September 2013
1
Contents
1. Pre- Commissioning
2. Preservation of pipeline
3. Commissioning Activities
2
Commissioning Procedures
These Procedures covers the following:
 Pre-commissioning, which covers all activities and approvals necessary to allow purging with gas and
pressurizing to normal operating pressure to commence.
 Pipeline preservation, in case gas-initiation of the pipeline is performed later than six months after
the installations are completed the pipeline is preserved.
 Commissioning of dry pipelines. The criteria for being considered a dry pipeline are as follows:
• Dew point temperature must be < - 20° C measured at atmospheric pressure.
• Over-pressure following sealing of the lines must be at least I barg.
• The acceptable minimum standard during the whole period of preservation is a dew
point temperature of - I0° C.
 Commissioning of wet pipelines. Wet pipelines are considered those that are not met the previous
criteria·
3
1.1 PRE-COMMISSIONING ACTIVITIES
On substantial completion of construction activities, Contractor mobilizes its commissioning team to
initiate pre-commissioning activities in a phased manner.
The objective of pre-commissioning is to ensure that the pipeline as well all the facilities have been
completed according to the Project Specifications and that commissioning and operation will take
place safely and effectively.
Also during the pre-commissioning should be verified that all the relevant data with the
commissioning of the pipeline has been received and that the commissioning procedure is
presented and discussed with all personnel involved.
Another important aspect which has to be verified during this procedure is that all the necessary
drawings, technical information, and O & M manuals have been received and that the operating
plan has been existing .
Pre-commissioning may therefore be defined as all the checks that are to be completed prior to
commissioning being permitted to commence.
4
The pre-commissioning phase includes three main types of field activities:
a) Systematic conformity checks, carried out on each item of equipment or component, such as
pressure gauges, cables, etc., to verify visually the condition of the equipment, the quality of the
installation, the compliance with project drawings and specifications, manufacturer's
instructions, safety rules, codes, standards and good engineering practices. These checks will
confirm the following:
• All pipe assemblies and weldings have been completed.
• All pipeline pressure and leak tests have been completed and relevant certified test
documents have been received (weld radiographs, hydrostatic test documents etc)
• Electrical and control installations have been completed and are functioning.
5
• Cathodic protection systems have been completed and are functioning.
• Security fences have been installed around all above ground high pressure pipeline facilities.
• Emergency vehicle access is provided to all pipe line facilities (land valve stations, MIR-stations,
Scraper Stations.
• Right-of-way restoration has been completed according to specifications and landowner
agreements and all environmental concerns have been addressed.
b) Equipment static/de-energized tests, to ensure the quality of a number of critical components.
This "cold" testing concerns all disciplines, e.g. calibration of instruments, machinery
alignments, setting of safety valves, pressure testing of piping, cable continuities, etc.
c) Dewatering and drying of the pipeline and the vessels has been completed in accordance with
specifications and approved procedures.
6
As soon as practical, the Pre-commissioning team shall acquire a complete set of drawings and data
as listed below:
1. As built drawings and technical information regarding:
• Pipeline sections between line valve stations : pipe logs showing the location, size, wall
thickness, and pipe grade
• Line Valve stations: schematic showing venting and valving arrangements, as well as
technical data regarding material, fittings, valves, etc.
• M/R Stations: schematics showing venting arrangements, customer interconnections for gas
service and by-pass technical data regarding material, fittings, valves, etc.
• Scraper Stations: schematics showing piping arrangement as well as technical data regarding
material, fittings, valves, etc.
• Cathodic protection facilities: including type and description of rectifiers, number and type of
sacrificial anodes, measuring posts, insulating couplings, type of pipeline external and internal
coating
7
2. Route Maps which indicate among the others the pipeline routing, the depth of pipeline, the
access routes to valve stations, M/R Stations , Scraper Stations, cathodic protection rectifiers
and measuring posts have been received.
3. 3. Vendor-supplied equipment design specifications, installation drawings, operation and
maintenance manuals.
4. 3. All QC documentation relating to the construction testing i.e. hydro test packs, cable
checklists etc. as well as emergency procedures and operating plans.
Pre-commissioning work described herein will require all necessary tools, test instruments, water,
air and electric power etc to be made available to the Pre-commissioning team. Also spare parts and
repair materials as well as that all the necessary tools and work equipment as pipe locators, gas
detection equipment etc should be available.
Each craftsman such as pipe fitter, millwright, mechanic, instrument technician, or electrician, who
is assisting the Pre-commissioning team, shall have his normal tools available.
8
All necessary tags, warning tapes, barricade tapes and safety supplies shall be made available at the
site. The following signs are posted at strategic locations before proceeding with the appropriate
Pre-commissioning activities:
Tags:
 No smoking
 Danger, high voltage
 Do not enter beyond this point
9
Finally, the following safety supplies are made available to all staff involved in the pre-commissioning
activities.
 Ear Protection
 Safety Glasses
 Hard Hats
 First Aid Kit
 Face Shield
 Chemical Gloves
 Safety Goggles
 Padlocks with Multi-Lock Clips
 Safety Boots
 Boiler suits/overalls
10
For the purpose of pre-commissioning, the facilities will be subdivided suitably into a few systems.
The pre-commissioning checks of each piece of equipment are to be as complete and as
comprehensive as possible to ensure that the equipment are installed as specified and will operate as
designed. Proper pre-commissioning will ensure that the facilities can be made operable with the
least number of problems. To achieve this,
(1) The Pre-commissioning Team shall become familiar with all data and information.
(2) The Pre-commissioning Team shall start all pre-commissioning checks as early as possible
during the construction activities to ensure that the final installation of all equipment is as designed
and specified.
11
All personnel involved in the pre-commissioning and commissioning activities have to be
educated with regard to the following:
• Access routes to line valve stations, MfR stations, and scraper stations.
• Vehicle and equipment use and capabilities.
• The overall commissioning plan and the co-ordination and procedures to be utilized.
• The job responsibilities of each individual and his part in the overall plan.
• Determination of gas volumes required for purging and loading.
• Sequence of valve sections to be purged and loaded
• Details of purging and loading procedures. Details .of emergency and operating plans and
responses to any problems or difficulties that may be encountered.
• The effects and precautions necessary when working with high pressure natural gas.
• Use and capabilities of telecommunication and mobile telecommunications systems.
Also it has to be verified that involved personnel have been trained and qualified for operating
the pipeline.
12
The following guidelines summarize all activities to be completed during the pre-commissioning
phase of the project.
1. Testing and adequate flushing of all piping systems.
2. Removal of all blinds or spool pieces used during hydrostatic testing.
3. Proper positioning of spectacle blinds.
4. Witness or calibrate, and test all instruments in accordance with the Pre-commissioning
procedures, and record all calibrations and test data on the checklists provided for each
instrument and instrument loop.
5. Verify that lubricants, oils, coolants, etc., required for all equipment are on the job site and in
good condition (i.e. not contaminated).
6. Ensure that fire extinguishers are in place.
7. Check all electrical closures.
8. Ensure that all escape routes are clear of obstacles.
13
9. Ensure that all eyewash stations are operational.
10. Wear personal safety equipment.
11. Clear area from unauthorized personnel.
12. Be aware of the wind direction.
13. Be aware of the designated meeting area location.
14. Ensure that fire detection equipment is operational.
14
General
Preservation of a pipeline is carried out to maintain the pre commissioning condition, which the
installations are in until commissioning comes into force.
2.1 Preservation with dry air
If the initial gas filling of the pipelines is carried out later than six months after the installation-
works are completed preservation of the pipelines takes place according to the dry air method. The
main criteria for a dry pipeline are as follows:
 Dewpoint temperature must be ≤ -20°C measured at atmospheric pressure.
 Overpressure after sealing of the pipelines must be at least one barg.
 The acceptable minimum norm during the entire preserva tion-period is a measured dewpoint
temperature of ≤ -10 °C (measured at atmospheric pressure and at an overpressure of one barg).
15
The dewpoint temperature and the pressure is measured and registered within the preservation
period with stated intervals since the pipeline-contractor as well as a neutral third party is
involved.
2.2 Preservation with nitrogen (N2)
If it is decided to preserve the pipeline by the use of nitrogen the criteria are as follows:
 Purge with nitrogen until achieving 100% N2
 The overpressure after sealing must be at least 2 barg.
Measurements of the pressure at stated intervals during the preservation period is required.
16
3.1 Commissioning of dry pipelines
3.1.1 General
Commissioning includes the following activities:
The supervision and execution of the Commissioning activities are to be carried out by DESFA’s
personnel who are suitably trained and qualified for this task.
Commissioning check· list is to be strictly adhered to during execution of the commissioning.
Commissioning is to take place in coordination with Gas Control Center. No valves are to be opened
without prior approval from Gas Control Center.
17
Purging of a section of pipeline is to be considered as complete when 100 % gas is measured 3
times at the exhaust point with two independent gas measuring instruments.
When commissioning a new section of pipeline, or possibly a modified section of pipeline (e.g.
in case of repair or construction activity) notification is to be carried out by means of form 2.2.b.
 Purging, loading, and placing into service may be carried out only after presentation of the
notification of placing into service.
 The person responsible for observation of the commissioning policy is DESFA’s District
Manager, or alternately, a deputy named by him.
The criteria for being considered a dry pipeline are as described here above, and if those criteria
are not fulfilled then the pipeline is considered as wet.
Sections of the pipeline which have been constructed, as well as sections of the pipeline on which
repairs have been carried out, contain air or a mixture of gas and air. These pipelines or sections
of pipelines must be placed into service in a safe, economical and environmentally responsible
manner.
18
The following description and points to be observed ensure a trouble-free process for commissioning
of dry pipelines.
 Prepare the scope and the technique for commissioning and complying with Gas Control
requirements
 Establish the purge direction
 Determine whether inert gas is required and eventually required volume
 Calculate the purge time
 Determine which will be the inlet throttle valve and exhaust valve and carry out a function
test of these valves
 Establish the purge velocity. This velocity is usually between 5 m/sec in the main pipeline if no
inert gas is used or 7-10 m/sec if inert gas is used
19
 Check all facilities which have a relation to the commissioning according to the safety check
list which is herewith
 Ensure that capable and adequate personnel is assigned
 Ensure satisfactory performance of vehicles, equipment, and instruments
 Ensure effective and reliable communications between the inlet point, the exhaust point,
and Gas Control Center
 Advise Gas Control Center of commencement of purging, loading, and placing into service
 Ensure with the Gas Control Center for the availability of the required quantities of gas
 In case of use of inert gas, the adequate volume will be determined from the cross sectional
area of the pipe. An inert gas plug approx. 300 m in length is recommended as it may be
difficult to maintain a purge velocity of 3 - 7 rn/s. The supervisor in charge of commissioning
will determine if inert gas is to be used
20
3.1.2 Commissioning procedure
 The procedure begins with the injection of gas , or inert gas if it is decided, into the inlet throttle
valve which is opened slowly, while measuring the velocity at the outlet throttle valve
 Then should regulate the purge velocity (usually approx. 10 rn/sec in the main
 pipeline - 90 m/sec from vent stack) following always the be given by a per son at the vent stack
 Commence timing of the purge only after regulation of the purge velocity has been achieved
 Close to the expiration of the purge time, the gas concentration is to be measured by means of
two independent gas measuring instruments
 After verification of measurements of 100 % Vol gas at least 3 times then first the throttling
valves of the exit and then the valves of the insert point are to be closed in that order
 All vented gas quantities are to be reported for the calculation of the vented gas
21
 Two pressure gauges and one pressure recorder are installed at the start and end of the pipeline
section to be loaded (one additional pressure gauge is to be kept in reserve in case of
malfunction). The range of the scales of the gauges and recorders must be at least equal to the
maximum possible loading pressure
 The pipeline is loaded in stages so that the pressure in the pipeline rises to 5 - 10 bar during
the first hour
 The second hour the throttle inner valve is opened further so that the pressure rises to 10 - 20
bar
 Finally the inlet throttle valve is opened further so that final loading pressure is reached after
three hours
 Depending on the quantity of gas supply available for loading the pipeline, lower pressure
increments are to be selected in accordance with Gas Control Center
22
 After each hour a· leak test of susceptible points on the pipeline (e.g. tie-in welds, flange
connections, etc.) is to be carried out using a foam producing liquid. If any leaks are found
permanent repairs are to be carried out in accordance with specifications before proceeding
with the loading operation
 Leaks from fittings should be tightened in accordance to vendors instructions
 Loading time for the pipeline or section of pipeline will generally be determined by the gas
volumes available and the configuration at the inlet and throttle valve
 After the pipeline has been loaded (pressure equalization) it will be connected to the pipeline
system
 For further commissioning of pipeline downstream Section the above procedure is repeated
23
3.2 Commissioning of wet pipelines
In the case of wet pipeline and before purging with natural gas it is necessary to dry the pipeline.
The cause of this is that under certain pressure and temperature conditions, gas hydrates will form
when hygroscopic water (i.e. water remaining after de-watering) comes into contact with gas. The
range of pressure and temperature, within which natural gas hydrates form, lies above 0o C
(water dew point) and 6 bar. A decomposition of gas hydrates occurs by an increase in temperature
or reduction in pressure.
Based on present experience the following dehydration procedures are generally accepted:
• Drying with dry air
• Absorption of residual water by alcohol
• Drying of residual water by vacuum
After the drying of the pipeline the procedure for the commissioning of dry pipeline is followed.
24

Mais conteúdo relacionado

Mais procurados

Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedureGerard B. Hawkins
 
Detail engineering of piping systems
Detail engineering of piping systemsDetail engineering of piping systems
Detail engineering of piping systemsjudithmorrison01
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
 
Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Vijay Sarathy
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure Varun Patel
 
Heat exchanger types and hydro testing
Heat exchanger types and hydro testingHeat exchanger types and hydro testing
Heat exchanger types and hydro testingwaqarahmed445
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingAbhijeet Nagle
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineeringMobinVarghese8
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for pipingKhiem Vo Duy
 

Mais procurados (20)

Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning Procedure
 
Detail engineering of piping systems
Detail engineering of piping systemsDetail engineering of piping systems
Detail engineering of piping systems
 
Pipe Support Field Inspection, Installation & Maintenance
Pipe Support Field Inspection, Installation & MaintenancePipe Support Field Inspection, Installation & Maintenance
Pipe Support Field Inspection, Installation & Maintenance
 
Nitrogen purging
Nitrogen  purgingNitrogen  purging
Nitrogen purging
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
Piping interview
Piping interviewPiping interview
Piping interview
 
Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
 
Heat exchanger types and hydro testing
Heat exchanger types and hydro testingHeat exchanger types and hydro testing
Heat exchanger types and hydro testing
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / Hydrotesting
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
 
Scope of work
Scope of workScope of work
Scope of work
 
Piping Fundamentals .pdf
Piping Fundamentals .pdfPiping Fundamentals .pdf
Piping Fundamentals .pdf
 
Hydrotest
HydrotestHydrotest
Hydrotest
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for piping
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
HAZARDS-Pneumatic Test(1)
HAZARDS-Pneumatic Test(1)HAZARDS-Pneumatic Test(1)
HAZARDS-Pneumatic Test(1)
 

Semelhante a Precommisioning and commissioning updated

Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Manohar Tatwawadi
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearMarty Stevenson
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersMarty Stevenson
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Commissioning Technician
Commissioning TechnicianCommissioning Technician
Commissioning Technicianudipta dey
 
61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-studyhomeworkping4
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikMOHAMAD ANWAR MALIK
 

Semelhante a Precommisioning and commissioning updated (20)

Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Plant start up
Plant start upPlant start up
Plant start up
 
my_cv_WP
my_cv_WPmy_cv_WP
my_cv_WP
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
1 80 fineshed
1 80 fineshed1 80 fineshed
1 80 fineshed
 
Safety plan
Safety planSafety plan
Safety plan
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul
 
Steam Blow out
Steam Blow outSteam Blow out
Steam Blow out
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation Switchgear
 
078 switchgear install 1.0
078 switchgear install 1.0078 switchgear install 1.0
078 switchgear install 1.0
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit Breakers
 
076 circuit breaker install 1.0
076 circuit breaker install 1.0076 circuit breaker install 1.0
076 circuit breaker install 1.0
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Commissioning Technician
Commissioning TechnicianCommissioning Technician
Commissioning Technician
 
61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-study
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
C.V
C.VC.V
C.V
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malik
 

Mais de Personal Secret

Noise PPT Slide with AGNICE CONTRACTING DUBAI
Noise PPT Slide with AGNICE CONTRACTING  DUBAINoise PPT Slide with AGNICE CONTRACTING  DUBAI
Noise PPT Slide with AGNICE CONTRACTING DUBAIPersonal Secret
 
Work at Height & Scaffolding Awareness 22.06.2021
Work at Height  & Scaffolding  Awareness 22.06.2021Work at Height  & Scaffolding  Awareness 22.06.2021
Work at Height & Scaffolding Awareness 22.06.2021Personal Secret
 
Ramadan Health & Safety Precautions
Ramadan Health & Safety PrecautionsRamadan Health & Safety Precautions
Ramadan Health & Safety PrecautionsPersonal Secret
 
Confined space entry ppt slide
Confined space entry ppt slideConfined space entry ppt slide
Confined space entry ppt slidePersonal Secret
 
First aid training good ppt
First aid training good pptFirst aid training good ppt
First aid training good pptPersonal Secret
 
Petrol area loading . unloading ppt
Petrol area loading . unloading  pptPetrol area loading . unloading  ppt
Petrol area loading . unloading pptPersonal Secret
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARDPersonal Secret
 
7 adco engr appreciation by william sir
7  adco engr appreciation by william sir7  adco engr appreciation by william sir
7 adco engr appreciation by william sirPersonal Secret
 

Mais de Personal Secret (14)

CHEMICAL SAFETY NEW.pdf
CHEMICAL SAFETY NEW.pdfCHEMICAL SAFETY NEW.pdf
CHEMICAL SAFETY NEW.pdf
 
FIRE ALARM SYSTEM.pdf
FIRE ALARM SYSTEM.pdfFIRE ALARM SYSTEM.pdf
FIRE ALARM SYSTEM.pdf
 
Noise PPT Slide with AGNICE CONTRACTING DUBAI
Noise PPT Slide with AGNICE CONTRACTING  DUBAINoise PPT Slide with AGNICE CONTRACTING  DUBAI
Noise PPT Slide with AGNICE CONTRACTING DUBAI
 
Work at Height & Scaffolding Awareness 22.06.2021
Work at Height  & Scaffolding  Awareness 22.06.2021Work at Height  & Scaffolding  Awareness 22.06.2021
Work at Height & Scaffolding Awareness 22.06.2021
 
Gas Tester Training
Gas Tester TrainingGas Tester Training
Gas Tester Training
 
Ramadan Health & Safety Precautions
Ramadan Health & Safety PrecautionsRamadan Health & Safety Precautions
Ramadan Health & Safety Precautions
 
Confined space entry ppt slide
Confined space entry ppt slideConfined space entry ppt slide
Confined space entry ppt slide
 
Housekeeping PowerPoint
Housekeeping PowerPointHousekeeping PowerPoint
Housekeeping PowerPoint
 
First aid training good ppt
First aid training good pptFirst aid training good ppt
First aid training good ppt
 
Petrol area loading . unloading ppt
Petrol area loading . unloading  pptPetrol area loading . unloading  ppt
Petrol area loading . unloading ppt
 
Zones
ZonesZones
Zones
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARD
 
Banks man awareness
Banks man awarenessBanks man awareness
Banks man awareness
 
7 adco engr appreciation by william sir
7  adco engr appreciation by william sir7  adco engr appreciation by william sir
7 adco engr appreciation by william sir
 

Último

Environmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptxEnvironmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptxhossanmdjobayer103
 
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
CSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENCSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENGeorgeDiamandis11
 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...AICCRA
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...SUHANI PANDEY
 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptxJIT KUMAR GUPTA
 
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...MOHANI PANDEY
 
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...tanu pandey
 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayGeorgeDiamandis11
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...Call Girls in Nagpur High Profile
 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...AICCRA
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995garthraymundo123
 
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verifiedDelhi Call girls
 
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...SUHANI PANDEY
 

Último (20)

Environmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptxEnvironmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptx
 
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
 
CSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -ENCSR_Tested activities in the classroom -EN
CSR_Tested activities in the classroom -EN
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
 
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
 
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting Day
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
 
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...Booking open Available Pune Call Girls Parvati Darshan  6297143586 Call Hot I...
Booking open Available Pune Call Girls Parvati Darshan 6297143586 Call Hot I...
 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
 
(Anamika) VIP Call Girls Jammu Call Now 8617697112 Jammu Escorts 24x7
(Anamika) VIP Call Girls Jammu Call Now 8617697112 Jammu Escorts 24x7(Anamika) VIP Call Girls Jammu Call Now 8617697112 Jammu Escorts 24x7
(Anamika) VIP Call Girls Jammu Call Now 8617697112 Jammu Escorts 24x7
 
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
 
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
 

Precommisioning and commissioning updated

  • 2. Contents 1. Pre- Commissioning 2. Preservation of pipeline 3. Commissioning Activities 2
  • 3. Commissioning Procedures These Procedures covers the following:  Pre-commissioning, which covers all activities and approvals necessary to allow purging with gas and pressurizing to normal operating pressure to commence.  Pipeline preservation, in case gas-initiation of the pipeline is performed later than six months after the installations are completed the pipeline is preserved.  Commissioning of dry pipelines. The criteria for being considered a dry pipeline are as follows: • Dew point temperature must be < - 20° C measured at atmospheric pressure. • Over-pressure following sealing of the lines must be at least I barg. • The acceptable minimum standard during the whole period of preservation is a dew point temperature of - I0° C.  Commissioning of wet pipelines. Wet pipelines are considered those that are not met the previous criteria· 3
  • 4. 1.1 PRE-COMMISSIONING ACTIVITIES On substantial completion of construction activities, Contractor mobilizes its commissioning team to initiate pre-commissioning activities in a phased manner. The objective of pre-commissioning is to ensure that the pipeline as well all the facilities have been completed according to the Project Specifications and that commissioning and operation will take place safely and effectively. Also during the pre-commissioning should be verified that all the relevant data with the commissioning of the pipeline has been received and that the commissioning procedure is presented and discussed with all personnel involved. Another important aspect which has to be verified during this procedure is that all the necessary drawings, technical information, and O & M manuals have been received and that the operating plan has been existing . Pre-commissioning may therefore be defined as all the checks that are to be completed prior to commissioning being permitted to commence. 4
  • 5. The pre-commissioning phase includes three main types of field activities: a) Systematic conformity checks, carried out on each item of equipment or component, such as pressure gauges, cables, etc., to verify visually the condition of the equipment, the quality of the installation, the compliance with project drawings and specifications, manufacturer's instructions, safety rules, codes, standards and good engineering practices. These checks will confirm the following: • All pipe assemblies and weldings have been completed. • All pipeline pressure and leak tests have been completed and relevant certified test documents have been received (weld radiographs, hydrostatic test documents etc) • Electrical and control installations have been completed and are functioning. 5
  • 6. • Cathodic protection systems have been completed and are functioning. • Security fences have been installed around all above ground high pressure pipeline facilities. • Emergency vehicle access is provided to all pipe line facilities (land valve stations, MIR-stations, Scraper Stations. • Right-of-way restoration has been completed according to specifications and landowner agreements and all environmental concerns have been addressed. b) Equipment static/de-energized tests, to ensure the quality of a number of critical components. This "cold" testing concerns all disciplines, e.g. calibration of instruments, machinery alignments, setting of safety valves, pressure testing of piping, cable continuities, etc. c) Dewatering and drying of the pipeline and the vessels has been completed in accordance with specifications and approved procedures. 6
  • 7. As soon as practical, the Pre-commissioning team shall acquire a complete set of drawings and data as listed below: 1. As built drawings and technical information regarding: • Pipeline sections between line valve stations : pipe logs showing the location, size, wall thickness, and pipe grade • Line Valve stations: schematic showing venting and valving arrangements, as well as technical data regarding material, fittings, valves, etc. • M/R Stations: schematics showing venting arrangements, customer interconnections for gas service and by-pass technical data regarding material, fittings, valves, etc. • Scraper Stations: schematics showing piping arrangement as well as technical data regarding material, fittings, valves, etc. • Cathodic protection facilities: including type and description of rectifiers, number and type of sacrificial anodes, measuring posts, insulating couplings, type of pipeline external and internal coating 7
  • 8. 2. Route Maps which indicate among the others the pipeline routing, the depth of pipeline, the access routes to valve stations, M/R Stations , Scraper Stations, cathodic protection rectifiers and measuring posts have been received. 3. 3. Vendor-supplied equipment design specifications, installation drawings, operation and maintenance manuals. 4. 3. All QC documentation relating to the construction testing i.e. hydro test packs, cable checklists etc. as well as emergency procedures and operating plans. Pre-commissioning work described herein will require all necessary tools, test instruments, water, air and electric power etc to be made available to the Pre-commissioning team. Also spare parts and repair materials as well as that all the necessary tools and work equipment as pipe locators, gas detection equipment etc should be available. Each craftsman such as pipe fitter, millwright, mechanic, instrument technician, or electrician, who is assisting the Pre-commissioning team, shall have his normal tools available. 8
  • 9. All necessary tags, warning tapes, barricade tapes and safety supplies shall be made available at the site. The following signs are posted at strategic locations before proceeding with the appropriate Pre-commissioning activities: Tags:  No smoking  Danger, high voltage  Do not enter beyond this point 9
  • 10. Finally, the following safety supplies are made available to all staff involved in the pre-commissioning activities.  Ear Protection  Safety Glasses  Hard Hats  First Aid Kit  Face Shield  Chemical Gloves  Safety Goggles  Padlocks with Multi-Lock Clips  Safety Boots  Boiler suits/overalls 10
  • 11. For the purpose of pre-commissioning, the facilities will be subdivided suitably into a few systems. The pre-commissioning checks of each piece of equipment are to be as complete and as comprehensive as possible to ensure that the equipment are installed as specified and will operate as designed. Proper pre-commissioning will ensure that the facilities can be made operable with the least number of problems. To achieve this, (1) The Pre-commissioning Team shall become familiar with all data and information. (2) The Pre-commissioning Team shall start all pre-commissioning checks as early as possible during the construction activities to ensure that the final installation of all equipment is as designed and specified. 11
  • 12. All personnel involved in the pre-commissioning and commissioning activities have to be educated with regard to the following: • Access routes to line valve stations, MfR stations, and scraper stations. • Vehicle and equipment use and capabilities. • The overall commissioning plan and the co-ordination and procedures to be utilized. • The job responsibilities of each individual and his part in the overall plan. • Determination of gas volumes required for purging and loading. • Sequence of valve sections to be purged and loaded • Details of purging and loading procedures. Details .of emergency and operating plans and responses to any problems or difficulties that may be encountered. • The effects and precautions necessary when working with high pressure natural gas. • Use and capabilities of telecommunication and mobile telecommunications systems. Also it has to be verified that involved personnel have been trained and qualified for operating the pipeline. 12
  • 13. The following guidelines summarize all activities to be completed during the pre-commissioning phase of the project. 1. Testing and adequate flushing of all piping systems. 2. Removal of all blinds or spool pieces used during hydrostatic testing. 3. Proper positioning of spectacle blinds. 4. Witness or calibrate, and test all instruments in accordance with the Pre-commissioning procedures, and record all calibrations and test data on the checklists provided for each instrument and instrument loop. 5. Verify that lubricants, oils, coolants, etc., required for all equipment are on the job site and in good condition (i.e. not contaminated). 6. Ensure that fire extinguishers are in place. 7. Check all electrical closures. 8. Ensure that all escape routes are clear of obstacles. 13
  • 14. 9. Ensure that all eyewash stations are operational. 10. Wear personal safety equipment. 11. Clear area from unauthorized personnel. 12. Be aware of the wind direction. 13. Be aware of the designated meeting area location. 14. Ensure that fire detection equipment is operational. 14
  • 15. General Preservation of a pipeline is carried out to maintain the pre commissioning condition, which the installations are in until commissioning comes into force. 2.1 Preservation with dry air If the initial gas filling of the pipelines is carried out later than six months after the installation- works are completed preservation of the pipelines takes place according to the dry air method. The main criteria for a dry pipeline are as follows:  Dewpoint temperature must be ≤ -20°C measured at atmospheric pressure.  Overpressure after sealing of the pipelines must be at least one barg.  The acceptable minimum norm during the entire preserva tion-period is a measured dewpoint temperature of ≤ -10 °C (measured at atmospheric pressure and at an overpressure of one barg). 15
  • 16. The dewpoint temperature and the pressure is measured and registered within the preservation period with stated intervals since the pipeline-contractor as well as a neutral third party is involved. 2.2 Preservation with nitrogen (N2) If it is decided to preserve the pipeline by the use of nitrogen the criteria are as follows:  Purge with nitrogen until achieving 100% N2  The overpressure after sealing must be at least 2 barg. Measurements of the pressure at stated intervals during the preservation period is required. 16
  • 17. 3.1 Commissioning of dry pipelines 3.1.1 General Commissioning includes the following activities: The supervision and execution of the Commissioning activities are to be carried out by DESFA’s personnel who are suitably trained and qualified for this task. Commissioning check· list is to be strictly adhered to during execution of the commissioning. Commissioning is to take place in coordination with Gas Control Center. No valves are to be opened without prior approval from Gas Control Center. 17
  • 18. Purging of a section of pipeline is to be considered as complete when 100 % gas is measured 3 times at the exhaust point with two independent gas measuring instruments. When commissioning a new section of pipeline, or possibly a modified section of pipeline (e.g. in case of repair or construction activity) notification is to be carried out by means of form 2.2.b.  Purging, loading, and placing into service may be carried out only after presentation of the notification of placing into service.  The person responsible for observation of the commissioning policy is DESFA’s District Manager, or alternately, a deputy named by him. The criteria for being considered a dry pipeline are as described here above, and if those criteria are not fulfilled then the pipeline is considered as wet. Sections of the pipeline which have been constructed, as well as sections of the pipeline on which repairs have been carried out, contain air or a mixture of gas and air. These pipelines or sections of pipelines must be placed into service in a safe, economical and environmentally responsible manner. 18
  • 19. The following description and points to be observed ensure a trouble-free process for commissioning of dry pipelines.  Prepare the scope and the technique for commissioning and complying with Gas Control requirements  Establish the purge direction  Determine whether inert gas is required and eventually required volume  Calculate the purge time  Determine which will be the inlet throttle valve and exhaust valve and carry out a function test of these valves  Establish the purge velocity. This velocity is usually between 5 m/sec in the main pipeline if no inert gas is used or 7-10 m/sec if inert gas is used 19
  • 20.  Check all facilities which have a relation to the commissioning according to the safety check list which is herewith  Ensure that capable and adequate personnel is assigned  Ensure satisfactory performance of vehicles, equipment, and instruments  Ensure effective and reliable communications between the inlet point, the exhaust point, and Gas Control Center  Advise Gas Control Center of commencement of purging, loading, and placing into service  Ensure with the Gas Control Center for the availability of the required quantities of gas  In case of use of inert gas, the adequate volume will be determined from the cross sectional area of the pipe. An inert gas plug approx. 300 m in length is recommended as it may be difficult to maintain a purge velocity of 3 - 7 rn/s. The supervisor in charge of commissioning will determine if inert gas is to be used 20
  • 21. 3.1.2 Commissioning procedure  The procedure begins with the injection of gas , or inert gas if it is decided, into the inlet throttle valve which is opened slowly, while measuring the velocity at the outlet throttle valve  Then should regulate the purge velocity (usually approx. 10 rn/sec in the main  pipeline - 90 m/sec from vent stack) following always the be given by a per son at the vent stack  Commence timing of the purge only after regulation of the purge velocity has been achieved  Close to the expiration of the purge time, the gas concentration is to be measured by means of two independent gas measuring instruments  After verification of measurements of 100 % Vol gas at least 3 times then first the throttling valves of the exit and then the valves of the insert point are to be closed in that order  All vented gas quantities are to be reported for the calculation of the vented gas 21
  • 22.  Two pressure gauges and one pressure recorder are installed at the start and end of the pipeline section to be loaded (one additional pressure gauge is to be kept in reserve in case of malfunction). The range of the scales of the gauges and recorders must be at least equal to the maximum possible loading pressure  The pipeline is loaded in stages so that the pressure in the pipeline rises to 5 - 10 bar during the first hour  The second hour the throttle inner valve is opened further so that the pressure rises to 10 - 20 bar  Finally the inlet throttle valve is opened further so that final loading pressure is reached after three hours  Depending on the quantity of gas supply available for loading the pipeline, lower pressure increments are to be selected in accordance with Gas Control Center 22
  • 23.  After each hour a· leak test of susceptible points on the pipeline (e.g. tie-in welds, flange connections, etc.) is to be carried out using a foam producing liquid. If any leaks are found permanent repairs are to be carried out in accordance with specifications before proceeding with the loading operation  Leaks from fittings should be tightened in accordance to vendors instructions  Loading time for the pipeline or section of pipeline will generally be determined by the gas volumes available and the configuration at the inlet and throttle valve  After the pipeline has been loaded (pressure equalization) it will be connected to the pipeline system  For further commissioning of pipeline downstream Section the above procedure is repeated 23
  • 24. 3.2 Commissioning of wet pipelines In the case of wet pipeline and before purging with natural gas it is necessary to dry the pipeline. The cause of this is that under certain pressure and temperature conditions, gas hydrates will form when hygroscopic water (i.e. water remaining after de-watering) comes into contact with gas. The range of pressure and temperature, within which natural gas hydrates form, lies above 0o C (water dew point) and 6 bar. A decomposition of gas hydrates occurs by an increase in temperature or reduction in pressure. Based on present experience the following dehydration procedures are generally accepted: • Drying with dry air • Absorption of residual water by alcohol • Drying of residual water by vacuum After the drying of the pipeline the procedure for the commissioning of dry pipeline is followed. 24