DREDGING
Definition:
• Dredging is an excavation activity or
operation usually carried out at least partly
underwater, in shallow seas or fresh
water areas with the purpose of gathering up
bottom sediments and disposing of them at a
different location.
• In all situations the operation is undertaken
by special floating plant, known as a dredger.
Dredger:
• A dredgers is a piece of equipment which
can dig, transport and dump a certain
amount of under water laying soil in a certain
time.
• The quantity of soil moved per unit of time is
called Production.
•

4 phases are:
- Excavation
- Lifting
- Transportation
-Disposal
Why dredging?
•

Capital works:Creation of new facilities, such as harbour
basins,deeper navigation channels etc



Infrastructure



coastal engineering



mining industry



•

Navigation

offshore industry

Maintenance works : Maintain design depth of navigation
channel and ports.

•

Remedial works: Careful removal of contaminated
material ,reuse or relocation of the material
Types Of Dredgers:
`
•

Mechanical Dredger

•

Hydraulic Dredger
Hydraulically

continuously
Discontinuously

Transport Via pipeline

Mechanically
Transport via conveyor
belt
Transport via
grab,ship,truck
Mechanical Dredger:
Mechanical Dredger:
In Mechanical dredgers materials conveyed by
mechanical contravenes.
• Bucket Ladder Dredger
• Grab Dredger
• Dipper/Back Hoe Dredger
Bucket Ladder Dredger:
Bucket Ladder Dredger:
Working method :
• The bucket ladder dredge is positioned on 6 wires. Under
working conditions the dredge swings around the bow
anchor.
• The bow anchor line or headline can have length longer
than 1000 m.
• In order to avoid dragging of the wire over the soil, which
results in a smaller radius, the wire is supported by a
headline pontoon.
• As a result of this long headline the cut width can be large
as well (200 m or more).
• The side-line winches take care of the swinging of the
dredge as well as the power necessary for the cutting
process.
• The swing speed depends on the soil condition, the layer
thickness cut.
• This type of dredge is suitable for excavating soft ground,
sand or gravel.
Specification:
• The size of these vessel is about 60m in length
and 15m in width, having a draft of about
2.5 to 3m.
• The capacity of bucket is about 1cubic meter.
• The digging depth commonly extend to 1 cubic
metre
• The output is the range of 250cubic meter/hr
Grab Dredger
Working method:
•

The dredgers can be moored by anchors or by poles
(spuds) .

•

The capacity of a grab dredger is expressed in the volume
of the grab.

•

Grab sizes varies between less than 1 m3 up to 200 m3.

•

The opening of the grab is controlled by the closing and
hoisting wire or by hydraulic cylinders.

•

For grab dredgers the method of anchoring and the
positioning system plays an important role for the
effectiveness of the dredger.
•

At every pontoon position an area as wide as
possible will be dredged.

•

The positioning is important to localize the bit of the
grab.
Specification:
• The Hull is generally 30m to 60m long and
15m cross, the boom is being 15m long.
• The capacity of a grab dredger is expressed in the
volume of the grab.
• Grab sizes varies between less than 1 m3 up to
200 m3.
• The opening of the grab is controlled by the
closing and hoisting wire or by hydraulic cylinders.
Dipper or Black Hoe Dredger:
Dipper or Back Hoe Dredger:
• This is similar to the land operator crawler shovel.
• It mounted on a Barge.
• It carries a lever outer end of which, a steel
bucket is attached.
• The lever can rotate both about the vertical and
horizontal axis.
•The bottom of bucket can be opened by operating
wire rope from the barge.
• The bucket scoops out the material and after
slewing, the contents of the bucket are dropped
on to the barge by opening bottom plate of the
bucket.
Specification:
• This type of dredge can dig in depths up to
15m of water.
• Dipper capacity varies from 1 to 4 cubic meter
and heavy capacities of about 12m3 are used
in panama canal.
Hydraulic Dredger:
Hydraulic dredgers use hydraulic pumps to
produce a slurry of the dredged material.
•

Profile or plain suction dredger

•

Cutter suction dredger

•

Trailing suction hopper dredger
Profile or plain suction dredger:
Plain Suction Dredger:
• Dredgers are equipped with a centrifugal pump
for raising mixture of soil and water to deliver the
material into the transport system.
• There is a plain end suction pipe, the suction
head buried to material to be excavated.
• These type of dredgers are well suited for free
running granular material.
Working method:
• These operate by sucking through a long
tube, like some vaccum cleaners but on a
larger scale.
• A plain suction dredger has no tool at the end
of the suction pipe to disturb the material.
This is often the most commonly used form of
dredging
Specification:
• The Dredging depth is about 15m.
• Bucket capacity is about 6cubic meter, then its used
for soft material.
• If a smaller capacity bucket of about 4 cubic meter,
then its used for dredging hard material.
Cutter Suction Dredger:
Cutter suction Dredger:
•

•

•

A cutter-suction dredger's (CSD) suction
tube has a cutting mechanism at the
.
suction inlet.
The cutting mechanism loosens the bed
material and transports it to the suction
mouth.
The dredged material is usually sucked up
by a wear-resistant centrifugal pump and
discharged either through a pipe line or to
a barge.
Cutter suction Dredger (cont…)
•

•

Cutter-suction dredgers are most often
used in geological areas consisting of hard
.
surface materials (for example gravel
deposits or surface bedrock) where a
standard suction dredger would be
ineffective.
In recent years, dredgers with more
powerful cutters have been built in order to
excavate harder rock without the need for
blasting.
Trailing suction Hopper Dredger:
• A trailing suction hopper dredger (TSHD) trails its
suction pipe when working, and loads the dredge
spoil into one or more hoppers in the vessel.
•

When the hoppers are full, the TSHD sails to a
disposal area and either dumps the material through
doors in the hull or pumps the material out of the
hoppers.

• Some dredges also self-offload using drag buckets
and conveyors
Specification:
•The normal dredging vary from 10 to 30m
•The hopper capacities vary from 300-11000cubic
meter.
•Majority of these dredgers are in the range of 5003500cubic meter.
IMPACTS OF DREDGING:
• Dredging can create disturbance to aquatic
ecosystem.
• This activities have the potential to change the
environment.
• Depending upon the nature of the dredged material,
its disturbance from the sea bed may lead to changes
in the chemical composition of the water.
• As well as toxicants, the nutrient elements,
particularly nitrogen and phosphorus, which control the
rate of marine plant growth can also be released from
sediments during dredging.
Thank You.

Mais conteúdo relacionado

Mais procurados

Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...A Makwana
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling EquipmentsRajarshi Patty
 
Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating EquipmentKiran Goswami
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniquesjamali husain
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rockkamariya keyur
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compactionPrasanthi Nelloor
 
Construction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationConstruction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationSagar Radadiya
 
Road construction equipment.pptx 2
Road construction equipment.pptx 2Road construction equipment.pptx 2
Road construction equipment.pptx 2AhmedZL
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFShankar Ramasamy
 

Mais procurados (20)

Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling Equipments
 
Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating Equipment
 
Construction Equipment -Crane - Hoisting equipment
Construction Equipment -Crane - Hoisting equipmentConstruction Equipment -Crane - Hoisting equipment
Construction Equipment -Crane - Hoisting equipment
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compaction
 
Well foundation
Well foundationWell foundation
Well foundation
 
Construction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationConstruction equipments - Introduction and Classification
Construction equipments - Introduction and Classification
 
Road construction equipment.pptx 2
Road construction equipment.pptx 2Road construction equipment.pptx 2
Road construction equipment.pptx 2
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
CLAM SHELL BUCKETS
CLAM SHELL BUCKETSCLAM SHELL BUCKETS
CLAM SHELL BUCKETS
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Compaction equipment
Compaction equipmentCompaction equipment
Compaction equipment
 
Concrete equipment
Concrete equipmentConcrete equipment
Concrete equipment
 
Dredging
DredgingDredging
Dredging
 
Road machinery
Road machineryRoad machinery
Road machinery
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 

Semelhante a Dredging equipment

Offshore mining
Offshore miningOffshore mining
Offshore miningAbhiRam152
 
MODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptxMODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptxsurekha1287
 
Heavy construction equipment
Heavy construction equipmentHeavy construction equipment
Heavy construction equipmentPritesh Parmar
 
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptxvikrantsingh170151
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipmentTareq Shreehah
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Mayur Rahangdale
 
Latest Construction Equipment's
Latest Construction Equipment'sLatest Construction Equipment's
Latest Construction Equipment'sMijanur Rahman
 
chapter 4 construction equipments.pptx
chapter 4  construction equipments.pptxchapter 4  construction equipments.pptx
chapter 4 construction equipments.pptxDine38
 
construction equipment.pptx
construction equipment.pptxconstruction equipment.pptx
construction equipment.pptxkingbutu
 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)Suhaa Chine
 
labour vs machionary (cep lecture)
labour vs machionary (cep lecture)labour vs machionary (cep lecture)
labour vs machionary (cep lecture)Safiullah Khan
 
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTUVATSAL PATEL
 
Chapter 1.pptx ghghghghghghghghghghghhgh
Chapter 1.pptx ghghghghghghghghghghghhghChapter 1.pptx ghghghghghghghghghghghhgh
Chapter 1.pptx ghghghghghghghghghghghhghSauravBhattacharjee12
 
Rippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentRippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentshalomjudit3
 

Semelhante a Dredging equipment (20)

Offshore mining
Offshore miningOffshore mining
Offshore mining
 
Introduction to dredging
Introduction to dredgingIntroduction to dredging
Introduction to dredging
 
DREDGING
DREDGINGDREDGING
DREDGING
 
Dredging
DredgingDredging
Dredging
 
MODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptxMODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptx
 
Heavy construction equipment
Heavy construction equipmentHeavy construction equipment
Heavy construction equipment
 
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 
Latest Construction Equipment's
Latest Construction Equipment'sLatest Construction Equipment's
Latest Construction Equipment's
 
chapter 4 construction equipments.pptx
chapter 4  construction equipments.pptxchapter 4  construction equipments.pptx
chapter 4 construction equipments.pptx
 
construction equipment.pptx
construction equipment.pptxconstruction equipment.pptx
construction equipment.pptx
 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)
 
labour vs machionary (cep lecture)
labour vs machionary (cep lecture)labour vs machionary (cep lecture)
labour vs machionary (cep lecture)
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
 
Chapter 1.pptx ghghghghghghghghghghghhgh
Chapter 1.pptx ghghghghghghghghghghghhghChapter 1.pptx ghghghghghghghghghghghhgh
Chapter 1.pptx ghghghghghghghghghghghhgh
 
Rippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentRippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipment
 
Backhoe Dredger
Backhoe Dredger Backhoe Dredger
Backhoe Dredger
 

Último

Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesShubhangi Sonawane
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIShubhangi Sonawane
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 

Último (20)

Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 

Dredging equipment

  • 2. Definition: • Dredging is an excavation activity or operation usually carried out at least partly underwater, in shallow seas or fresh water areas with the purpose of gathering up bottom sediments and disposing of them at a different location. • In all situations the operation is undertaken by special floating plant, known as a dredger.
  • 3. Dredger: • A dredgers is a piece of equipment which can dig, transport and dump a certain amount of under water laying soil in a certain time. • The quantity of soil moved per unit of time is called Production.
  • 4. • 4 phases are: - Excavation - Lifting - Transportation -Disposal
  • 5. Why dredging? • Capital works:Creation of new facilities, such as harbour basins,deeper navigation channels etc   Infrastructure  coastal engineering  mining industry  • Navigation offshore industry Maintenance works : Maintain design depth of navigation channel and ports. • Remedial works: Careful removal of contaminated material ,reuse or relocation of the material
  • 6. Types Of Dredgers: ` • Mechanical Dredger • Hydraulic Dredger Hydraulically continuously Discontinuously Transport Via pipeline Mechanically Transport via conveyor belt Transport via grab,ship,truck
  • 8.
  • 9.
  • 10. Mechanical Dredger: In Mechanical dredgers materials conveyed by mechanical contravenes. • Bucket Ladder Dredger • Grab Dredger • Dipper/Back Hoe Dredger
  • 12.
  • 14. Working method : • The bucket ladder dredge is positioned on 6 wires. Under working conditions the dredge swings around the bow anchor. • The bow anchor line or headline can have length longer than 1000 m. • In order to avoid dragging of the wire over the soil, which results in a smaller radius, the wire is supported by a headline pontoon. • As a result of this long headline the cut width can be large as well (200 m or more).
  • 15. • The side-line winches take care of the swinging of the dredge as well as the power necessary for the cutting process. • The swing speed depends on the soil condition, the layer thickness cut. • This type of dredge is suitable for excavating soft ground, sand or gravel.
  • 16. Specification: • The size of these vessel is about 60m in length and 15m in width, having a draft of about 2.5 to 3m. • The capacity of bucket is about 1cubic meter. • The digging depth commonly extend to 1 cubic metre • The output is the range of 250cubic meter/hr
  • 18. Working method: • The dredgers can be moored by anchors or by poles (spuds) . • The capacity of a grab dredger is expressed in the volume of the grab. • Grab sizes varies between less than 1 m3 up to 200 m3. • The opening of the grab is controlled by the closing and hoisting wire or by hydraulic cylinders. • For grab dredgers the method of anchoring and the positioning system plays an important role for the effectiveness of the dredger.
  • 19. • At every pontoon position an area as wide as possible will be dredged. • The positioning is important to localize the bit of the grab.
  • 20. Specification: • The Hull is generally 30m to 60m long and 15m cross, the boom is being 15m long. • The capacity of a grab dredger is expressed in the volume of the grab. • Grab sizes varies between less than 1 m3 up to 200 m3. • The opening of the grab is controlled by the closing and hoisting wire or by hydraulic cylinders.
  • 21. Dipper or Black Hoe Dredger:
  • 22.
  • 23. Dipper or Back Hoe Dredger: • This is similar to the land operator crawler shovel. • It mounted on a Barge. • It carries a lever outer end of which, a steel bucket is attached. • The lever can rotate both about the vertical and horizontal axis. •The bottom of bucket can be opened by operating wire rope from the barge.
  • 24. • The bucket scoops out the material and after slewing, the contents of the bucket are dropped on to the barge by opening bottom plate of the bucket. Specification: • This type of dredge can dig in depths up to 15m of water. • Dipper capacity varies from 1 to 4 cubic meter and heavy capacities of about 12m3 are used in panama canal.
  • 25. Hydraulic Dredger: Hydraulic dredgers use hydraulic pumps to produce a slurry of the dredged material. • Profile or plain suction dredger • Cutter suction dredger • Trailing suction hopper dredger
  • 26. Profile or plain suction dredger:
  • 27. Plain Suction Dredger: • Dredgers are equipped with a centrifugal pump for raising mixture of soil and water to deliver the material into the transport system. • There is a plain end suction pipe, the suction head buried to material to be excavated. • These type of dredgers are well suited for free running granular material.
  • 28. Working method: • These operate by sucking through a long tube, like some vaccum cleaners but on a larger scale. • A plain suction dredger has no tool at the end of the suction pipe to disturb the material. This is often the most commonly used form of dredging
  • 29. Specification: • The Dredging depth is about 15m. • Bucket capacity is about 6cubic meter, then its used for soft material. • If a smaller capacity bucket of about 4 cubic meter, then its used for dredging hard material.
  • 31. Cutter suction Dredger: • • • A cutter-suction dredger's (CSD) suction tube has a cutting mechanism at the . suction inlet. The cutting mechanism loosens the bed material and transports it to the suction mouth. The dredged material is usually sucked up by a wear-resistant centrifugal pump and discharged either through a pipe line or to a barge.
  • 32. Cutter suction Dredger (cont…) • • Cutter-suction dredgers are most often used in geological areas consisting of hard . surface materials (for example gravel deposits or surface bedrock) where a standard suction dredger would be ineffective. In recent years, dredgers with more powerful cutters have been built in order to excavate harder rock without the need for blasting.
  • 33. Trailing suction Hopper Dredger: • A trailing suction hopper dredger (TSHD) trails its suction pipe when working, and loads the dredge spoil into one or more hoppers in the vessel. • When the hoppers are full, the TSHD sails to a disposal area and either dumps the material through doors in the hull or pumps the material out of the hoppers. • Some dredges also self-offload using drag buckets and conveyors
  • 34. Specification: •The normal dredging vary from 10 to 30m •The hopper capacities vary from 300-11000cubic meter. •Majority of these dredgers are in the range of 5003500cubic meter.
  • 35. IMPACTS OF DREDGING: • Dredging can create disturbance to aquatic ecosystem. • This activities have the potential to change the environment. • Depending upon the nature of the dredged material, its disturbance from the sea bed may lead to changes in the chemical composition of the water. • As well as toxicants, the nutrient elements, particularly nitrogen and phosphorus, which control the rate of marine plant growth can also be released from sediments during dredging.