UNDP GEF Success Stories on renewable and
energy efficiency in the Western Balkans
Region
Sub-Regional Conference on Sustainable Energy in
South Eastern Europe , 9-10 December 2013
John O’Brien, Regional Technical Advisor
Climate Change Mitigation
UNDP Bratislava Regional Centre
Slovakia
Presentation Structure
1. Why what we do is important?
2. General Observations – What constitutes a successful
Project?
3. Specific Case Studies – Albania SWH & Croatia EE
- Adaptive Management
- Strong Regulatory & Legal Framework
- Scaling Up & Market Transformation
4. Concluding Remarks – Lessons Learned
2
IPCC predicts a rise in average temperature up to 6 degrees celcius by 2100

3
Successful projects do a
lot more than just
organizing a few
workshops and
seminars and
distributing some
materials …
I give projects high
marks if they implement
highly or reasonably
transformational
activities …

Outputs

Transformational

New Policies,
Legislation, Regulations

Energy-Efficiency Laws,
Building Codes,
Renewable Energy Laws,
Green Tarriffs

Highly
Transformational
(provided there is
enforcement)

Action Plans & Strategies

Sustainable Energy
Action Plans, Municipal
Energy Plans,
Sustainable Transport
Plans

Reasonably
transformational (if
investment funds
available)

Demonstration Projects

Revolving Funds,
Investment Funds &
Financial Support
Mechanisms

Reasonably
transformational (if
funds replenished)

Demonstrations Projects

Grant Funded DemoProjects

Moderately
transformational

Training Materials

What makes a
project
transformational
and highly
successful?

Outcome

Capacity Building
materials

Moderately
transformational

Workshops & Seminars

Capacity Building Events
with Key Stakeholders

Moderately
transformational

Information & Awareness

Materials including
websites …

Moderately
trensformational
4
Case Studies: Two Successful UNDP GEF Projects …

Albania Solar Water Heating
Project (2009 – 2014)

Croatia EE in Residential &
Service Sectors (2003 -2013)

Rating: HS (highly satisfactory)

Rating: HS (highly satisfactory)
5
Case Study Number 1 – Albania Solar Water Heating

Albania – Solar Water Heating Project – UNDP GEF - $1 million
Target of 75,000 m2 of new installed collector area over the
duration of the project as well as annual sales of over 20,000
m2 with expected continued growth to 520,000 m2 of installed
capacity by the year 2020. This is over 300MW of avoided
fossil fuel installed capacity. GHG reduction potential of over
800,000 tonnes of CO2e. Ends in mid-2015
Key Achievements

(i) At mid-term nearly 40,000 m2 of new SWH capacity was
installed, over 50% of the final impact;
(ii) Adoption of national product standards for SWH;
(iii) A national action plan on renewable energy
(iv) A new renewable energy law was passed in Albania, with the
assistance of the project, providing preferential tarriffs for RE
6 6
Case Study Number 2 – Croatia Energy-Efficiency in Residential & Service
Sectors – ran from 2003 - 2013

Key Achievements
(i) National EE Master-plan with the
Programme of Implementation 2008-2016
(ii) Energy Charter: signed by all towns and
counties in the Republic of Croatia
(iii)National database of energy-efficiency
measures created, updated, and
maintained
(iv)All municipalities in Croatia implementing
energy management information systems
(v) 63% of households in Croatia switched to
the use of CFL bulbs
(vi)Ownership by local and national authorities
was a key success factor
7
Both Albania & Croatia projects undertook adaptive management
Albania project was supposed to benefit from UNEP assistance for
capacity building & training activities but it never really came so the
project took it upon itself to develop training materials and deliver
training sessions on SWH;
Croatia project entitled ‘Removing Barriers to Energy-Efficiency in
the Residential & Service Sectors’ and ended up with a main focus
on the public & municipal sectors. Initial focus on CFL distribution &
loan guarantee mechanism was replaced with a focus on energy
management information systems for public sector. Ran for 10 yrs.
The initial project design of the Croatia EE project was not suited to
the circumstances that the project found itself in when it started …
8
Adaptive Management
In particular, the Croatia EE project developed and implemented a
web based energy management information system (EMIS) to
allow for continuous data collection of energy usage in buildings …
Enables easy analysis and interpretation of energy and water
usage data on local, regional or national level from one central
place.

The EMIS can be accessed by any computer with an internet connection
The EMIS is in the process of being transferred from Croatia to Serbia …
9
Albania SWH & Croatia EE projects helped introduce new legislation
& plans …
Albania Renewable Energy Law (April 2013)
- national binding objective for RE by the year 2020
- incentives to facilitate grid connections for Albanian companies
- guaranteed long term power purchase agreements for 15 years
- streamlined licensing and permitting procedures
- preferential feed-in tarriffs for renewable energy
Croatia EE Project (2006-2013) contributed to
- Energy Efficiency master plan 2008-2016
- Energy strategy of Croatia
- First National Energy Efficiency action plan (2008-2010)
- Second National Energy Efficiency Action Plan (up to 2013)
- Law on Efficient end use of Energy (2012)
10
Demonstrations on their own are not enough unless they involve
scaling up ….
Both projects involve scaling up & market transformation
Albania SWH project supported several muncipal sector
demonstration projects and envisages scaling up through an
investment grant mechanism before end of the project;
Croatia EE project started with a pilot project on ‘introduction of
Systematic Energy management system in city of Sisak in 2006 and
this was used to launch a national EMIS project in December 2007
The Croatia EE project led to significant leveraging of additional
funds, leveraging over $40 million USD in additional public funding
for energy-efficiency;
The Albania SWH project envisages at least $15 million in
leveraging from the financial support mechanism (investment grant
mechanism)
11
Key UNDP/GEF rules for Adaptive Management …
Project objective and outcomes are difficult to change…once that prodoc is
signed you are “locked in” as regards expected achievements (unless you
want to go back to GEF)
…but project outputs, activities and sub-activities can be adjusted; a prodoc is a
living document and not “cast in stone.” Adaptive management should start
from project inception. Not wait until the mid-term evaluation.
In fact, the Project Manager should constantly monitor them and adapt as
necessary, after consultations with key partners. A reason why Albania &
Croatia projects have been successful is continual adaptive management
Adaptive management is a strategy emphasizing the need to change with the
environment and to learn from doing, even from failures.
Unfortunately, UNDP’s M&E culture is one where “failures” are seen as a
weakness and not as an opportunity for adaptation and improvement. I have
never ever seen a Project Manager give a Project a ‘U’ rating.
12
Why are Mid-Term Evaluations Important?
Mid-Term evaluations are important because they provide a
stock-taking of all that the project has achieved so far and can
provide concrete recommendations to improve the project over
the second half of the project lifetime … Recommendations
should be clear, specific, well defined and measurable …
Example of poor MTE (based on one recent example):
-The project needs one person in charge and not two;
-The project should not follow exactly what is in Prodoc/RCE;
-The project needs to do adaptive management;
The same evaluator excused a project that did nothing for two
years with the following comment
- The project did not know they could do adaptive management
13
We also learn lessons from projects that were
less successful?
Russia Greening Sochi – Poor project design & short time-frame
makes it very hard for a project to be sucessful. $1 million dollars
and two years and six components to transform the Sochi
Olympics was not enough. (project will finish in early 2014)
Ukraine ESCO Rivne – To succesfully achieve ESCO you need to
focus on financing arrangements and this is very challenging in
some countries. Establishing ESCO markets is not easy and ESCO
Rivne was never an ESCO (started in 2000 and finished in 2012)
Serbia Sustainable Transport - $1 million USD to transform the
transportation system of the city of Belgrade is not enough for a
transformational impact and project held MTE 3 ¼ years into a 4
year project & with almost no funds left (project will finish in early
2014 with very low global environmental benefits)
14
Lessons learnt: Working Well and Areas for Improvement
UNDP general works well when it comes to
 working at a local level (municipalities, local governments)
 changes in policies, legislation, regulation
 awareness raising activities
 guidebooks, training materials
 demonstration activities
Where UNDP can sometimes impprove
 Coordination with other Agencies
 Financial Support Mechanisms
 Finding Investors/Engaging Private Sector
& getting them to invest …
1515
‘Instead of trying to change the world, lets try to change ourself
…’ (Nelson Mandela 1918 – 2013)
16

Mais conteúdo relacionado

Mais procurados

Major projects in Victoria: challenges, issues, and where to from here?
Major projects in Victoria: challenges, issues, and where to from here?Major projects in Victoria: challenges, issues, and where to from here?
Major projects in Victoria: challenges, issues, and where to from here?
Paul O'Connor
 
SEFA ANNUAL REPORT 2015
SEFA ANNUAL REPORT 2015SEFA ANNUAL REPORT 2015
SEFA ANNUAL REPORT 2015
Goran Lima
 
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
KTN
 
Celia Chambers - Northern Ireland plugged in places project
Celia Chambers  - Northern Ireland plugged in places projectCelia Chambers  - Northern Ireland plugged in places project
Celia Chambers - Northern Ireland plugged in places project
Keith Nolan
 
Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...
Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...
Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...
RCREEE
 

Mais procurados (19)

UNECE Renewable Energy Status: Key messages on the status of renewables in 17...
UNECE Renewable Energy Status: Key messages on the status of renewables in 17...UNECE Renewable Energy Status: Key messages on the status of renewables in 17...
UNECE Renewable Energy Status: Key messages on the status of renewables in 17...
 
Unlocking Capital for Land Use and Conservation Projects: the Business Case f...
Unlocking Capital for Land Use and Conservation Projects: the Business Case f...Unlocking Capital for Land Use and Conservation Projects: the Business Case f...
Unlocking Capital for Land Use and Conservation Projects: the Business Case f...
 
CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...
CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...
CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...
 
Major projects in Victoria: challenges, issues, and where to from here?
Major projects in Victoria: challenges, issues, and where to from here?Major projects in Victoria: challenges, issues, and where to from here?
Major projects in Victoria: challenges, issues, and where to from here?
 
Climate change and energy policy in the construction sector berlin-germany-...
Climate change and energy policy in the construction sector   berlin-germany-...Climate change and energy policy in the construction sector   berlin-germany-...
Climate change and energy policy in the construction sector berlin-germany-...
 
SEFA ANNUAL REPORT 2015
SEFA ANNUAL REPORT 2015SEFA ANNUAL REPORT 2015
SEFA ANNUAL REPORT 2015
 
Solving the finance conundrum affecting innovative renewable energy technologies
Solving the finance conundrum affecting innovative renewable energy technologiesSolving the finance conundrum affecting innovative renewable energy technologies
Solving the finance conundrum affecting innovative renewable energy technologies
 
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
 
Marie executive summary
Marie executive summaryMarie executive summary
Marie executive summary
 
BRICS Infrastructure Investment, May 2014
BRICS Infrastructure Investment, May 2014BRICS Infrastructure Investment, May 2014
BRICS Infrastructure Investment, May 2014
 
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
 
Celia Chambers - Northern Ireland plugged in places project
Celia Chambers  - Northern Ireland plugged in places projectCelia Chambers  - Northern Ireland plugged in places project
Celia Chambers - Northern Ireland plugged in places project
 
Program Management in Developing Countries
Program Management in Developing CountriesProgram Management in Developing Countries
Program Management in Developing Countries
 
Ecoheat4eu - Executive summary report
Ecoheat4eu - Executive summary reportEcoheat4eu - Executive summary report
Ecoheat4eu - Executive summary report
 
Marie pdf13
Marie pdf13Marie pdf13
Marie pdf13
 
Comesa investment teaser 2011
Comesa investment teaser 2011Comesa investment teaser 2011
Comesa investment teaser 2011
 
Results of lebanon’s national energy efficiency and renewable energy action (...
Results of lebanon’s national energy efficiency and renewable energy action (...Results of lebanon’s national energy efficiency and renewable energy action (...
Results of lebanon’s national energy efficiency and renewable energy action (...
 
Sizing Renewable Energy Systems for Different Facilities and Translation to C...
Sizing Renewable Energy Systems for Different Facilities and Translation to C...Sizing Renewable Energy Systems for Different Facilities and Translation to C...
Sizing Renewable Energy Systems for Different Facilities and Translation to C...
 
Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...
Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...
Pcc climate finance_implications_for_re_&_ee_projects_in_mena_region cdm work...
 

Destaque (6)

6 miroslav hrenovcik undp brc greening activity
6 miroslav hrenovcik undp brc greening activity6 miroslav hrenovcik undp brc greening activity
6 miroslav hrenovcik undp brc greening activity
 
25 marina olshanskaya gef innovation zagreb
25 marina olshanskaya gef innovation zagreb25 marina olshanskaya gef innovation zagreb
25 marina olshanskaya gef innovation zagreb
 
Tcpip
TcpipTcpip
Tcpip
 
Android gamesanalysis hunger-gamesfinal
Android gamesanalysis hunger-gamesfinalAndroid gamesanalysis hunger-gamesfinal
Android gamesanalysis hunger-gamesfinal
 
26 sinisa rodic distributed intelligence and energy - sinisa rodic undp co bi_h
26 sinisa rodic distributed intelligence and energy - sinisa rodic undp co bi_h26 sinisa rodic distributed intelligence and energy - sinisa rodic undp co bi_h
26 sinisa rodic distributed intelligence and energy - sinisa rodic undp co bi_h
 
Paul hockenos energiewende keynote zagreb
 Paul hockenos  energiewende keynote zagreb Paul hockenos  energiewende keynote zagreb
Paul hockenos energiewende keynote zagreb
 

Semelhante a 5 john o'brien presentations success stories

Session1.1 jts julia chenut
Session1.1 jts julia chenutSession1.1 jts julia chenut
Session1.1 jts julia chenut
SHAREPROJECT
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countries
Global CCS Institute
 
Presentation_Gambia SE4ALL AA and IP_v2
Presentation_Gambia SE4ALL AA and IP_v2Presentation_Gambia SE4ALL AA and IP_v2
Presentation_Gambia SE4ALL AA and IP_v2
Dr. Edward Saja Sanneh
 
ELENA assistance case study - Pool Engineering S.r.l
ELENA assistance case study - Pool Engineering S.r.lELENA assistance case study - Pool Engineering S.r.l
ELENA assistance case study - Pool Engineering S.r.l
Marina Turcati
 
Apec workshop 2 presentation 17 apec workshop 2 frank mourits
Apec workshop 2 presentation 17 apec workshop 2   frank mouritsApec workshop 2 presentation 17 apec workshop 2   frank mourits
Apec workshop 2 presentation 17 apec workshop 2 frank mourits
Global CCS Institute
 

Semelhante a 5 john o'brien presentations success stories (20)

Kiev presentations validation workshop 24 september
Kiev   presentations validation workshop 24 septemberKiev   presentations validation workshop 24 september
Kiev presentations validation workshop 24 september
 
N__Libya_RE_National_Plan.pdf
N__Libya_RE_National_Plan.pdfN__Libya_RE_National_Plan.pdf
N__Libya_RE_National_Plan.pdf
 
IHA Congress 2011 - Jasper Oduor global worshop
IHA Congress 2011 - Jasper Oduor global worshopIHA Congress 2011 - Jasper Oduor global worshop
IHA Congress 2011 - Jasper Oduor global worshop
 
Energy Infrastructure Package: What is in it for HVDC Grids?
Energy Infrastructure Package: What is in it for HVDC Grids?Energy Infrastructure Package: What is in it for HVDC Grids?
Energy Infrastructure Package: What is in it for HVDC Grids?
 
Session1.1 jts julia chenut
Session1.1 jts julia chenutSession1.1 jts julia chenut
Session1.1 jts julia chenut
 
Oulu: The implementation of the climate change programme as a cross administr...
Oulu: The implementation of the climate change programme as a cross administr...Oulu: The implementation of the climate change programme as a cross administr...
Oulu: The implementation of the climate change programme as a cross administr...
 
Climate finance van de ven (ebrd)scaling up cf ccxg gf march2014
Climate finance van de ven (ebrd)scaling up cf ccxg gf march2014Climate finance van de ven (ebrd)scaling up cf ccxg gf march2014
Climate finance van de ven (ebrd)scaling up cf ccxg gf march2014
 
Mexico CCUS roadmap, Moises Davila, SENER
Mexico CCUS roadmap, Moises Davila, SENERMexico CCUS roadmap, Moises Davila, SENER
Mexico CCUS roadmap, Moises Davila, SENER
 
Alterenergy - Guidelines for Sustainable Energy Management in the Adriatic Area
Alterenergy - Guidelines for Sustainable Energy Management in the Adriatic AreaAlterenergy - Guidelines for Sustainable Energy Management in the Adriatic Area
Alterenergy - Guidelines for Sustainable Energy Management in the Adriatic Area
 
Þróunarsjóður EFTA - Óttar Freyr Gíslason
Þróunarsjóður EFTA - Óttar Freyr GíslasonÞróunarsjóður EFTA - Óttar Freyr Gíslason
Þróunarsjóður EFTA - Óttar Freyr Gíslason
 
Marie project - leaflet
Marie project - leafletMarie project - leaflet
Marie project - leaflet
 
1st issue of LiCEA newsletter
1st issue of LiCEA newsletter1st issue of LiCEA newsletter
1st issue of LiCEA newsletter
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countries
 
Integrated, adaptable and affordable packages for the deep renovation of buil...
Integrated, adaptable and affordable packages for the deep renovation of buil...Integrated, adaptable and affordable packages for the deep renovation of buil...
Integrated, adaptable and affordable packages for the deep renovation of buil...
 
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
 
The European Strategic Energy Technology Plan (SET-Plan)
The European Strategic Energy Technology Plan (SET-Plan)The European Strategic Energy Technology Plan (SET-Plan)
The European Strategic Energy Technology Plan (SET-Plan)
 
Presentation_Gambia SE4ALL AA and IP_v2
Presentation_Gambia SE4ALL AA and IP_v2Presentation_Gambia SE4ALL AA and IP_v2
Presentation_Gambia SE4ALL AA and IP_v2
 
ELENA assistance case study - Pool Engineering S.r.l
ELENA assistance case study - Pool Engineering S.r.lELENA assistance case study - Pool Engineering S.r.l
ELENA assistance case study - Pool Engineering S.r.l
 
Apec workshop 2 presentation 17 apec workshop 2 frank mourits
Apec workshop 2 presentation 17 apec workshop 2   frank mouritsApec workshop 2 presentation 17 apec workshop 2   frank mourits
Apec workshop 2 presentation 17 apec workshop 2 frank mourits
 
CoM Barcelona_Bossio
CoM Barcelona_BossioCoM Barcelona_Bossio
CoM Barcelona_Bossio
 

Mais de UNDPhr

Mais de UNDPhr (20)

Plan razvoja Jadrtovca i Morinja
Plan razvoja Jadrtovca i MorinjaPlan razvoja Jadrtovca i Morinja
Plan razvoja Jadrtovca i Morinja
 
Sustav za praćenje, mjerenje i verifikaciju ušteda energije
Sustav za praćenje, mjerenje i verifikaciju ušteda energijeSustav za praćenje, mjerenje i verifikaciju ušteda energije
Sustav za praćenje, mjerenje i verifikaciju ušteda energije
 
UNDP_Energy Audits_2015
UNDP_Energy Audits_2015UNDP_Energy Audits_2015
UNDP_Energy Audits_2015
 
Energetski plan Nacionalnog parka Plitvička jezera_REGEA
Energetski plan Nacionalnog parka Plitvička jezera_REGEAEnergetski plan Nacionalnog parka Plitvička jezera_REGEA
Energetski plan Nacionalnog parka Plitvička jezera_REGEA
 
Nacionalno koordinacijsko tijelo za energetsku učinkovitost
Nacionalno koordinacijsko tijelo za energetsku učinkovitostNacionalno koordinacijsko tijelo za energetsku učinkovitost
Nacionalno koordinacijsko tijelo za energetsku učinkovitost
 
HEP - Current status and perspectives of ESCO projects in Croatia
HEP - Current status and   perspectives of ESCO projects in CroatiaHEP - Current status and   perspectives of ESCO projects in Croatia
HEP - Current status and perspectives of ESCO projects in Croatia
 
ENVIRONMENTAL PROTECTION AND ENERGY EFFICIENCY FUND
ENVIRONMENTAL PROTECTION AND ENERGY EFFICIENCY FUNDENVIRONMENTAL PROTECTION AND ENERGY EFFICIENCY FUND
ENVIRONMENTAL PROTECTION AND ENERGY EFFICIENCY FUND
 
Energy Insitute Hrvoje Pozar
Energy Insitute Hrvoje PozarEnergy Insitute Hrvoje Pozar
Energy Insitute Hrvoje Pozar
 
APN_EMIS_Funcionalities_07_2015
APN_EMIS_Funcionalities_07_2015APN_EMIS_Funcionalities_07_2015
APN_EMIS_Funcionalities_07_2015
 
Projektni paket - Ličko-senjska županija
Projektni paket - Ličko-senjska županijaProjektni paket - Ličko-senjska županija
Projektni paket - Ličko-senjska županija
 
Projektni paket - Sisačko-moslavačka županija
Projektni paket - Sisačko-moslavačka županijaProjektni paket - Sisačko-moslavačka županija
Projektni paket - Sisačko-moslavačka županija
 
Projektni paket - Karlovačka zupanija
Projektni paket  - Karlovačka zupanijaProjektni paket  - Karlovačka zupanija
Projektni paket - Karlovačka zupanija
 
Strateške smjernice - Sisačko-moslavačka županija
Strateške smjernice - Sisačko-moslavačka županijaStrateške smjernice - Sisačko-moslavačka županija
Strateške smjernice - Sisačko-moslavačka županija
 
Strateške smjernice - Ličko-senjska županija
Strateške smjernice - Ličko-senjska županijaStrateške smjernice - Ličko-senjska županija
Strateške smjernice - Ličko-senjska županija
 
Strateške smjernice - Karlovačka županija
Strateške smjernice - Karlovačka županijaStrateške smjernice - Karlovačka županija
Strateške smjernice - Karlovačka županija
 
Sustainable energy solutions in the Western Balkans
Sustainable energy solutions in the Western BalkansSustainable energy solutions in the Western Balkans
Sustainable energy solutions in the Western Balkans
 
Cooperation EU and the Western Balkans
Cooperation EU and the Western BalkansCooperation EU and the Western Balkans
Cooperation EU and the Western Balkans
 
Sustainable Energy - Martin Krause
Sustainable Energy - Martin KrauseSustainable Energy - Martin Krause
Sustainable Energy - Martin Krause
 
Better project - Introduction
Better project - IntroductionBetter project - Introduction
Better project - Introduction
 
EU project pipeline_FINAL_15122014
EU project pipeline_FINAL_15122014EU project pipeline_FINAL_15122014
EU project pipeline_FINAL_15122014
 

Último

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Último (20)

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Manulife - Insurer Innovation Award 2024
Manulife - Insurer Innovation Award 2024Manulife - Insurer Innovation Award 2024
Manulife - Insurer Innovation Award 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 

5 john o'brien presentations success stories

  • 1. UNDP GEF Success Stories on renewable and energy efficiency in the Western Balkans Region Sub-Regional Conference on Sustainable Energy in South Eastern Europe , 9-10 December 2013 John O’Brien, Regional Technical Advisor Climate Change Mitigation UNDP Bratislava Regional Centre Slovakia
  • 2. Presentation Structure 1. Why what we do is important? 2. General Observations – What constitutes a successful Project? 3. Specific Case Studies – Albania SWH & Croatia EE - Adaptive Management - Strong Regulatory & Legal Framework - Scaling Up & Market Transformation 4. Concluding Remarks – Lessons Learned 2
  • 3. IPCC predicts a rise in average temperature up to 6 degrees celcius by 2100 3
  • 4. Successful projects do a lot more than just organizing a few workshops and seminars and distributing some materials … I give projects high marks if they implement highly or reasonably transformational activities … Outputs Transformational New Policies, Legislation, Regulations Energy-Efficiency Laws, Building Codes, Renewable Energy Laws, Green Tarriffs Highly Transformational (provided there is enforcement) Action Plans & Strategies Sustainable Energy Action Plans, Municipal Energy Plans, Sustainable Transport Plans Reasonably transformational (if investment funds available) Demonstration Projects Revolving Funds, Investment Funds & Financial Support Mechanisms Reasonably transformational (if funds replenished) Demonstrations Projects Grant Funded DemoProjects Moderately transformational Training Materials What makes a project transformational and highly successful? Outcome Capacity Building materials Moderately transformational Workshops & Seminars Capacity Building Events with Key Stakeholders Moderately transformational Information & Awareness Materials including websites … Moderately trensformational 4
  • 5. Case Studies: Two Successful UNDP GEF Projects … Albania Solar Water Heating Project (2009 – 2014) Croatia EE in Residential & Service Sectors (2003 -2013) Rating: HS (highly satisfactory) Rating: HS (highly satisfactory) 5
  • 6. Case Study Number 1 – Albania Solar Water Heating Albania – Solar Water Heating Project – UNDP GEF - $1 million Target of 75,000 m2 of new installed collector area over the duration of the project as well as annual sales of over 20,000 m2 with expected continued growth to 520,000 m2 of installed capacity by the year 2020. This is over 300MW of avoided fossil fuel installed capacity. GHG reduction potential of over 800,000 tonnes of CO2e. Ends in mid-2015 Key Achievements (i) At mid-term nearly 40,000 m2 of new SWH capacity was installed, over 50% of the final impact; (ii) Adoption of national product standards for SWH; (iii) A national action plan on renewable energy (iv) A new renewable energy law was passed in Albania, with the assistance of the project, providing preferential tarriffs for RE 6 6
  • 7. Case Study Number 2 – Croatia Energy-Efficiency in Residential & Service Sectors – ran from 2003 - 2013 Key Achievements (i) National EE Master-plan with the Programme of Implementation 2008-2016 (ii) Energy Charter: signed by all towns and counties in the Republic of Croatia (iii)National database of energy-efficiency measures created, updated, and maintained (iv)All municipalities in Croatia implementing energy management information systems (v) 63% of households in Croatia switched to the use of CFL bulbs (vi)Ownership by local and national authorities was a key success factor 7
  • 8. Both Albania & Croatia projects undertook adaptive management Albania project was supposed to benefit from UNEP assistance for capacity building & training activities but it never really came so the project took it upon itself to develop training materials and deliver training sessions on SWH; Croatia project entitled ‘Removing Barriers to Energy-Efficiency in the Residential & Service Sectors’ and ended up with a main focus on the public & municipal sectors. Initial focus on CFL distribution & loan guarantee mechanism was replaced with a focus on energy management information systems for public sector. Ran for 10 yrs. The initial project design of the Croatia EE project was not suited to the circumstances that the project found itself in when it started … 8
  • 9. Adaptive Management In particular, the Croatia EE project developed and implemented a web based energy management information system (EMIS) to allow for continuous data collection of energy usage in buildings … Enables easy analysis and interpretation of energy and water usage data on local, regional or national level from one central place. The EMIS can be accessed by any computer with an internet connection The EMIS is in the process of being transferred from Croatia to Serbia … 9
  • 10. Albania SWH & Croatia EE projects helped introduce new legislation & plans … Albania Renewable Energy Law (April 2013) - national binding objective for RE by the year 2020 - incentives to facilitate grid connections for Albanian companies - guaranteed long term power purchase agreements for 15 years - streamlined licensing and permitting procedures - preferential feed-in tarriffs for renewable energy Croatia EE Project (2006-2013) contributed to - Energy Efficiency master plan 2008-2016 - Energy strategy of Croatia - First National Energy Efficiency action plan (2008-2010) - Second National Energy Efficiency Action Plan (up to 2013) - Law on Efficient end use of Energy (2012) 10
  • 11. Demonstrations on their own are not enough unless they involve scaling up …. Both projects involve scaling up & market transformation Albania SWH project supported several muncipal sector demonstration projects and envisages scaling up through an investment grant mechanism before end of the project; Croatia EE project started with a pilot project on ‘introduction of Systematic Energy management system in city of Sisak in 2006 and this was used to launch a national EMIS project in December 2007 The Croatia EE project led to significant leveraging of additional funds, leveraging over $40 million USD in additional public funding for energy-efficiency; The Albania SWH project envisages at least $15 million in leveraging from the financial support mechanism (investment grant mechanism) 11
  • 12. Key UNDP/GEF rules for Adaptive Management … Project objective and outcomes are difficult to change…once that prodoc is signed you are “locked in” as regards expected achievements (unless you want to go back to GEF) …but project outputs, activities and sub-activities can be adjusted; a prodoc is a living document and not “cast in stone.” Adaptive management should start from project inception. Not wait until the mid-term evaluation. In fact, the Project Manager should constantly monitor them and adapt as necessary, after consultations with key partners. A reason why Albania & Croatia projects have been successful is continual adaptive management Adaptive management is a strategy emphasizing the need to change with the environment and to learn from doing, even from failures. Unfortunately, UNDP’s M&E culture is one where “failures” are seen as a weakness and not as an opportunity for adaptation and improvement. I have never ever seen a Project Manager give a Project a ‘U’ rating. 12
  • 13. Why are Mid-Term Evaluations Important? Mid-Term evaluations are important because they provide a stock-taking of all that the project has achieved so far and can provide concrete recommendations to improve the project over the second half of the project lifetime … Recommendations should be clear, specific, well defined and measurable … Example of poor MTE (based on one recent example): -The project needs one person in charge and not two; -The project should not follow exactly what is in Prodoc/RCE; -The project needs to do adaptive management; The same evaluator excused a project that did nothing for two years with the following comment - The project did not know they could do adaptive management 13
  • 14. We also learn lessons from projects that were less successful? Russia Greening Sochi – Poor project design & short time-frame makes it very hard for a project to be sucessful. $1 million dollars and two years and six components to transform the Sochi Olympics was not enough. (project will finish in early 2014) Ukraine ESCO Rivne – To succesfully achieve ESCO you need to focus on financing arrangements and this is very challenging in some countries. Establishing ESCO markets is not easy and ESCO Rivne was never an ESCO (started in 2000 and finished in 2012) Serbia Sustainable Transport - $1 million USD to transform the transportation system of the city of Belgrade is not enough for a transformational impact and project held MTE 3 ¼ years into a 4 year project & with almost no funds left (project will finish in early 2014 with very low global environmental benefits) 14
  • 15. Lessons learnt: Working Well and Areas for Improvement UNDP general works well when it comes to  working at a local level (municipalities, local governments)  changes in policies, legislation, regulation  awareness raising activities  guidebooks, training materials  demonstration activities Where UNDP can sometimes impprove  Coordination with other Agencies  Financial Support Mechanisms  Finding Investors/Engaging Private Sector & getting them to invest … 1515
  • 16. ‘Instead of trying to change the world, lets try to change ourself …’ (Nelson Mandela 1918 – 2013) 16

Notas do Editor

  1. We are now living in a fossil fuel age at the peak of its strength. Almost 90% of all energy supply comes from fossil fuels. Nicolas Stern, author of the Stern Report said ‘I got it wrong on climate change. It is much worse that I thought …’ There is no scientific consensus on climate change?   Over 800 scientists were initially selected to work on the latest report from the Intergovernmental Panel on Climate Change, which published its summary on Friday. The full report will cite thousands of scientific papers, and has been through many rounds of review, involving a total of 136,706 comments. And the report’s conclusion? “Warming of the climate system is unequivocal.”   Global Warming has Stopped   Nope. Global warming has accelerated, with more overall global warming in the past 15 years than the prior 15 years. For each of the last three decades the Earth’s surface has been successively warmer than any preceding decade since 1850.   The recent pause in global warming shows that scientists are wrong   Average air temperature increase has slowed over the last 15 years. But that’s probably because 90% of overall warming goes into heating the oceans, and the oceans have been warming dramatically. That doesn’t make it OK.
  2. The poor evaluations of Mr ‘Marginally Satisfactory!!’
  3. You learn more in life when you are not so successful …