentBizsafe Risk Assessment
Bizsafe Risk Assessment
 
Bizsafe risk assessment
Bizsafe risk assessmentBizsafe risk assessment
Bizsafe risk assessment
 
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and CommunicationSession 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
 
Session 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis ISession 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis I
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
 
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment ProcessSession 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
 

Último

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...RKavithamani
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 

Último (20)

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 

Risk Assessment

  • 1. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 1 | P a g e RISK ASSESSMENT PROCEDURE DISCLAIM ER:  This document is the sole property of Urban Landscapes, No part of this document shall be re- created, copied, Referenced or translated without the written prior consent and approval of the Management Representative.  This document has been prepared in accordance with the requirements of the OHSAS 18001:2007 standard & QCS 2014  Where applicable, to be stamped "Controlled" in red color ink, indicating that the document is a COPY of the MASTER, and is verified and approved by the Management Representative of Urban Landscapes.
  • 2. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 2 | P a g e Document Title RISK ASSESSMENT PROCEDURE Prepared by Name Arun Gangadharan Position HSSE Manager Date 28/5/2020 Signature Audited & reviewed by Name Jodman Position QA/QC MANAGER Date 28/5/2020 Signature Approved by Name Chadi Position Managing partner Date 28/5/2020 Signature
  • 3. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 3 | P a g e CONTENTS Pge No. 01 AMENDMENT SHEET 04 02 OBJECTIVE 05 03 SCOPE OF IMPLEMENTATION 05 04 DEFINITIONS 05 05 CROSS REFRENCES 05 06 RESPONSIBILITIES 05 07 PROCESS/ REQUIREMENTS 06 08 RECORDS RETENTION 10 09 DOCUMENT FILING 10 10 FORMS 11
  • 4. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 4 | P a g e 01. AMENDMENT SHEET Description of Amendment Issue Rev Date Amended Pages
  • 5. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 5 | P a g e 02. OBJECTIVE To identify the hazards associated with all work activities of company and quantification of associated risk to place best possible operational controls to bring risk at As Low As Reasonably Practicable (ALARP) level. The main aim throughout this procedure and guidance is to follow the principles of (Prevention - Protection- information - Monitoring - Review) 03. SCOPE To determine measures required for eliminating hazards and reducing the risk for provision safe workplace.This procedure covers all Landscapes Projects and locations under the control of Landscapes. 04. DEFINITIONS 4.1 ALARP As Low As Reasonably Practicable 4.2 Company Urban Landscapes 4.3 Contractor The person(s) / firm(s) whose services, supply or product has been accepted by the company 4.4 Hazard Source, situation or act with a potential for harm in terms of human injury or ill health or combination of these 4.5 HIRAC Hazard Identification, Risk Assessment and Control 4.6 HSE Health Safety and Environment 4.7 May The use of may indicated – to be considered 4.8 PBG Project Business Group 4.9 PPE Personal Protective Equipment 4.10 Risk Combination of the likelihood and consequence(s) of a specified hazardous event occurring 4.11 Risk Assessment Overall process of estimating the magnitude of risk and deciding whether or not the risk is tolerable 4.12 Shall The use of ‘Shall’ indicates mandatory requirement 4.13 Tolerable Risk The risk that has been reduced to a level that can be endured by the organization having regard to its legal obligations and its own HSE Policy
  • 6. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 6 | P a g e 4.14 Probability The likelihood of a specific outcome, measured by the ratio of specific outcome to the total number of possible outcomes. 4.15 Severity The outcome of an event or situations expressed qualitatively or quantitatively, being a loss, injury, disadvantage or gain. 05. REFRENCES QCS 2014, Section 11Part 2.4.1 06. RESPONSIBILITIES PROJECT MANAGER  To ensure that a sufficient resources for carrying out risk assessments are in place and the risk assessment findings are being applied as part of the hazard control and analysis strategy  To review the effectiveness of the system to ensure that a safe system of work is in place. CONSTRUCTIONMANAGERS/ ENGINEER  To ensure that the requirements of this procedure are known to all employees and understood by Subcontractors at the kick-off meeting stage or at workplace.  To provide technical input into the formulation of the risk assessments and shall review prior to its distribution.  To supply information relevant to the scope of works. SUPERVISORS  To assist in developing work risk assessments.  To liaise with other disciplines I task supervision to ensure that conflicts of interest are accommodated.  To ensure that the requirements identified during the development of the Risk assessment is adequate in terms of detail and are being effectively communicated to all personnel involved with the task. PROJECT HSSE MANAGER/ INCHARGE  To associate with the Construction Team and ensure that the requirements outlined in this procedure are understood and are being implemented.
  • 7. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 7 | P a g e  To audit the task against the requirements specified to ensure compliance.  To carry out reviews of risk assessments on a periodic basis. Generally once in a year.  Review after any incident.  To train urban landscapes Field personnel in the requirements of the HSSE details in the risk assessment. SUBCONTRACTORS  To coordinate, develop and implement safe systems of work that includes the requirements of this procedure.  To ensure that sufficient resources are available to address the requirements of this procedure competently and efficiently.  To train their personnel in the requirements of the HSSE details in the risk assessment. 07. PROCESS / REQUIREMENTS 7.1 RISK ASSESSMENT TEAM Based in project specific job requirement and complexity of operations, Risk assessment team members shall be selected. Ideally the team members shall consist of various disciples viz: Civil, Mechanical, Electrical, Process, commissioning, HSE etc. 7.2 TRAINING Familiarization training shall be conducted on Hazard Identification Risk Assessment and control prior to start of study. 7.3 RISK ASSESSMENT PROCESS The following six elements shall be considered during the HIRAC process  Hazard Identification  Persons / Environment / Asset / Reputation of Risk  Evaluation of Risk level  Risk controls (existing and additional)  Record of risk assessment findings  Monitoring and Review 7.3.1 Hazard Identification is performed considering the following consequences  Personal Injury
  • 8. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 8 | P a g e  Asset Damage  Environmental Impact  Reputation 7.3.2 The purpose of this study is to identify the hazard, access the risks associated with these identified hazards and suggest risk reducing measures. 7.3.3 The first step of the HIRAC is to identify the activity of a department for which you want to access the risk involved. 7.3.4 After selecting the particular work activity list down the sub activities looks to each sub activity from all perspective to find out both major and minor hazards associated with that activity of work. 7.3.5 The next step after determining the hazard is to note down all the existing control measures which are being followed currently. The control measures is of THREE types.  Engineering Control (ex. Access, Excess)  Administration Control (ex. Permit to work, supervision)  Personal Protective Equipment (ex. Full body harness) 7.3.6 Evaluation of Risk: For evaluation of hazard the following criteria can be used. 7.3.6.1 Likelihood: In the below table we have to choose the chances of the occurrence of the hazards Assessments can be done either Quantitative or Qualitative: Quantitative Assessment: Frequency of Failure (F) Probability (Frequency) 1 Improbable: Less than once in 10years or more 2 Remote: Unlikely to occur during life cycle of the system (once in 6-10 years) 3 Rare: At least once in life cycle system (typically) once in SIX years 4 Reasonably Probable: Several times during life cycle of the system or at least once in THREE years 5 Frequent: Repeatedly during life cycle of the system or at least once in a year. Table 1
  • 9. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 9 | P a g e 7.3.6.2 Possible Consequence (Severity): In the below table the consequence of hazards is to be noted. Severity (C) People Asset (Amount in INR) Environment Reputation 1 Minor injury illness (first aid) Ten Thousand Minor spills or fugitive emission Individual concern 2 Medical aid injury ONE Lakh Controlled Environment Release (with in limit) Local / community attention 3 Disabling injury(s) TEN Lakh Major sustained Environmental release Provincial attention 4 Single Fatality ONE Crore Some permanent ecological damage Industry wide attention 5 Multiple Fatalities TEN Crore Widespread – Permanent ecological damage National and International attention Table 2 7.3.6.3 RISK MATRIX Once each hazard is ranked in terms of likelihood and consequences, it can be plotted on a risk matrix and associated risk level can be determined. Consequence levels are determined with reference to loss of people, asset damage, Environment and reputation. The risk level defines three areas:  Low: Either the evaluated risk is negligible or the corresponding system / item are acceptable as they are.  Medium: Risk falls in ALARP region and risk control options are then to be proposed and assed in accordance with safety objectives.  High: Risk is found unacceptable and corresponding source of risk is to be removed.
  • 10. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 10 | P a g e Shown in Below Grid Hazard Ranking Risk Level (r) Unacceptable High ALARP Medium Acceptable Low Table 3 5 4 3 2 1 1 2 3 4 5 Quatitative assessment. The principle is the same as for Qualitative assessments, but numerical scores rather than a grade are assigned to probability and consequences. The probability or likelihood of the event is rated on a scale of 1 to 5 as follows: Level 1 Very unlikely to happen Level 2 Unlikely to happen, but not by any means impossible Level 3 likely to happen, and would not be totally unexpected. Level 4 It is very likely to happen, and would not be at all unusual Level 5 It is certain to happen. The consequences or the severity of the event, should it happen, are also then rated on a scale of 1to 5 as follows: Level 1 No injury. It would be a 'near miss'. Minor property damage. Consequence F R E Q U E N C Y
  • 11. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 11 | P a g e Level 2 Minor injury. Less than three days' work time lost. Property damage more than just minor likely to happen, and would not be totally unexpected. Level 3 Reportable injury to the HSE with over three days' time lost, but not a major injury. Substantial property damage or something causing environmental damage Level 4 Major injury, long term absence. Major damage, serious environmental impact. Level 5 Fatal accident or multiple major injuries. Public or others could be involved as well. All possible resulting numbers are calculated by multiplying all the probability figures by all the consequence figures. These are included in the matrix, as shown below. This means that once a risk assessment has been made on a particular activity, and the probability factor is multiplied by the consequence factor, the number produced indicates where the assessment places the risk associated with the activity on the matrix. Clearly, the higher the resulting number, the less acceptable the level of risk. The matrix shows where actions need to be taken to reduce either the probability or the consequences in order to reduce the risks to an acceptable level. Probability 5 5 10 15 20 25 4 4 8 12 16 20 3 3 6 9 12 15 2 2 4 6 8 10 1 1 2 3 4 5 1 2 3 4 5 Consequences Risks with a rating above 1 6 are unacceptable and the work will not be undertaken until the risk has been reduced.
  • 12. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 12 | P a g e RECORD YOUR FINDINGS AND IMPLEMENT THEM Putting the results of your risk assessment into practice will make a difference when looking after people and your business. Writing down the results of your risk assessment, and sharing them with your staff, encourages you to do this. If you have fewer than five employees you do not have to write anything down, though it is useful so that you can review it at a later date if, for example, something changes. When writing down your results, keep it simple, for example, 'Tripping over rubbish: bins provided, staff instructed, weekly housekeeping checks', or 'Fume from welding: local exhaust ventilation used and regularly checked'. We do not expect a risk assessment to be perfect, but it must be suitable and sufficient. You need to be able to show that:  a proper check was made;  you asked who might be affected;  you dealt with all the significant hazards, taking into account the number of people who could be involved;  the precautions are reasonable, and the remaining risk is low; and.  You involved your staff or their representatives in the process. A good plan of action often includes a mixture of different things such as;  a few cheap or easy improvements that can be done quickly, perhaps as a temporary solution until more reliable controls are in place;  long-term solutions to those risks most likely to cause accidents or ill health;  long-term solutions to those risks with the worst potential consequences;  arrangements for training employees on the main risks that remain and how they are to be controlled;  regular checks to make sure that the control measures stay in place; and  Clear responsibilities - who will lead on what action, and by when Remember, prioritize and tackle the most important things first. As you complete each action,
  • 13. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 13 | P a g e tick it off your plan. Review your risk assessment and update if necessary Few workplaces stay the same. Sooner or later, you will bring in new equipment, substances and procedures that could lead to new hazards. It makes sense, therefore, to review what you are doing on an ongoing basis. Every year or so formally review where you are, to make sure you are still improving, or at least not sliding back. Look at your risk assessment again. Have there been any changes? Are there improvements you still need to make? Have your workers spotted a problem? Have you learnt anything from accidents or near misses? Make sure your risk assessment stays up to date. During the year, if there is a significant change, don't wait. Check your risk assessment and, where necessary, amend it. If possible, it is best to think about the risk assessment when you're planning your change - that way you leave yourself more flexibility. 08. RECORDS Records necessary to implement this procedure shall be kept with the HSSE Senior Manager for a period not less than 3 years. 09. DOCUMENT FILING The original version of this procedure along with the rest of the procedures shall be maintained with the HSSE Senior Manager and the procedure shall have a reference number: OHSP- RA – UL- 001 Rev 00. 10. FORMS Risk Assessment Form OHSF-RA-UL-RA-01 Rev 00 Risk Assessment INDEX OHSF-RA-UL-RA-02Rev 00
  • 14. Document Reference OHSP- RA – UL- 001 Rev00. Revision 00 Issue Date 01 June 2020 14 | P a g e