SlideShare uma empresa Scribd logo
1 de 5
Baixar para ler offline
Ranking of “Causes of Disputes” and “Use of Dispute
Resolution Methods” for Construction Industry in Gujarat
Dr Rajiv Bhatt1
, Abhishek Shah2
, Prof J J Bhavsar3
1
Associate Professor, Civil Engineering Department, A.D.Patel Institute of Technology, Karamsad, Gujarat, India
E-mail: rajiv7967@gmail.com
2
P.G. Scholar, Construction Engineering and Management section, Civil Engineering Department, Birla Vishvakarma Mahavidyalaya,
V.V.Nagar, Gujarat, India
E-mail: abhishekshah51@gmail.com
3
Associate Professor, Civil Engineering Department, Birla Vishvakarma Mahavidyalaya, V.V.Nagar, Gujarat, India
E-mail: jjbhavsar@bvmengineering.ac.in
Abstract:
Presently India is in the developing phase which brings tremendous growth of construction industry.
Construction industry is witnessing all kinds of projects across the country. Many projects are suffering
from major issues like conflict between parties, claim generations and dispute occurrence. This study
focuses on ranking of factors which contributes as “Causes of Disputes”, “Impact on project scenario” and
“Use of Dispute resolution methods”. During this study, 70 feedbacks were collected from Architects,
Contractors and Developers from Ahmedabad city of Gujarat state of India. Responses were analyzed by
Weighted Average Method and Relative Importance Index method. It was found that “Finance and payment
issues”, “Poor work quality” and “Extra items” are the three major causes which contribute for occurrence of
disputes. This study found that due to arising of dispute reputation of both the parties gets disturbed.
Keywords: Disputes, Construction Industry, Weighted Average Index, Relative Importance Index
Introduction
India is a developing country. The construction
sector of India is growing rapidly. There are
many ongoing Infrastructure projects in India of
Billions of Dollars where the delay or stoppage of
work due to any reason cannot be acceptable. In
this rapidly growing construction industry many
times claims arise between client and contractors.
Construction Claim can be defined as a request
by either party to the contract, usually the
Contractor, for compensation for damages caused
by failure of the other party to fulfill his part of
obligations as specified in the contract. The
compensation is usually in the form of the
additional payment or an extension of time
(EOT).
Construction claims are measured by many
project participants to be one of the most
disturbing and unpleasant events of a project.
Today, construction projects are the subject
matter of more claims than in any other industry.
The high competition has forced contractors to
submit projects with minimum profits in order to
stay in business. In addition to their multiparty
nature, projects are becoming more complex and
risky. This has placed an added burden on
contractors to construct increasingly sophisticated
and risky projects with less resources and profits.
Under these circumstances, it is not surprising
that the number of claims within the construction
industry continues to increase.
During the execution of a project, several issues
arise that cannot be resolver among project
participants. Such issues typically involve
contractor requesting for either time extension or
for additional cost, or sometimes both. Such
requests by the contractor are referred as Claims.
However if the owner does not agree to the
claims put out by the contractor and there are
differences in the interpretations, the issue takes
the form of dispute. Claims are becoming an
inevitable and unavoidable stress in modern
projects involving new technology, specifications
and high expectations from the owner.
Construction claims are defined as
“a request for compensation for damages incurred
by any party to a contract” (Semple et al, 1994).
Construction dispute are defined as “any contract
question or controversy that must be settled
beyond the jobsite management” (Diekmann and
Girard, 1995).
There are many reasons for claims time,
machinery, material, manpower, money, price
escalation, accident on site, change in design and
many other are major reasons for dispute between
two parties which results into disputes, if the
disputes are Claims and Counterclaims.
To solve this Claims there are certain dispute
resolution techniques are available like
arbitration, conciliation, mediation dispute
resolution board. In this paper authors have listed
17 different causes for occurrence of disputes in
construction industry. Further 8 different issue
matters are listed which are created in project
scenario as an impact of dispute occurrence. Total
8 different methods are found which are
prevailing as on today among construction
stakeholders for dispute resolution. Objective of
this paper is to develop ranking of causes, impact
on issues and use of DRM‟s through statistical
techniques.
Literature Review
As per study carried out by Zaneldin.E.K (2006),
“Changes” and “Extra work” are the two major causes
for dispute generation in UAE. They concluded that
„„change orders‟‟ are the most frequent cause of
claims while „„delay caused by owner‟‟ was
ranked second. „„Planning errors‟‟ were ranked
last, indicating that it is the least frequent cause of
claims. Cakmak.E and Cakmak.P.I (2014) carried
out the study of causes of disputes in construction
industry of Turkey by Analytic Network
technique. They have classified the causes under
seven different categories as: Owner related,
Contractor related, Design related, Contract
related, Human behavior related, Project related
and External factors. Edwin H.W. Chan and
Henry C.H. Suen (2004) found that arbitration is
the most popular dispute resolution mechanism,
after negotiation, for resolving disputes in
international construction disputes in China.
Research Methodology
In this paper authors have tried to work out ranking of
causes of disputes in construction industry along with
ranking of impacts of these disputes. Further this work
includes the ranking of various methods used by
construction industry for dispute resolution. The
survey questionnaire was designed to get the ranking
of above three issues by suitable technique. The
Survey questionnaire is given in appendix 1. The
survey questionnaire is made of four sections. Section
A includes demographic information of respondents.
Section B includes questions about causes of
construction disputes. Section C includes Impacts of
disputes and Section D includes ranking for dispute
resolution methods. Respondents has to tick mark any
one option for each raw under the category of
Strongly disagree(1), Disagree(2), Neutral(3),
Agree(4) and Strongly Agree(5).
It was planned to collect the feedbacks from various
stakeholders of construction industry from
Ahmedabad city of Gujarat state of India. The survey
has included Architects, Contractors and Developers.
This research work includes use of Weighted Average
Method (W.I) and Relative Importance Index method
(R.I.I).
Data Collection
The total population data was collected from different
sources of the city which is as given below: Number
of Builders, Contractors and Architects in Ahmedabad
according to Ahmedabad Urban Development
Authority (AUDA) = 1714 Sample size required for
the present study was calculated as given below.
of Builder / Developers, Contractors / Engineers and
Architects in Ahmedabad according to Ahmedabad
Urban Development Authority ( AUDA ) = 1714
Sample size required for the present study was
calculated as given below.
The formula below was used to determine the sample
size of unlimited population (Creative Research
Systems, 2001):
SS = [Z2
× P × (1-P)] / C2
Where,
SS = Sample Size.
Z = Z Value (e.g. 1.96 for 95% confidence
interval).
P = Percentage picking a choice, expressed as
decimal, (0.50 used for sample size needed).
C = Confidence interval (0.1)
POP = Population
SS = [1.962
× 0.5 × (1- 0.5)] / .12
= 96.04
Correction for finite population:
POP
SS
SS
SSnew
1
1



99.90
1714
104.96
1
04.96



newSS
So, total responses required are 91. During the data
collection stage, total 105 questionnaire were
distributed out of which 70 feedbacks were recived
back. Out of the total responses, 36 were from
Contractors, 23 from Developers, and 11 were from
Architects.
Data Analysis
This research work has used following two methods
for carrying out ranking work.
1. WEIGHTED AVERAGE METHOD: Data of
all these table were analyzed by a weighted
average was calculated for each type of claims
as follows:
Weighted Average Index = (Wi* Xi) / N;
where Wi is the weight assigned to the ith
option; Xi is the number of respondents who
selected the ith
option; and N is the total number
of respondents (70 in this study).
Table 1: Rank of causes of disputes by different
methods
Sr.
No. Cause
Rank as
per W.I
Method
Rank as
per R.I.I
method
1
Finance and Payment
Issue 1 1
2 Time Overrun 7 7
3 Cost Overrun 6 6
4 Price Escalation 14 14
5 Work Change Orders 5 5
6 Poor Communication 12 12
7 Design Errors 4 4
8 Inclement Weather 17 17
9 Extra Items 3 3
10
Unforseen Site
Condition 13 13
11 Poor Work Quality 2 2
12
Incomplete
information in Tender 9 9
13
Delay in issuing Site,
Drawings, Materials 8 8
14
Return of Security
Deposit 16 16
15
Unfair allocation of
Risk 15 15
16
Delay in Clients
Response 11 11
17
Mistakes in Contract
Document 10 10
2. RII INDEX METHOD: Data of all these table
were analyzed by a RII Index was calculated
for each type of claims as follows:
RII Index = Σ W/ (A*N)
Where, W = weighting given to each factor by the
respondents which ranges from 1 to 5,
A = highest weight (i.e. 5 in this case) and
N = total number of respondents.
According to above two methods ranking of causes of
construction disputes are found as per table 1 given
below.
Regarding Impact of causes of disputes on various
situations of construction project, ranking by
respondents is given in table 2.
Table 2: Ranking for Impact on various issues by
WI and RII methods
Sr.
No.
Impact matter
Rank
as per
W.I
Method
Rank
as per
R.I.I
method
1
Damaged business
relationship 2 2
2 Increased project costs 3 3
3 Project Delays 6 6
4 Undermine team spirit 7 7
5
Damaging company
reputation 1 1
6 Dispute escalation 8 8
7 Poor client satisfaction 5 5
8
Delay in project
completion 4 4
Regarding ranking of dispute resolution techniques,
findings are given below in table 3.
Table 3: Ranking to use of DRM by WI and RII
method
Sr.
No.
Dispute Resolution
Methods
Rank as
per W.I
Method
Rank as
per
R.I.I
method
A Adjuducation 5 5
B Arbitration 6 6
C Dispute Review Board 7 7
D Expert Determination 3 3
E Litigation 8 8
F Mini-trial 4 4
G Mediation 2 2
H Negotiation 1 1
Results and Discussion:
From present study it is found that “Finance and
payment issues” is having first rank among all causes
for generation of dispute. Second rank was given to
“Poor work quality” by the respondents. “Extra items”
is having third rank and “Design errors” is having
fourth rank in causes of disputes. “Inclement weather”
is having lowest rank. Respondents felt that disputes
in construction industry damages the reputation of
both the parties. This is found by getting first rank for
“Damaging company reputation” in Impact matters.
Further, respondents have given lowest rank to
“Dispute Escalation” matter. Respondents have given
first rank to “Negotiation” method for dispute
resolution and last rank is given to “Litigation”
method.
Conclusion
Present study focuses on study of causes of
construction disputes, it‟s impact on various aspects
and different methods used for dispute resolution.
Weighted average method [W.I], and Relative
importance index methods [RII] were used to work
out ranking of various factors. Total 70 feedbacks
were analyzed through above two techniques. It is
found that “Finance and payment issues”, “Poor work
quality” and “Extra items” are the three major causes
which leads towards occurrence of disputes. So,
contractors and clients must try to create an
environment during project executions such that
above causes are avoided. As far as use of a various
DRM‟s, it was found that Arbitration is not much
popular in Ahmedabad region among construction
industry. Looking to the benefits and legal backing
available with Arbitration, construction industry
should go for arbitration rather than mini-trials.
Acknowledgement
Authors are highly grateful to all participating
construction professionals for spending their valuable
time and giving their feedbacks on survey
questionnaire.
References
1. Zaneldin.E.K. (2006), “Construction
claims in United Arab Emirates: Types,
causes, and frequency”, International
Journal of Project Management , 24, 453–
459.
2. Cakmak.E and Cakmak.P.I (2014), “An
analysis of causes of disputes in the
construction industry using analytical
network process”, Procedia - Social and
Behavioral Sciences 109, 183 – 187
3. Edwin H.W. Chan and Henry C.H. Suen
(2004), “Dispute resolution management
for international construction projects in
China”, Emerald Management Decision
Vol. 43 No. 4, pp. 589-602
4. Zaneldin.E.K. (2006),“Construction
claims in the united arab emirates: types,
causes, and frequency” 21st Annual
ARCOM Conference, 7-9 September
2005, SOAS, University of London.
Association of Researchers in
Construction Management, Vol. 2, 813-
22.
5. Semple, C., Hartman, F., and Jergeas, G.
(1994). Construction claims and disputes:
causes and cost/time overruns. ASCE
Journal of Construction, Engineering and
Management, 120(4), pp.785-795
6. Diekmann, J.E., Girard, M.J. (1995). “Are
contract disputes predictable?” ASCE
Journal of Construction Engineering and
Management, 121(4), pp.355-363
7. http://www.surveysystem.com/sample-
size-formula.htm, accessed on 21st
November 2014.

Mais conteúdo relacionado

Mais procurados

time bar clauses
time bar clausestime bar clauses
time bar clauses
AMILA GAYAN
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
Khalil Hasan
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
Galala University
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
abdmuhaiminyunus
 

Mais procurados (20)

FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
 
Fidic
FidicFidic
Fidic
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contract
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminar
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Construction claims management
Construction claims managementConstruction claims management
Construction claims management
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver book
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Construction Law Conference Presentation
Construction Law Conference PresentationConstruction Law Conference Presentation
Construction Law Conference Presentation
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law
 
Construction contract
Construction contractConstruction contract
Construction contract
 

Destaque

RICS Certificate in Quantity Surveying
RICS Certificate in Quantity SurveyingRICS Certificate in Quantity Surveying
RICS Certificate in Quantity Surveying
Mark Drinan
 
Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolution
rcnewcomer
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
Mohammed Tanbouz
 

Destaque (9)

STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
 
RICS Certificate in Quantity Surveying
RICS Certificate in Quantity SurveyingRICS Certificate in Quantity Surveying
RICS Certificate in Quantity Surveying
 
The Red Book Presentation 16 Jan2010
The Red Book Presentation 16 Jan2010The Red Book Presentation 16 Jan2010
The Red Book Presentation 16 Jan2010
 
Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolution
 
Pathway guide quantity_surveying_construction_dwl_pt
Pathway guide quantity_surveying_construction_dwl_ptPathway guide quantity_surveying_construction_dwl_pt
Pathway guide quantity_surveying_construction_dwl_pt
 
Quantity surveying practise
Quantity surveying practiseQuantity surveying practise
Quantity surveying practise
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom Market
 

Semelhante a "Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Construction Industry in Gujarat" during "

Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
IJMREMJournal
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
IJMREMJournal
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
IAEME Publication
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
IAEME Publication
 

Semelhante a "Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Construction Industry in Gujarat" during " (20)

A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction Project
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
ASSIGNMENT II AHP CPM.pptx
ASSIGNMENT II AHP CPM.pptxASSIGNMENT II AHP CPM.pptx
ASSIGNMENT II AHP CPM.pptx
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
A RATIONAL APPROACH FOR ASSESSING THE COMPETITIVE BIDDING OF INFRASTRUCTURE P...
A RATIONAL APPROACH FOR ASSESSING THE COMPETITIVE BIDDING OF INFRASTRUCTURE P...A RATIONAL APPROACH FOR ASSESSING THE COMPETITIVE BIDDING OF INFRASTRUCTURE P...
A RATIONAL APPROACH FOR ASSESSING THE COMPETITIVE BIDDING OF INFRASTRUCTURE P...
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
 

Mais de Abhishek Shah

Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
Abhishek Shah
 

Mais de Abhishek Shah (6)

Mechanical Compaction of Concrete
Mechanical Compaction of Concrete Mechanical Compaction of Concrete
Mechanical Compaction of Concrete
 
Ready Mix Concrete
Ready Mix ConcreteReady Mix Concrete
Ready Mix Concrete
 
Standard test on fresh concrete
Standard test on fresh concreteStandard test on fresh concrete
Standard test on fresh concrete
 
Application & Comparison of different Formwork System used within Ind...
Application  &  Comparison  of  different  Formwork System  used  within  Ind...Application  &  Comparison  of  different  Formwork System  used  within  Ind...
Application & Comparison of different Formwork System used within Ind...
 
Ready Mix Concrete: Economic and Qualitative Growth for Construction Industry
Ready Mix Concrete: Economic and Qualitative Growth for Construction IndustryReady Mix Concrete: Economic and Qualitative Growth for Construction Industry
Ready Mix Concrete: Economic and Qualitative Growth for Construction Industry
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 

Último

Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
Health
 

Último (20)

Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 

"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Construction Industry in Gujarat" during "

  • 1. Ranking of “Causes of Disputes” and “Use of Dispute Resolution Methods” for Construction Industry in Gujarat Dr Rajiv Bhatt1 , Abhishek Shah2 , Prof J J Bhavsar3 1 Associate Professor, Civil Engineering Department, A.D.Patel Institute of Technology, Karamsad, Gujarat, India E-mail: rajiv7967@gmail.com 2 P.G. Scholar, Construction Engineering and Management section, Civil Engineering Department, Birla Vishvakarma Mahavidyalaya, V.V.Nagar, Gujarat, India E-mail: abhishekshah51@gmail.com 3 Associate Professor, Civil Engineering Department, Birla Vishvakarma Mahavidyalaya, V.V.Nagar, Gujarat, India E-mail: jjbhavsar@bvmengineering.ac.in Abstract: Presently India is in the developing phase which brings tremendous growth of construction industry. Construction industry is witnessing all kinds of projects across the country. Many projects are suffering from major issues like conflict between parties, claim generations and dispute occurrence. This study focuses on ranking of factors which contributes as “Causes of Disputes”, “Impact on project scenario” and “Use of Dispute resolution methods”. During this study, 70 feedbacks were collected from Architects, Contractors and Developers from Ahmedabad city of Gujarat state of India. Responses were analyzed by Weighted Average Method and Relative Importance Index method. It was found that “Finance and payment issues”, “Poor work quality” and “Extra items” are the three major causes which contribute for occurrence of disputes. This study found that due to arising of dispute reputation of both the parties gets disturbed. Keywords: Disputes, Construction Industry, Weighted Average Index, Relative Importance Index Introduction India is a developing country. The construction sector of India is growing rapidly. There are many ongoing Infrastructure projects in India of Billions of Dollars where the delay or stoppage of work due to any reason cannot be acceptable. In this rapidly growing construction industry many times claims arise between client and contractors. Construction Claim can be defined as a request by either party to the contract, usually the Contractor, for compensation for damages caused by failure of the other party to fulfill his part of obligations as specified in the contract. The compensation is usually in the form of the additional payment or an extension of time (EOT). Construction claims are measured by many project participants to be one of the most disturbing and unpleasant events of a project. Today, construction projects are the subject matter of more claims than in any other industry. The high competition has forced contractors to submit projects with minimum profits in order to stay in business. In addition to their multiparty nature, projects are becoming more complex and risky. This has placed an added burden on contractors to construct increasingly sophisticated and risky projects with less resources and profits. Under these circumstances, it is not surprising that the number of claims within the construction industry continues to increase. During the execution of a project, several issues arise that cannot be resolver among project participants. Such issues typically involve contractor requesting for either time extension or for additional cost, or sometimes both. Such requests by the contractor are referred as Claims. However if the owner does not agree to the claims put out by the contractor and there are
  • 2. differences in the interpretations, the issue takes the form of dispute. Claims are becoming an inevitable and unavoidable stress in modern projects involving new technology, specifications and high expectations from the owner. Construction claims are defined as “a request for compensation for damages incurred by any party to a contract” (Semple et al, 1994). Construction dispute are defined as “any contract question or controversy that must be settled beyond the jobsite management” (Diekmann and Girard, 1995). There are many reasons for claims time, machinery, material, manpower, money, price escalation, accident on site, change in design and many other are major reasons for dispute between two parties which results into disputes, if the disputes are Claims and Counterclaims. To solve this Claims there are certain dispute resolution techniques are available like arbitration, conciliation, mediation dispute resolution board. In this paper authors have listed 17 different causes for occurrence of disputes in construction industry. Further 8 different issue matters are listed which are created in project scenario as an impact of dispute occurrence. Total 8 different methods are found which are prevailing as on today among construction stakeholders for dispute resolution. Objective of this paper is to develop ranking of causes, impact on issues and use of DRM‟s through statistical techniques. Literature Review As per study carried out by Zaneldin.E.K (2006), “Changes” and “Extra work” are the two major causes for dispute generation in UAE. They concluded that „„change orders‟‟ are the most frequent cause of claims while „„delay caused by owner‟‟ was ranked second. „„Planning errors‟‟ were ranked last, indicating that it is the least frequent cause of claims. Cakmak.E and Cakmak.P.I (2014) carried out the study of causes of disputes in construction industry of Turkey by Analytic Network technique. They have classified the causes under seven different categories as: Owner related, Contractor related, Design related, Contract related, Human behavior related, Project related and External factors. Edwin H.W. Chan and Henry C.H. Suen (2004) found that arbitration is the most popular dispute resolution mechanism, after negotiation, for resolving disputes in international construction disputes in China. Research Methodology In this paper authors have tried to work out ranking of causes of disputes in construction industry along with ranking of impacts of these disputes. Further this work includes the ranking of various methods used by construction industry for dispute resolution. The survey questionnaire was designed to get the ranking of above three issues by suitable technique. The Survey questionnaire is given in appendix 1. The survey questionnaire is made of four sections. Section A includes demographic information of respondents. Section B includes questions about causes of construction disputes. Section C includes Impacts of disputes and Section D includes ranking for dispute resolution methods. Respondents has to tick mark any one option for each raw under the category of Strongly disagree(1), Disagree(2), Neutral(3), Agree(4) and Strongly Agree(5). It was planned to collect the feedbacks from various stakeholders of construction industry from Ahmedabad city of Gujarat state of India. The survey has included Architects, Contractors and Developers. This research work includes use of Weighted Average Method (W.I) and Relative Importance Index method (R.I.I). Data Collection The total population data was collected from different sources of the city which is as given below: Number of Builders, Contractors and Architects in Ahmedabad according to Ahmedabad Urban Development Authority (AUDA) = 1714 Sample size required for the present study was calculated as given below. of Builder / Developers, Contractors / Engineers and Architects in Ahmedabad according to Ahmedabad Urban Development Authority ( AUDA ) = 1714 Sample size required for the present study was calculated as given below.
  • 3. The formula below was used to determine the sample size of unlimited population (Creative Research Systems, 2001): SS = [Z2 × P × (1-P)] / C2 Where, SS = Sample Size. Z = Z Value (e.g. 1.96 for 95% confidence interval). P = Percentage picking a choice, expressed as decimal, (0.50 used for sample size needed). C = Confidence interval (0.1) POP = Population SS = [1.962 × 0.5 × (1- 0.5)] / .12 = 96.04 Correction for finite population: POP SS SS SSnew 1 1    99.90 1714 104.96 1 04.96    newSS So, total responses required are 91. During the data collection stage, total 105 questionnaire were distributed out of which 70 feedbacks were recived back. Out of the total responses, 36 were from Contractors, 23 from Developers, and 11 were from Architects. Data Analysis This research work has used following two methods for carrying out ranking work. 1. WEIGHTED AVERAGE METHOD: Data of all these table were analyzed by a weighted average was calculated for each type of claims as follows: Weighted Average Index = (Wi* Xi) / N; where Wi is the weight assigned to the ith option; Xi is the number of respondents who selected the ith option; and N is the total number of respondents (70 in this study). Table 1: Rank of causes of disputes by different methods Sr. No. Cause Rank as per W.I Method Rank as per R.I.I method 1 Finance and Payment Issue 1 1 2 Time Overrun 7 7 3 Cost Overrun 6 6 4 Price Escalation 14 14 5 Work Change Orders 5 5 6 Poor Communication 12 12 7 Design Errors 4 4 8 Inclement Weather 17 17 9 Extra Items 3 3 10 Unforseen Site Condition 13 13 11 Poor Work Quality 2 2 12 Incomplete information in Tender 9 9 13 Delay in issuing Site, Drawings, Materials 8 8 14 Return of Security Deposit 16 16 15 Unfair allocation of Risk 15 15 16 Delay in Clients Response 11 11 17 Mistakes in Contract Document 10 10 2. RII INDEX METHOD: Data of all these table were analyzed by a RII Index was calculated for each type of claims as follows: RII Index = Σ W/ (A*N)
  • 4. Where, W = weighting given to each factor by the respondents which ranges from 1 to 5, A = highest weight (i.e. 5 in this case) and N = total number of respondents. According to above two methods ranking of causes of construction disputes are found as per table 1 given below. Regarding Impact of causes of disputes on various situations of construction project, ranking by respondents is given in table 2. Table 2: Ranking for Impact on various issues by WI and RII methods Sr. No. Impact matter Rank as per W.I Method Rank as per R.I.I method 1 Damaged business relationship 2 2 2 Increased project costs 3 3 3 Project Delays 6 6 4 Undermine team spirit 7 7 5 Damaging company reputation 1 1 6 Dispute escalation 8 8 7 Poor client satisfaction 5 5 8 Delay in project completion 4 4 Regarding ranking of dispute resolution techniques, findings are given below in table 3. Table 3: Ranking to use of DRM by WI and RII method Sr. No. Dispute Resolution Methods Rank as per W.I Method Rank as per R.I.I method A Adjuducation 5 5 B Arbitration 6 6 C Dispute Review Board 7 7 D Expert Determination 3 3 E Litigation 8 8 F Mini-trial 4 4 G Mediation 2 2 H Negotiation 1 1 Results and Discussion: From present study it is found that “Finance and payment issues” is having first rank among all causes for generation of dispute. Second rank was given to “Poor work quality” by the respondents. “Extra items” is having third rank and “Design errors” is having fourth rank in causes of disputes. “Inclement weather” is having lowest rank. Respondents felt that disputes in construction industry damages the reputation of both the parties. This is found by getting first rank for “Damaging company reputation” in Impact matters. Further, respondents have given lowest rank to “Dispute Escalation” matter. Respondents have given first rank to “Negotiation” method for dispute resolution and last rank is given to “Litigation” method. Conclusion Present study focuses on study of causes of construction disputes, it‟s impact on various aspects and different methods used for dispute resolution. Weighted average method [W.I], and Relative importance index methods [RII] were used to work out ranking of various factors. Total 70 feedbacks were analyzed through above two techniques. It is found that “Finance and payment issues”, “Poor work quality” and “Extra items” are the three major causes which leads towards occurrence of disputes. So, contractors and clients must try to create an environment during project executions such that above causes are avoided. As far as use of a various DRM‟s, it was found that Arbitration is not much popular in Ahmedabad region among construction industry. Looking to the benefits and legal backing available with Arbitration, construction industry should go for arbitration rather than mini-trials. Acknowledgement Authors are highly grateful to all participating construction professionals for spending their valuable time and giving their feedbacks on survey questionnaire. References 1. Zaneldin.E.K. (2006), “Construction claims in United Arab Emirates: Types, causes, and frequency”, International Journal of Project Management , 24, 453– 459. 2. Cakmak.E and Cakmak.P.I (2014), “An analysis of causes of disputes in the
  • 5. construction industry using analytical network process”, Procedia - Social and Behavioral Sciences 109, 183 – 187 3. Edwin H.W. Chan and Henry C.H. Suen (2004), “Dispute resolution management for international construction projects in China”, Emerald Management Decision Vol. 43 No. 4, pp. 589-602 4. Zaneldin.E.K. (2006),“Construction claims in the united arab emirates: types, causes, and frequency” 21st Annual ARCOM Conference, 7-9 September 2005, SOAS, University of London. Association of Researchers in Construction Management, Vol. 2, 813- 22. 5. Semple, C., Hartman, F., and Jergeas, G. (1994). Construction claims and disputes: causes and cost/time overruns. ASCE Journal of Construction, Engineering and Management, 120(4), pp.785-795 6. Diekmann, J.E., Girard, M.J. (1995). “Are contract disputes predictable?” ASCE Journal of Construction Engineering and Management, 121(4), pp.355-363 7. http://www.surveysystem.com/sample- size-formula.htm, accessed on 21st November 2014.