Monthly Status
Briefing
November 2012
Project Background

   The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely
    destroy 2,611 tons of mustard agent in mortar rounds and artillery
    projectiles stored at the U.S. Army Pueblo Chemical Depot (PCD).

   Neutralization followed by biotreatment is the technology selected by the
    Department of Defense to destroy the Pueblo chemical weapons stockpile.

   The Program Executive Officer, Assembled Chemical Weapons Alternatives
    (ACWA), headquartered at Aberdeen Proving Ground, Maryland, is
    responsible for managing all aspects of the safe and environmentally sound
    destruction of the chemical weapons stockpiles in Colorado and Kentucky.

   The Bechtel Pueblo Team (BPT) is a partnership of Bechtel National, Inc.,
    URS, Parsons, and Battelle Memorial Institute. The BPT functions as the
    systems contractor selected to design, build, systemize, pilot test, operate,
    and close the PCAPP.



                                                                                    2
Bechtel Pueblo Team

                        Systems Contractor

 Project management                          Design/engineering
 Business services                           Procurement/subcontracting
 Safety and quality                          Construction



                       Teaming Subcontractors




   Systemization    Process design              Environmental permitting
   Pilot testing    Process equipment            and compliance
   Operations        fabrication                 Laboratory management
   Closure          Support to systemization    Pilot testing
                      and operations


                                                                              3
Staffing


            Bechtel Pueblo Team
             non-manual: 653
                –   Pueblo County local hires: 139

                – Colorado hires (outside Pueblo
                 County): 37
                – Other locations: 3


            Construction Workers: 373
                – Bechtel direct-hire craft workers:
                  102
                – Subcontractor personnel: 89




                                                       4
Employment Opportunities


        Hotline

     (719)549-4003

        Website

http://pueblo.bechtel.com




                            5
Safety


             As of October 31, 2012,
         PCAPP Project staff accomplished:

               188 Safe Work Days

               1,058,213 Safe Work Hours




                                             6
Destruction Technology


  Step 1   Removal of Energetics                   Step 4    Biotreatment
           Robotic equipment removes energetics              Microbes treat the hydrolysate,
           (explosives) from the weapon. The                 breaking it down into brine. The brine
           energetics will be disposed of at a               is separated with water being recycled
           permitted facility offsite.                       back to the plant and salt cakes shipped
                                                             for disposal at a permitted facility.

 Step 2    Removal of                               Step 5   Thermal Treatment and
           Mustard Agent                                     Disposal of Metal Parts
           The inside of the weapon is remotely              Metal Parts are heated to 1,000 degrees
           accessed and mustard agent is washed              Fahrenheit for 15 minutes and can then
           out with high-pressure water.                     be recycled.


 Step 3    Neutralization of                       Neutralization followed by
           Mustard Agent                           biotreatment will be used to
           The mustard agent is neutralized with   destroy the Colorado chemical
           caustic solution and hot water. The
           byproduct is called hydrolysate.        weapons stockpile.




                                                                                                        7
Pueblo Chemical Agent-Destruction
Pilot Plant—Site Plan




                                    8
PCAPP Site Overview


            4                                              3
                                                                         7
                                 5
                                                 2

                            1




                                     6
                                                                    8




                          Northwestern Corner - Observation Point

       1   Enhanced Reconfiguration Building         5    Agent Filtration Area
       2   Automated Guided Vehicle Corridor         6    Munitions Service Magazine
       3   Agent Processing Building                 7    Control and Support Building
       4   Biotreatment Area                         8    Munitions Service Magazine corridor


                                                                                                9
Systemization

As the project transitions from construction to systemization, the
following systems have been turned over to the start-up group to begin
the systemization process:
                                                            Steam and Condensate—APB/Biotreatment Area
   Plant & Instrument Air
                                                             (BTA)/Brine Reduction System (BRS) Distribution
   Hot Process Water—Agent Processing Building
                                                            Bulk Chemical Storage and Distribution—DAP, UREA
    (APB) Hot Process Water Tank and Heating Coil.
                                                             and 25% caustic
   Agent Collection and Neutralization System—
                                                            Projectile Handling and Projectile Disassembly—
    Hydrolysate Collection and Storage—Yard
                                                             Projectile Mortar Disassembly systems and Related
   HVAC Hot Water—Pumps and related tanks, Heat             Equipment—Lines 1, 2, and 3
    Exchangers and Outside Rack Piping

   Breathing Air—A & B Compressor/Purifier
    Packages, Receiver and Chiller, Bottle Filling
    Station

   Enhanced Reconfiguration Building (ERB) Supply
    Air Handling Units/Control Room and Support
    Areas Ventilation System

   Steam Supply—Fuel Oil Piping, Natural Gas
    Piping, Amine Feed Skid, Boilers A & B" and
    Outside Rack Steam

   ERB 480V Substation

                                  To learn more about Systemization, watch the video at
                             http://www.peoacwa.army.mil/info/video/systemization_yt.html

                                                                                                               10
Systemization (cont.)
    Brine Reduction Belt Feed System
                                                          Critical Power Panels—ERB
    Chilled Water—Chillers, Distribution to various
                                                          Essential Power Panel—ECF
     HVAC units, recirculation units, autoclave and
     Off-Gas Treatment scrubber                           Water Recovery—Brine Concentrator Feed Tanks
                                                           “A“, “B”, and “C” and BC Feed Tanks Off-Gas Treatment
    Decon Solution Storage and Distribution—APB
                                                          Munitions Washout System-Instrument Air Distribution,
    Immobilized Cell Bioreactor (ICB) Feed,
                                                           Process Water Distribution, Hydraulic Power Line 1 & 2
     Biotreatment, ICB Blower and Off Gas
     Treatment—Modules 1/2/3/4                            Munitions Treatment Unit*
    Plant Air–BTA, APB and ERB Distribution

    Process Cooling Water—BRS Distribution

    Potable Water—ERB, APB and BRS

    ERB Electrical Room Ventilation System

    Munitions/Parts Monitoring-ERB

    Process Cooling Water—PCW Pumps, Tanks,
     Chemical Feed Skids, Cooling Towers, BRS
     Distribution

    Main Sanitary Waste—Lift Stations, Waste
     Tank and Pumps

    Non-Essential Power Panel-Entry Control
     Facility (ECF)

                                   To learn more about Systemization, watch the video at            *Newly added
                              http://www.peoacwa.army.mil/info/video/systemization_yt.html

                                                                                                                    11
Treaty Building




       Formerly the general foreman’s trailer, the treaty trailer now sits in its
       permanent location on the PCAPP site. The trailer was moved in three
       sections in early November.

                                                                                    12
Agent Processing Building




       This lift assist will be used to place munitions on the feed conveyors to the
       Projectile Mortar Disassembly machines and the Munitions Washout Station
       feed conveyors.

                                                                                       13
Agent Processing Building




      The Munitions Treatment Unit awaits testing in the APB. Agent residue left in
      the munition bodies will be thermally treated to 1,000 degrees Fahrenheit.

                                                                                      14
Executive Visit




        Bechtel President and Chief Operating Officer Bill Dudley (third from left) visited
        PCAPP earlier this month, accompanied by Executive Assistant Carlos Ruiz (left) and
        General Manager of Defense and Security Greg Frank (right). Project Manager Doug
        Omichinski (second from right) and Construction Manager Ryan Atwell (yellow hat),
        lead the tour.

                                                                                              15
Contact Information


    Pueblo Chemical                  U.S. Army
Stockpile Outreach Office      Pueblo Chemical Depot
     104 West B Street           45825 Highway 96 East
       719-546-0400                  719-549-4135

       Tom Schultz                 Chuck Sprague
            PCAPP                  Public Affairs Officer
   Public Affairs Specialist
                                      Ken Roque
       Geoff Roper             Deputy Public Affairs Officer
    Community Outreach
        Manager

     Sandy Romero
    Bechtel Pueblo Team
  Communications Manager


                                                               16

Mais conteúdo relacionado

Mais procurados

Bio Storage Labs & Repository Overview
Bio Storage  Labs & Repository OverviewBio Storage  Labs & Repository Overview
Bio Storage Labs & Repository Overviewtanyaray
 
Kinetics & Reactor Modeling
Kinetics & Reactor ModelingKinetics & Reactor Modeling
Kinetics & Reactor Modelingrkasharma
 
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...Gerard B. Hawkins
 
(Bio)pharmaceutical plant design
(Bio)pharmaceutical plant design(Bio)pharmaceutical plant design
(Bio)pharmaceutical plant designMarcin Konarski
 
Dosing strong acid and caustic soda
Dosing strong acid and caustic sodaDosing strong acid and caustic soda
Dosing strong acid and caustic sodajoostjansma
 
Choosing Hydroprocessing Scheme
Choosing Hydroprocessing SchemeChoosing Hydroprocessing Scheme
Choosing Hydroprocessing Schemeguest99f5e58
 
Technical Paper About Refinery Hydroprocessing Technology Selection.Pdf
Technical Paper About Refinery Hydroprocessing Technology Selection.PdfTechnical Paper About Refinery Hydroprocessing Technology Selection.Pdf
Technical Paper About Refinery Hydroprocessing Technology Selection.PdfAlpesh Gurjar
 

Mais procurados (20)

September 2012 BGCAPP Monthly Status Briefing
September 2012 BGCAPP Monthly Status BriefingSeptember 2012 BGCAPP Monthly Status Briefing
September 2012 BGCAPP Monthly Status Briefing
 
June 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
June 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...June 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
June 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
 
Modelling, Simulation and Optimization of Refining Processes
Modelling, Simulation and Optimization of Refining ProcessesModelling, Simulation and Optimization of Refining Processes
Modelling, Simulation and Optimization of Refining Processes
 
August 2012 BGCAPP Monthly Status Briefing
August 2012 BGCAPP Monthly Status BriefingAugust 2012 BGCAPP Monthly Status Briefing
August 2012 BGCAPP Monthly Status Briefing
 
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
 
BGCAPP Monthly Status Briefing December 2011
BGCAPP Monthly Status Briefing December 2011BGCAPP Monthly Status Briefing December 2011
BGCAPP Monthly Status Briefing December 2011
 
BGCAPP Monthly Status Briefing November 2011
BGCAPP Monthly Status Briefing November 2011BGCAPP Monthly Status Briefing November 2011
BGCAPP Monthly Status Briefing November 2011
 
March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
 
May 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Brief...
May 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Brief...May 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Brief...
May 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Brief...
 
July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
 
BGCAPP Monthly Status Briefing - September 2011
BGCAPP Monthly Status Briefing - September 2011BGCAPP Monthly Status Briefing - September 2011
BGCAPP Monthly Status Briefing - September 2011
 
Bio Storage Labs & Repository Overview
Bio Storage  Labs & Repository OverviewBio Storage  Labs & Repository Overview
Bio Storage Labs & Repository Overview
 
BGCAPP Monthly Status Briefing October 2011
BGCAPP Monthly Status Briefing October 2011BGCAPP Monthly Status Briefing October 2011
BGCAPP Monthly Status Briefing October 2011
 
Kinetics & Reactor Modeling
Kinetics & Reactor ModelingKinetics & Reactor Modeling
Kinetics & Reactor Modeling
 
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...PRE-SULFIDING & ON-LINE SULFIDING of  VULCAN Series CoMo and NiMo Catalyst in...
PRE-SULFIDING & ON-LINE SULFIDING of VULCAN Series CoMo and NiMo Catalyst in...
 
(Bio)pharmaceutical plant design
(Bio)pharmaceutical plant design(Bio)pharmaceutical plant design
(Bio)pharmaceutical plant design
 
Desalination
DesalinationDesalination
Desalination
 
Dosing strong acid and caustic soda
Dosing strong acid and caustic sodaDosing strong acid and caustic soda
Dosing strong acid and caustic soda
 
Choosing Hydroprocessing Scheme
Choosing Hydroprocessing SchemeChoosing Hydroprocessing Scheme
Choosing Hydroprocessing Scheme
 
Technical Paper About Refinery Hydroprocessing Technology Selection.Pdf
Technical Paper About Refinery Hydroprocessing Technology Selection.PdfTechnical Paper About Refinery Hydroprocessing Technology Selection.Pdf
Technical Paper About Refinery Hydroprocessing Technology Selection.Pdf
 

Semelhante a November 2012 BGCAPP Monthly Status Briefing

General Water Treatment For Cooling Water
General Water Treatment For Cooling WaterGeneral Water Treatment For Cooling Water
General Water Treatment For Cooling WaterGerard B. Hawkins
 
Shell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling WaterShell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling WaterGerard B. Hawkins
 
Selection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation ColumnsSelection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation ColumnsGerard B. Hawkins
 
Biological Systems - A Special Case
Biological Systems - A Special CaseBiological Systems - A Special Case
Biological Systems - A Special CaseGerard B. Hawkins
 
Code of Practice - Centrifugal Pump Operation and Maintenance
Code of Practice - Centrifugal Pump Operation and Maintenance Code of Practice - Centrifugal Pump Operation and Maintenance
Code of Practice - Centrifugal Pump Operation and Maintenance Gerard B. Hawkins
 
Physical Properties for Heat Exchanger Design
Physical Properties for Heat Exchanger DesignPhysical Properties for Heat Exchanger Design
Physical Properties for Heat Exchanger DesignGerard B. Hawkins
 
Shortcut Methods of Distillation Design
Shortcut Methods of Distillation DesignShortcut Methods of Distillation Design
Shortcut Methods of Distillation DesignGerard B. Hawkins
 
Reactor Modeling Tools - An Overview
Reactor Modeling Tools - An OverviewReactor Modeling Tools - An Overview
Reactor Modeling Tools - An OverviewGerard B. Hawkins
 
2012 ERN Conference - Oral Presentation
2012 ERN Conference - Oral Presentation2012 ERN Conference - Oral Presentation
2012 ERN Conference - Oral PresentationWilliam Broughton
 
HPL Report on Pumps in IOP by Subham Shit
HPL Report on Pumps in IOP by Subham ShitHPL Report on Pumps in IOP by Subham Shit
HPL Report on Pumps in IOP by Subham ShitSubham Shît
 
HPL Report on Pumps in IOP by Subham Shit [Final]
HPL Report on Pumps in IOP by Subham Shit [Final]HPL Report on Pumps in IOP by Subham Shit [Final]
HPL Report on Pumps in IOP by Subham Shit [Final]Subham Shit
 
Selection of Heat Exchanger Types
Selection of Heat Exchanger TypesSelection of Heat Exchanger Types
Selection of Heat Exchanger TypesGerard B. Hawkins
 

Semelhante a November 2012 BGCAPP Monthly Status Briefing (20)

April 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Bri...
April 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Bri...April 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Bri...
April 2012 - Pueblo Chemical Agent-Destruction Pilot Plant Monthly Status Bri...
 
PCAPP Monthly Status Briefing October 2011
PCAPP Monthly Status Briefing October 2011PCAPP Monthly Status Briefing October 2011
PCAPP Monthly Status Briefing October 2011
 
PCAPP Monthly Status Briefing - September 2011
PCAPP Monthly Status Briefing - September 2011PCAPP Monthly Status Briefing - September 2011
PCAPP Monthly Status Briefing - September 2011
 
PCAPP Monthly Status Briefing November 2011
PCAPP Monthly Status Briefing November 2011PCAPP Monthly Status Briefing November 2011
PCAPP Monthly Status Briefing November 2011
 
October 2012 BGCAPP Monthly Status Briefing
October 2012 BGCAPP Monthly Status BriefingOctober 2012 BGCAPP Monthly Status Briefing
October 2012 BGCAPP Monthly Status Briefing
 
General Water Treatment For Cooling Water
General Water Treatment For Cooling WaterGeneral Water Treatment For Cooling Water
General Water Treatment For Cooling Water
 
Shell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling WaterShell and Tube Heat Exchangers Using Cooling Water
Shell and Tube Heat Exchangers Using Cooling Water
 
Selection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation ColumnsSelection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation Columns
 
Biological Systems - A Special Case
Biological Systems - A Special CaseBiological Systems - A Special Case
Biological Systems - A Special Case
 
Code of Practice - Centrifugal Pump Operation and Maintenance
Code of Practice - Centrifugal Pump Operation and Maintenance Code of Practice - Centrifugal Pump Operation and Maintenance
Code of Practice - Centrifugal Pump Operation and Maintenance
 
Physical Properties for Heat Exchanger Design
Physical Properties for Heat Exchanger DesignPhysical Properties for Heat Exchanger Design
Physical Properties for Heat Exchanger Design
 
Shortcut Methods of Distillation Design
Shortcut Methods of Distillation DesignShortcut Methods of Distillation Design
Shortcut Methods of Distillation Design
 
December 2012 BGCAPP Monthly Status Briefing
December 2012 BGCAPP Monthly Status BriefingDecember 2012 BGCAPP Monthly Status Briefing
December 2012 BGCAPP Monthly Status Briefing
 
Reactor Modeling Tools - An Overview
Reactor Modeling Tools - An OverviewReactor Modeling Tools - An Overview
Reactor Modeling Tools - An Overview
 
2012 ERN Conference - Oral Presentation
2012 ERN Conference - Oral Presentation2012 ERN Conference - Oral Presentation
2012 ERN Conference - Oral Presentation
 
HPL Report on Pumps in IOP by Subham Shit
HPL Report on Pumps in IOP by Subham ShitHPL Report on Pumps in IOP by Subham Shit
HPL Report on Pumps in IOP by Subham Shit
 
HPL Report on Pumps in IOP by Subham Shit [Final]
HPL Report on Pumps in IOP by Subham Shit [Final]HPL Report on Pumps in IOP by Subham Shit [Final]
HPL Report on Pumps in IOP by Subham Shit [Final]
 
Selection of Heat Exchanger Types
Selection of Heat Exchanger TypesSelection of Heat Exchanger Types
Selection of Heat Exchanger Types
 
Boiler Feedwater Pumps
Boiler Feedwater PumpsBoiler Feedwater Pumps
Boiler Feedwater Pumps
 
Simon Lovich, Air Engineers
Simon Lovich, Air Engineers Simon Lovich, Air Engineers
Simon Lovich, Air Engineers
 

Mais de Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

Mais de Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013
 
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 

November 2012 BGCAPP Monthly Status Briefing

  • 2. Project Background  The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611 tons of mustard agent in mortar rounds and artillery projectiles stored at the U.S. Army Pueblo Chemical Depot (PCD).  Neutralization followed by biotreatment is the technology selected by the Department of Defense to destroy the Pueblo chemical weapons stockpile.  The Program Executive Officer, Assembled Chemical Weapons Alternatives (ACWA), headquartered at Aberdeen Proving Ground, Maryland, is responsible for managing all aspects of the safe and environmentally sound destruction of the chemical weapons stockpiles in Colorado and Kentucky.  The Bechtel Pueblo Team (BPT) is a partnership of Bechtel National, Inc., URS, Parsons, and Battelle Memorial Institute. The BPT functions as the systems contractor selected to design, build, systemize, pilot test, operate, and close the PCAPP. 2
  • 3. Bechtel Pueblo Team Systems Contractor  Project management  Design/engineering  Business services  Procurement/subcontracting  Safety and quality  Construction Teaming Subcontractors  Systemization  Process design  Environmental permitting  Pilot testing  Process equipment and compliance  Operations fabrication  Laboratory management  Closure  Support to systemization  Pilot testing and operations 3
  • 4. Staffing  Bechtel Pueblo Team non-manual: 653 – Pueblo County local hires: 139 – Colorado hires (outside Pueblo County): 37 – Other locations: 3  Construction Workers: 373 – Bechtel direct-hire craft workers: 102 – Subcontractor personnel: 89 4
  • 5. Employment Opportunities Hotline (719)549-4003 Website http://pueblo.bechtel.com 5
  • 6. Safety As of October 31, 2012, PCAPP Project staff accomplished:  188 Safe Work Days  1,058,213 Safe Work Hours 6
  • 7. Destruction Technology Step 1 Removal of Energetics Step 4 Biotreatment Robotic equipment removes energetics Microbes treat the hydrolysate, (explosives) from the weapon. The breaking it down into brine. The brine energetics will be disposed of at a is separated with water being recycled permitted facility offsite. back to the plant and salt cakes shipped for disposal at a permitted facility. Step 2 Removal of Step 5 Thermal Treatment and Mustard Agent Disposal of Metal Parts The inside of the weapon is remotely Metal Parts are heated to 1,000 degrees accessed and mustard agent is washed Fahrenheit for 15 minutes and can then out with high-pressure water. be recycled. Step 3 Neutralization of Neutralization followed by Mustard Agent biotreatment will be used to The mustard agent is neutralized with destroy the Colorado chemical caustic solution and hot water. The byproduct is called hydrolysate. weapons stockpile. 7
  • 9. PCAPP Site Overview 4 3 7 5 2 1 6 8 Northwestern Corner - Observation Point 1 Enhanced Reconfiguration Building 5 Agent Filtration Area 2 Automated Guided Vehicle Corridor 6 Munitions Service Magazine 3 Agent Processing Building 7 Control and Support Building 4 Biotreatment Area 8 Munitions Service Magazine corridor 9
  • 10. Systemization As the project transitions from construction to systemization, the following systems have been turned over to the start-up group to begin the systemization process:  Steam and Condensate—APB/Biotreatment Area  Plant & Instrument Air (BTA)/Brine Reduction System (BRS) Distribution  Hot Process Water—Agent Processing Building  Bulk Chemical Storage and Distribution—DAP, UREA (APB) Hot Process Water Tank and Heating Coil. and 25% caustic  Agent Collection and Neutralization System—  Projectile Handling and Projectile Disassembly— Hydrolysate Collection and Storage—Yard Projectile Mortar Disassembly systems and Related  HVAC Hot Water—Pumps and related tanks, Heat Equipment—Lines 1, 2, and 3 Exchangers and Outside Rack Piping  Breathing Air—A & B Compressor/Purifier Packages, Receiver and Chiller, Bottle Filling Station  Enhanced Reconfiguration Building (ERB) Supply Air Handling Units/Control Room and Support Areas Ventilation System  Steam Supply—Fuel Oil Piping, Natural Gas Piping, Amine Feed Skid, Boilers A & B" and Outside Rack Steam  ERB 480V Substation To learn more about Systemization, watch the video at http://www.peoacwa.army.mil/info/video/systemization_yt.html 10
  • 11. Systemization (cont.)  Brine Reduction Belt Feed System  Critical Power Panels—ERB  Chilled Water—Chillers, Distribution to various  Essential Power Panel—ECF HVAC units, recirculation units, autoclave and Off-Gas Treatment scrubber  Water Recovery—Brine Concentrator Feed Tanks “A“, “B”, and “C” and BC Feed Tanks Off-Gas Treatment  Decon Solution Storage and Distribution—APB  Munitions Washout System-Instrument Air Distribution,  Immobilized Cell Bioreactor (ICB) Feed, Process Water Distribution, Hydraulic Power Line 1 & 2 Biotreatment, ICB Blower and Off Gas Treatment—Modules 1/2/3/4  Munitions Treatment Unit*  Plant Air–BTA, APB and ERB Distribution  Process Cooling Water—BRS Distribution  Potable Water—ERB, APB and BRS  ERB Electrical Room Ventilation System  Munitions/Parts Monitoring-ERB  Process Cooling Water—PCW Pumps, Tanks, Chemical Feed Skids, Cooling Towers, BRS Distribution  Main Sanitary Waste—Lift Stations, Waste Tank and Pumps  Non-Essential Power Panel-Entry Control Facility (ECF) To learn more about Systemization, watch the video at *Newly added http://www.peoacwa.army.mil/info/video/systemization_yt.html 11
  • 12. Treaty Building Formerly the general foreman’s trailer, the treaty trailer now sits in its permanent location on the PCAPP site. The trailer was moved in three sections in early November. 12
  • 13. Agent Processing Building This lift assist will be used to place munitions on the feed conveyors to the Projectile Mortar Disassembly machines and the Munitions Washout Station feed conveyors. 13
  • 14. Agent Processing Building The Munitions Treatment Unit awaits testing in the APB. Agent residue left in the munition bodies will be thermally treated to 1,000 degrees Fahrenheit. 14
  • 15. Executive Visit Bechtel President and Chief Operating Officer Bill Dudley (third from left) visited PCAPP earlier this month, accompanied by Executive Assistant Carlos Ruiz (left) and General Manager of Defense and Security Greg Frank (right). Project Manager Doug Omichinski (second from right) and Construction Manager Ryan Atwell (yellow hat), lead the tour. 15
  • 16. Contact Information Pueblo Chemical U.S. Army Stockpile Outreach Office Pueblo Chemical Depot 104 West B Street 45825 Highway 96 East 719-546-0400 719-549-4135 Tom Schultz Chuck Sprague PCAPP Public Affairs Officer Public Affairs Specialist Ken Roque Geoff Roper Deputy Public Affairs Officer Community Outreach Manager Sandy Romero Bechtel Pueblo Team Communications Manager 16