BILLS OF QUANTITIES (BOQ)
The survival of any business is heavily depend on the success of commercial
management. When it comes to commercial management in construction industry, Bill of
Quantities (BOQ) is the term which brings attention of every construction professionals
and stakeholders.
It is one of the communication tool which connects the parties (Client, consultant &
contractor) of construction project. Keith defines, BOQ is a schedule which categories,
details and quantifies the materials and other cost items to be used in construction project.
It is important to know that, direct costs & indirect costs are to be considered for complete
cost of the project which are covered in different parts of the BOQ.
Generally BOQ is in tabular form which contents description, unit, quantity, rate & amount
in different columns.
Sample
BOQ Document, PDF
Description column provides a brief explanation of what to be done. For example, in the first item,
the 32mm diameter CPVC pipes should be laid for cold water services in 20 bar operating pressure.
Specification & drawings are other two important items to be analyzed in detail for clear
understanding. Here the term engineer means the consultant for the project.
The Importance of BOQ
BOQ shall be used in every phase (pre-contract & post-contract) of the project but need of BOQ
differs based on different contract agreements & project. The major usages are listed below.
1. It provides basic idea of the project by giving the quantities to tenderers.
2. It defines the extent of the work. (But it should be identified in line with drawings &
specification as well).
3. It gives estimated or anticipated contract sum. (very important to client)
4. It provides a basis for valuation of variation. (Variation is to be discussed in detail).
The major Parts of BOQ
Parts of BOQ can be varied according to the project size as well the practices. Generally it has
measured works, Preliminaries & Provisional sums. The contract sum would be addition of these
three items.
BILL OF QUANTITIES
INTRODUCTION
 Quantity surveying emerged as a separate profession in Britain in the 19th century. It is
simply a task of measuring construction work required to implement the architects' design
for new or renovated buildings. The purpose of the work is to produce quantified
specifications of works known as Bills of Quantities.
OBJECTIVES
 The objectives of the Bill of Quantities are: (1) to provide sufficient information on the
quantities of Works to be performed to enable bids to be prepared efficiently and
accurately; and when a contract has been entered into, (2) to provide a priced Bill of
Quantities foruse in the periodic valuation of works executed.
 In order to attain these objectives, works are itemized in the Bill of Quantities in sufficient
detail to distinguish between the
different classes of works, or between works of the same nature carried out in different
locations or in other circumstances which may
give rise to different considerations of cost. Consistent with these requirements, the layout
and content of the Bill of Quantities are required to be
as simple and brief as possible.
 The large data bank of information contained in the Bill of Quantities can be used in many
ways to help the post-contract control of a project.
QUANTITY SURVEYOR
 Bill of Quantities form a part of the contract in many countries. The World
 Bank and FIDIC documents also include Bill of Quantities.
 In order to produce the Bill of Quantities, a detailed quantity survey ormaterials takeoff
has to be completed. The services are provided by a professional Quantity Surveyor (QS).
 A Quantity Surveyor is usually hired by the owner at the inception of a project. The QS
makes cost feasibility studies, establishes construction budget, makes cost checks at all
stages of the design process, and prepares a final Bill of Quantities. This Bill of Quantities is
included in the bidding documents of the project. The bidders use this information, along
with the construction drawings and specifications, as the basis fortheir pricing of the work.
 The QS advises the owner on contractual arrangements and compiles certificates of interim
and final payment to the contractordoing the work.
 Based on their detailed knowledge of construction costs, the Quantity Surveyors
can provide design cost planning service that allows customers to decide on their total
budget, even before any design work is commissioned. Without cost planning, designs may
result in bids that are too expensive.
AN OVERVIEW OF BILLS OF QUANTITIES
 The Bills of Quantities are usually indicated by items of work, units of measurement,
quantities of work, rate fordoing the work, and total value of the work. An example is
shown below:
ItemID
Descriptionof
item
Unit of
measurement
Quantityof work Rate inUS $
Total amountinUS
$
1
Reinforced
cementconcrete
workin grade
beams(attaining
compressive
strengthof 3,000
psi in 28 days)
withthe leanest
permissible mix,
2:3:6 with3/4"
downgraded
crushedstone as
coarse aggregate
Cubicyard 1,000 75 75,000
and coarse sand
withan FMnot
lessthan2.7 as
fine aggregate.
 Usually the contractorgoes through the Bills of Quantities and would quote her/his rate as
a percentage above or below the rates indicated.
 Even though the QS employed by the owner provides a detailed estimate forthe project,
sometimes the rates and total amount to do the works may not be shown in the Bills of
Quantities. In that case, the bidder provides the rates of the items at which she/he is
capable to do the works.
 Pricing of different items of work are done on the basis of the cost of materials, equipment,
labor, and overheads and profit.
o Materials: The materials costs are calculated by examining the material quotations
received fromsuppliers, applying appropriate wastage factors, and delivery charges.
o Equipment: Cost of equipment is calculated usually as a percentage of the cost of
materials. Depending on whether the equipment is owned or rented, this percentage
will vary.
o Labor: The most difficult element to price is the labor cost. Most of the times, it is
not sufficient to rely on published standard rates. Allowances for absences due to
sickness, loss of time due to inclement weather, overtime, etc. are required to be
built in to arrive at a pragmatic all-inclusive labor rate. Rate of productivity is another
factorthat plays an important role in fixing labor prices.
o Overheads and profit: Once the cost of materials, equipment, and labor has been
added up, a percentage foroverhead and profit is added to the item rate. This
percentage may vary from project to project depending on how well the document
has been prepared by the QS and also on market conditions. It may range from2.5 to
over 25 percent.
 Once the pricing of all individual items forall trades is completed, the amounts are carried
to a summary page to indicate the total bid price.
SOME OTHER ADVANTAGES OF THE USE OF
BILL OF QUANTITIES
 Save the cost and time of several contractors measuring the same design in order to
calculate their bids for competition.
 Provide a consistent basis for competitive bids so that the contractorwho is the most
efficient and least expensive in providing the items of work is likely to be commissioned for
the job.
 Provide an open basis forthe contract; the client provides an extensive and clear statement
of the work he/she requires and the contractorstates the price at which he/she is prepared
to undertake the job.
 Provide a very strong basis for financial administration of the contract.
The preparation of a BQ also has other advantages as well, such as:
 Assisting the comparison and assessment of tenders, as tenders will be based on the same
information;
 Providing a good and fair basis for assessing variations during construction;
 Being a basis for assessing and recommending progress claims and payments;
 Helping to reduce the tender period (and its associated costs) as the tenderers then do not have to
each individually reproduce the tender documents for their own ‘quick’ (though it may take
weeks), and sometimes abridged, measurement and builders’ quantities;
 And it also provides a basis for project cost analysis, so that future cost planning efforts have
reliable information to refer to.
Benefits of Bills of Quantities
Bills of Quantities which we produce allow for obtaining a competitive tender price for
completing the building works, valuing the extent of building works complete for the
purpose of making payments to the contractor, valuing variations in the content or extent
of building works, or to support applications for tax or other financial incentives.
Our detailed measurement for the purpose of bills of quantities production is beneficial for
a number of reasons:
 It saves considerable time and cost of several contractors measuring the same
design in order to calculate their bids for competition;
 It provides a consistent basis for obtaining competitive tenders from contractors;
 It provides an extensive and clear statement of the work to be executed;
 It provides a very strong basis for budgetary control and accurate cost reporting of
the contract including:
- the preparation of cash flow forecasts,
- a basis for valuing variations, and
- a basis for the preparation of progress payments (ie. interim payments)
 It allows, when BQ items are codified, reconciliation and any necessary transfers
and adjustments to be made to the cost plan;
 When priced it provides data to support claims for grants;
 It provides one of the best sources of real-time cost data, which can be used for
estimating the cost of future building projects
Types of Bill of Quantities
The main use of a bill of quantities in support of a contract is the traditional and proven
means of securing a lump-sum price for carrying out the building works for the client.
SC Quantity Surveyors produce several types of Bills of Quantities which include
 Firm (to obtain a lump-sum price for a fully designed building project)
 Approximate (subject to re measurement as built)
Firm Bill of Quantities
The reliability of the tender price will increase in relation to the accuracy of the quantities
provided (i.e. the more precisely the work is measured and described). Provided there
were no design changes, then firm bills of quantities would provide a price at tender stage,
which would equal the final cost. However, there will be changes, and the bill of quantities
provides a good basis for cost control, since the direct cost can be assessed with
reference to the bill of quantity rates. In general the firmer the bill of quantities the better it
is as a means of financial control.
Approximate Bill of Quantities
SC Quantity Surveyors can produce approximate bills of quantities which are mainly used
when there is insufficient details to prepare firm bills of quantities or where the client has
decided that the time and cost of a firm bill of quantities is not warranted. These types of
contracts do not provide a lump-sum price, but instead tender price totals (ie. a quantified
schedule of rates), since the quantities are subject to re-measurement on completion by
the quantity surveyor. In general these contracts are usually subject to greater variation
than lump sum contracts and therefore should only be used where time is a limiting factor
or where there is great uncertainty in respect of certain elements, such as major
excavations and earthworks.
It is important to note that the initial resource cost of approximate bills of quantities is likely
to be lower than firm bills of quantities, but the need for re-measurement invariably results
in an overall higher resource cost. Although the measured quantities are approximate, the
descriptions of work items should be correct in the approximate bill of quantities.
Bills of Quantities that are required for a lump sum contract based on firm or approximate
quantities will normally be prepared by the employer's quantity surveyor, whereas under a
design and build contract, the employer's project team will prepare the employer's
requirements and the Bill of Quantities or quantified schedules of work will be prepared by
either the main contractor or, more likely, the main contractor's work package contractors.
In general the choice of who quantifies building works is solely down to the employer's
preference of contract strategy.

Mais conteúdo relacionado

Mais procurados

Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
Waqas Aslam
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
Thomas Britto
 

Mais procurados (20)

SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Types of civil engineering drawing
Types of civil engineering drawingTypes of civil engineering drawing
Types of civil engineering drawing
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Construction contract
Construction contract Construction contract
Construction contract
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Construction phases
Construction phasesConstruction phases
Construction phases
 

Semelhante a Bills of quantities

Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
Hamdija Velagic
 
Quantycosts consultants Profile
Quantycosts consultants ProfileQuantycosts consultants Profile
Quantycosts consultants Profile
Maina Wanjama
 

Semelhante a Bills of quantities (20)

Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 
Qsx
QsxQsx
Qsx
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
QSS
QSSQSS
QSS
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Construction management 2
Construction management 2Construction management 2
Construction management 2
 
Taking off qs
Taking off qsTaking off qs
Taking off qs
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Vetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh projectVetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh project
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
 
Quantycosts consultants Profile
Quantycosts consultants ProfileQuantycosts consultants Profile
Quantycosts consultants Profile
 
Aiab089228
Aiab089228Aiab089228
Aiab089228
 

Mais de Ar.Vijay Kumar (12)

HISTORY OF LANDSCAPE AROUND WORLD WIDE.pptx
HISTORY OF LANDSCAPE AROUND WORLD WIDE.pptxHISTORY OF LANDSCAPE AROUND WORLD WIDE.pptx
HISTORY OF LANDSCAPE AROUND WORLD WIDE.pptx
 
ENVIRONMENT STUDY.pptx
ENVIRONMENT STUDY.pptxENVIRONMENT STUDY.pptx
ENVIRONMENT STUDY.pptx
 
ENVIRONMENT STUDY.pdf
ENVIRONMENT STUDY.pdfENVIRONMENT STUDY.pdf
ENVIRONMENT STUDY.pdf
 
Site consideration
Site considerationSite consideration
Site consideration
 
Housing construction technology
Housing construction technology Housing construction technology
Housing construction technology
 
Wall finishes
Wall finishesWall finishes
Wall finishes
 
Colour
ColourColour
Colour
 
Furniture and furnishings
Furniture  and furnishingsFurniture  and furnishings
Furniture and furnishings
 
Role of different art forms in interior design
Role of different art forms in interior designRole of different art forms in interior design
Role of different art forms in interior design
 
Introduction to interior design
Introduction to interior designIntroduction to interior design
Introduction to interior design
 
Theory of design & the constraints involved in an interior design process.
Theory of design & the constraints involved in an interior design process.Theory of design & the constraints involved in an interior design process.
Theory of design & the constraints involved in an interior design process.
 
Factors affeccting cost estimates of a project
Factors affeccting cost estimates of a projectFactors affeccting cost estimates of a project
Factors affeccting cost estimates of a project
 

Último

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
Health
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 

Último (20)

Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

Bills of quantities

  • 1. BILLS OF QUANTITIES (BOQ) The survival of any business is heavily depend on the success of commercial management. When it comes to commercial management in construction industry, Bill of Quantities (BOQ) is the term which brings attention of every construction professionals and stakeholders. It is one of the communication tool which connects the parties (Client, consultant & contractor) of construction project. Keith defines, BOQ is a schedule which categories, details and quantifies the materials and other cost items to be used in construction project. It is important to know that, direct costs & indirect costs are to be considered for complete cost of the project which are covered in different parts of the BOQ. Generally BOQ is in tabular form which contents description, unit, quantity, rate & amount in different columns. Sample BOQ Document, PDF Description column provides a brief explanation of what to be done. For example, in the first item, the 32mm diameter CPVC pipes should be laid for cold water services in 20 bar operating pressure.
  • 2. Specification & drawings are other two important items to be analyzed in detail for clear understanding. Here the term engineer means the consultant for the project. The Importance of BOQ BOQ shall be used in every phase (pre-contract & post-contract) of the project but need of BOQ differs based on different contract agreements & project. The major usages are listed below. 1. It provides basic idea of the project by giving the quantities to tenderers. 2. It defines the extent of the work. (But it should be identified in line with drawings & specification as well). 3. It gives estimated or anticipated contract sum. (very important to client) 4. It provides a basis for valuation of variation. (Variation is to be discussed in detail). The major Parts of BOQ Parts of BOQ can be varied according to the project size as well the practices. Generally it has measured works, Preliminaries & Provisional sums. The contract sum would be addition of these three items.
  • 3. BILL OF QUANTITIES INTRODUCTION  Quantity surveying emerged as a separate profession in Britain in the 19th century. It is simply a task of measuring construction work required to implement the architects' design for new or renovated buildings. The purpose of the work is to produce quantified specifications of works known as Bills of Quantities. OBJECTIVES  The objectives of the Bill of Quantities are: (1) to provide sufficient information on the quantities of Works to be performed to enable bids to be prepared efficiently and accurately; and when a contract has been entered into, (2) to provide a priced Bill of Quantities foruse in the periodic valuation of works executed.  In order to attain these objectives, works are itemized in the Bill of Quantities in sufficient detail to distinguish between the different classes of works, or between works of the same nature carried out in different locations or in other circumstances which may give rise to different considerations of cost. Consistent with these requirements, the layout and content of the Bill of Quantities are required to be as simple and brief as possible.  The large data bank of information contained in the Bill of Quantities can be used in many ways to help the post-contract control of a project.
  • 4. QUANTITY SURVEYOR  Bill of Quantities form a part of the contract in many countries. The World  Bank and FIDIC documents also include Bill of Quantities.  In order to produce the Bill of Quantities, a detailed quantity survey ormaterials takeoff has to be completed. The services are provided by a professional Quantity Surveyor (QS).  A Quantity Surveyor is usually hired by the owner at the inception of a project. The QS makes cost feasibility studies, establishes construction budget, makes cost checks at all stages of the design process, and prepares a final Bill of Quantities. This Bill of Quantities is included in the bidding documents of the project. The bidders use this information, along with the construction drawings and specifications, as the basis fortheir pricing of the work.  The QS advises the owner on contractual arrangements and compiles certificates of interim and final payment to the contractordoing the work.  Based on their detailed knowledge of construction costs, the Quantity Surveyors can provide design cost planning service that allows customers to decide on their total budget, even before any design work is commissioned. Without cost planning, designs may result in bids that are too expensive. AN OVERVIEW OF BILLS OF QUANTITIES  The Bills of Quantities are usually indicated by items of work, units of measurement, quantities of work, rate fordoing the work, and total value of the work. An example is shown below: ItemID Descriptionof item Unit of measurement Quantityof work Rate inUS $ Total amountinUS $ 1 Reinforced cementconcrete workin grade beams(attaining compressive strengthof 3,000 psi in 28 days) withthe leanest permissible mix, 2:3:6 with3/4" downgraded crushedstone as coarse aggregate Cubicyard 1,000 75 75,000
  • 5. and coarse sand withan FMnot lessthan2.7 as fine aggregate.  Usually the contractorgoes through the Bills of Quantities and would quote her/his rate as a percentage above or below the rates indicated.  Even though the QS employed by the owner provides a detailed estimate forthe project, sometimes the rates and total amount to do the works may not be shown in the Bills of Quantities. In that case, the bidder provides the rates of the items at which she/he is capable to do the works.  Pricing of different items of work are done on the basis of the cost of materials, equipment, labor, and overheads and profit. o Materials: The materials costs are calculated by examining the material quotations received fromsuppliers, applying appropriate wastage factors, and delivery charges. o Equipment: Cost of equipment is calculated usually as a percentage of the cost of materials. Depending on whether the equipment is owned or rented, this percentage will vary. o Labor: The most difficult element to price is the labor cost. Most of the times, it is not sufficient to rely on published standard rates. Allowances for absences due to sickness, loss of time due to inclement weather, overtime, etc. are required to be built in to arrive at a pragmatic all-inclusive labor rate. Rate of productivity is another factorthat plays an important role in fixing labor prices. o Overheads and profit: Once the cost of materials, equipment, and labor has been added up, a percentage foroverhead and profit is added to the item rate. This percentage may vary from project to project depending on how well the document has been prepared by the QS and also on market conditions. It may range from2.5 to over 25 percent.  Once the pricing of all individual items forall trades is completed, the amounts are carried to a summary page to indicate the total bid price.
  • 6. SOME OTHER ADVANTAGES OF THE USE OF BILL OF QUANTITIES  Save the cost and time of several contractors measuring the same design in order to calculate their bids for competition.  Provide a consistent basis for competitive bids so that the contractorwho is the most efficient and least expensive in providing the items of work is likely to be commissioned for the job.  Provide an open basis forthe contract; the client provides an extensive and clear statement of the work he/she requires and the contractorstates the price at which he/she is prepared to undertake the job.  Provide a very strong basis for financial administration of the contract. The preparation of a BQ also has other advantages as well, such as:  Assisting the comparison and assessment of tenders, as tenders will be based on the same information;  Providing a good and fair basis for assessing variations during construction;  Being a basis for assessing and recommending progress claims and payments;  Helping to reduce the tender period (and its associated costs) as the tenderers then do not have to each individually reproduce the tender documents for their own ‘quick’ (though it may take weeks), and sometimes abridged, measurement and builders’ quantities;  And it also provides a basis for project cost analysis, so that future cost planning efforts have reliable information to refer to. Benefits of Bills of Quantities Bills of Quantities which we produce allow for obtaining a competitive tender price for completing the building works, valuing the extent of building works complete for the purpose of making payments to the contractor, valuing variations in the content or extent of building works, or to support applications for tax or other financial incentives. Our detailed measurement for the purpose of bills of quantities production is beneficial for a number of reasons:  It saves considerable time and cost of several contractors measuring the same design in order to calculate their bids for competition;  It provides a consistent basis for obtaining competitive tenders from contractors;  It provides an extensive and clear statement of the work to be executed;  It provides a very strong basis for budgetary control and accurate cost reporting of the contract including: - the preparation of cash flow forecasts,
  • 7. - a basis for valuing variations, and - a basis for the preparation of progress payments (ie. interim payments)  It allows, when BQ items are codified, reconciliation and any necessary transfers and adjustments to be made to the cost plan;  When priced it provides data to support claims for grants;  It provides one of the best sources of real-time cost data, which can be used for estimating the cost of future building projects Types of Bill of Quantities The main use of a bill of quantities in support of a contract is the traditional and proven means of securing a lump-sum price for carrying out the building works for the client. SC Quantity Surveyors produce several types of Bills of Quantities which include  Firm (to obtain a lump-sum price for a fully designed building project)  Approximate (subject to re measurement as built) Firm Bill of Quantities The reliability of the tender price will increase in relation to the accuracy of the quantities provided (i.e. the more precisely the work is measured and described). Provided there were no design changes, then firm bills of quantities would provide a price at tender stage, which would equal the final cost. However, there will be changes, and the bill of quantities provides a good basis for cost control, since the direct cost can be assessed with reference to the bill of quantity rates. In general the firmer the bill of quantities the better it is as a means of financial control. Approximate Bill of Quantities SC Quantity Surveyors can produce approximate bills of quantities which are mainly used when there is insufficient details to prepare firm bills of quantities or where the client has decided that the time and cost of a firm bill of quantities is not warranted. These types of contracts do not provide a lump-sum price, but instead tender price totals (ie. a quantified schedule of rates), since the quantities are subject to re-measurement on completion by the quantity surveyor. In general these contracts are usually subject to greater variation than lump sum contracts and therefore should only be used where time is a limiting factor or where there is great uncertainty in respect of certain elements, such as major excavations and earthworks. It is important to note that the initial resource cost of approximate bills of quantities is likely to be lower than firm bills of quantities, but the need for re-measurement invariably results in an overall higher resource cost. Although the measured quantities are approximate, the descriptions of work items should be correct in the approximate bill of quantities.
  • 8. Bills of Quantities that are required for a lump sum contract based on firm or approximate quantities will normally be prepared by the employer's quantity surveyor, whereas under a design and build contract, the employer's project team will prepare the employer's requirements and the Bill of Quantities or quantified schedules of work will be prepared by either the main contractor or, more likely, the main contractor's work package contractors. In general the choice of who quantifies building works is solely down to the employer's preference of contract strategy.