Schedule the following activities using CPM: b. What is the critical path? multiple choice 1 A-C-E-F-G-H A-B-E-H A-B-D-F-G-H A-B-D-E-H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? multiple choice 2 E 1 week H 2 weeks. C 5 weeks E 2 weeks. B 1 week D 3 weeks. ACTIVITYIMMEDIATE PREDECESSORTIME (WEEKS)A3BA4CA5DB4EC D8FD6GF4HE G5.