1. Dummy Activity
A Dummy activity is an imaginary activity. It does not exist in the
Project activities. It is used in the network diagram to show dependency
relationship or connectivity between two or more activities. It is
represented by a dotted arrow.
Dummy activities are a useful tool to implement when the
specific relationship between two particular activities on the arrow
diagramming method cannot specifically be linked or conceptualized
through simple use of arrows going from one activity to another.
Activity Preceding Activity
D B
E B, C
Activity D follows activity B. Activity E follows both the activities B &
C. Hence, for drawing E, we need to show a connection between B & C.
Hence, from B we will draw a Dummy activity on C.
---------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------
Name : Abdinur Omar Mohamud
ID:EN0109017