SlideShare uma empresa Scribd logo
1 de 4
Baixar para ler offline
Technical Bulletin



H            IGH DENSITY POLYETHYLENE PIPE
                  HDPE Pipe Installation Practice

LANE corrugated high density polyethylene               Classes IA, IB, and II are preferred over Class III
(HDPE) pipe, appropriate backfill material and          when available because they are stiffer materials,
proper installation practice all work together to       limit pipe deflection and permit greater fill heights.
result in a dependable drainage installation. HDPE      Also, construction may be faster because less
pipe, like all flexible pipes, depends on soil-pipe     compactive effort is generally required. Class III
interaction to develop its strength. Thus, proper       material should not be used where water
installation and backfilling are essential to           conditions in a trench can cause instability.
successful performance. This technical bulletin
addresses typical installations in trench and
embankment conditions. Unusual conditions may
                                                             BACKFILL MATERIAL SIZE
require additional investigations, including the            Pipe Diameter (ID)            Max. Particle Size
recommendations of a qualified geotechnical or              in.           mm               in.            mm
soils engineer. More detailed information on                6             150              3/8            10
installation and backfill may be found in ASTM
D2321, " Standard Practice for Underground                  8-15          200-375          5/8            15
Installation of Thermoplastic Pipe for Sewers and           18-48         450-1200         1 1/2          40
Other Gravity-Flow Applications."

Installation practices must always comply               Cement slurry and controlled low strength material
with local, state and federal codes and                 (CLSM) are excellent backfill material provided
                                                        they yield adequate compressive strength and the
safety regulations.
                                                        pipe is restrained to avoid flotation during
                                                        installation.
Material for Foundation,
Bedding and Backfill                                    Foundation and Bedding
The pipe must be surrounded by compacted
material to distribute vertical loads uniformly to      A good foundation and bedding are critical to pipe
the pipe and to provide passive resistance to pipe      performance and service life. They are essential to
deflection. Material selection depends on               help maintain proper pipe elevation, eliminate
availability and cost. Granular materials with little   undesirable stresses in the pipe and ensure good
or no plasticity are preferred. Frozen lumps,           hydraulic performance.
chunks of clay, organic matter and large rock are
unacceptable. Acceptable materials are                  The foundation material beneath the pipe must
summarized in Table 1 by their ASTM Class and           provide a uniform resistance to the loads on the
Soil Group designation.                                 pipe.




                               www.lane-enterprises.com
Sharp longitudinal and lateral variations      However, if special equipment is available
in the foundation must be avoided. If          to provide a quality installation with a
rock is encountered, excavate and replace      narrow trench, the minimum width can be
with gravel or lightly compacted material.     reduced. If material such as CLSM is
Such cushion should have a depth of            used that requires no compaction, the
approximately ½ in. per ft. (42 mm/m) of       trench width can be as little as the pipe
the planned fill depth over the pipe           outside diameter, plus 6 in. (150 mm).
(6 in.-150 mm minimum, 24 in.-600 mm
maximum). If soft foundation material is       The trench must be filled with material,
encountered that must be removed to            placed and compacted in layers to form a
maintain grade, remove the material for a      "structural backfill" surrounding the pipe.
depth of about 2 ft. (0.6 m) and replace       The backfill must be compacted to a
with suitable compacted material. The          minimum of 90 percent of maximum
width of this material should be 2.5 diam-     density as determined by ASTM D698 or
eters on either side of the pipe for pipe 12   AASHTO T99. The envelope should
in. (300 mm) diameter or less. For larger      extend to 12 in. (300 mm) above the top
pipe, the width should be established by       of the pipe before the remainder of the fill
the engineer.                                  is placed in the trench. The trench wall is
                                               assumed to have a stiffness at least that of
The upper 4 in. (100 mm) of the bedding        the compacted backfill. If soft trench
should be relatively loose material so the     walls are encountered, additional
corrugations can be seated. Frozen             excavation may be required.
lumps, chunks of clay, organic matter and
large rock are unacceptable. The pipe
may be installed by shaping the bedding
surface to conform to the pipe
for a width of about one-half
the diameter. A second method
is to place the pipe directly on
the bedding, in which case
particular care must be taken
to compact the backfill under
the haunches of the pipe to
provide uniform support.

Trench
Construction
The trench should be wide
enough for placement and
compaction of backfill, especially the         Excavate trenches to ensure the trench
material placed beside the pipe and that in    walls are stable under all conditions.
the haunch area below the spring line.         Slope the walls or provide support in
Generally, the minimum trench width            conformance with safety standards. All
should not be less than the greater of (1)     appropriate safety practices and
the pipe outside diameter plus 16 in. (400     regulations must be followed to avoid
mm), or (2) the pipe outside diameter          trench collapse. If high ground water is
times 1.25, plus 12 in. (300 mm).              encountered, dewatering may be required
                                               to achieve a safe installation that meets
                                               requirements.
Embankment Construction                                         Backfill Placement
In embankment construction, the compacted                       In either trench or embankment construction, the
envelope of "structural backfill" must surround the             backfill material must be placed in layers and
pipe with a width adequate to resist forces caused              compacted to a minimum of 90 percent of
by construction equipment. The width of this zone               maximum density as determined by ASTM D698
on each side of the pipe should be one diameter,                or ASSHTO T99. The maximum thickness of the
with a minimum of 12 in. (300 mm) and a                         layers or lifts should not exceed 6 in. (150 mm).
maximum of 24 in. (600 mm). The envelope                        The lift thickness, placement technique and
should extend to 12 in. (300 mm) above the top of               compaction method must be such that compaction
the pipe before normal embankment material is                   under the haunches is obtained.
placed.
                                                                                              continued on next page >
                                 TABLE 1
                       Recommended Backfill Materials
 ASTM                                             ASTM                                                         Similar
 D2321                     Type                  D2487                    Description                         AASHTO
 Class                                          Soil Group                                                      Type
                                                             Angular, crushed stone or rock, crushed
   IA        Manufactured Aggregates;                        gravel, broken coral, crushed slag, cinders
             open-graded, clean.                             or shells; large void content, contain little
                                                             or no fines.
             Manufactured Processed                          Angular, crushed stone (or other Class 1A
   IB                                                        materials) and stone/sand mixtures with
             Aggregates; dense-graded,
             clean.                                          gradations selected to minimize migration
                                                             of adjacent soils; contain little or no fines.
                                                  GW         Well-graded gravels and gravel/sand                A1,
   II        Coarse-Grained Soils; clean.
                                                             mixtures, little or no fines.                      A3
                                                   GP        Poorly graded gravels and gravel/sand
                                                             mixtures, little or no fines.
                                                  SW         Well-graded sands and gravelly sands,
                                                             little or no fines.
                                                   SP        Poorly-graded sands and gravelly sands,
                                                             little or no fines.
             Coarse-Grained Soils; borderline     e.g.       Sands which are borderline between
             clean to with fines.                 GW         clean and with fines.
                                                  GC
                                                  SP
                                                  SM
   III       Coarse-Grained Soils with Fines.     GM         Silty gravels, gravel-sand-silt mixtures.          A2


                                                  GC         Clayey gravels, gravel-sand-clay mixtures.
                                                  SM         Silty sands, sand-clay mixtures
                                                  SC         Clayey sands, sand/clay mixtures.

         Note: Compact backfill material to minimum of 90% of maximum density per ASTM D698 or AASHTO T99.
         Table adapted from ASTM D2321.
Each layer must be compacted before the next lift is placed. Backfill
must proceed evenly on each side of the pipe. Care must be taken to
avoid pipe distortion or excessive local or general deflection. Such
unacceptable deformations can result from either excessive or inadequate
compaction or from construction equipment. Do not allow compaction
or other equipment to contact and damage the pipe. Compaction
techniques must be compatible with the backfill materials used, and the
width of the area being compacted.

Mechanical compaction is generally used. However, water consolidation
methods can be used on free-draining backfill material if care is taken to
prevent flotation. Conditions must be controlled and approved by the
engineer.

Construction Loads
It is important to protect the pipe from equipment loads during
construction. Heavy equipment must not be allowed close to or over
buried pipe unless provisions are made to accommodate the resultant
loads. Depending on the size of the equipment and class of fill material,
a minimum cover from 2 ft. (0.6 m) to 4 ft. (1.2 m), or more for
exceptional loads, may be required. (see table 2) For shallow
installations, it may be necessary to mound and compact material over
the pipe to provide the minimum cover. The mound can be removed and
final grade established after construction.
                                             TABLE 2
                   COVER FOR CONSTRUCTION LOADS
                                  Minimum Cover, in., for indicated Axle Loads, kips
  Nominal Pipe                                                                                                                    Drain with Lane
  Diameter, ft              18.0-50.0             50.0-75.0            75.0-110.0               110.0-150.0
                                                                                                                                    Lane Enterprises, Inc.
  2.0-3.0                      24.0                  30.0                  36.0                      36.0                      3905 Hartzdale Drive, Suite 514
                                                                                                                                   Camp Hill, PA 17011
  3.5-4.0                      36.0                  36.0                  42.0                      48.0                     717-761-8175 Fax 717-761-5055
  4.5-5.0                      36.0                  36.0                  42.0                      48.0
                                                                                                                                          New York
 Minimum cover shall be measured from the top of the pipe to the
                                                                                                                                Ballston Spa 518-885-4385
 top of the maintained construction roadway surface. If unpaved,                                                                    Bath 607-776-3366
 the surface shall be maintained.
                                                                                                                                       North Carolina
Multiple Pipes                                                                                                                   Statesville 704-872-2471

When two or more pipes are installed in adjacent parallel lines, sufficient                                                             Pennsylvania
space must be provided between the pipes to provide for adequate                                                                  Bedford 814-623-1191
compaction of the structural backfill. One rule-of-thumb is to use a                                                              Carlisle 717-249-8342
spacing between pipes equal to 12 in. (300 mm), or one-half the nominal                                                        King of Prussia 610-272-4531
pipe diameter, whichever is greater. This can be increased if necessary to                                                        Pulaski 412-652-7747
accommodate compaction.
                                                                                                                                          Virginia
                                                                                                                                  Bealeton 540-439-3201
 The information contained in this technical bulletin is general in nature and is intended for use in conjunction with
 competent engineering advice as to its suitability for any specific application. Nothing in this bulletin is intended as a        Dublin 540-674-4645
 representative or warranty that such data is suitable for any particular application or purpose.
                                                                                                                                www.lane-enterprises.com

Mais conteúdo relacionado

Mais procurados

Building materials
Building materialsBuilding materials
Building materialsAlay Desai
 
Half brick walling calculations
Half brick walling calculationsHalf brick walling calculations
Half brick walling calculationsdoogstone
 
Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]Prakash Kumar Sekar
 
Lpg reticulated gas system (cylinder bank) digital energy
Lpg reticulated gas system (cylinder bank) digital energyLpg reticulated gas system (cylinder bank) digital energy
Lpg reticulated gas system (cylinder bank) digital energyAbu Bakar Siddiqui
 
Mechanical systems of building (1)
Mechanical systems of building (1)Mechanical systems of building (1)
Mechanical systems of building (1)Muhammad Muhyuddin
 
Equipment selection (RAC)
Equipment selection (RAC)Equipment selection (RAC)
Equipment selection (RAC)Konal Singh
 
MAINTENANCE AND REPAIR STRATEGIES
MAINTENANCE AND REPAIR STRATEGIESMAINTENANCE AND REPAIR STRATEGIES
MAINTENANCE AND REPAIR STRATEGIESSelva Prakash
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsAnkit Patel
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specificationsSimran Vats
 
Underground construction
Underground constructionUnderground construction
Underground constructionPavan Kumar N
 
Civil Infrastructure Management Powerpoint Presentation Slides
Civil Infrastructure Management Powerpoint Presentation SlidesCivil Infrastructure Management Powerpoint Presentation Slides
Civil Infrastructure Management Powerpoint Presentation SlidesSlideTeam
 
Raft Foundation b.arch 8th sem
Raft Foundation b.arch 8th semRaft Foundation b.arch 8th sem
Raft Foundation b.arch 8th semujjwal jharsi
 

Mais procurados (20)

Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Building materials
Building materialsBuilding materials
Building materials
 
Half brick walling calculations
Half brick walling calculationsHalf brick walling calculations
Half brick walling calculations
 
Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]
 
Soil testing service for construction
Soil testing service for constructionSoil testing service for construction
Soil testing service for construction
 
Lpg reticulated gas system (cylinder bank) digital energy
Lpg reticulated gas system (cylinder bank) digital energyLpg reticulated gas system (cylinder bank) digital energy
Lpg reticulated gas system (cylinder bank) digital energy
 
Mechanical systems of building (1)
Mechanical systems of building (1)Mechanical systems of building (1)
Mechanical systems of building (1)
 
Equipment selection (RAC)
Equipment selection (RAC)Equipment selection (RAC)
Equipment selection (RAC)
 
Masonry
MasonryMasonry
Masonry
 
Defects in buildings
Defects in buildings Defects in buildings
Defects in buildings
 
MAINTENANCE AND REPAIR STRATEGIES
MAINTENANCE AND REPAIR STRATEGIESMAINTENANCE AND REPAIR STRATEGIES
MAINTENANCE AND REPAIR STRATEGIES
 
Types of floor finishes
Types of floor finishesTypes of floor finishes
Types of floor finishes
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairs
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Water leakage problem
Water leakage problem Water leakage problem
Water leakage problem
 
Testing of stones
Testing of stonesTesting of stones
Testing of stones
 
Underground construction
Underground constructionUnderground construction
Underground construction
 
Masonry work
Masonry workMasonry work
Masonry work
 
Civil Infrastructure Management Powerpoint Presentation Slides
Civil Infrastructure Management Powerpoint Presentation SlidesCivil Infrastructure Management Powerpoint Presentation Slides
Civil Infrastructure Management Powerpoint Presentation Slides
 
Raft Foundation b.arch 8th sem
Raft Foundation b.arch 8th semRaft Foundation b.arch 8th sem
Raft Foundation b.arch 8th sem
 

Semelhante a Hdpe installation practice

Aggrigatemortor 170209141826
Aggrigatemortor 170209141826Aggrigatemortor 170209141826
Aggrigatemortor 170209141826ram saran
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.AJINKYA THAKRE
 
Construction of flexible pavement in brief
Construction of flexible pavement in briefConstruction of flexible pavement in brief
Construction of flexible pavement in briefAJINKYA THAKRE
 
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...IRJET Journal
 
Dams and control works
Dams and control worksDams and control works
Dams and control worksjulian21323
 
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNITA presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNITRiteshmani Tripathi
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design informationcathexis123
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design informationcathexis123
 
Geotech and Pavement Design Information
Geotech and Pavement Design InformationGeotech and Pavement Design Information
Geotech and Pavement Design InformationJ C
 
Strength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste MaterialsStrength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste MaterialsIRJET Journal
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavementpokjak80
 
B-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptB-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptmosesnhidza
 
Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and PracticeSenthamizhan M
 
Research in Geotechnical Engineering
Research in Geotechnical EngineeringResearch in Geotechnical Engineering
Research in Geotechnical EngineeringAbhineet Godayal CE
 

Semelhante a Hdpe installation practice (20)

02_siteworks.ppt
02_siteworks.ppt02_siteworks.ppt
02_siteworks.ppt
 
Aggrigatemortor 170209141826
Aggrigatemortor 170209141826Aggrigatemortor 170209141826
Aggrigatemortor 170209141826
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
 
Construction of flexible pavement in brief
Construction of flexible pavement in briefConstruction of flexible pavement in brief
Construction of flexible pavement in brief
 
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
 
Dams and control works
Dams and control worksDams and control works
Dams and control works
 
3873
38733873
3873
 
7873
78737873
7873
 
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNITA presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
 
Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design information
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design information
 
Geotech and Pavement Design Information
Geotech and Pavement Design InformationGeotech and Pavement Design Information
Geotech and Pavement Design Information
 
Strength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste MaterialsStrength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste Materials
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavement
 
B-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptB-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.ppt
 
Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and Practice
 
pile wall
pile wallpile wall
pile wall
 
Research in Geotechnical Engineering
Research in Geotechnical EngineeringResearch in Geotechnical Engineering
Research in Geotechnical Engineering
 
Bubble Deck Slab PPT.pptx
Bubble Deck Slab PPT.pptxBubble Deck Slab PPT.pptx
Bubble Deck Slab PPT.pptx
 

Mais de TADSA1

CATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSACATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSATADSA1
 
FICHA TÉCNICA LANE
FICHA TÉCNICA LANEFICHA TÉCNICA LANE
FICHA TÉCNICA LANETADSA1
 
GUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓNGUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓNTADSA1
 
HDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍAHDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍATADSA1
 
Manual de instalacion
Manual de instalacionManual de instalacion
Manual de instalacionTADSA1
 
Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2TADSA1
 
Hdpe installation practice
Hdpe installation practiceHdpe installation practice
Hdpe installation practiceTADSA1
 
Hdpe perforation guide
Hdpe perforation guideHdpe perforation guide
Hdpe perforation guideTADSA1
 
Ficha tecnica lane
Ficha tecnica laneFicha tecnica lane
Ficha tecnica laneTADSA1
 

Mais de TADSA1 (9)

CATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSACATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSA
 
FICHA TÉCNICA LANE
FICHA TÉCNICA LANEFICHA TÉCNICA LANE
FICHA TÉCNICA LANE
 
GUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓNGUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓN
 
HDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍAHDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍA
 
Manual de instalacion
Manual de instalacionManual de instalacion
Manual de instalacion
 
Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2
 
Hdpe installation practice
Hdpe installation practiceHdpe installation practice
Hdpe installation practice
 
Hdpe perforation guide
Hdpe perforation guideHdpe perforation guide
Hdpe perforation guide
 
Ficha tecnica lane
Ficha tecnica laneFicha tecnica lane
Ficha tecnica lane
 

Último

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 

Último (20)

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 

Hdpe installation practice

  • 1. Technical Bulletin H IGH DENSITY POLYETHYLENE PIPE HDPE Pipe Installation Practice LANE corrugated high density polyethylene Classes IA, IB, and II are preferred over Class III (HDPE) pipe, appropriate backfill material and when available because they are stiffer materials, proper installation practice all work together to limit pipe deflection and permit greater fill heights. result in a dependable drainage installation. HDPE Also, construction may be faster because less pipe, like all flexible pipes, depends on soil-pipe compactive effort is generally required. Class III interaction to develop its strength. Thus, proper material should not be used where water installation and backfilling are essential to conditions in a trench can cause instability. successful performance. This technical bulletin addresses typical installations in trench and embankment conditions. Unusual conditions may BACKFILL MATERIAL SIZE require additional investigations, including the Pipe Diameter (ID) Max. Particle Size recommendations of a qualified geotechnical or in. mm in. mm soils engineer. More detailed information on 6 150 3/8 10 installation and backfill may be found in ASTM D2321, " Standard Practice for Underground 8-15 200-375 5/8 15 Installation of Thermoplastic Pipe for Sewers and 18-48 450-1200 1 1/2 40 Other Gravity-Flow Applications." Installation practices must always comply Cement slurry and controlled low strength material with local, state and federal codes and (CLSM) are excellent backfill material provided they yield adequate compressive strength and the safety regulations. pipe is restrained to avoid flotation during installation. Material for Foundation, Bedding and Backfill Foundation and Bedding The pipe must be surrounded by compacted material to distribute vertical loads uniformly to A good foundation and bedding are critical to pipe the pipe and to provide passive resistance to pipe performance and service life. They are essential to deflection. Material selection depends on help maintain proper pipe elevation, eliminate availability and cost. Granular materials with little undesirable stresses in the pipe and ensure good or no plasticity are preferred. Frozen lumps, hydraulic performance. chunks of clay, organic matter and large rock are unacceptable. Acceptable materials are The foundation material beneath the pipe must summarized in Table 1 by their ASTM Class and provide a uniform resistance to the loads on the Soil Group designation. pipe. www.lane-enterprises.com
  • 2. Sharp longitudinal and lateral variations However, if special equipment is available in the foundation must be avoided. If to provide a quality installation with a rock is encountered, excavate and replace narrow trench, the minimum width can be with gravel or lightly compacted material. reduced. If material such as CLSM is Such cushion should have a depth of used that requires no compaction, the approximately ½ in. per ft. (42 mm/m) of trench width can be as little as the pipe the planned fill depth over the pipe outside diameter, plus 6 in. (150 mm). (6 in.-150 mm minimum, 24 in.-600 mm maximum). If soft foundation material is The trench must be filled with material, encountered that must be removed to placed and compacted in layers to form a maintain grade, remove the material for a "structural backfill" surrounding the pipe. depth of about 2 ft. (0.6 m) and replace The backfill must be compacted to a with suitable compacted material. The minimum of 90 percent of maximum width of this material should be 2.5 diam- density as determined by ASTM D698 or eters on either side of the pipe for pipe 12 AASHTO T99. The envelope should in. (300 mm) diameter or less. For larger extend to 12 in. (300 mm) above the top pipe, the width should be established by of the pipe before the remainder of the fill the engineer. is placed in the trench. The trench wall is assumed to have a stiffness at least that of The upper 4 in. (100 mm) of the bedding the compacted backfill. If soft trench should be relatively loose material so the walls are encountered, additional corrugations can be seated. Frozen excavation may be required. lumps, chunks of clay, organic matter and large rock are unacceptable. The pipe may be installed by shaping the bedding surface to conform to the pipe for a width of about one-half the diameter. A second method is to place the pipe directly on the bedding, in which case particular care must be taken to compact the backfill under the haunches of the pipe to provide uniform support. Trench Construction The trench should be wide enough for placement and compaction of backfill, especially the Excavate trenches to ensure the trench material placed beside the pipe and that in walls are stable under all conditions. the haunch area below the spring line. Slope the walls or provide support in Generally, the minimum trench width conformance with safety standards. All should not be less than the greater of (1) appropriate safety practices and the pipe outside diameter plus 16 in. (400 regulations must be followed to avoid mm), or (2) the pipe outside diameter trench collapse. If high ground water is times 1.25, plus 12 in. (300 mm). encountered, dewatering may be required to achieve a safe installation that meets requirements.
  • 3. Embankment Construction Backfill Placement In embankment construction, the compacted In either trench or embankment construction, the envelope of "structural backfill" must surround the backfill material must be placed in layers and pipe with a width adequate to resist forces caused compacted to a minimum of 90 percent of by construction equipment. The width of this zone maximum density as determined by ASTM D698 on each side of the pipe should be one diameter, or ASSHTO T99. The maximum thickness of the with a minimum of 12 in. (300 mm) and a layers or lifts should not exceed 6 in. (150 mm). maximum of 24 in. (600 mm). The envelope The lift thickness, placement technique and should extend to 12 in. (300 mm) above the top of compaction method must be such that compaction the pipe before normal embankment material is under the haunches is obtained. placed. continued on next page > TABLE 1 Recommended Backfill Materials ASTM ASTM Similar D2321 Type D2487 Description AASHTO Class Soil Group Type Angular, crushed stone or rock, crushed IA Manufactured Aggregates; gravel, broken coral, crushed slag, cinders open-graded, clean. or shells; large void content, contain little or no fines. Manufactured Processed Angular, crushed stone (or other Class 1A IB materials) and stone/sand mixtures with Aggregates; dense-graded, clean. gradations selected to minimize migration of adjacent soils; contain little or no fines. GW Well-graded gravels and gravel/sand A1, II Coarse-Grained Soils; clean. mixtures, little or no fines. A3 GP Poorly graded gravels and gravel/sand mixtures, little or no fines. SW Well-graded sands and gravelly sands, little or no fines. SP Poorly-graded sands and gravelly sands, little or no fines. Coarse-Grained Soils; borderline e.g. Sands which are borderline between clean to with fines. GW clean and with fines. GC SP SM III Coarse-Grained Soils with Fines. GM Silty gravels, gravel-sand-silt mixtures. A2 GC Clayey gravels, gravel-sand-clay mixtures. SM Silty sands, sand-clay mixtures SC Clayey sands, sand/clay mixtures. Note: Compact backfill material to minimum of 90% of maximum density per ASTM D698 or AASHTO T99. Table adapted from ASTM D2321.
  • 4. Each layer must be compacted before the next lift is placed. Backfill must proceed evenly on each side of the pipe. Care must be taken to avoid pipe distortion or excessive local or general deflection. Such unacceptable deformations can result from either excessive or inadequate compaction or from construction equipment. Do not allow compaction or other equipment to contact and damage the pipe. Compaction techniques must be compatible with the backfill materials used, and the width of the area being compacted. Mechanical compaction is generally used. However, water consolidation methods can be used on free-draining backfill material if care is taken to prevent flotation. Conditions must be controlled and approved by the engineer. Construction Loads It is important to protect the pipe from equipment loads during construction. Heavy equipment must not be allowed close to or over buried pipe unless provisions are made to accommodate the resultant loads. Depending on the size of the equipment and class of fill material, a minimum cover from 2 ft. (0.6 m) to 4 ft. (1.2 m), or more for exceptional loads, may be required. (see table 2) For shallow installations, it may be necessary to mound and compact material over the pipe to provide the minimum cover. The mound can be removed and final grade established after construction. TABLE 2 COVER FOR CONSTRUCTION LOADS Minimum Cover, in., for indicated Axle Loads, kips Nominal Pipe Drain with Lane Diameter, ft 18.0-50.0 50.0-75.0 75.0-110.0 110.0-150.0 Lane Enterprises, Inc. 2.0-3.0 24.0 30.0 36.0 36.0 3905 Hartzdale Drive, Suite 514 Camp Hill, PA 17011 3.5-4.0 36.0 36.0 42.0 48.0 717-761-8175 Fax 717-761-5055 4.5-5.0 36.0 36.0 42.0 48.0 New York Minimum cover shall be measured from the top of the pipe to the Ballston Spa 518-885-4385 top of the maintained construction roadway surface. If unpaved, Bath 607-776-3366 the surface shall be maintained. North Carolina Multiple Pipes Statesville 704-872-2471 When two or more pipes are installed in adjacent parallel lines, sufficient Pennsylvania space must be provided between the pipes to provide for adequate Bedford 814-623-1191 compaction of the structural backfill. One rule-of-thumb is to use a Carlisle 717-249-8342 spacing between pipes equal to 12 in. (300 mm), or one-half the nominal King of Prussia 610-272-4531 pipe diameter, whichever is greater. This can be increased if necessary to Pulaski 412-652-7747 accommodate compaction. Virginia Bealeton 540-439-3201 The information contained in this technical bulletin is general in nature and is intended for use in conjunction with competent engineering advice as to its suitability for any specific application. Nothing in this bulletin is intended as a Dublin 540-674-4645 representative or warranty that such data is suitable for any particular application or purpose. www.lane-enterprises.com