SlideShare uma empresa Scribd logo
1 de 4
Baixar para ler offline
Identifying the Critical Path

Scenario:

Activity duration estimates for the sidewalk replacement work package have been determined
as shown. You’ve started thinking about when you’ll be able to begin work and what resources
might be available. You examine the company master project schedule and find some openings
where your project might fit in, but you’re unsure if the work that needs to be accomplished can
be performed in the available time slots.




    1. Perform a forward pass to determine the early start (ES) and early finish (EF) for each activity.
       Enter your answers in the appropriate place in the network diagram. What is the ES for activity
       2.3.3.1, Remove Old Sidewalk?

        The ES for the first activity is assumed to be zero.

    2. What is the EF for activity 2.3.3.1?

        EF is 20, the same as the duration.

    3. What are the ES and EF for activity 2.3.3.2, Excavate Lawn?

        EF is 20, the EF for the predecessor activity. EF is 45, its ES + duration.




1                                        Identifying the Critical Path
4. Calculate the ES and EF for the remaining activities. Why is the ES for activity 2.3.3.5 the same as
       the ES for activity 2.3.3.4?

        They both have the same predecessor activity (2.3.3.3).

    5. How do you calculate the ES for the last activity, 2.3.3.7?

        The ES for the last activity is calculated by taking the EF from 2.3.3.4 and adding the 16-hour
        finish-to-start lag for the concrete to cure.

    6. What does your network diagram look like with a forward pass?




    7. Perform a backward pass to determine the late start (LS) and late finish (LF) for each activity.
       Enter your answers in the appropriate place in the network diagram. What is the LF for activity
       2.3.3.7, Remove Forms?

        The LF for the last activity is the same as its EF, which is 81.

    8. Why is the LF for activity 2.2.3.4, Pour Concrete, the same as its EF?

        The activity is on the critical path.

    9. Why is the LF for activity 2.3.3.6, Lay Sod, higher than the LS for activity 2.3.3.4, Pour Concrete?

        There is a 16-hour lag between the finish activity 2.3.3.4, Pour Concrete, and the start of actifity
        2.3.3.7, Remove Forms.


2                                        Identifying the Critical Path
10. What does your completed diagram look like with a backward pass?




    11. Determine the float for this network. Which activities have total float in this network? How
        much float do they have?

        Activities 2.3.3.5 and 2.3.3.6 are the only activities with total float because they are not on the
        critical path. Each has a total float of 10 hours (LF-EF or LS-ES).

    12. Does that mean that those activities can each flex their start or finish time by the total float
        hours?

        No. The 10 hours of total float are shared by the two activities. If activity 2.3.3.5 is delayed for
        eight hours, there will only be two hours of float left for activity 2.3.3.6.

    13. Which activities have free float?

        Only activity 2.3.3.6, Lay Sod, has free float, because it’s the only activity that can safely be
        delayed without delaying the ES of the subsequent activity, which is on the critical path.

    14. How much free float does that activity have?

        Activity 2.3.3.6 has 10 hours of free float, which is the same as its total float. However, activity
        2.3.3.5 does not have free float. The activity shares the 10 hours of total float with activity
        2.3.3.6.

3                                       Identifying the Critical Path
15. What would happen to the free float of that activity if its concurrent activity used up the hours
        of total float?

        It would go to zero, so activity 2.3.3.6 would no longer have any float.

    16. What is the critical path?

        There are two possible paths through the activities. The total duration nodes 2.3.3.1 + 2.3.3.2 +
        2.3.3.3 + 2.3.3.5 + 2.3.3.6 + 2.3.3.7 = 71. The total duration for nodes 2.3.3.1 + 2.3.3.2 + 2.3.3.3 +
        2.3.3.4 + 2.3.3.7 = 81 counting the 16-hour lag for the concrete curing, so that is the critical path.

    17. What will happen to the total time if it takes 12 hours to pour the concrete?

        Activity 2.3.3.4, Pour Concrete, has an estimated duration of eight hours and is on the critical
        path. So if the actual duration of that activity increases by four hours, the total time will also
        increase by four hours.

    18. What will happen to the total time if it takes 10 hours to lay the sod?

        Activity 2.3.3.6, Lay Sod, is not on the critical path. So if the actual duration of that activity
        increases by two hours, the total time will not be affected.

    19. What will happen to the total time if it takes 20 hours to lay the sod?

        The critical path will change, and total time will increase to 83 hours.




4                                        Identifying the Critical Path

Mais conteúdo relacionado

Semelhante a Capm scenario identifying the critical path answers

12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
Ahmad Basim Hamza
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
BetshaTizazu2
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
licpn03
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
infinitepestcontrol
 
Pert- program evaluation and review technique
Pert- program evaluation and review techniquePert- program evaluation and review technique
Pert- program evaluation and review technique
Vinci Viveka
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
hannahpepino1
 
Unit 2 Modeling of Programs A function maps inputs to out.docx
Unit 2 Modeling of Programs A function maps inputs to out.docxUnit 2 Modeling of Programs A function maps inputs to out.docx
Unit 2 Modeling of Programs A function maps inputs to out.docx
dickonsondorris
 

Semelhante a Capm scenario identifying the critical path answers (20)

Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
Management science
Management scienceManagement science
Management science
 
Session B1 - Planning, Scheduling Monitoring and Control
Session B1 - Planning, Scheduling Monitoring and ControlSession B1 - Planning, Scheduling Monitoring and Control
Session B1 - Planning, Scheduling Monitoring and Control
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
 
Pert- program evaluation and review technique
Pert- program evaluation and review techniquePert- program evaluation and review technique
Pert- program evaluation and review technique
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Unit 2 Modeling of Programs A function maps inputs to out.docx
Unit 2 Modeling of Programs A function maps inputs to out.docxUnit 2 Modeling of Programs A function maps inputs to out.docx
Unit 2 Modeling of Programs A function maps inputs to out.docx
 

Mais de University High School - Fresno

Mais de University High School - Fresno (14)

Dah time mgmt matching exercise answers
Dah time mgmt matching exercise answersDah time mgmt matching exercise answers
Dah time mgmt matching exercise answers
 
Capm time mgmt fas track as
Capm time mgmt fas track asCapm time mgmt fas track as
Capm time mgmt fas track as
 
Capm ccvc capm time 4th edition pmbok review
Capm ccvc capm time   4th edition pmbok reviewCapm ccvc capm time   4th edition pmbok review
Capm ccvc capm time 4th edition pmbok review
 
Capm test taking preparation hints
Capm test taking preparation hintsCapm test taking preparation hints
Capm test taking preparation hints
 
Capm process cheat sheet
Capm process cheat sheetCapm process cheat sheet
Capm process cheat sheet
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Capm time mgmt matching exercise
Capm time mgmt matching exerciseCapm time mgmt matching exercise
Capm time mgmt matching exercise
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Zoskctr hints tips 20090723doc
Zoskctr hints tips 20090723docZoskctr hints tips 20090723doc
Zoskctr hints tips 20090723doc
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Source code examples
Source code examplesSource code examples
Source code examples
 
Business computing survey
Business computing surveyBusiness computing survey
Business computing survey
 
Watson
WatsonWatson
Watson
 

Capm scenario identifying the critical path answers

  • 1. Identifying the Critical Path Scenario: Activity duration estimates for the sidewalk replacement work package have been determined as shown. You’ve started thinking about when you’ll be able to begin work and what resources might be available. You examine the company master project schedule and find some openings where your project might fit in, but you’re unsure if the work that needs to be accomplished can be performed in the available time slots. 1. Perform a forward pass to determine the early start (ES) and early finish (EF) for each activity. Enter your answers in the appropriate place in the network diagram. What is the ES for activity 2.3.3.1, Remove Old Sidewalk? The ES for the first activity is assumed to be zero. 2. What is the EF for activity 2.3.3.1? EF is 20, the same as the duration. 3. What are the ES and EF for activity 2.3.3.2, Excavate Lawn? EF is 20, the EF for the predecessor activity. EF is 45, its ES + duration. 1 Identifying the Critical Path
  • 2. 4. Calculate the ES and EF for the remaining activities. Why is the ES for activity 2.3.3.5 the same as the ES for activity 2.3.3.4? They both have the same predecessor activity (2.3.3.3). 5. How do you calculate the ES for the last activity, 2.3.3.7? The ES for the last activity is calculated by taking the EF from 2.3.3.4 and adding the 16-hour finish-to-start lag for the concrete to cure. 6. What does your network diagram look like with a forward pass? 7. Perform a backward pass to determine the late start (LS) and late finish (LF) for each activity. Enter your answers in the appropriate place in the network diagram. What is the LF for activity 2.3.3.7, Remove Forms? The LF for the last activity is the same as its EF, which is 81. 8. Why is the LF for activity 2.2.3.4, Pour Concrete, the same as its EF? The activity is on the critical path. 9. Why is the LF for activity 2.3.3.6, Lay Sod, higher than the LS for activity 2.3.3.4, Pour Concrete? There is a 16-hour lag between the finish activity 2.3.3.4, Pour Concrete, and the start of actifity 2.3.3.7, Remove Forms. 2 Identifying the Critical Path
  • 3. 10. What does your completed diagram look like with a backward pass? 11. Determine the float for this network. Which activities have total float in this network? How much float do they have? Activities 2.3.3.5 and 2.3.3.6 are the only activities with total float because they are not on the critical path. Each has a total float of 10 hours (LF-EF or LS-ES). 12. Does that mean that those activities can each flex their start or finish time by the total float hours? No. The 10 hours of total float are shared by the two activities. If activity 2.3.3.5 is delayed for eight hours, there will only be two hours of float left for activity 2.3.3.6. 13. Which activities have free float? Only activity 2.3.3.6, Lay Sod, has free float, because it’s the only activity that can safely be delayed without delaying the ES of the subsequent activity, which is on the critical path. 14. How much free float does that activity have? Activity 2.3.3.6 has 10 hours of free float, which is the same as its total float. However, activity 2.3.3.5 does not have free float. The activity shares the 10 hours of total float with activity 2.3.3.6. 3 Identifying the Critical Path
  • 4. 15. What would happen to the free float of that activity if its concurrent activity used up the hours of total float? It would go to zero, so activity 2.3.3.6 would no longer have any float. 16. What is the critical path? There are two possible paths through the activities. The total duration nodes 2.3.3.1 + 2.3.3.2 + 2.3.3.3 + 2.3.3.5 + 2.3.3.6 + 2.3.3.7 = 71. The total duration for nodes 2.3.3.1 + 2.3.3.2 + 2.3.3.3 + 2.3.3.4 + 2.3.3.7 = 81 counting the 16-hour lag for the concrete curing, so that is the critical path. 17. What will happen to the total time if it takes 12 hours to pour the concrete? Activity 2.3.3.4, Pour Concrete, has an estimated duration of eight hours and is on the critical path. So if the actual duration of that activity increases by four hours, the total time will also increase by four hours. 18. What will happen to the total time if it takes 10 hours to lay the sod? Activity 2.3.3.6, Lay Sod, is not on the critical path. So if the actual duration of that activity increases by two hours, the total time will not be affected. 19. What will happen to the total time if it takes 20 hours to lay the sod? The critical path will change, and total time will increase to 83 hours. 4 Identifying the Critical Path