Environment Impact Assessment (EIA)
Notification 2006
Information Sources:
1.) Environment Impact Notification 2006; Gazette of India, 14th September, 2006
2.) Green Tapism; Environment Support Group; 2007
3.) Image of tree from http://www.cherrytreebooks.net/Images/CTBooksTreeLogo.gif
 Central Government hereby directs that on and from the date of its
publication (14th September, 2006)
 the required construction of new projects
 the expansion or modernization of existing projects
shall be undertaken in any part of India only after the prior
environmental clearance from the Central Government
or
as the case may be, by the State Level Environment Impact Assessment
Authority.
EIA 2006
Categorization of projects and activities
 All projects and activities are broadly categorized in to
two categories - Category A and B (based on size or capacity)
 extent of impacts
 impacts on natural and man made resources
 impacts on human health
Requirements of prior Environmental
Clearance (EC)
 Which projects require EC?
 All new projects or activities listed in the Schedule to this
notification
 Expansion and modernization of existing projects or activities
listed in the Schedule to this notification
 Any change in product - mix in an existing manufacturing unit
included in Schedule
 EC by whom?
 Category A projects: Central Government in the Ministry of Environment
and Forests
 Base decisions on the recommendation by Expert Appraisal Committee (EAC)
 Category B projects: At state level the State Environment Impact
Assessment Authority (SEIAA)
 The SEIAA shall base its decision on the recommendations of a State or Union
territory level Expert Appraisal Committee (SEAC) as to be constituted for in
this notification
Requirements of prior Environmental
Clearance (EC)
Stages in EC process
 Stage 1: Screening
 Stage 2: Scoping
 Stage 3: Public Consultation
 Stage 4: Appraisal
Stage 3: Public consultation
 Process by which the concerns of local affected persons
and others who have plausible stake in the environmental
impacts of the project or activity are ascertained
 Public Consultation shall ordinarily have two components
 public hearing at the site or in its close proximity- district wise, to
be carried out for ascertaining concerns of local affected persons
 obtain responses in writing from other concerned persons having
a plausible stake in the environmental aspects of the project
Stage 3: Public consultation
 Public hearing shall be conducted by the State Pollution Control Board
(SPCB)
 forward proceedings to the regulatory authority concerned within 45 days
 If not appoint another independent organization to do the same within
another 45 days
 If the public agency nominated reports that it is not possible to
conduct the public hearing in a manner which will enable the views of
the concerned local persons to be freely expressed
 It shall report the facts in detail to the concerned regulatory authority
 After due consideration of the report shall rule that the public
consultation in the case need not include the public hearing
Component 1: Public hearing
Component 2: Responses from other
concerned persons
 Invite responses from such concerned persons by placing on their website
the Summary EIA report
 Use other appropriate media for ensuring wide publicity about the project
 Within seven days of the receipt of a written request for arranging the public
hearing
 Confidential information including non-disclosable or legally privileged
information involving Intellectual Property Right shall not be placed on the
website
 Make available on written request from any concerned person the Draft EIA
report for inspection at a notified place during normal office hours till the
date of the public hearing
 All the responses received as part of this public consultation process shall be
forwarded to the applicant through the quickest available means
After public consultation…
 Applicant shall address all environmental concerns
expressed during this process
 Make appropriate changes in the draft EIA
 Final EIA report shall be submitted by the applicant to the
concerned regulatory authority for appraisal
Stage 4: Appraisal
 Detailed scrutiny by the EAC or SEAC of
 documents like the Final EIA report
 outcome of the public consultations including public hearing
proceedings
 submitted by the applicant to the regulatory authority concerned
for grant of environmental clearance
 EAC or SEAC shall
 recommend to the regulatory authority concerned
 either for grant of prior environmental clearance on stipulated terms and
conditions
 or rejection of the application for prior environmental clearance, together with
reasons for the same.
Stage 4: Appraisal
Grant or Rejection of EC
 The regulatory authority shall consider the recommendations of the
EAC or SEAC concerned and convey its decision to the applicant
 The regulatory authority shall normally accept the recommendations
of the Expert Committees
 In cases where it disagrees with the recommendations of the Expert
Committee (Central or State), the regulatory authority shall request
reconsideration by the Central or State Expert Appraisal Committee
 After reconsideration, irrespective of views of Expert Committee,
decision of the regulatory authority concerned shall be final
 If decision not granted within stipulated time, the applicant may
proceed as if the environment clearance sought for has been granted
or denied by the regulatory authority in terms of the final
recommendations of the Expert Committee concerned
 Deliberate concealment and/or submission of false or misleading
information or data which is material to screening or scoping or
appraisal or decision on the application shall make the application
liable for rejection
 Rejection of an application or cancellation of a prior environmental
clearance already granted shall be decided by the regulatory
authority, after giving a personal hearing to the applicant, and
following the principles of natural justice
Grant or Rejection of EC
Validity of Environmental Clearance
 Ten years in the case of River Valley projects
 Thirty years for mining projects
 Five years in the case of all other projects and activities
Post Environmental Clearance
Monitoring
 Mandatory for the project management to submit half-
yearly compliance reports in respect of the stipulated
prior environmental clearance terms
Summary of EIA process
and Rough Timelines
Submission of application (Form 1, prelim reports)
Stage 1: Screening; Decide project A, B1 or B2
Stage 2: Scoping; Come up with Terms of Reference (TOR)
Prepare preliminary EIA report
Stage 3: Public consultation (2 components)
Stage 4: Appraisal
Final Decision
60 days
45 days
60 days
15 days
30 days
Investor
Expert
Committee
Investor
State Pollution
Control Board
Expert
Committee
Regulatory
Authority
Who does it?
Update EIA report (Investor)
Loopholes and deficiencies
 Stage 1 - Screening
 Based on info supplied by investor
 Pre-feasibility report and conceptual plan - no guidelines or
requirements, thereby no need to address environmental issues
 Stage 2 - Scoping
 No public participation in scoping process - local knowledge about
what environmental concerns should be investigated is not given
consideration
 Biased in securing favorable Terms of Reference (TOR) for
investors
 Access to TOR limited
 Stage 3 – Public consultation
 Unclear wording and definitions
 Can be avoided if regulatory agency feels it difficult to conduct it
owing to local situation
 Other concerned persons having plausible stake shall submit
responses only in writing
 Hearing shall be conducted at the site or in its close proximity
 No quorum required for holding public consultation
 Huge list of exemptions for certain types of projects that cause deep
environmental impact without justification
 Weak wording that widens the scope of these exemptions
 Tight timeline: 45 days from the time requested by the investor
Loopholes and deficiencies
 Limiting access to information
 Only summary EIA report made available, not the full EIA with all
TOR from the scoping process
 Confidential information need not be disclosed in summary EIA
 Publicity
 Use of internet as the main means
 No definition on how publicity should be carried out
Loopholes and deficiencies
 Appraisal
 No public participation
 Arguments between regulatory authority and expert committee
made known only to investor and not to public
 Iron hand given to regulatory authority to make final decision –
Expert committee opinion can be disregarded
 Deemed Clearance: Incase decision is not given within the
prescribed timelines, applicant may proceed as though clearance
has been granted or denied
Loopholes and deficiencies

Mais conteúdo relacionado

Mais procurados

Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrithvi Ghag
 
Environmental Audit and Environmental Impact Assessment
Environmental Audit and Environmental Impact AssessmentEnvironmental Audit and Environmental Impact Assessment
Environmental Audit and Environmental Impact AssessmentEffah Effervescence
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentSonikaPawar
 
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)Lucasrukona
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentSamanth kumar
 
Impact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaImpact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaMizanur R. Shohel
 
Environmental impact assessment methodology
Environmental impact assessment methodologyEnvironmental impact assessment methodology
Environmental impact assessment methodologyJustin Joy
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentSayyid Ina
 
Environmental Impact Assessment, Initial Environmental Examination
Environmental Impact Assessment, Initial Environmental ExaminationEnvironmental Impact Assessment, Initial Environmental Examination
Environmental Impact Assessment, Initial Environmental ExaminationNabin Lamichhane
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1hirencd
 
Hazardous waste ( management & handling ) rules, 1989
Hazardous waste ( management & handling  ) rules, 1989Hazardous waste ( management & handling  ) rules, 1989
Hazardous waste ( management & handling ) rules, 1989Arvind Kumar
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)eAmbiente
 

Mais procurados (20)

Environmental clearance
Environmental clearanceEnvironmental clearance
Environmental clearance
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental Audit and Environmental Impact Assessment
Environmental Audit and Environmental Impact AssessmentEnvironmental Audit and Environmental Impact Assessment
Environmental Audit and Environmental Impact Assessment
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
EIA Methods
EIA MethodsEIA Methods
EIA Methods
 
Impact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaImpact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eia
 
Eia 2006 vs. eia 2020
Eia 2006 vs. eia 2020Eia 2006 vs. eia 2020
Eia 2006 vs. eia 2020
 
Eia screening
Eia screeningEia screening
Eia screening
 
Environmental Audit
Environmental AuditEnvironmental Audit
Environmental Audit
 
Environmental impact assessment methodology
Environmental impact assessment methodologyEnvironmental impact assessment methodology
Environmental impact assessment methodology
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Environmental Impact Assessment, Initial Environmental Examination
Environmental Impact Assessment, Initial Environmental ExaminationEnvironmental Impact Assessment, Initial Environmental Examination
Environmental Impact Assessment, Initial Environmental Examination
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
 
Hazardous waste ( management & handling ) rules, 1989
Hazardous waste ( management & handling  ) rules, 1989Hazardous waste ( management & handling  ) rules, 1989
Hazardous waste ( management & handling ) rules, 1989
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Strategic Environmental Assessment Methodology
Strategic Environmental Assessment MethodologyStrategic Environmental Assessment Methodology
Strategic Environmental Assessment Methodology
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
 

Destaque

Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentVinod Burdak
 
Ministry of Environment & Forests Notification 2006
Ministry of Environment & Forests Notification 2006Ministry of Environment & Forests Notification 2006
Ministry of Environment & Forests Notification 2006kopila
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentBimal Antony
 
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Probir Bidhan
 
Part 3 lecture- environmnetal regulation in energy sector
Part 3 lecture- environmnetal regulation in energy sectorPart 3 lecture- environmnetal regulation in energy sector
Part 3 lecture- environmnetal regulation in energy sectorProf. (Dr.) Tabrez Ahmad
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxMd. Mahmudor Rahman
 
Allegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-DasAllegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-DasKamalendu Das
 
MOEF Notification on Online Data Reporting
MOEF Notification on Online Data Reporting MOEF Notification on Online Data Reporting
MOEF Notification on Online Data Reporting Aman Deep Dubey
 
Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...
Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...
Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...Ecotist
 
Eia basic concepts_15_dec05
Eia basic concepts_15_dec05Eia basic concepts_15_dec05
Eia basic concepts_15_dec05Shimalsh
 
Environmental impact assessment of padma multipurpose bridge
Environmental impact assessment of padma multipurpose bridgeEnvironmental impact assessment of padma multipurpose bridge
Environmental impact assessment of padma multipurpose bridgeZuhair Ahmed Kowshik
 
Rampal power plant
Rampal power plantRampal power plant
Rampal power plantUzzal Mridha
 
Environmental Impact Assessment( EIA)
Environmental Impact Assessment( EIA)Environmental Impact Assessment( EIA)
Environmental Impact Assessment( EIA)Priyanka Singh
 
Environmental clearance procedure in India: Principal of Governance
Environmental clearance procedure in India: Principal of GovernanceEnvironmental clearance procedure in India: Principal of Governance
Environmental clearance procedure in India: Principal of GovernanceAjay Bidyarthy
 

Destaque (20)

Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Ministry of Environment & Forests Notification 2006
Ministry of Environment & Forests Notification 2006Ministry of Environment & Forests Notification 2006
Ministry of Environment & Forests Notification 2006
 
Eia
EiaEia
Eia
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
 
Part 3 lecture- environmnetal regulation in energy sector
Part 3 lecture- environmnetal regulation in energy sectorPart 3 lecture- environmnetal regulation in energy sector
Part 3 lecture- environmnetal regulation in energy sector
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptx
 
Allegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-DasAllegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-Das
 
PMBP SALIENTS
PMBP SALIENTSPMBP SALIENTS
PMBP SALIENTS
 
MOEF Notification on Online Data Reporting
MOEF Notification on Online Data Reporting MOEF Notification on Online Data Reporting
MOEF Notification on Online Data Reporting
 
Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...
Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...
Presentation on Monitoring, Mechanism for implementation of the EIA Notificat...
 
padma
padmapadma
padma
 
Eia basic concepts_15_dec05
Eia basic concepts_15_dec05Eia basic concepts_15_dec05
Eia basic concepts_15_dec05
 
Environmental impact assessment of padma multipurpose bridge
Environmental impact assessment of padma multipurpose bridgeEnvironmental impact assessment of padma multipurpose bridge
Environmental impact assessment of padma multipurpose bridge
 
Rampal power plant
Rampal power plantRampal power plant
Rampal power plant
 
What is eia
What is eiaWhat is eia
What is eia
 
Rampal Power Station
Rampal Power StationRampal Power Station
Rampal Power Station
 
Environmental Impact Assessment( EIA)
Environmental Impact Assessment( EIA)Environmental Impact Assessment( EIA)
Environmental Impact Assessment( EIA)
 
Environmental clearance procedure in India: Principal of Governance
Environmental clearance procedure in India: Principal of GovernanceEnvironmental clearance procedure in India: Principal of Governance
Environmental clearance procedure in India: Principal of Governance
 

Semelhante a Eia act 2006

MOE EBR training slides Dec 2010
MOE EBR training slides Dec 2010MOE EBR training slides Dec 2010
MOE EBR training slides Dec 2010ecocommish
 
The Planning Series 10 - Environmental Impact Assessment
The Planning Series 10 - Environmental Impact AssessmentThe Planning Series 10 - Environmental Impact Assessment
The Planning Series 10 - Environmental Impact AssessmentDr Georgette Kluiters
 
Eia procedural-guideline
Eia procedural-guidelineEia procedural-guideline
Eia procedural-guidelineHussaini Omale
 
EIA SCREENING presentation
EIA SCREENING  presentationEIA SCREENING  presentation
EIA SCREENING presentationSyeda Fatima
 
Environmental Impact Assessment and Meaningful Citizen Participation
Environmental Impact Assessment and Meaningful Citizen ParticipationEnvironmental Impact Assessment and Meaningful Citizen Participation
Environmental Impact Assessment and Meaningful Citizen ParticipationPublic Affairs Centre
 
EIA_Chapter 1.pptx
EIA_Chapter 1.pptxEIA_Chapter 1.pptx
EIA_Chapter 1.pptxtesfaye88
 
170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptxAnandkumarJoshi2
 
All you need to know about Environmental Clearance.pdf
All you need to know about Environmental Clearance.pdfAll you need to know about Environmental Clearance.pdf
All you need to know about Environmental Clearance.pdfJagriti Agarwal
 
Environmental Impact assessment
Environmental Impact assessmentEnvironmental Impact assessment
Environmental Impact assessmentDavis Ciprikis
 
January 17th- EIRs
January 17th- EIRsJanuary 17th- EIRs
January 17th- EIRsCEQAplanner
 
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfHajiraThabasum
 
USPTO Cleantech Customer Partnership Slides
USPTO Cleantech Customer Partnership SlidesUSPTO Cleantech Customer Partnership Slides
USPTO Cleantech Customer Partnership Slidesuspto
 
Cleantech customer partnership slides
Cleantech customer partnership slidesCleantech customer partnership slides
Cleantech customer partnership slidesPaul Fucito
 
EIA Report Preparation and its Challenges.pptx
 EIA Report Preparation and its Challenges.pptx EIA Report Preparation and its Challenges.pptx
EIA Report Preparation and its Challenges.pptxAmit Chaudhary
 

Semelhante a Eia act 2006 (20)

MOE EBR training slides Dec 2010
MOE EBR training slides Dec 2010MOE EBR training slides Dec 2010
MOE EBR training slides Dec 2010
 
The Planning Series 10 - Environmental Impact Assessment
The Planning Series 10 - Environmental Impact AssessmentThe Planning Series 10 - Environmental Impact Assessment
The Planning Series 10 - Environmental Impact Assessment
 
Eia procedural-guideline
Eia procedural-guidelineEia procedural-guideline
Eia procedural-guideline
 
EIA.pptx
EIA.pptxEIA.pptx
EIA.pptx
 
EIA
EIAEIA
EIA
 
EIA SCREENING presentation
EIA SCREENING  presentationEIA SCREENING  presentation
EIA SCREENING presentation
 
Environmental Impact Assessment and Meaningful Citizen Participation
Environmental Impact Assessment and Meaningful Citizen ParticipationEnvironmental Impact Assessment and Meaningful Citizen Participation
Environmental Impact Assessment and Meaningful Citizen Participation
 
Eia and its process
Eia and its processEia and its process
Eia and its process
 
EIA_Chapter 1.pptx
EIA_Chapter 1.pptxEIA_Chapter 1.pptx
EIA_Chapter 1.pptx
 
What Next After Accreditation?
What Next After Accreditation?What Next After Accreditation?
What Next After Accreditation?
 
170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx
 
All you need to know about Environmental Clearance.pdf
All you need to know about Environmental Clearance.pdfAll you need to know about Environmental Clearance.pdf
All you need to know about Environmental Clearance.pdf
 
Environmental Impact assessment
Environmental Impact assessmentEnvironmental Impact assessment
Environmental Impact assessment
 
January 17th- EIRs
January 17th- EIRsJanuary 17th- EIRs
January 17th- EIRs
 
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
 
USPTO Cleantech Customer Partnership Slides
USPTO Cleantech Customer Partnership SlidesUSPTO Cleantech Customer Partnership Slides
USPTO Cleantech Customer Partnership Slides
 
Cleantech customer partnership slides
Cleantech customer partnership slidesCleantech customer partnership slides
Cleantech customer partnership slides
 
EIA Report Preparation and its Challenges.pptx
 EIA Report Preparation and its Challenges.pptx EIA Report Preparation and its Challenges.pptx
EIA Report Preparation and its Challenges.pptx
 
BMC My Bill, Bill Analysis
BMC My Bill, Bill AnalysisBMC My Bill, Bill Analysis
BMC My Bill, Bill Analysis
 
External communication
External communicationExternal communication
External communication
 

Mais de Tej Kiran

Transactional Analysis and Communction
Transactional Analysis and CommunctionTransactional Analysis and Communction
Transactional Analysis and CommunctionTej Kiran
 
Organizational communication
Organizational communicationOrganizational communication
Organizational communicationTej Kiran
 
Leadership and group
Leadership and groupLeadership and group
Leadership and groupTej Kiran
 
Internal and external
Internal   and   externalInternal   and   external
Internal and externalTej Kiran
 
Barriers in communication
Barriers in communicationBarriers in communication
Barriers in communicationTej Kiran
 
communtication
 communtication communtication
communticationTej Kiran
 
Partnership accounts
Partnership accountsPartnership accounts
Partnership accountsTej Kiran
 
Basics of company accounts and issue of shares
Basics of company accounts and issue of sharesBasics of company accounts and issue of shares
Basics of company accounts and issue of sharesTej Kiran
 
Amalgamation and absorption
Amalgamation and absorptionAmalgamation and absorption
Amalgamation and absorptionTej Kiran
 
Cash flow statement
Cash flow statementCash flow statement
Cash flow statementTej Kiran
 
Water resources in india
Water resources in indiaWater resources in india
Water resources in indiaTej Kiran
 
Role of govt in environment
Role of govt in environmentRole of govt in environment
Role of govt in environmentTej Kiran
 
Population growth & its effect on environment
Population growth & its effect on environmentPopulation growth & its effect on environment
Population growth & its effect on environmentTej Kiran
 
Noise pollution
Noise pollutionNoise pollution
Noise pollutionTej Kiran
 
Natural resources
Natural resourcesNatural resources
Natural resourcesTej Kiran
 
Environmental activism
Environmental activismEnvironmental activism
Environmental activismTej Kiran
 

Mais de Tej Kiran (20)

Transactional Analysis and Communction
Transactional Analysis and CommunctionTransactional Analysis and Communction
Transactional Analysis and Communction
 
Organizational communication
Organizational communicationOrganizational communication
Organizational communication
 
Leadership
LeadershipLeadership
Leadership
 
Leadership and group
Leadership and groupLeadership and group
Leadership and group
 
Leadership
Leadership Leadership
Leadership
 
Internal and external
Internal   and   externalInternal   and   external
Internal and external
 
Barriers in communication
Barriers in communicationBarriers in communication
Barriers in communication
 
communtication
 communtication communtication
communtication
 
Partnership accounts
Partnership accountsPartnership accounts
Partnership accounts
 
Basics of company accounts and issue of shares
Basics of company accounts and issue of sharesBasics of company accounts and issue of shares
Basics of company accounts and issue of shares
 
Amalgamation and absorption
Amalgamation and absorptionAmalgamation and absorption
Amalgamation and absorption
 
Cash flow statement
Cash flow statementCash flow statement
Cash flow statement
 
Water resources in india
Water resources in indiaWater resources in india
Water resources in india
 
Solid waste
Solid wasteSolid waste
Solid waste
 
Role of govt in environment
Role of govt in environmentRole of govt in environment
Role of govt in environment
 
Population growth & its effect on environment
Population growth & its effect on environmentPopulation growth & its effect on environment
Population growth & its effect on environment
 
Noise pollution
Noise pollutionNoise pollution
Noise pollution
 
Natural resources
Natural resourcesNatural resources
Natural resources
 
Iso
IsoIso
Iso
 
Environmental activism
Environmental activismEnvironmental activism
Environmental activism
 

Último

Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Standkumarajju5765
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...SUHANI PANDEY
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...tanu pandey
 
Training Of Trainers FAI Eng. Basel Tilapia Welfare.pdf
Training Of Trainers FAI Eng. Basel Tilapia Welfare.pdfTraining Of Trainers FAI Eng. Basel Tilapia Welfare.pdf
Training Of Trainers FAI Eng. Basel Tilapia Welfare.pdfBasel Ahmed
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024itadmin50
 
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...Call Girls in Nagpur High Profile
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp NumberHot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Numberkumarajju5765
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abrahamssuserbb03ff
 
CSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENCSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENGeorgeDiamandis11
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Servicesdollysharma2066
 
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...PsychicRuben LoveSpells
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...SUHANI PANDEY
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Bookingtanu pandey
 

Último (20)

Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
9953056974 ,Low Rate Call Girls In Adarsh Nagar Delhi 24hrs Available
9953056974 ,Low Rate Call Girls In Adarsh Nagar  Delhi 24hrs Available9953056974 ,Low Rate Call Girls In Adarsh Nagar  Delhi 24hrs Available
9953056974 ,Low Rate Call Girls In Adarsh Nagar Delhi 24hrs Available
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
 
Training Of Trainers FAI Eng. Basel Tilapia Welfare.pdf
Training Of Trainers FAI Eng. Basel Tilapia Welfare.pdfTraining Of Trainers FAI Eng. Basel Tilapia Welfare.pdf
Training Of Trainers FAI Eng. Basel Tilapia Welfare.pdf
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024
 
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
 
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort serviceyoung Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp NumberHot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abraham
 
CSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENCSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -EN
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
 
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
$ Love Spells 💎 (310) 882-6330 in Pennsylvania, PA | Psychic Reading Best Bla...
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
 

Eia act 2006

  • 1. Environment Impact Assessment (EIA) Notification 2006 Information Sources: 1.) Environment Impact Notification 2006; Gazette of India, 14th September, 2006 2.) Green Tapism; Environment Support Group; 2007 3.) Image of tree from http://www.cherrytreebooks.net/Images/CTBooksTreeLogo.gif
  • 2.  Central Government hereby directs that on and from the date of its publication (14th September, 2006)  the required construction of new projects  the expansion or modernization of existing projects shall be undertaken in any part of India only after the prior environmental clearance from the Central Government or as the case may be, by the State Level Environment Impact Assessment Authority. EIA 2006
  • 3. Categorization of projects and activities  All projects and activities are broadly categorized in to two categories - Category A and B (based on size or capacity)  extent of impacts  impacts on natural and man made resources  impacts on human health
  • 4. Requirements of prior Environmental Clearance (EC)  Which projects require EC?  All new projects or activities listed in the Schedule to this notification  Expansion and modernization of existing projects or activities listed in the Schedule to this notification  Any change in product - mix in an existing manufacturing unit included in Schedule
  • 5.  EC by whom?  Category A projects: Central Government in the Ministry of Environment and Forests  Base decisions on the recommendation by Expert Appraisal Committee (EAC)  Category B projects: At state level the State Environment Impact Assessment Authority (SEIAA)  The SEIAA shall base its decision on the recommendations of a State or Union territory level Expert Appraisal Committee (SEAC) as to be constituted for in this notification Requirements of prior Environmental Clearance (EC)
  • 6. Stages in EC process  Stage 1: Screening  Stage 2: Scoping  Stage 3: Public Consultation  Stage 4: Appraisal
  • 7. Stage 3: Public consultation  Process by which the concerns of local affected persons and others who have plausible stake in the environmental impacts of the project or activity are ascertained
  • 8.  Public Consultation shall ordinarily have two components  public hearing at the site or in its close proximity- district wise, to be carried out for ascertaining concerns of local affected persons  obtain responses in writing from other concerned persons having a plausible stake in the environmental aspects of the project Stage 3: Public consultation
  • 9.  Public hearing shall be conducted by the State Pollution Control Board (SPCB)  forward proceedings to the regulatory authority concerned within 45 days  If not appoint another independent organization to do the same within another 45 days  If the public agency nominated reports that it is not possible to conduct the public hearing in a manner which will enable the views of the concerned local persons to be freely expressed  It shall report the facts in detail to the concerned regulatory authority  After due consideration of the report shall rule that the public consultation in the case need not include the public hearing Component 1: Public hearing
  • 10. Component 2: Responses from other concerned persons  Invite responses from such concerned persons by placing on their website the Summary EIA report  Use other appropriate media for ensuring wide publicity about the project  Within seven days of the receipt of a written request for arranging the public hearing  Confidential information including non-disclosable or legally privileged information involving Intellectual Property Right shall not be placed on the website  Make available on written request from any concerned person the Draft EIA report for inspection at a notified place during normal office hours till the date of the public hearing  All the responses received as part of this public consultation process shall be forwarded to the applicant through the quickest available means
  • 11. After public consultation…  Applicant shall address all environmental concerns expressed during this process  Make appropriate changes in the draft EIA  Final EIA report shall be submitted by the applicant to the concerned regulatory authority for appraisal
  • 12. Stage 4: Appraisal  Detailed scrutiny by the EAC or SEAC of  documents like the Final EIA report  outcome of the public consultations including public hearing proceedings  submitted by the applicant to the regulatory authority concerned for grant of environmental clearance
  • 13.  EAC or SEAC shall  recommend to the regulatory authority concerned  either for grant of prior environmental clearance on stipulated terms and conditions  or rejection of the application for prior environmental clearance, together with reasons for the same. Stage 4: Appraisal
  • 14. Grant or Rejection of EC  The regulatory authority shall consider the recommendations of the EAC or SEAC concerned and convey its decision to the applicant  The regulatory authority shall normally accept the recommendations of the Expert Committees  In cases where it disagrees with the recommendations of the Expert Committee (Central or State), the regulatory authority shall request reconsideration by the Central or State Expert Appraisal Committee  After reconsideration, irrespective of views of Expert Committee, decision of the regulatory authority concerned shall be final
  • 15.  If decision not granted within stipulated time, the applicant may proceed as if the environment clearance sought for has been granted or denied by the regulatory authority in terms of the final recommendations of the Expert Committee concerned  Deliberate concealment and/or submission of false or misleading information or data which is material to screening or scoping or appraisal or decision on the application shall make the application liable for rejection  Rejection of an application or cancellation of a prior environmental clearance already granted shall be decided by the regulatory authority, after giving a personal hearing to the applicant, and following the principles of natural justice Grant or Rejection of EC
  • 16. Validity of Environmental Clearance  Ten years in the case of River Valley projects  Thirty years for mining projects  Five years in the case of all other projects and activities
  • 17. Post Environmental Clearance Monitoring  Mandatory for the project management to submit half- yearly compliance reports in respect of the stipulated prior environmental clearance terms
  • 18. Summary of EIA process and Rough Timelines Submission of application (Form 1, prelim reports) Stage 1: Screening; Decide project A, B1 or B2 Stage 2: Scoping; Come up with Terms of Reference (TOR) Prepare preliminary EIA report Stage 3: Public consultation (2 components) Stage 4: Appraisal Final Decision 60 days 45 days 60 days 15 days 30 days Investor Expert Committee Investor State Pollution Control Board Expert Committee Regulatory Authority Who does it? Update EIA report (Investor)
  • 19. Loopholes and deficiencies  Stage 1 - Screening  Based on info supplied by investor  Pre-feasibility report and conceptual plan - no guidelines or requirements, thereby no need to address environmental issues  Stage 2 - Scoping  No public participation in scoping process - local knowledge about what environmental concerns should be investigated is not given consideration  Biased in securing favorable Terms of Reference (TOR) for investors  Access to TOR limited
  • 20.  Stage 3 – Public consultation  Unclear wording and definitions  Can be avoided if regulatory agency feels it difficult to conduct it owing to local situation  Other concerned persons having plausible stake shall submit responses only in writing  Hearing shall be conducted at the site or in its close proximity  No quorum required for holding public consultation  Huge list of exemptions for certain types of projects that cause deep environmental impact without justification  Weak wording that widens the scope of these exemptions  Tight timeline: 45 days from the time requested by the investor Loopholes and deficiencies
  • 21.  Limiting access to information  Only summary EIA report made available, not the full EIA with all TOR from the scoping process  Confidential information need not be disclosed in summary EIA  Publicity  Use of internet as the main means  No definition on how publicity should be carried out Loopholes and deficiencies
  • 22.  Appraisal  No public participation  Arguments between regulatory authority and expert committee made known only to investor and not to public  Iron hand given to regulatory authority to make final decision – Expert committee opinion can be disregarded  Deemed Clearance: Incase decision is not given within the prescribed timelines, applicant may proceed as though clearance has been granted or denied Loopholes and deficiencies