John james village wvcc presentation 3 december 2014
1. John James Village Project
Presentation
Woden Valley Community Council Meeting 3 December 2014
Presenter: Mark Blake - Point Project Management
2. Background
• Leukaemia Foundation in ACT/SNSW –
current arrangements
• March 2012 - official Lifecycle opening
• June 2012 – MOU between John James
Foundation and Leukaemia Foundation
• 2012 – 2014 site identification
• Land allocated April 2014
3. Garran Site Investigation
• Contamination Assessment: Likelihood, if any, low
• Flood Control Study: TAMS Requirements of sale of the land
• Traffic and Parking: Development to have insignificant impact on road
network
• Vegetation: Tree assessment found best opportunity for development in
centre of the block. (current site). Large area of site infested by weeds.
• Acoustic Study: Protection against Hindmarsh Dr.
• Services: New site services for development
• Civil: New footpath on Rusden St.
• Walking Trail: Existing trail to remain
• Fauna: No Endangered Species found on site.
5. Village Characteristics
• Low scale development
intended to be
sympathetic to
surroundings
• Single level development
• Off-street car parking
• Emphasis on landscaping
6. Project Timeline
• Development Application lodged – December 2014
• Building Approval – April 2015
• Construction Commence – May 2015
• Construction Complete – July 2016