SlideShare uma empresa Scribd logo
1 de 23
Baixar para ler offline
1
UV
Disinfection
System
Detailed Design
Ashbridges Bay
Treatment Plant
2
• Meeting Objective
• Project Background
• Project Implementation
• Design Criteria
• UV Disinfection Facility
• UV Supplier Selection
• Effluent Discharge Management
• Capital / Project Schedule
Agenda
2
3
Presentation of the UV Disinfection Facility detailed
design prior to Tendering and Construction
Meeting Objective
3
4
Project Background
• Improved ABTP discharge treated effluent
quality
• Discontinue use of the Seawall Gates
• Improved nearshore water quality at ABTP
• Eliminate chlorination by-products during
normal operation
• Eliminate residual chlorine during by-pass
• Increased ABTP process reliability and
operational flexibility
• Connect to the new outfall
4
5
Project Objective
• Design and construct an UV disinfection facility that meets all
regulations
Success Factors
• Elimination of residual chlorine discharge to the lake
• Discontinue the use of the seawall gates
• Improvement of the nearshore water quality
• Meeting EA commitments
Project Implementation
5
6
• Effluent flows
– 818 MLD (rated capacity)
– 2,000 MLD
– 3,300 MLD
• Effluent UV disinfection (normal operation)
• Effluent chlorination / dechlorination (by-pass mode)
Design Criteria
6
7
Project Overview
Seawall
Substation
Upgrades and
New Standby
Generators
Plant Water
Pumping Station
Upgrades
New
Disinfection
Building
New Bypass
Water Tower
Elimination
New Outfall
(by others)
7
8
New Disinfection Building
8
9
Disinfection Building Overview
Architectural 3D
Ground Floor Plan
9
10
Disinfection Building Overview
Architectural 3D
Second Floor Plan
10
11
Disinfection Building Overview
Architectural 3D
Third Floor Plan
11
12
Disinfection Building Overview
• Combination of Green Roof / Cool Roof
• Solar Wall
Green Roof
Architectural 3D
Roof Plan
12
13
UV Facility
UV
Equipment
UV Channel
13
14
Sodium hypochlorite
Sodium bisulfite
Chemical Storage and Dosing System
14
15
Energy Conservation Measures
• Green Roof
• Solar Wall
• Heat recovery to reduce operational cost
• Occupied/ unoccupied control (light and heat)
• VFDs provided to all fans & pumps
• Heat reclaim for domestic water heating
• Ultra high efficiency and high efficiency motors and
lighting
• Mechanical control system linked to ABTP central
computer system
• Environmentally friendly refrigerants in air-
conditioning system
• Variable Refrigerant Flow (VRF) in air-conditioning
system
15
16
UV Equipment Competitive Pre-Selection
Monetary Criteria
• Equipment capital cost
• Facility capital cost
• Operating cost
Non-Monetary Criteria
• Vendor experience
• Performance guarantee
• Service capabilities
• Replacement parts
• Reference facilities
16
17
• Highest score
• Lower energy consumption
• Lower number of lamps
UV Pre-selected Supplier – TrojanUV
Lamp Technology
Number of
Lamps
Required
Power Draw
Low Pressure – High Output 4,720 1,180 kW
Medium Pressure – High Output 1,680 4,300 kW
New Low Pressure – Very High Output 1,408 1,280 kW
17
18
Discharge To Lake 2017 – 2020 (during UV facility
construction)
By-Pass
Disinfection
Existing Outfall
and Seawall Gates
18
19
Discharge to Lake 2020 to 2023 (UV operation during
new outfall construction)
By-Pass
Disinfection
Existing Outfall
and Seawall Gates
UV Disinfection
UV
19
20
Discharge to Lake 2023 (UV and new outfall)
By-Pass
Disinfection
UV Disinfection
UV
New 3,923 MLD
Outfall
20
21
Cost and Project Schedule
Total Project Cost (2019 CAD) $220M
Total Estimated Construction Duration 3 years
2017 2018 2019 2020 2021 2022 2023
100%
Detailed
Design
Start
Construction
UV
Operation
Old Outfall
UV
Operation
New
Outfall
Design Construction Operation
Tender
21
22
Conclusions
• Meeting EA requirements and applicable regulations
• Eliminate effluent chlorination (during normal operation
with UV)
• Improve effluent quality and near shore lake water quality
22
23
Thank you
23

Mais conteúdo relacionado

Mais procurados

LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
HartTWI
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
ascemiami-dade
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
Mark Oberschmidt
 

Mais procurados (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University Course
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Road Salt Regional Perspective: New York State Success Stories
Road Salt Regional Perspective: New York State Success StoriesRoad Salt Regional Perspective: New York State Success Stories
Road Salt Regional Perspective: New York State Success Stories
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
SmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network PlanningSmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network Planning
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
 
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 

Semelhante a Disinfection System

Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology Forum
John Glenning
 
Capstone turbine corporation e-finity distributed generation
Capstone turbine corporation  e-finity distributed generation Capstone turbine corporation  e-finity distributed generation
Capstone turbine corporation e-finity distributed generation
TNenergy
 
Parmenter, Brady, Presentation
Parmenter, Brady, PresentationParmenter, Brady, Presentation
Parmenter, Brady, Presentation
Brady Parmenter
 
Utilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water QualityUtilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water Quality
Muhammad Naeem Ashraf
 

Semelhante a Disinfection System (20)

Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
 
Project review
Project reviewProject review
Project review
 
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
 
Optimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy EfficiencyOptimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy Efficiency
 
Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology Forum
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
The role of AnMBR LEtm Anaerobic MBR in environmental improvements at the Gle...
 
Capstone turbine corporation e-finity distributed generation
Capstone turbine corporation  e-finity distributed generation Capstone turbine corporation  e-finity distributed generation
Capstone turbine corporation e-finity distributed generation
 
Design2Occupancy Services LLP Company Profile
Design2Occupancy Services LLP Company ProfileDesign2Occupancy Services LLP Company Profile
Design2Occupancy Services LLP Company Profile
 
annalee-1207
annalee-1207annalee-1207
annalee-1207
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
Parmenter, Brady, Presentation
Parmenter, Brady, PresentationParmenter, Brady, Presentation
Parmenter, Brady, Presentation
 
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
Closer Look At Infrastructure Sustainability - Engineering Perspective - Infr...
 
Utilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water QualityUtilizing Online TOC Monitoring to Control Industrial Water Quality
Utilizing Online TOC Monitoring to Control Industrial Water Quality
 
Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment
 
automating coating process
automating coating processautomating coating process
automating coating process
 
Hestia Energy - Levin Igloo Retrofit
Hestia Energy - Levin Igloo Retrofit Hestia Energy - Levin Igloo Retrofit
Hestia Energy - Levin Igloo Retrofit
 
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptxcase-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
case-study-sustainable-mixed-use-development-in-historic-urban-areas (2).pptx
 
Power-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperPower-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion Paper
 
Storm water harvestin_Anamrita khan_2013
Storm water harvestin_Anamrita khan_2013Storm water harvestin_Anamrita khan_2013
Storm water harvestin_Anamrita khan_2013
 

Mais de Toronto Public Consultation Unit

Mais de Toronto Public Consultation Unit (20)

King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
 
General information
General informationGeneral information
General information
 
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
 
Downsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study BoardsDownsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study Boards
 
Downsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study MapsDownsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study Maps
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
King-Liberty Pedestrian / Cycling Bridge
King-Liberty Pedestrian / Cycling Bridge King-Liberty Pedestrian / Cycling Bridge
King-Liberty Pedestrian / Cycling Bridge
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
 

Último

Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
 
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
nehasharma67844
 

Último (20)

Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
SMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptxSMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptx
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
 
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
 

Disinfection System

  • 2. 2 • Meeting Objective • Project Background • Project Implementation • Design Criteria • UV Disinfection Facility • UV Supplier Selection • Effluent Discharge Management • Capital / Project Schedule Agenda 2
  • 3. 3 Presentation of the UV Disinfection Facility detailed design prior to Tendering and Construction Meeting Objective 3
  • 4. 4 Project Background • Improved ABTP discharge treated effluent quality • Discontinue use of the Seawall Gates • Improved nearshore water quality at ABTP • Eliminate chlorination by-products during normal operation • Eliminate residual chlorine during by-pass • Increased ABTP process reliability and operational flexibility • Connect to the new outfall 4
  • 5. 5 Project Objective • Design and construct an UV disinfection facility that meets all regulations Success Factors • Elimination of residual chlorine discharge to the lake • Discontinue the use of the seawall gates • Improvement of the nearshore water quality • Meeting EA commitments Project Implementation 5
  • 6. 6 • Effluent flows – 818 MLD (rated capacity) – 2,000 MLD – 3,300 MLD • Effluent UV disinfection (normal operation) • Effluent chlorination / dechlorination (by-pass mode) Design Criteria 6
  • 7. 7 Project Overview Seawall Substation Upgrades and New Standby Generators Plant Water Pumping Station Upgrades New Disinfection Building New Bypass Water Tower Elimination New Outfall (by others) 7
  • 12. 12 Disinfection Building Overview • Combination of Green Roof / Cool Roof • Solar Wall Green Roof Architectural 3D Roof Plan 12
  • 14. 14 Sodium hypochlorite Sodium bisulfite Chemical Storage and Dosing System 14
  • 15. 15 Energy Conservation Measures • Green Roof • Solar Wall • Heat recovery to reduce operational cost • Occupied/ unoccupied control (light and heat) • VFDs provided to all fans & pumps • Heat reclaim for domestic water heating • Ultra high efficiency and high efficiency motors and lighting • Mechanical control system linked to ABTP central computer system • Environmentally friendly refrigerants in air- conditioning system • Variable Refrigerant Flow (VRF) in air-conditioning system 15
  • 16. 16 UV Equipment Competitive Pre-Selection Monetary Criteria • Equipment capital cost • Facility capital cost • Operating cost Non-Monetary Criteria • Vendor experience • Performance guarantee • Service capabilities • Replacement parts • Reference facilities 16
  • 17. 17 • Highest score • Lower energy consumption • Lower number of lamps UV Pre-selected Supplier – TrojanUV Lamp Technology Number of Lamps Required Power Draw Low Pressure – High Output 4,720 1,180 kW Medium Pressure – High Output 1,680 4,300 kW New Low Pressure – Very High Output 1,408 1,280 kW 17
  • 18. 18 Discharge To Lake 2017 – 2020 (during UV facility construction) By-Pass Disinfection Existing Outfall and Seawall Gates 18
  • 19. 19 Discharge to Lake 2020 to 2023 (UV operation during new outfall construction) By-Pass Disinfection Existing Outfall and Seawall Gates UV Disinfection UV 19
  • 20. 20 Discharge to Lake 2023 (UV and new outfall) By-Pass Disinfection UV Disinfection UV New 3,923 MLD Outfall 20
  • 21. 21 Cost and Project Schedule Total Project Cost (2019 CAD) $220M Total Estimated Construction Duration 3 years 2017 2018 2019 2020 2021 2022 2023 100% Detailed Design Start Construction UV Operation Old Outfall UV Operation New Outfall Design Construction Operation Tender 21
  • 22. 22 Conclusions • Meeting EA requirements and applicable regulations • Eliminate effluent chlorination (during normal operation with UV) • Improve effluent quality and near shore lake water quality 22