Water Rate Presentation
Water and Sewer Committee
Toledo Regional Chamber of Commerce
April 19, 2013
Deputy Mayor Steve Herwat
Commissioner of Water Treatment
David Leffler
Treatment Plant Additions
(Total $96,600,000)
Basin 7 – includes a 20 MGD Treatment Train including, Flocculation,
Sedimentation and Filtration Facilities - $53,400,000
Basin 8 – includes a 20 MGD Treatment Train including, Flocculation,
Sedimentation and Filtration Facilities - $43,200,000
Raw Water Intake Impr.
$1,775,000
Structural, Interior
and Exterior Improvements
Low Service PS Improvements
$20,633,000
Electrical Upgrades, Pump Rehab,
Piping Gallery Improvements
Equipment Replacements, Security
Chemical Feed System Impr.
$10,384,000
Carbon, Alum, Lime and Soda Ash
Flocculation/Sedimentation Basin Impr.
$14,321,000
Equipment Replacements and Structural
Improvements
Filter System Improvements
$37,695,000
Piping and Valve Replacements and
Rehabilitation, Pumping System Impr.,
Filter Wash Water Facility Impr., etc.
High Service PS Improvements
$12,172,000
Electrical Upgrades, Pump Rehab, Piping Gallery
Improvements, Equipment Replacements
Heatherdowns PS Impr.
$5,530,000
Electrical Upgrades, Pump
And Equipment Rehab,
Structural Improvements
Residuals Handling
$20,542,000
Press and Thickener Rehabilitation, Additional
Thickener Tank, Additional Press and Bldg Expansion
Additional Facility Improvements
1. SCADA System Replacement $5,000,000
2. Power Supply Improvements $ 7,000,000
3. HVAC Improvements $1,869,000
4. Filter Plant Roof Replacements $15,000,000
5. Structural Repairs to Plant $2,638, 000
6. Administration Bldg Offices and Property
Acquisition $4,804,000
Toledo Division of Water Treatment - Improvement Costs
Total Cost - $263,963,000
Expenditures from 2013 through 2018 total $235,072,958
New Disinfection Facilities
$8,000,000
Chlorine and Chlorine Dioxide Generation and
Feed Equip., Masonry Building
Commissioner of Engineering Services
Robin Whitney
•Introductions
•Overview
Toledo Water Distribution Study
Toledo Water Service Area
2012 Water Distribution Study
• Completed by Outside Engineering Firm
• Computer Model of All Pipes
• Serves Demands Through 2035
• Provides Redundancy
City of Toledo Water Distribution System
1,190 miles of pipe
• 4” to 96” Pipes
• Dating to 1870
• 58% of System is 6”
Cast Iron
---Small diameter pipe is
Ductile Iron since 1960s
---Large diameter pipe is
Steel and Concrete Cylinder
Water Distribution System Challenges
Aging – over 50% pre-1930
Water Distribution System Challenges
Main Breaks - More than 300 on average per year
Water Distribution System Challenges
4” Mains, 6 miles, 1874-1954
Water Distribution System Challenges
Dead End Mains – water quality, pressure, redundancy issues
Water Distribution System Challenges
Steel Mains – corrosion, lower useful life
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
Percent
Decade
Age and Break Distribution
Main Breaks
% of System
Main Replacement Criteria
• Break History
• Flow/Pressure Problems
• 4” Serving Hydrant
• Scheduled Road Construction
• Cost of Replacement/Cost of Repair
• Year of Construction – Baby Boomer Era
• Criticality
• Other (diameter, corrosion, material,
geographic zone, age)
Current Main Replacement Program
• $2.5 million per year
• Prioritized replacement criteria
• Approx. 3.1 miles per year (1100 total miles)
• 0.27% of the system
• 366 year average replacement cycle
• Also replacing large steel mains - $1.5 million
every other year
Current Loop Closure Program
• Separate program to loop dead end mains
• $200,000 per year
• Improves
– Water quality
– Fire flow capacity
– Redundancy
Goals of Proposed Program
• Replace at least 1% of system per year. (Based
on 100 years expected life)
• Replace all 4” mains serving hydrants within
10 years.
• Close all significant dead end mains within 10
years.
Current
Main Replacement Program
• $2.5 million per year
• 0.27% of system per year
• 366 year average cycle
• Approx. 3.1 miles per year
Proposed
Main Replacement Program
• $10 million per year
• 1.1% of system per year
• 91 year average cycle
• Approx. 12.4 miles per year
Current
Loop Closure Program
$200,000 per year
Steel Main Replacement
$1.5 million every other year
Proposed
Loop Closure Program
$500,000 per year
Steel Main Replacement
$1.5 million every other year
Current
Dead End Mains
Minimal Program
4” Mains
Minimal Program
Proposed
Dead End Mains
Close all significant dead end mains within 10 years
4” Mains
Replace all 4” mains serving hydrants within 10 years
Department of Public Utilities Director
David Welch
Five-Year Water Rate Program
2014-2018
In 2018…
34.2 cents more daily for typical customers
8.6 cents more daily for Homestead customers
2012 Water Rate Comparison
2012 Rates
City 1,000 cu. ft.
per month
Akron, OH $25.15
Ann Arbor, MI $20.56
Canton, OH $17.94
Cincinnati, OH $25.63
Cleveland, OH $32.60
Columbus, OH $33.35
Detroit, MI $25.12
Fort Wayne, IN $22.20
Average of Above Cities $25.32
TOLEDO, OH $13.33
TOLEDO, OH (2018 rate as proposed) $24.93
US Median $29.85
Midwest Median $25.68
Water Rate Increase Supports
 Comprehensive plan to address needed improvements
in water treatment plant and distribution system
 $314 million total cost of all projects
 Rate increase leverages bond funding
Deputy Mayor Steve Herwat
Deputy Mayor Steve Herwat
Five-Year Water Rate Program
2014-2018
In 2018…
34.2 cents more daily for typical customers
8.6 cents more daily for Homestead customers

Mais conteúdo relacionado

Mais procurados

1: Introduction to Water and Energy Efficiency in Water Supply
1: Introduction to Water and Energy Efficiency in Water Supply1: Introduction to Water and Energy Efficiency in Water Supply
1: Introduction to Water and Energy Efficiency in Water SupplyAlliance To Save Energy
 
Providing safe, clean water for Santa Clara County
Providing safe, clean water for Santa Clara CountyProviding safe, clean water for Santa Clara County
Providing safe, clean water for Santa Clara CountyLaura Rinaldi
 
Anders, Water Rates
Anders, Water RatesAnders, Water Rates
Anders, Water RatesTWCA
 
Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...
Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...
Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...Raden Ajeng Koesoemo Roekmi
 
Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)GardinerEast
 
Lead Infrastructure Policy Brief - Siwula
Lead Infrastructure Policy Brief - SiwulaLead Infrastructure Policy Brief - Siwula
Lead Infrastructure Policy Brief - SiwulaPatrick Siwula
 
Robert Moylan masccc 2013
Robert Moylan masccc 2013Robert Moylan masccc 2013
Robert Moylan masccc 2013Jen Boudrie
 
Issues of water conservation in Bengallaru_Thippeswamy _2013
Issues of water conservation in Bengallaru_Thippeswamy _2013Issues of water conservation in Bengallaru_Thippeswamy _2013
Issues of water conservation in Bengallaru_Thippeswamy _2013India Water Portal
 
Waukesha Diversion Impacts on the Baseflow of the Fox River
Waukesha Diversion Impacts on the Baseflow of the Fox RiverWaukesha Diversion Impacts on the Baseflow of the Fox River
Waukesha Diversion Impacts on the Baseflow of the Fox RiverPatrick Siwula
 
Community Presentation Measure Q
Community Presentation Measure QCommunity Presentation Measure Q
Community Presentation Measure Qhermosahero
 
Laurel Hill Reclaimed Water
Laurel Hill Reclaimed WaterLaurel Hill Reclaimed Water
Laurel Hill Reclaimed WaterFairfax County
 

Mais procurados (13)

1: Introduction to Water and Energy Efficiency in Water Supply
1: Introduction to Water and Energy Efficiency in Water Supply1: Introduction to Water and Energy Efficiency in Water Supply
1: Introduction to Water and Energy Efficiency in Water Supply
 
Providing safe, clean water for Santa Clara County
Providing safe, clean water for Santa Clara CountyProviding safe, clean water for Santa Clara County
Providing safe, clean water for Santa Clara County
 
Anders, Water Rates
Anders, Water RatesAnders, Water Rates
Anders, Water Rates
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...
Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...
Developing Sustainable Urban Water Management Framework for Kabupaten Bekasi,...
 
Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)
 
Lead Infrastructure Policy Brief - Siwula
Lead Infrastructure Policy Brief - SiwulaLead Infrastructure Policy Brief - Siwula
Lead Infrastructure Policy Brief - Siwula
 
Robert Moylan masccc 2013
Robert Moylan masccc 2013Robert Moylan masccc 2013
Robert Moylan masccc 2013
 
Issues of water conservation in Bengallaru_Thippeswamy _2013
Issues of water conservation in Bengallaru_Thippeswamy _2013Issues of water conservation in Bengallaru_Thippeswamy _2013
Issues of water conservation in Bengallaru_Thippeswamy _2013
 
Waukesha Diversion Impacts on the Baseflow of the Fox River
Waukesha Diversion Impacts on the Baseflow of the Fox RiverWaukesha Diversion Impacts on the Baseflow of the Fox River
Waukesha Diversion Impacts on the Baseflow of the Fox River
 
City of Hugo - Stormwater Management Plan
City of Hugo - Stormwater Management PlanCity of Hugo - Stormwater Management Plan
City of Hugo - Stormwater Management Plan
 
Community Presentation Measure Q
Community Presentation Measure QCommunity Presentation Measure Q
Community Presentation Measure Q
 
Laurel Hill Reclaimed Water
Laurel Hill Reclaimed WaterLaurel Hill Reclaimed Water
Laurel Hill Reclaimed Water
 

Semelhante a City of Toledo Department of Public Utilities Water Rate Presentation to the Toledo Regional Chamber of Commerce

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Toronto Public Consultation Unit
 
The Pros & Cons of Water Meter Automation
The Pros & Cons of Water Meter AutomationThe Pros & Cons of Water Meter Automation
The Pros & Cons of Water Meter Automationsecoshare
 
DS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master PlanDS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master PlanCityofKilleen
 
Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019Franklin Matters
 
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...Texas Living Waters Project
 
DPW Waterworks Presentation July2009
DPW Waterworks Presentation July2009DPW Waterworks Presentation July2009
DPW Waterworks Presentation July2009Franklin Matters
 
BH BL BPA Town Hall Visioning Committee Update
BH BL BPA Town Hall Visioning Committee UpdateBH BL BPA Town Hall Visioning Committee Update
BH BL BPA Town Hall Visioning Committee UpdateRick Noel
 
Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...
Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...
Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...Texas Living Waters Project
 
2010-2016 Challenges and Solutions
2010-2016 Challenges and Solutions2010-2016 Challenges and Solutions
2010-2016 Challenges and SolutionsMichael Leamons
 
cost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.pptcost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.pptMohankumar612520
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05HartTWI
 
Taking Water Efficiency to the Limit
Taking Water Efficiency to the LimitTaking Water Efficiency to the Limit
Taking Water Efficiency to the LimitScott Bowman
 
Winter Springs 2023 Water and Wastewater Rate Study
Winter Springs 2023 Water and Wastewater Rate StudyWinter Springs 2023 Water and Wastewater Rate Study
Winter Springs 2023 Water and Wastewater Rate StudyVictoriaColangelo
 
2023 Winter Springs Water and Wastewater Rate Study Presentation
2023 Winter Springs Water and Wastewater Rate Study Presentation2023 Winter Springs Water and Wastewater Rate Study Presentation
2023 Winter Springs Water and Wastewater Rate Study PresentationVictoriaColangelo
 
Hazel Run: Upgrading Your Wastewater Treatment: You Have Choices
Hazel Run: Upgrading Your Wastewater Treatment: You Have ChoicesHazel Run: Upgrading Your Wastewater Treatment: You Have Choices
Hazel Run: Upgrading Your Wastewater Treatment: You Have Choicesdmalchow
 
Kohler save h20 america
Kohler save h20 americaKohler save h20 america
Kohler save h20 americaBearbradley
 
Partnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, COPartnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, COPark Pride
 

Semelhante a City of Toledo Department of Public Utilities Water Rate Presentation to the Toledo Regional Chamber of Commerce (20)

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
The Pros & Cons of Water Meter Automation
The Pros & Cons of Water Meter AutomationThe Pros & Cons of Water Meter Automation
The Pros & Cons of Water Meter Automation
 
DS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master PlanDS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master Plan
 
Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019
 
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
 
DPW Waterworks Presentation July2009
DPW Waterworks Presentation July2009DPW Waterworks Presentation July2009
DPW Waterworks Presentation July2009
 
BH BL BPA Town Hall Visioning Committee Update
BH BL BPA Town Hall Visioning Committee UpdateBH BL BPA Town Hall Visioning Committee Update
BH BL BPA Town Hall Visioning Committee Update
 
1.3 pbcwud update
1.3 pbcwud update1.3 pbcwud update
1.3 pbcwud update
 
Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...
Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...
Case Studies: SWIFT Funds for Municipal Conservation in City of Keller & City...
 
State of the City 2012
State of the City 2012State of the City 2012
State of the City 2012
 
2010-2016 Challenges and Solutions
2010-2016 Challenges and Solutions2010-2016 Challenges and Solutions
2010-2016 Challenges and Solutions
 
cost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.pptcost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.ppt
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
 
Taking Water Efficiency to the Limit
Taking Water Efficiency to the LimitTaking Water Efficiency to the Limit
Taking Water Efficiency to the Limit
 
Winter Springs 2023 Water and Wastewater Rate Study
Winter Springs 2023 Water and Wastewater Rate StudyWinter Springs 2023 Water and Wastewater Rate Study
Winter Springs 2023 Water and Wastewater Rate Study
 
2023 Winter Springs Water and Wastewater Rate Study Presentation
2023 Winter Springs Water and Wastewater Rate Study Presentation2023 Winter Springs Water and Wastewater Rate Study Presentation
2023 Winter Springs Water and Wastewater Rate Study Presentation
 
NZC - Bob Olsson
NZC - Bob OlssonNZC - Bob Olsson
NZC - Bob Olsson
 
Hazel Run: Upgrading Your Wastewater Treatment: You Have Choices
Hazel Run: Upgrading Your Wastewater Treatment: You Have ChoicesHazel Run: Upgrading Your Wastewater Treatment: You Have Choices
Hazel Run: Upgrading Your Wastewater Treatment: You Have Choices
 
Kohler save h20 america
Kohler save h20 americaKohler save h20 america
Kohler save h20 america
 
Partnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, COPartnerships for Greening Atlanta - SF, DQ, CO
Partnerships for Greening Atlanta - SF, DQ, CO
 

City of Toledo Department of Public Utilities Water Rate Presentation to the Toledo Regional Chamber of Commerce

  • 1. Water Rate Presentation Water and Sewer Committee Toledo Regional Chamber of Commerce April 19, 2013
  • 3. Commissioner of Water Treatment David Leffler
  • 4. Treatment Plant Additions (Total $96,600,000) Basin 7 – includes a 20 MGD Treatment Train including, Flocculation, Sedimentation and Filtration Facilities - $53,400,000 Basin 8 – includes a 20 MGD Treatment Train including, Flocculation, Sedimentation and Filtration Facilities - $43,200,000 Raw Water Intake Impr. $1,775,000 Structural, Interior and Exterior Improvements Low Service PS Improvements $20,633,000 Electrical Upgrades, Pump Rehab, Piping Gallery Improvements Equipment Replacements, Security Chemical Feed System Impr. $10,384,000 Carbon, Alum, Lime and Soda Ash Flocculation/Sedimentation Basin Impr. $14,321,000 Equipment Replacements and Structural Improvements Filter System Improvements $37,695,000 Piping and Valve Replacements and Rehabilitation, Pumping System Impr., Filter Wash Water Facility Impr., etc. High Service PS Improvements $12,172,000 Electrical Upgrades, Pump Rehab, Piping Gallery Improvements, Equipment Replacements Heatherdowns PS Impr. $5,530,000 Electrical Upgrades, Pump And Equipment Rehab, Structural Improvements Residuals Handling $20,542,000 Press and Thickener Rehabilitation, Additional Thickener Tank, Additional Press and Bldg Expansion Additional Facility Improvements 1. SCADA System Replacement $5,000,000 2. Power Supply Improvements $ 7,000,000 3. HVAC Improvements $1,869,000 4. Filter Plant Roof Replacements $15,000,000 5. Structural Repairs to Plant $2,638, 000 6. Administration Bldg Offices and Property Acquisition $4,804,000 Toledo Division of Water Treatment - Improvement Costs Total Cost - $263,963,000 Expenditures from 2013 through 2018 total $235,072,958 New Disinfection Facilities $8,000,000 Chlorine and Chlorine Dioxide Generation and Feed Equip., Masonry Building
  • 5. Commissioner of Engineering Services Robin Whitney
  • 7. 2012 Water Distribution Study • Completed by Outside Engineering Firm • Computer Model of All Pipes • Serves Demands Through 2035 • Provides Redundancy
  • 8. City of Toledo Water Distribution System 1,190 miles of pipe • 4” to 96” Pipes • Dating to 1870 • 58% of System is 6” Cast Iron ---Small diameter pipe is Ductile Iron since 1960s ---Large diameter pipe is Steel and Concrete Cylinder
  • 9. Water Distribution System Challenges Aging – over 50% pre-1930
  • 10. Water Distribution System Challenges Main Breaks - More than 300 on average per year
  • 11. Water Distribution System Challenges 4” Mains, 6 miles, 1874-1954
  • 12. Water Distribution System Challenges Dead End Mains – water quality, pressure, redundancy issues
  • 13. Water Distribution System Challenges Steel Mains – corrosion, lower useful life
  • 15. Main Replacement Criteria • Break History • Flow/Pressure Problems • 4” Serving Hydrant • Scheduled Road Construction • Cost of Replacement/Cost of Repair • Year of Construction – Baby Boomer Era • Criticality • Other (diameter, corrosion, material, geographic zone, age)
  • 16. Current Main Replacement Program • $2.5 million per year • Prioritized replacement criteria • Approx. 3.1 miles per year (1100 total miles) • 0.27% of the system • 366 year average replacement cycle • Also replacing large steel mains - $1.5 million every other year
  • 17. Current Loop Closure Program • Separate program to loop dead end mains • $200,000 per year • Improves – Water quality – Fire flow capacity – Redundancy
  • 18. Goals of Proposed Program • Replace at least 1% of system per year. (Based on 100 years expected life) • Replace all 4” mains serving hydrants within 10 years. • Close all significant dead end mains within 10 years.
  • 19. Current Main Replacement Program • $2.5 million per year • 0.27% of system per year • 366 year average cycle • Approx. 3.1 miles per year Proposed Main Replacement Program • $10 million per year • 1.1% of system per year • 91 year average cycle • Approx. 12.4 miles per year
  • 20. Current Loop Closure Program $200,000 per year Steel Main Replacement $1.5 million every other year Proposed Loop Closure Program $500,000 per year Steel Main Replacement $1.5 million every other year
  • 21. Current Dead End Mains Minimal Program 4” Mains Minimal Program Proposed Dead End Mains Close all significant dead end mains within 10 years 4” Mains Replace all 4” mains serving hydrants within 10 years
  • 22. Department of Public Utilities Director David Welch
  • 23. Five-Year Water Rate Program 2014-2018 In 2018… 34.2 cents more daily for typical customers 8.6 cents more daily for Homestead customers
  • 24. 2012 Water Rate Comparison 2012 Rates City 1,000 cu. ft. per month Akron, OH $25.15 Ann Arbor, MI $20.56 Canton, OH $17.94 Cincinnati, OH $25.63 Cleveland, OH $32.60 Columbus, OH $33.35 Detroit, MI $25.12 Fort Wayne, IN $22.20 Average of Above Cities $25.32 TOLEDO, OH $13.33 TOLEDO, OH (2018 rate as proposed) $24.93 US Median $29.85 Midwest Median $25.68
  • 25. Water Rate Increase Supports  Comprehensive plan to address needed improvements in water treatment plant and distribution system  $314 million total cost of all projects  Rate increase leverages bond funding
  • 28.
  • 29.
  • 30. Five-Year Water Rate Program 2014-2018 In 2018… 34.2 cents more daily for typical customers 8.6 cents more daily for Homestead customers

Notas do Editor

  1. 24” Danny Thomas Park Waterline: 6” main off the 16” main on Dorr Street near Richards
  2. The average over 15 years is 328: the average over the most recent 5 years is 312.