17. REGULATORY MARKET ENVIRONMENTS
• Finland
– Medium reliability: SAIDI for MV/LV grid 138 min (2007 – 2009)
– All the DSOs have to show plans to stick to the roadmap every two
years. (Goal 2028)
Maximum outage in
urban areas
Maximum outage in
other areas
0
50
100
150
200
0 36 72 108 144 180 216 252 288
Repayment in % of the annual bill
Outage in hours
Repayment to the customer of the annual bill
due to outage hours
6 12
18. REGULATORY MARKET ENVIRONMENTS
§ Germany
§ High reliability: SAIDI for MV/LV grid 15.31 min (2011)
§ Regulation focuses heavily on investment effectiveness à lower
cost e.g. per feeder km
-300000
-250000
-200000
-150000
-100000
-50000
0
50000
100000
0 20 40 60 80
Outage Cost
Outage Cost
From 1% bonus to 8 % penalty (6 MEUR Revenue)
2013/2014 2017/2018
Influencable costs Allowed revenue - end of 2nd
regulation period
Allowed revenue - beginning of 2nd
regulation period
Momentary non
influencable costs
Permanently non
influencable costs
Permanently non
influencable costs
Momentary non
influencable costs
-1,5%
Max 40%
Min 60%
19. REGULATORY MARKET ENVIRONMENTS
§ Italy
§ Medium reliability (vs. FI, DE) , SAIDI ~49min (2009)
§ Good incentives for grid reliability and for automation.
§ New mechanisms further incentive crucial areas and e.g. 25% of
the secondary substations for investments in next years.