SlideShare uma empresa Scribd logo
1 de 59
By: Anand Bobade (nnbobade@gmail.com)
PMP - PMBOK : 47 Process definitions
Integration Scope Time Cost Quality
Human
Resource
Communication Risk Procurement Stakeholder
Learn Project Management & prepare for PMP exam:
 Learn visually
 Detailed coverage of all PMP concepts
 Sample Questions
By: Anand Bobade (nmbobade@gmail.com)
Processes & activities needed to identify, define, combine, unify, &
coordinate the various processes & project management activities
within the PM process groups
Initiating Planning Executing Monitoring &
Controlling
Closing
Develop Project
charter
Develop Project
Management plan
Direct & Manage
Project Work
Monitor & Control
Project work
Close Project or
Phase
Perform Integrated
Change control
PMBOK Chap 4: Project Integration Management
Things work out best for those who make the best of how things work out.
- John Wooden
By: Anand Bobade (nmbobade@gmail.com)
4.1 Develop Project Charter
The document that formally authorizes a project, and
provide the project manager with the authority to
apply organizational resources to the project activities.
It is a well-defined project start and project boundaries, creation of
a formal record of the project & a direct way for senior
management to formally accept and commit to the project
Key project
stakeholders
should sign a
project charter to
acknowledge
agreement on the
need and intent
of the project
By: Anand Bobade (nmbobade@gmail.com)
4.2 Develop Project Management Plan
The process of defining, preparing, coordinating &
integrating subsidiary plans.
It is a central document that defines the basis of all
project work. It defines how the project will be
executed, monitored and controlled, and closed.
Defining
Preparing Coordinating
Integrating
Subsidiary
Plans
By: Anand Bobade (nmbobade@gmail.com)
4.3 Direct & Manage Project Work
The process of performing work defined in PMP
to achieve project’s objectives.
It provides the overall Management of project work.
Performing work Defined in PMP
Achieve Project
objectives
By: Anand Bobade (nmbobade@gmail.com)
4.4 Monitor and Control Project Work
Tracking, reviewing, & reporting progress to
meet performance objectives defined in PMP
Progress
Tracking Reviewing Reporting
It allows stakeholder to understand current state of
project, steps taken, budget, schedule & scope
forecasts.
Performance Objective
By: Anand Bobade (nmbobade@gmail.com)
4.5 Perform Integrated Change Control
The process of reviewing all CR’s, approving changes &
managing changes to deliverables, OPA, project
documents & PMP; & communicating their deposition.
It allows documented changes within project to be
considered in a integrated fashion while reducing a
project risk, which often arises from changes made
without considering overall project objectives or plans.
Reviewing &
approving CR’s
Managing changes
Communicating
CR’s
By: Anand Bobade (nmbobade@gmail.com)
Finalizing
all
activities
4.6 Close Project or Phase
The process of finalizing all activities across all of the PMP Groups
to formally complete the project or phase.
It provides lesson learned, the formal ending of the project work,
and release of organization resources to pursue new endeavors.
Project
Phase
By: Anand Bobade (nmbobade@gmail.com)
Ensure that the project includes all the work required, and only the
work required, to complete the project successfully.
Initiating Planning Executing Monitoring and
Controlling
Closing
Plan scope
management
Define scope Validate Scope
Collect
requirements
Create WBS Control Scope
PMBOK Chap 5 - Project Scope Management
Opportunity is missed by most people because it is dressed in overalls and looks like
work. - Thomas Edison
By: Anand Bobade (nmbobade@gmail.com)
5.1 Plan scope management
Creating a scope management plan – how scope
will be defined, validated, and controlled.
It provides guidance & direction on how scope will be managed
throughout the project.
By: Anand Bobade (nmbobade@gmail.com)
Defined
ControlledValidated
Ensure that the
project includes
all the work
required, and
only the work
required, to
complete the
project
successfully.
By: Anand Bobade (nmbobade@gmail.com)
5.2 Collect Requirements
Determining, documenting, and managing stakeholder
needs and requirements to meet project objectives.
It provides the basis for defining & managing the project scope
including product scope.
By: Anand Bobade (nmbobade@gmail.com)
Requirements
Unambiguous
Traceable
Complete
Consistent
Acceptable to
stakeholders
Determining
ManagingDocumenting
Project
By: Anand Bobade (nmbobade@gmail.com)
5.3. Define Scope
Process of developing a detailed description of
the project and product.
It describes the project, service, or result boundaries by
defining which of the requirements collected will be
included in and excluded from the project scope.
By: Anand Bobade (nmbobade@gmail.com)
Project Product. Scope Baseline
Detailed
Description
By: Anand Bobade (nmbobade@gmail.com)
5.4. Create WBS
Subdividing project deliverables & project work
into smaller, more manageable components.
It provides the structured VISION of what has to be
delivered.
Business process
re-engineering Project
As-is Study
Finance Dept.
Procurement
Dept.
Benchmarking
As-is
Process Re-
engineering
For Finance dept.
For Procurement
dept.
Smaller &
Manageable
components
Subdividing
project
By: Anand Bobade (nmbobade@gmail.com)
It brings objectivity to the acceptance process and increases the
chance of final product, service, or result acceptance by validating
each deliverable.
5.5 Validate Scope
Formalizing acceptance of the completed project deliverables
Business process re-
engineering Project
Process
Re-engineering (BRS)
•
Stakeholders
Walkthrough
Document review
Quality review
Deliverable
Acceptance Or
Change Request
At the end of each Phase or Project
By: Anand Bobade (nmbobade@gmail.com)
5.6 Control Scope
Monitoring the status of the project and product scope
and managing changes to the scope baseline
It allows the scope baseline to be maintained
throughout the project.
Monitoring
status of
Project
Monitor
product
scope
Manage
changes to
scope baseline
Includes the processes required to accomplish timely
completion of the project
Initiating Planning Executing Monitoring &
Controlling
Closing
Plan Schedule
management
Estimate Activity
resource
Control Schedule
Define Activities Estimate Activity
Duration
Sequence Activities Develop Schedule
PMBOK Chap6- Project Time Management
If you think you are too small to make a difference, try sleeping with a mosquito.
By: Dalai Lama
6.1 Plan Schedule management
The process of establishing policies, procedures, &
documentation for planning, developing, managing,
executing, & controlling the project schedule
The key benefit is to provide guidance and direction on
how the project schedule will be managed.
Establishing
Planning, Developing,
Managing, Executing
Controlling
6.2 Define Activities
It break down work packages into activities that provide
a basis for estimating, scheduling, executing,
monitoring, & controlling the project work
The process of identifying & documenting the specific
actions to be performed to produce the project
deliverables.
Identifying &
Documenting
Project Deliverables
Specific
Actions
Produce
6.3 Sequence Activities
It defines the logical sequence of work to obtain the
greatest efficiency given all project constraints.
Project
Activities
Identifying &
Documenting
The process of identifying and documenting
relationships among the project activities.
Relationship
6.4: Estimate Activity resource
It identifies the type, quantity, and characteristics of
resources required to complete the activity which
allows more accurate cost and duration estimates.
Type &
Quantities
Material
Human resources
Equipment
Supplies
Estimating type & quantities of material, human
resources, equipment, or supplies required to perform
each activity
Perform
Estimating
6.5 Estimate Activity Duration
It provides the amount of time each activity will take to
complete, which is a major input to Develop Schedule
process.
Estimating the number of work periods needed to
complete individual activities with estimated resources
Activity
Estimating Work Periods Complete activity
6.6 Develop Schedule
By entering the schedule activities, duration, resources, resource
availability & logical relationship in to the scheduling tools, It generates
schedule model with planned dates for completing project activities.
Activity
sequences
Activity
Durations
Resource
Requirements
Schedule
Constraints
Create Project Schedule
Analysing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model
Analyze
6.7 Control Schedule
It defines the logical sequence of work to obtain the
greatest efficiency given all project constraints.
Monitoring the status of project activities to update project
progress & manage changes to schedule baseline to achieve plan.
Monitoring status
of Project activities
Update
project
progress
Manage schedule
baseline changes
By: Anand Bobade (nmbobade@gmail.com)
Cost Management includes the processes involved in estimating,
budgeting, and controlling costs so that the project can be completed
within the approved budget.
Initiating Planning Executing Monitoring
& Controlling
Closing
Plan Cost
management
Determine Budget Control Cost
Estimate Cost
PMBOK Chap 7 – Project Cost Management
By: Anand Bobade (nmbobade@gmail.com)
Success is walking from failure to failure with no loss of enthusiasm.
By: Winston Churchill
By: Anand Bobade (nmbobade@gmail.com)
7.1 Plan Cost Management
Establishes Policies, procedures & documentation
for planning, managing, expending, controlling
project costs.
It provides guidance and direction on how the project
costs will be managed throughout the project.
Establishing
Planning Managing
Expending Controlling
By: Anand Bobade (nmbobade@gmail.com)
7.2 Estimate Cost
The process of developing an APPROXIMATION of the
monetary resources needed to complete project
activities.
It determines the amount of cost required to complete
project work.
Activity1 Resource Cost
Project Cost
Activity2 Resource Cost
Approximation
By: Anand Bobade (nmbobade@gmail.com)
7.3 Determine Budget
Aggregating the estimated costs of individual
activities or work packages to establish an authorized
cost baseline.
Determines the cost baseline against which project
performance can be monitored and controlled
Activity1 Resource Cost
Cost Baseline
Activity2 Resource Cost
Contingency
Reserve
Aggregation
By: Anand Bobade (nmbobade@gmail.com)
7.4 Control Cost
Provides the means to recognize variance from the plan
in order to take corrective action and minimize risk.
Monitoring the status of the project to update the
project costs & managing changes to the cost baseline.
Monitoring Project
status
Update project
Cost
Manage cost
baseline changes
Quality is the degree to which the project fulfils requirements.
Quality Management includes creating and following policies and
procedures in order to ensure that a project meets the defined needs
it was intended to meet.
Initiating Planning Executing Monitoring &
Controlling
Closing
Plan Quality
management
Perform Quality
Assurance
Control Quality
management
PMBOK Chap 8 – Project Quality Management
If you don't have time to do it right, when will you have time to do it over?
By: John Wooden
By: Anand Bobade (nmbobade@gmail.com)
8.1 Plan Quality Management
It is the process of identifying quality requirements and/or standards
for the project and its deliverables, and documenting how the project
will demonstrate compliance with relevant quality requirements.
Project
Requirements
It provides guidance & direction on how quality will be managed and
validated throughout the project.
By: Anand Bobade (nmbobade@gmail.com)
8.2 Perform Quality Assurance
It facilitates the improvement of quality processes.
It is the process of auditing quality requirements & results from
quality control measurements to ensure that appropriate quality
standards & operational definitions are used.
By: Anand Bobade (nmbobade@gmail.com)
Ensure Quality Standards &
Operational Definitions are used
Quality Requirements Quality Control Measures
Results
8.3 Control Quality
Monitoring & Recording
Recommend
-ation
Action
Action
Execute Quality activities Assess Performance Recommend Changes
Process of monitoring & recording results of executing quality
activities to assess performance & recommend necessary changes.
- Identifying causes of poor process/product quality & recommend action
-Validating that project deliverables & work meet the requirements.
By: Anand Bobade (nmbobade@gmail.com)
By: Anand Bobade (nmbobade@gmail.com)
PMBOK Chap 9 - Human Resource Management
Includes the processes that Organize, Manage & Lead
the Project Team.
Initiating Planning Executing Monitoring
& Controlling
Closing
Plan HR
Management
Acquire Project
Team
Manage Project
Team
Develop Project
Team
I am convinced that nothing we do is more important than hiring and developing
people. At the end of the day you bet on people, not on strategies.
– Lawrence Bossidy, GE
By: Anand Bobade (nmbobade@gmail.com)
9.1 Plan Human Resource Management
Identifying & documenting project roles,
responsibilities, required skills, reporting
relationships, & creating a staffing engagement plan.
It establishes project roles & responsibilities, project
organization charts, & the staffing management plan
including the timetable of staff acquisition & release.
Identifying &
Documenting
Roles Staff Engag’t plan
Responsibilities Relationships
Human Resource
Management
By: Anand Bobade (nmbobade@gmail.com)
9.2 Acquire Project Team
Confirming human resource availability and obtaining
the team necessary to complete project activities
The key benefit consists of outlining & guiding team selection
and responsibility assignment to obtain a successful team.
Acquire Project Team
Confirming
Human Resource
Availability
Obtaining the
Team
Key Benefit
Outlining Team
Selection
Guiding Team
Selection
Responsibility
assignment
Complete project activities Obtain a successful team
By: Anand Bobade (nmbobade@gmail.com)
9.3 Develop Project Team
Improving competencies, team member interaction,
and overall team environment to enhance project
performance.
It results in improved teamwork, enhanced people skills &
competencies, motivated employees, reduced staff turnover
rates, & improved overall project performance.
Improving
Competencies
Team Member
Interaction
Overall Team
Environment
Enhanceproject
performance.
Results in:
Teamwork
People skills
Competencies
Motivated Emp.
Reduced turnover
By: Anand Bobade (nmbobade@gmail.com)
9.4 Manage Project Team
Tracking team member performance, providing
feedback, resolving issues, and managing team changes
to optimize project performance
It influences team behavior, manages conflict, resolves
issues, and appraises team member performance.
Manage Project Team
Tracking
Performance
Providing
Feedback
Resolving
Issues
Team
changes
Optimizeproject
performance.
Team Behavior
Manages Conflict
Resolves Issues
Appraises
Performance
The process required to ensure timely and appropriate generation,
collection, distribution, storage, retrieval, and ultimate disposition
of project information.
Initiating Planning Executing Monitoring &
Controlling
Closing
Plan Communication Manage
Communication
Control
Communication
PMBOK Chap 10-Project Communication Management
To effectively communicate, we must realize that we are all different in the way we
perceive the world and use this understanding as a guide to our communication
with others. - Anthony Robbins
By: Anand Bobade (nmbobade@gmail.com)
Overview
10.1 Plan communication Management
Process of developing an appropriate approach and plan for
project communications based on stakeholder’s information
needs and requirements, and available organizational assets.
The key benefit his process is that it identifies & documents approach to
communicate most effectively and efficiently with stakeholders.
Effective
Communication:
• Providing only the information that is needed.Efficient Communication
Approach
&
Plan
Right format Right time
Right audience Right impact
10.2 Manage Communications
It is the process of creating, collecting, distributing, storing,
retrieving, and the ultimate disposition of project information
in accordance to the communications management plan.
The key benefit of this process is that it enables an efficient and
effective communications flow between project stakeholders.
Creating Collecting Distributing
Storing Retrieving Disposition
10.3 Control Communications
Process of monitoring & controlling communications
throughout the entire project life cycle to ensure the
information needs of the project stakeholders are met.
The key benefit of this process is that it ensures an optimal information
flow among all communication participants, at any moment in time.
Optimal information flow
Project lifecycle
Stakeholders
Information
Needs
By: Anand Bobade (nmbobade@gmail.com)
PMBOK Chap 11 – Project Risk Management
The Objective of Project Risk Management are to increase the
likelihood & impact of positive events, and decrease the likelihood &
impact of negative events in the projects.
Initiating Planning Executing Monitoring &
Controlling
Closing
Plan Risk
Management
Perform Quantit’ve
Risk Analysis
Monitor and Control
Risks
Identify Risk Plan Risk Response
Perform Qualitative
Risk Analysis
Risk comes from not knowing what you're doing.
By: Warren Buffett
By: Anand Bobade (nmbobade@gmail.com)
11.1 Plan Risk Management -> Definition
The process of defining how to conduct risk
management activities for a project.
It ensures that the degree, type, and visibility of risk
management are commensurate with both the risks &
importance of the project to the organization.
Identify
Asses(Probability &
Impact)
Treatment (Risk
Response)
Monitor & Review
Planning how
to approach &
execute project
risk
management
activities
By: Anand Bobade (nmbobade@gmail.com)
11.2 Identify Risk -> Definition
Determine which risks may affect the project &
document their characteristics
The documentation of existing risks & knowledge &
ability it provides to project team to anticipate events.
Project
Risk1
Risk2
Risk3
Risk4Risk5
Risk6
Risk7
Risk
Charaterstics1
Charaterstics2
Charaterstics3
Determine Risks Documenting their characteristics
By: Anand Bobade (nmbobade@gmail.com)
11.3 Perform Qualitative Risk Analysis-> Definition
It is the process of prioritizing risks for further
analysis or action by assessing & combining their
probability of occurrence & impact.
It enables PM to reduce the level of uncertainty
and to focus on high-priority risks
Focus on
High
Probability
& high
impact
Risks
Identified Risks Qualitative Analysis Prioritized Risk
By: Anand Bobade (nmbobade@gmail.com)
11.4 Perform Quantitative Risk Analysis
Numerically analyzing the effect of
identified risks on overall project objectives.
It produces quantitative risk information to support
decision making in order to reduce project uncertainty.
Identified Risks Quantitative Analysis
Quantitative Risk
Information
Analyses
effect on
Project
Objectives
By: Anand Bobade (nmbobade@gmail.com)
11.5 Plan Risk Responses
Process of developing options & actions to
enhance opportunities & to reduce threats to
project objectives.
It addresses the risks by their priority, inserting
resources & activities into the budget, schedule
& PMP as needed.
By: Anand Bobade (nmbobade@gmail.com)
11.6 Control Risks -> Definition
It is the process of implementing risk response plans, tracking
identified risks, monitoring residual risks, identifying new risks,
and evaluating risk process effectiveness throughout the
project.
It improves efficiency of risk approach
throughout project life cycle to continuously
optimize risk responses.
Risk Response Plans
Tracking identified
risks
Monitoring residual
risks
Identifying new
risks
Implementing
By: Anand Bobade (nmbobade@gmail.com)
PMBOK Chap 12 – Project Procurement Management
The processes necessary to purchase or acquire product, services,
or results needed from outside the project team.
Initiating Planning Executing Monitoring &
Controlling
Closing
Plan Procurement
Management
Conduct
Procurement
Control
Procurement
Close Procurement
We cannot solve our problems with the same thinking we used when we created
them.
- Albert Einstein
By: Anand Bobade (nmbobade@gmail.com)
12.1 Plan Procurement Management
The process of documenting project procurement
decisions, specifying the approach, and identifying
potential sellers.
It determines whether to acquire outside support, and
if so, what to acquire, how to acquire it, how much is
needed, and when to acquire it.
Procurement
decisions
Specifying
approach
Identifying
potential sellers.
By: Anand Bobade (nmbobade@gmail.com)
12.2 Conduct Procurement
The process of obtaining seller responses, selecting a
seller, and awarding a contract.
It provides alignment of internal & external stakeholder
expectations through established agreements.
Seller1
Responses
Seller2
Responses
Seller3
Responses
Seller4
Responses
Selection
process
Review
prop.
Evaluate
Seller
Obtaining seller responses Selecting a seller Selected Seller
Awarding a
Contract
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement
The process of managing procurement relationships,
monitoring contract performance, and making changes
and corrections to contracts as appropriate.
It ensures that both the seller’s & buyer’s performance
meets procurement requirements according to the
terms of the legal agreement.
Managing
procurement
relationships
Monitoring
contract
performance
Making
changes and corrections
to contracts
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement
The process of completing each procurement.
It documents agreements and related documentation
for future reference.
Procurement 1
Procurement 2
Individual
procurement
Closure
By: Anand Bobade (nmbobade@gmail.com)
PMBOK Chap 13– Stakeholder Management
Identifying the people, groups, or organizations that could impact
or be impacted by the project, to analyze stakeholder expectations
and their impact on the project, and to develop appropriate
management strategies.
Initiating Planning Executing Monitoring &
Controlling
Closing
Identify
Stakeholders
Plan Stakeholder
Management
Manage
Stakeholder
Engagement
Control
Stakeholder
Engagement
The conventional definition of management is getting work done through people,
but real management is developing people through work.
By: Anand Bobade (nmbobade@gmail.com)
13.1 Identify Stakeholders
Identifying the people, groups, or organizations that could impact or
be impacted by a decision, activity, or outcome of the project,
Analyzing and documenting relevant information regarding their
interests, involvement, interdependencies, influence, and potential
impact on project success.
Identifying
Decision Activity
Outcome
People Group
Organization
Impact or
Impacted by
Project
By: Anand Bobade (nmbobade@gmail.com)
13.2 Plan Stakeholder Management
Developing appropriate management strategies to
effectively engage stakeholders throughout the project
life cycle, based on the analysis of their needs,
interests, and potential impact on project success.
Engage StakeholdersDeveloping Strategies
To
Needs Interests Impact
Analyzing
By: Anand Bobade (nmbobade@gmail.com)
13.3 Manage Stakeholder Engagement
Communicating & working with stakeholders to meet
their needs/ expectations, address issues as they occur,
& foster appropriate stakeholder engagement in
project activities throughout project life cycle.
Increase support & minimize resistance from
stakeholders, significantly increasing the chances to
achieve project success.
Communicating & working
with stakeholder
Meet Needs, expectations
& address issues
Foster stakeholders
engagement
By: Anand Bobade (nmbobade@gmail.com)
13.4 Control Stakeholder Engagement
Monitoring overall project stakeholder relationships
and adjusting strategies and plans for engaging
stakeholders
It will maintain or increase the efficiency and
effectiveness of stakeholder engagement activities as
the project evolves and its environment changes.
Monitoring stakeholder
relationships
Adjusting strategies and
plans
Engaging stakeholders
Additional Free Resources
Visit Slide Share website & you will find other Knowledge area presentation… Please share!!

Mais conteúdo relacionado

Mais procurados

Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CycleAnand Bobade
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage CommunicationDavidMcLachlan1
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!Sasan Hosseyni
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 

Mais procurados (20)

Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management Overview
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage Communication
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 

Semelhante a PMP 47 process definitions

PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6gatecomro
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre..."Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...SN Panigrahi, PMP
 
Project management slide - Introduction
Project management slide - IntroductionProject management slide - Introduction
Project management slide - IntroductionAlbert Poghosyan
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 
Project management professional
Project management professionalProject management professional
Project management professionalReema
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentationpats384888
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Project management processes ch3 (1)
Project management processes ch3 (1)Project management processes ch3 (1)
Project management processes ch3 (1)hinasardar2
 

Semelhante a PMP 47 process definitions (20)

PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Project Management
Project ManagementProject Management
Project Management
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre..."Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
"Project Management Concepts - Ready Reckoner" By SN Panigrahi, A QUick Refre...
 
Project management slide - Introduction
Project management slide - IntroductionProject management slide - Introduction
Project management slide - Introduction
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
Project management professional
Project management professionalProject management professional
Project management professional
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentation
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project management processes ch3 (1)
Project management processes ch3 (1)Project management processes ch3 (1)
Project management processes ch3 (1)
 

Mais de Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 

Mais de Anand Bobade (18)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 

Último

CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 

Último (20)

Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 

PMP 47 process definitions

  • 1. By: Anand Bobade (nnbobade@gmail.com) PMP - PMBOK : 47 Process definitions Integration Scope Time Cost Quality Human Resource Communication Risk Procurement Stakeholder Learn Project Management & prepare for PMP exam:  Learn visually  Detailed coverage of all PMP concepts  Sample Questions
  • 2. By: Anand Bobade (nmbobade@gmail.com) Processes & activities needed to identify, define, combine, unify, & coordinate the various processes & project management activities within the PM process groups Initiating Planning Executing Monitoring & Controlling Closing Develop Project charter Develop Project Management plan Direct & Manage Project Work Monitor & Control Project work Close Project or Phase Perform Integrated Change control PMBOK Chap 4: Project Integration Management Things work out best for those who make the best of how things work out. - John Wooden
  • 3. By: Anand Bobade (nmbobade@gmail.com) 4.1 Develop Project Charter The document that formally authorizes a project, and provide the project manager with the authority to apply organizational resources to the project activities. It is a well-defined project start and project boundaries, creation of a formal record of the project & a direct way for senior management to formally accept and commit to the project Key project stakeholders should sign a project charter to acknowledge agreement on the need and intent of the project
  • 4. By: Anand Bobade (nmbobade@gmail.com) 4.2 Develop Project Management Plan The process of defining, preparing, coordinating & integrating subsidiary plans. It is a central document that defines the basis of all project work. It defines how the project will be executed, monitored and controlled, and closed. Defining Preparing Coordinating Integrating Subsidiary Plans
  • 5. By: Anand Bobade (nmbobade@gmail.com) 4.3 Direct & Manage Project Work The process of performing work defined in PMP to achieve project’s objectives. It provides the overall Management of project work. Performing work Defined in PMP Achieve Project objectives
  • 6. By: Anand Bobade (nmbobade@gmail.com) 4.4 Monitor and Control Project Work Tracking, reviewing, & reporting progress to meet performance objectives defined in PMP Progress Tracking Reviewing Reporting It allows stakeholder to understand current state of project, steps taken, budget, schedule & scope forecasts. Performance Objective
  • 7. By: Anand Bobade (nmbobade@gmail.com) 4.5 Perform Integrated Change Control The process of reviewing all CR’s, approving changes & managing changes to deliverables, OPA, project documents & PMP; & communicating their deposition. It allows documented changes within project to be considered in a integrated fashion while reducing a project risk, which often arises from changes made without considering overall project objectives or plans. Reviewing & approving CR’s Managing changes Communicating CR’s
  • 8. By: Anand Bobade (nmbobade@gmail.com) Finalizing all activities 4.6 Close Project or Phase The process of finalizing all activities across all of the PMP Groups to formally complete the project or phase. It provides lesson learned, the formal ending of the project work, and release of organization resources to pursue new endeavors. Project Phase
  • 9. By: Anand Bobade (nmbobade@gmail.com) Ensure that the project includes all the work required, and only the work required, to complete the project successfully. Initiating Planning Executing Monitoring and Controlling Closing Plan scope management Define scope Validate Scope Collect requirements Create WBS Control Scope PMBOK Chap 5 - Project Scope Management Opportunity is missed by most people because it is dressed in overalls and looks like work. - Thomas Edison
  • 10. By: Anand Bobade (nmbobade@gmail.com) 5.1 Plan scope management Creating a scope management plan – how scope will be defined, validated, and controlled. It provides guidance & direction on how scope will be managed throughout the project. By: Anand Bobade (nmbobade@gmail.com) Defined ControlledValidated Ensure that the project includes all the work required, and only the work required, to complete the project successfully.
  • 11. By: Anand Bobade (nmbobade@gmail.com) 5.2 Collect Requirements Determining, documenting, and managing stakeholder needs and requirements to meet project objectives. It provides the basis for defining & managing the project scope including product scope. By: Anand Bobade (nmbobade@gmail.com) Requirements Unambiguous Traceable Complete Consistent Acceptable to stakeholders Determining ManagingDocumenting Project
  • 12. By: Anand Bobade (nmbobade@gmail.com) 5.3. Define Scope Process of developing a detailed description of the project and product. It describes the project, service, or result boundaries by defining which of the requirements collected will be included in and excluded from the project scope. By: Anand Bobade (nmbobade@gmail.com) Project Product. Scope Baseline Detailed Description
  • 13. By: Anand Bobade (nmbobade@gmail.com) 5.4. Create WBS Subdividing project deliverables & project work into smaller, more manageable components. It provides the structured VISION of what has to be delivered. Business process re-engineering Project As-is Study Finance Dept. Procurement Dept. Benchmarking As-is Process Re- engineering For Finance dept. For Procurement dept. Smaller & Manageable components Subdividing project
  • 14. By: Anand Bobade (nmbobade@gmail.com) It brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable. 5.5 Validate Scope Formalizing acceptance of the completed project deliverables Business process re- engineering Project Process Re-engineering (BRS) • Stakeholders Walkthrough Document review Quality review Deliverable Acceptance Or Change Request At the end of each Phase or Project
  • 15. By: Anand Bobade (nmbobade@gmail.com) 5.6 Control Scope Monitoring the status of the project and product scope and managing changes to the scope baseline It allows the scope baseline to be maintained throughout the project. Monitoring status of Project Monitor product scope Manage changes to scope baseline
  • 16. Includes the processes required to accomplish timely completion of the project Initiating Planning Executing Monitoring & Controlling Closing Plan Schedule management Estimate Activity resource Control Schedule Define Activities Estimate Activity Duration Sequence Activities Develop Schedule PMBOK Chap6- Project Time Management If you think you are too small to make a difference, try sleeping with a mosquito. By: Dalai Lama
  • 17. 6.1 Plan Schedule management The process of establishing policies, procedures, & documentation for planning, developing, managing, executing, & controlling the project schedule The key benefit is to provide guidance and direction on how the project schedule will be managed. Establishing Planning, Developing, Managing, Executing Controlling
  • 18. 6.2 Define Activities It break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, & controlling the project work The process of identifying & documenting the specific actions to be performed to produce the project deliverables. Identifying & Documenting Project Deliverables Specific Actions Produce
  • 19. 6.3 Sequence Activities It defines the logical sequence of work to obtain the greatest efficiency given all project constraints. Project Activities Identifying & Documenting The process of identifying and documenting relationships among the project activities. Relationship
  • 20. 6.4: Estimate Activity resource It identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates. Type & Quantities Material Human resources Equipment Supplies Estimating type & quantities of material, human resources, equipment, or supplies required to perform each activity Perform Estimating
  • 21. 6.5 Estimate Activity Duration It provides the amount of time each activity will take to complete, which is a major input to Develop Schedule process. Estimating the number of work periods needed to complete individual activities with estimated resources Activity Estimating Work Periods Complete activity
  • 22. 6.6 Develop Schedule By entering the schedule activities, duration, resources, resource availability & logical relationship in to the scheduling tools, It generates schedule model with planned dates for completing project activities. Activity sequences Activity Durations Resource Requirements Schedule Constraints Create Project Schedule Analysing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model Analyze
  • 23. 6.7 Control Schedule It defines the logical sequence of work to obtain the greatest efficiency given all project constraints. Monitoring the status of project activities to update project progress & manage changes to schedule baseline to achieve plan. Monitoring status of Project activities Update project progress Manage schedule baseline changes
  • 24. By: Anand Bobade (nmbobade@gmail.com) Cost Management includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. Initiating Planning Executing Monitoring & Controlling Closing Plan Cost management Determine Budget Control Cost Estimate Cost PMBOK Chap 7 – Project Cost Management By: Anand Bobade (nmbobade@gmail.com) Success is walking from failure to failure with no loss of enthusiasm. By: Winston Churchill
  • 25. By: Anand Bobade (nmbobade@gmail.com) 7.1 Plan Cost Management Establishes Policies, procedures & documentation for planning, managing, expending, controlling project costs. It provides guidance and direction on how the project costs will be managed throughout the project. Establishing Planning Managing Expending Controlling
  • 26. By: Anand Bobade (nmbobade@gmail.com) 7.2 Estimate Cost The process of developing an APPROXIMATION of the monetary resources needed to complete project activities. It determines the amount of cost required to complete project work. Activity1 Resource Cost Project Cost Activity2 Resource Cost Approximation
  • 27. By: Anand Bobade (nmbobade@gmail.com) 7.3 Determine Budget Aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. Determines the cost baseline against which project performance can be monitored and controlled Activity1 Resource Cost Cost Baseline Activity2 Resource Cost Contingency Reserve Aggregation
  • 28. By: Anand Bobade (nmbobade@gmail.com) 7.4 Control Cost Provides the means to recognize variance from the plan in order to take corrective action and minimize risk. Monitoring the status of the project to update the project costs & managing changes to the cost baseline. Monitoring Project status Update project Cost Manage cost baseline changes
  • 29. Quality is the degree to which the project fulfils requirements. Quality Management includes creating and following policies and procedures in order to ensure that a project meets the defined needs it was intended to meet. Initiating Planning Executing Monitoring & Controlling Closing Plan Quality management Perform Quality Assurance Control Quality management PMBOK Chap 8 – Project Quality Management If you don't have time to do it right, when will you have time to do it over? By: John Wooden By: Anand Bobade (nmbobade@gmail.com)
  • 30. 8.1 Plan Quality Management It is the process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with relevant quality requirements. Project Requirements It provides guidance & direction on how quality will be managed and validated throughout the project. By: Anand Bobade (nmbobade@gmail.com)
  • 31. 8.2 Perform Quality Assurance It facilitates the improvement of quality processes. It is the process of auditing quality requirements & results from quality control measurements to ensure that appropriate quality standards & operational definitions are used. By: Anand Bobade (nmbobade@gmail.com) Ensure Quality Standards & Operational Definitions are used Quality Requirements Quality Control Measures Results
  • 32. 8.3 Control Quality Monitoring & Recording Recommend -ation Action Action Execute Quality activities Assess Performance Recommend Changes Process of monitoring & recording results of executing quality activities to assess performance & recommend necessary changes. - Identifying causes of poor process/product quality & recommend action -Validating that project deliverables & work meet the requirements. By: Anand Bobade (nmbobade@gmail.com)
  • 33. By: Anand Bobade (nmbobade@gmail.com) PMBOK Chap 9 - Human Resource Management Includes the processes that Organize, Manage & Lead the Project Team. Initiating Planning Executing Monitoring & Controlling Closing Plan HR Management Acquire Project Team Manage Project Team Develop Project Team I am convinced that nothing we do is more important than hiring and developing people. At the end of the day you bet on people, not on strategies. – Lawrence Bossidy, GE
  • 34. By: Anand Bobade (nmbobade@gmail.com) 9.1 Plan Human Resource Management Identifying & documenting project roles, responsibilities, required skills, reporting relationships, & creating a staffing engagement plan. It establishes project roles & responsibilities, project organization charts, & the staffing management plan including the timetable of staff acquisition & release. Identifying & Documenting Roles Staff Engag’t plan Responsibilities Relationships Human Resource Management
  • 35. By: Anand Bobade (nmbobade@gmail.com) 9.2 Acquire Project Team Confirming human resource availability and obtaining the team necessary to complete project activities The key benefit consists of outlining & guiding team selection and responsibility assignment to obtain a successful team. Acquire Project Team Confirming Human Resource Availability Obtaining the Team Key Benefit Outlining Team Selection Guiding Team Selection Responsibility assignment Complete project activities Obtain a successful team
  • 36. By: Anand Bobade (nmbobade@gmail.com) 9.3 Develop Project Team Improving competencies, team member interaction, and overall team environment to enhance project performance. It results in improved teamwork, enhanced people skills & competencies, motivated employees, reduced staff turnover rates, & improved overall project performance. Improving Competencies Team Member Interaction Overall Team Environment Enhanceproject performance. Results in: Teamwork People skills Competencies Motivated Emp. Reduced turnover
  • 37. By: Anand Bobade (nmbobade@gmail.com) 9.4 Manage Project Team Tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance It influences team behavior, manages conflict, resolves issues, and appraises team member performance. Manage Project Team Tracking Performance Providing Feedback Resolving Issues Team changes Optimizeproject performance. Team Behavior Manages Conflict Resolves Issues Appraises Performance
  • 38. The process required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information. Initiating Planning Executing Monitoring & Controlling Closing Plan Communication Manage Communication Control Communication PMBOK Chap 10-Project Communication Management To effectively communicate, we must realize that we are all different in the way we perceive the world and use this understanding as a guide to our communication with others. - Anthony Robbins By: Anand Bobade (nmbobade@gmail.com) Overview
  • 39. 10.1 Plan communication Management Process of developing an appropriate approach and plan for project communications based on stakeholder’s information needs and requirements, and available organizational assets. The key benefit his process is that it identifies & documents approach to communicate most effectively and efficiently with stakeholders. Effective Communication: • Providing only the information that is needed.Efficient Communication Approach & Plan Right format Right time Right audience Right impact
  • 40. 10.2 Manage Communications It is the process of creating, collecting, distributing, storing, retrieving, and the ultimate disposition of project information in accordance to the communications management plan. The key benefit of this process is that it enables an efficient and effective communications flow between project stakeholders. Creating Collecting Distributing Storing Retrieving Disposition
  • 41. 10.3 Control Communications Process of monitoring & controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met. The key benefit of this process is that it ensures an optimal information flow among all communication participants, at any moment in time. Optimal information flow Project lifecycle Stakeholders Information Needs
  • 42. By: Anand Bobade (nmbobade@gmail.com) PMBOK Chap 11 – Project Risk Management The Objective of Project Risk Management are to increase the likelihood & impact of positive events, and decrease the likelihood & impact of negative events in the projects. Initiating Planning Executing Monitoring & Controlling Closing Plan Risk Management Perform Quantit’ve Risk Analysis Monitor and Control Risks Identify Risk Plan Risk Response Perform Qualitative Risk Analysis Risk comes from not knowing what you're doing. By: Warren Buffett
  • 43. By: Anand Bobade (nmbobade@gmail.com) 11.1 Plan Risk Management -> Definition The process of defining how to conduct risk management activities for a project. It ensures that the degree, type, and visibility of risk management are commensurate with both the risks & importance of the project to the organization. Identify Asses(Probability & Impact) Treatment (Risk Response) Monitor & Review Planning how to approach & execute project risk management activities
  • 44. By: Anand Bobade (nmbobade@gmail.com) 11.2 Identify Risk -> Definition Determine which risks may affect the project & document their characteristics The documentation of existing risks & knowledge & ability it provides to project team to anticipate events. Project Risk1 Risk2 Risk3 Risk4Risk5 Risk6 Risk7 Risk Charaterstics1 Charaterstics2 Charaterstics3 Determine Risks Documenting their characteristics
  • 45. By: Anand Bobade (nmbobade@gmail.com) 11.3 Perform Qualitative Risk Analysis-> Definition It is the process of prioritizing risks for further analysis or action by assessing & combining their probability of occurrence & impact. It enables PM to reduce the level of uncertainty and to focus on high-priority risks Focus on High Probability & high impact Risks Identified Risks Qualitative Analysis Prioritized Risk
  • 46. By: Anand Bobade (nmbobade@gmail.com) 11.4 Perform Quantitative Risk Analysis Numerically analyzing the effect of identified risks on overall project objectives. It produces quantitative risk information to support decision making in order to reduce project uncertainty. Identified Risks Quantitative Analysis Quantitative Risk Information Analyses effect on Project Objectives
  • 47. By: Anand Bobade (nmbobade@gmail.com) 11.5 Plan Risk Responses Process of developing options & actions to enhance opportunities & to reduce threats to project objectives. It addresses the risks by their priority, inserting resources & activities into the budget, schedule & PMP as needed.
  • 48. By: Anand Bobade (nmbobade@gmail.com) 11.6 Control Risks -> Definition It is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project. It improves efficiency of risk approach throughout project life cycle to continuously optimize risk responses. Risk Response Plans Tracking identified risks Monitoring residual risks Identifying new risks Implementing
  • 49. By: Anand Bobade (nmbobade@gmail.com) PMBOK Chap 12 – Project Procurement Management The processes necessary to purchase or acquire product, services, or results needed from outside the project team. Initiating Planning Executing Monitoring & Controlling Closing Plan Procurement Management Conduct Procurement Control Procurement Close Procurement We cannot solve our problems with the same thinking we used when we created them. - Albert Einstein
  • 50. By: Anand Bobade (nmbobade@gmail.com) 12.1 Plan Procurement Management The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers. It determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it. Procurement decisions Specifying approach Identifying potential sellers.
  • 51. By: Anand Bobade (nmbobade@gmail.com) 12.2 Conduct Procurement The process of obtaining seller responses, selecting a seller, and awarding a contract. It provides alignment of internal & external stakeholder expectations through established agreements. Seller1 Responses Seller2 Responses Seller3 Responses Seller4 Responses Selection process Review prop. Evaluate Seller Obtaining seller responses Selecting a seller Selected Seller Awarding a Contract
  • 52. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement The process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate. It ensures that both the seller’s & buyer’s performance meets procurement requirements according to the terms of the legal agreement. Managing procurement relationships Monitoring contract performance Making changes and corrections to contracts
  • 53. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement The process of completing each procurement. It documents agreements and related documentation for future reference. Procurement 1 Procurement 2 Individual procurement Closure
  • 54. By: Anand Bobade (nmbobade@gmail.com) PMBOK Chap 13– Stakeholder Management Identifying the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies. Initiating Planning Executing Monitoring & Controlling Closing Identify Stakeholders Plan Stakeholder Management Manage Stakeholder Engagement Control Stakeholder Engagement The conventional definition of management is getting work done through people, but real management is developing people through work.
  • 55. By: Anand Bobade (nmbobade@gmail.com) 13.1 Identify Stakeholders Identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project, Analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success. Identifying Decision Activity Outcome People Group Organization Impact or Impacted by Project
  • 56. By: Anand Bobade (nmbobade@gmail.com) 13.2 Plan Stakeholder Management Developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success. Engage StakeholdersDeveloping Strategies To Needs Interests Impact Analyzing
  • 57. By: Anand Bobade (nmbobade@gmail.com) 13.3 Manage Stakeholder Engagement Communicating & working with stakeholders to meet their needs/ expectations, address issues as they occur, & foster appropriate stakeholder engagement in project activities throughout project life cycle. Increase support & minimize resistance from stakeholders, significantly increasing the chances to achieve project success. Communicating & working with stakeholder Meet Needs, expectations & address issues Foster stakeholders engagement
  • 58. By: Anand Bobade (nmbobade@gmail.com) 13.4 Control Stakeholder Engagement Monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders It will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes. Monitoring stakeholder relationships Adjusting strategies and plans Engaging stakeholders
  • 59. Additional Free Resources Visit Slide Share website & you will find other Knowledge area presentation… Please share!!