Problems From UNIT I


               1) A ∆-connected resistive load of 8000 kW is connected to the low-tension, ∆- connected side
                   of a Y-∆
   transformer rated 10,000 kVA, 138/13.8 kV. Find the load resistance in ohms in each phase as measured
   from line to neutral on the high-tension side of the transformer. Neglect transformer impedance and assume
   rated voltage is applied to transformer primary.
   [2.38K]
2) Solve problem 1 if the same resistors are reconnected in Y.
   [2.38K]
3) Draw the pu impedance diagram for the power system shown in the figure. Neglect resistance, and use a
   base of 100 MV A, 220 kV in 50 Ω line. The ratings of the generator, motor and transformers are:
   Generator 40 MV A, 25 kV, X” = 20%, Motor 50 MV A, 11 kV, X” = 30%,
   Y-Y transformer, 40 MV A, 33 Y-220 Y kV, X = 15%,
   Y-Δ transformer, 30 MV A, 11 Δ-220 Y kV, X = 15%




                                                                           [0.29,0.6,0.375,0.5,0.103]
4) Taking a base of 100MVA and 11KV in the generator circuit, draw the per unit impedance diagram for the
    power system shown in the below drawn figure. Neglect resistance. The data of the lines are in ohms. The
    ratings of the various components are:
           Generator: 50 MV A, 12
           kV, X = 25% ;
           Motor: 45 MV A, 13 kV,
           X = 20%;
           T1: 50 MV A, 11/220 kV,
            X = 10%;
           T2: 30 MV A, 220/22kV,
            X = 15%;
           T3: A bank of three 1Φ
            transformers having
           rating 15MVA,
           230/20KV,
           X = 10%;
           Load: 100+j200Ω.
   [0.595,0.2,0.165,0.243,0.165,0.2066,0.5,20.66+j41.32]
5)      Taking a base of 200MVA and 33KV in the generator circuit, draw the per unit
          impedance diagram for the power system shown in the below drawn figure. Neglect
          resistance. The data of the lines are in ohms. The ratings of the various components are:
          Generator: 100 MV A, 11
          kV, X = 20% ;
          T1: 50 MV A, 11/220 kV,
           X = 15%;
          T2: A bank of three 1Φ
           transformers having
          rating 20MVA,
          230/33KV,
          X = 10%;
          Load: 60+j20Ω.
        [0.044,0.033,0.0367,0.0344,4.015+j1.34]

6) The one-line diagram of an unloaded power system is shown below. Reactances of the two sections of
   transmission line are shown on the diagram. The generators are rated as follows:
   Generator 1:     20 MVA, 13.8 kV, X”= 0.20 pu
   Generator 2:     30 MVA, 18.0 kV, X”= 0.20 pu
   Generator 3:     30 MVA, 20.0 kV, X”=0.20 pu
   Transformer T1: 25 MVA 220Y/ 13.8∆ kV, X=10%
   Transformer T2: single phase units each rated 10 MVA, 127/18 kV, X=10%
   Transformer T3: 35 MVA, 220 Y/22Y kV, X=10%
   Draw the impedance diagram with all the reactances marked in pu and with letters to indicate points
   corresponding to one line diagram. Choose a base of 50 MVA, 13.8 kV in the circuit of generator 1.




                  [0.5,0.2,0.0826,0.275,0.143,0.333,0.1033,0.167]
7) The figure shows the schematic diagram of a radial transmission system. The ratings and reactances of the
   various components are shown therein. A load of 60 MW at 0.9 power factor lagging is tapped from the 66
   KV substation which is to be maintained at 60 kV . Calculate the terminal voltage of the synchronous
   machine represent the transmission line and the transformers by series reactances only.




   [12KV]

8) A 50MVA, 30KV, 3 phase, 60Hz synchronous generator has a synchronous reactance of 9 ohms/phase and
   a negligible resistance. The generator is delivering rated power at a 0.8 pf lagging at the rated terminal
   voltage to an infinite bus.
   (i) Find the Ef and delta
   (ii) with the excitation held constant at the value found in (i), the driving torque is reduced until the
   generator is delivering 25MW. Determine the armature current.
   [23.557,17.1deg; 0.8073KA, 0.596lagging]

9) Draw the impedance diagram for the power system shown in the figure. Mark impedances in per unit.
   Neglect resistance, and use a base of 50 kVA, 138 kV in the 40-Ώ line. The rating of the generators,
   motors, and transformers are:
   Generator 1:                     20 MVA, 18.0 kV, X” = 20%
   Generator 2:                     20 MVA, 18.0 kV, X” = 20%
   Synchronous motor 3:             30 MVA, 13.8 kV, X”= 20%
   Three-phase Y-Y transformers: 20 MVA, 138Y/20Y kV, X= 10%
   Three-phase Y-∆ transformers: 15 MVA, 138Y/13.8∆ kV, X=10%




       [0.405, 0.333,0.405,0.105,0.053,0.053,0.25X4Transformers; 0.333X2Transformers]

Mais conteúdo relacionado

Mais procurados

Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit ivAbha Tripathi
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23BinodKumarSahu5
 
power system analysis lecture 1
power system analysis lecture 1power system analysis lecture 1
power system analysis lecture 1Audih Alfaoury
 
Electrical machines solved objective
Electrical machines solved objectiveElectrical machines solved objective
Electrical machines solved objectivemaheshwareshwar
 
Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313Fazal Ur Rehman
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysisHari Kumar
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculationobaidurbd
 
Term question eee 305
Term question eee 305Term question eee 305
Term question eee 305TamimAhmed43
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questionsguest4ca222
 
analisa sistem tenaga lanjut
analisa sistem tenaga lanjutanalisa sistem tenaga lanjut
analisa sistem tenaga lanjutsuparman unkhair
 

Mais procurados (20)

Unit4questions
Unit4questionsUnit4questions
Unit4questions
 
Unit v
Unit vUnit v
Unit v
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit iv
 
Questions unit4
Questions unit4Questions unit4
Questions unit4
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Questions unit3
Questions unit3Questions unit3
Questions unit3
 
Unsymmetrical Fault
Unsymmetrical FaultUnsymmetrical Fault
Unsymmetrical Fault
 
Unit1questions
Unit1questionsUnit1questions
Unit1questions
 
electrical objective
electrical objectiveelectrical objective
electrical objective
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23
 
Fundamental Power System
Fundamental Power SystemFundamental Power System
Fundamental Power System
 
power system analysis lecture 1
power system analysis lecture 1power system analysis lecture 1
power system analysis lecture 1
 
Electrical machines solved objective
Electrical machines solved objectiveElectrical machines solved objective
Electrical machines solved objective
 
Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysis
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculation
 
Term question eee 305
Term question eee 305Term question eee 305
Term question eee 305
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questions
 
analisa sistem tenaga lanjut
analisa sistem tenaga lanjutanalisa sistem tenaga lanjut
analisa sistem tenaga lanjut
 

Destaque

Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!PRABHAHARAN429
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysiskirkusawi
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysisdivyanshuprakashrock
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagramnanonon
 
Per unit representation
Per unit representationPer unit representation
Per unit representationMd. Rimon Mia
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis pptkarikalan123
 
ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation Chandrabhan Sharma
 
Power system analysis (III-EEE)
Power system analysis  (III-EEE)Power system analysis  (III-EEE)
Power system analysis (III-EEE)betasam
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedureMustafa Ismail
 
2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - Electrical
2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - Electrical2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - Electrical
2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - ElectricalZimbrick Buick/GMC West
 
Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...
Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...
Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...Francisco Gonzalez-Longatt
 
Micro Processor Lab Manual!
Micro Processor Lab Manual!Micro Processor Lab Manual!
Micro Processor Lab Manual!PRABHAHARAN429
 

Destaque (20)

Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!
 
load flow 1
 load flow 1 load flow 1
load flow 1
 
Single line diagram
Single line diagramSingle line diagram
Single line diagram
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysis
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagram
 
Per unit representation
Per unit representationPer unit representation
Per unit representation
 
Per unit system
Per unit systemPer unit system
Per unit system
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
49 single line diagram
49 single line diagram49 single line diagram
49 single line diagram
 
Unit1 8
Unit1 8Unit1 8
Unit1 8
 
ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation
 
Power system analysis (III-EEE)
Power system analysis  (III-EEE)Power system analysis  (III-EEE)
Power system analysis (III-EEE)
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedure
 
Rk21 power flow_sparse2
Rk21 power flow_sparse2Rk21 power flow_sparse2
Rk21 power flow_sparse2
 
2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - Electrical
2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - Electrical2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - Electrical
2011 GMC Sierra & 2011 GMC Yukon Upfitting Wisconsin - Electrical
 
Quantity and unit
Quantity and unitQuantity and unit
Quantity and unit
 
Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...
Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...
Creating and Using Study Cases in DIgSILENT PowerFactory. Case P.M. Anderson ...
 
Micro Processor Lab Manual!
Micro Processor Lab Manual!Micro Processor Lab Manual!
Micro Processor Lab Manual!
 

Semelhante a Unit 1, Power system Analysis

CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxCHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxLiewChiaPing
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptxssuser99d6551
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsIsham Rashik
 
CHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.pptCHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.pptLiewChiaPing
 
EE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsEE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsSanthosh Kumar
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301Ravi Anand
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protectionHakim Futra
 
147110756 march-2005
147110756 march-2005147110756 march-2005
147110756 march-2005homeworkping3
 
Power Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptxPower Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptxaafadf1
 
Fault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdfFault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdfSaravanan A
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITAbinaya Saraswathy T
 
Series and Parallel Circuits.ppt.pptx
Series and Parallel Circuits.ppt.pptxSeries and Parallel Circuits.ppt.pptx
Series and Parallel Circuits.ppt.pptxROLANDOMORALES28
 
Assignment & solution (selected)
Assignment & solution (selected)Assignment & solution (selected)
Assignment & solution (selected)efrataderebe
 
Lecture dc machines
Lecture dc machinesLecture dc machines
Lecture dc machinessudeep kumar
 

Semelhante a Unit 1, Power system Analysis (20)

CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxCHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generators
 
CHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.pptCHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.ppt
 
EE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsEE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_Questions
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301
 
Dc machines
Dc machinesDc machines
Dc machines
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protection
 
Dc machine practical
Dc machine practical Dc machine practical
Dc machine practical
 
147110756 march-2005
147110756 march-2005147110756 march-2005
147110756 march-2005
 
Power Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptxPower Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptx
 
Fault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdfFault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdf
 
D05432435
D05432435D05432435
D05432435
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
 
PEQPAU.pdf
PEQPAU.pdfPEQPAU.pdf
PEQPAU.pdf
 
Single phase transformer
Single phase transformerSingle phase transformer
Single phase transformer
 
Series and Parallel Circuits.ppt.pptx
Series and Parallel Circuits.ppt.pptxSeries and Parallel Circuits.ppt.pptx
Series and Parallel Circuits.ppt.pptx
 
E&e lab manual
E&e lab manualE&e lab manual
E&e lab manual
 
Assignment & solution (selected)
Assignment & solution (selected)Assignment & solution (selected)
Assignment & solution (selected)
 
Lecture dc machines
Lecture dc machinesLecture dc machines
Lecture dc machines
 

Mais de Abha Tripathi

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteriaAbha Tripathi
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Abha Tripathi
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical componentsAbha Tripathi
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system componentsAbha Tripathi
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel PlantAbha Tripathi
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, Abha Tripathi
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator ProblemAbha Tripathi
 

Mais de Abha Tripathi (15)

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
 
Dc Distributed Load
Dc Distributed LoadDc Distributed Load
Dc Distributed Load
 

Último

Personalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes GuàrdiaPersonalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes GuàrdiaEADTU
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024Borja Sotomayor
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project researchCaitlinCummins3
 
Play hard learn harder: The Serious Business of Play
Play hard learn harder:  The Serious Business of PlayPlay hard learn harder:  The Serious Business of Play
Play hard learn harder: The Serious Business of PlayPooky Knightsmith
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonhttgc7rh9c
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....Ritu480198
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17Celine George
 
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfDiuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfKartik Tiwari
 
Graduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxGraduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxneillewis46
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxCeline George
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024Elizabeth Walsh
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111GangaMaiya1
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnershipsexpandedwebsite
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfNirmal Dwivedi
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code ExamplesPeter Brusilovsky
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...Nguyen Thanh Tu Collection
 

Último (20)

Personalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes GuàrdiaPersonalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes Guàrdia
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
 
Play hard learn harder: The Serious Business of Play
Play hard learn harder:  The Serious Business of PlayPlay hard learn harder:  The Serious Business of Play
Play hard learn harder: The Serious Business of Play
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17
 
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfDiuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
 
Graduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxGraduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptx
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code Examples
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 

Unit 1, Power system Analysis

  • 1. Problems From UNIT I 1) A ∆-connected resistive load of 8000 kW is connected to the low-tension, ∆- connected side of a Y-∆ transformer rated 10,000 kVA, 138/13.8 kV. Find the load resistance in ohms in each phase as measured from line to neutral on the high-tension side of the transformer. Neglect transformer impedance and assume rated voltage is applied to transformer primary. [2.38K] 2) Solve problem 1 if the same resistors are reconnected in Y. [2.38K] 3) Draw the pu impedance diagram for the power system shown in the figure. Neglect resistance, and use a base of 100 MV A, 220 kV in 50 Ω line. The ratings of the generator, motor and transformers are: Generator 40 MV A, 25 kV, X” = 20%, Motor 50 MV A, 11 kV, X” = 30%, Y-Y transformer, 40 MV A, 33 Y-220 Y kV, X = 15%, Y-Δ transformer, 30 MV A, 11 Δ-220 Y kV, X = 15% [0.29,0.6,0.375,0.5,0.103] 4) Taking a base of 100MVA and 11KV in the generator circuit, draw the per unit impedance diagram for the power system shown in the below drawn figure. Neglect resistance. The data of the lines are in ohms. The ratings of the various components are: Generator: 50 MV A, 12 kV, X = 25% ; Motor: 45 MV A, 13 kV, X = 20%; T1: 50 MV A, 11/220 kV, X = 10%; T2: 30 MV A, 220/22kV, X = 15%; T3: A bank of three 1Φ transformers having rating 15MVA, 230/20KV, X = 10%; Load: 100+j200Ω. [0.595,0.2,0.165,0.243,0.165,0.2066,0.5,20.66+j41.32]
  • 2. 5) Taking a base of 200MVA and 33KV in the generator circuit, draw the per unit impedance diagram for the power system shown in the below drawn figure. Neglect resistance. The data of the lines are in ohms. The ratings of the various components are: Generator: 100 MV A, 11 kV, X = 20% ; T1: 50 MV A, 11/220 kV, X = 15%; T2: A bank of three 1Φ transformers having rating 20MVA, 230/33KV, X = 10%; Load: 60+j20Ω. [0.044,0.033,0.0367,0.0344,4.015+j1.34] 6) The one-line diagram of an unloaded power system is shown below. Reactances of the two sections of transmission line are shown on the diagram. The generators are rated as follows: Generator 1: 20 MVA, 13.8 kV, X”= 0.20 pu Generator 2: 30 MVA, 18.0 kV, X”= 0.20 pu Generator 3: 30 MVA, 20.0 kV, X”=0.20 pu Transformer T1: 25 MVA 220Y/ 13.8∆ kV, X=10% Transformer T2: single phase units each rated 10 MVA, 127/18 kV, X=10% Transformer T3: 35 MVA, 220 Y/22Y kV, X=10% Draw the impedance diagram with all the reactances marked in pu and with letters to indicate points corresponding to one line diagram. Choose a base of 50 MVA, 13.8 kV in the circuit of generator 1. [0.5,0.2,0.0826,0.275,0.143,0.333,0.1033,0.167]
  • 3. 7) The figure shows the schematic diagram of a radial transmission system. The ratings and reactances of the various components are shown therein. A load of 60 MW at 0.9 power factor lagging is tapped from the 66 KV substation which is to be maintained at 60 kV . Calculate the terminal voltage of the synchronous machine represent the transmission line and the transformers by series reactances only. [12KV] 8) A 50MVA, 30KV, 3 phase, 60Hz synchronous generator has a synchronous reactance of 9 ohms/phase and a negligible resistance. The generator is delivering rated power at a 0.8 pf lagging at the rated terminal voltage to an infinite bus. (i) Find the Ef and delta (ii) with the excitation held constant at the value found in (i), the driving torque is reduced until the generator is delivering 25MW. Determine the armature current. [23.557,17.1deg; 0.8073KA, 0.596lagging] 9) Draw the impedance diagram for the power system shown in the figure. Mark impedances in per unit. Neglect resistance, and use a base of 50 kVA, 138 kV in the 40-Ώ line. The rating of the generators, motors, and transformers are: Generator 1: 20 MVA, 18.0 kV, X” = 20% Generator 2: 20 MVA, 18.0 kV, X” = 20% Synchronous motor 3: 30 MVA, 13.8 kV, X”= 20% Three-phase Y-Y transformers: 20 MVA, 138Y/20Y kV, X= 10% Three-phase Y-∆ transformers: 15 MVA, 138Y/13.8∆ kV, X=10% [0.405, 0.333,0.405,0.105,0.053,0.053,0.25X4Transformers; 0.333X2Transformers]