7. 2012 Water Distribution Study
• Completed by Outside Engineering Firm
• Computer Model of All Pipes
• Serves Demands Through 2035
• Provides Redundancy
8. City of Toledo Water Distribution System
1,190 miles of pipe
• 4” to 96” Pipes
• Dating to 1870
• 58% of System is 6”
Cast Iron
---Small diameter pipe is
Ductile Iron since 1960s
---Large diameter pipe is
Steel and Concrete Cylinder
15. Main Replacement Criteria
• Break History
• Flow/Pressure Problems
• 4” Serving Hydrant
• Scheduled Road Construction
• Cost of Replacement/Cost of Repair
• Year of Construction – Baby Boomer Era
• Criticality
• Other (diameter, corrosion, material,
geographic zone, age)
16. Current Main Replacement Program
• $2.5 million per year
• Prioritized replacement criteria
• Approx. 3.1 miles per year (1100 total miles)
• 0.27% of the system
• 366 year average replacement cycle
• Also replacing large steel mains - $1.5 million
every other year
17. Current Loop Closure Program
• Separate program to loop dead end mains
• $200,000 per year
• Improves
– Water quality
– Fire flow capacity
– Redundancy
18. Goals of Proposed Program
• Replace at least 1% of system per year. (Based
on 100 years expected life)
• Replace all 4” mains serving hydrants within
10 years.
• Close all significant dead end mains within 10
years.
19. Current
Main Replacement Program
• $2.5 million per year
• 0.27% of system per year
• 366 year average cycle
• Approx. 3.1 miles per year
Proposed
Main Replacement Program
• $10 million per year
• 1.1% of system per year
• 91 year average cycle
• Approx. 12.4 miles per year
20. Current
Loop Closure Program
$200,000 per year
Steel Main Replacement
$1.5 million every other year
Proposed
Loop Closure Program
$500,000 per year
Steel Main Replacement
$1.5 million every other year
21. Current
Dead End Mains
Minimal Program
4” Mains
Minimal Program
Proposed
Dead End Mains
Close all significant dead end mains within 10 years
4” Mains
Replace all 4” mains serving hydrants within 10 years
23. Five-Year Water Rate Program
2014-2018
In 2018…
34.2 cents more daily for typical customers
8.6 cents more daily for Homestead customers
24. 2012 Water Rate Comparison
2012 Rates
City 1,000 cu. ft.
per month
Akron, OH $25.15
Ann Arbor, MI $20.56
Canton, OH $17.94
Cincinnati, OH $25.63
Cleveland, OH $32.60
Columbus, OH $33.35
Detroit, MI $25.12
Fort Wayne, IN $22.20
Average of Above Cities $25.32
TOLEDO, OH $13.33
TOLEDO, OH (2018 rate as proposed) $24.93
US Median $29.85
Midwest Median $25.68
25. Water Rate Increase Supports
Comprehensive plan to address needed improvements
in water treatment plant and distribution system
$314 million total cost of all projects
Rate increase leverages bond funding