1. Clarify & Validate the Problem
Project Opportunity Statement: Findings revealed during a May-
Dec, 2012 data collection of the 305 MXS Inspection Flight have
identified a total of 123.3 task hours resulting in delays during KC-10 A-
Check insp and 113.6 hours during C-17 HSC Insp.
O O D AO O D A
0
200
KC-10 C-17
Inspection Hrs
11/9 Non-Value Hrs
2. Break Down the Problem and Identify
Performance Gaps
11 of 26 Pre-Dock meetings missing key Mx personnel
24 of 26 Pre-Dock meetings required additional research
by MXS personnel (missing TNB/Supply information).
Avg weekly delay time for: KC-10 = 11hrs C-17 = 9hrs
O O D AO O D A
3. Set Improvement Target
Develop and implement countermeasures that will contribute
to the 20% HSC/A-Check delays initiative, by Dec 1, 2013.
O O D AO O D A
0
50
100
1-Mar
1-Apr
1-May
1-Jun
1-Jul
1-Aug
1-Sep
1-Oct
1-Nov
1-Dec
Inspection Delays
Inspection Delays
4. Determine Root Cause
20%of all HSC and A-
Checkdelays attributed to
currentManagement
processes
Personnel Process
Machine
Policy
Complacency
(not everyone
attending the Pre-
dockmeeting)
SheetMetal discrepanciesnot
evail'dprior to HSC/A-Ck
P & S holds conducts
meeting. MXS has little
voice inoutcome
TNB and Supply status
not verifiedprior to
Pre-Dockmeeting
No enforced
attendance to
Pre-DockmeetingNot enough specialists to
cover 24-7 operations (wait
to sign off write ups.
781Kwrite-up
verbage leads FL to
await HSC/A-Ck.
No standardized
pre-dockmeeting
process
AFI-21-101
Key results from RCA:
- Pre-Dock planning, attendance and process lack
standardization
- Flight line processes priorto acft accepted by
MXS are creating delays that could be avoided
O O D AO O D A
6. See Countermeasures Through
Event POC Sched Status
Generate new predock
requirements
SSgt Biggs 27-Mar-13 c/w
Generate MXSPredock
attendance requirement proced
TSgt White 27-Mar-13 c/w
Change Metals Tech shift
schedule to 24 hour coverage
MSgt Harrell 15 April13 c/w
Implement: Doc #’s and TNB
verified prior to Pre-Dock meet
TSgt White 15 April13 c/w
Implemented MXSpre-pre-dock
meeting
SMSgt Davies 15 April13
3 Jan 14
c/w
ID manning document issues
regarding KC-10 positions
Chief
Snelgrow
1 Oct 13
12 Apr 14
c/w
O O D AO O D A
5. Develop Countermeasures O O D AO O D A
7. Confirm Results & Process
Great efficiency realized with the combined efforts of Combs, Production, & DC
Pre-Dock
Meeting
Supply Number
(Parts)
Specialist
Availability
TNB Status Acft downtime
(after flying)
All required
members now
present.
Document #’s
categorized
appropriatelyand
valid
Expertise now
available 24 hrs
per day
Parts on-hand
detailedby
GO81 rep at
Pre-Dock
Flight Line
realizedseverity
of time, now
work c/w inside
hangar
Impact: Acft
Status is
known by all
Impact: 98.9%
delays reduced/
correct parts
issued
Impact: Drastic
decrease in
inspectiontime
to FMC status
Impact: Major
reduction in
DD’s returned
to flight line
Impact:
Inspectioncycle
time decreasedto
parts availability
Combs= Parts issuer DC= Dock Chief Delays reduced >20%
O O D AO O D A
8. Standardize Successful Processes
With the implementation of stardardized managerial practices, the delays
have greatly been reduced. By utilizing various AFSO21 methods the
ACFT phased inspection delays have been reduced by > 20%
 Created Benchmark achievement for other bases to emulate
 New Pre-Dock meetings are standardized by written policy
 Manning document reviewed and updated to reflect need of
assets
 All meetings are tracked by production superintendent and
sustained through documentation
 Entry into CPI-MT/approval to proceed with future events of
the project
O O D AO O D A
Team Lead:TSgt White
Team Members: Chief Snelgrow, SMSgt Bondi, MSgt Kennedy, SMSgt Evans,
Facilitors(s):(L)MSgt Patrick Muma, (CoFac) MSgt Nails, (Ob) TSgt SmithJ.
Approval Information/Signatures
Champion: Maj Szatkowski, 305 MXS/CC
Process Owner: Capt Sarrah Jones,305 MXS/MOO
USAF Problem-Solving Process
305 MXS HSC/A-Check Management Delays:
Improvement Event #1
Pre-Dock
Meeting
Supply Number
(Parts)
Specialist
Availability
TNB Status Acft downtime
(after flying)
Key members
not present.
Document #’s
not valid
Expertise not
available 24 hrs
per day
Parts on-hand
unknown at
Pre-Dock
Often several
days from last
Acft flt toMXS
accept
Impact: True
Acft Status is
Unkn at meet
Impact: Parts
needre-order and
delay duringfix
Impact: Delays
to insp, waiting
for next shift
Impact: DD’s
pushedback
to AMXS
Impact: Ineffic.
use of time,
before acft enters
hangar
VSM Highlights
-Est and enforce Pre-Dock
process
-Generate and enforce Pre-
Dock attendance by all req.
- Implemented MXS pre-pre-
dock meeting
- Implement: Doc #’s and TNB
verified prior to Pre-Dock meet
- Change Metals Tech shift
schedule to 24 hour coverage
- ID manning document
issues regarding KC-10
positions
7. Confirm Results & Process
a. How are we performing relative to the Observe phase
(Steps 1 & 2)?
b. How are we performing relative to Step 3?
c. How are we performing relative to Financial Reporting Template
projections?
d. If we are not meeting targets, do we need to return to Step 4?
- Most problemsolving “breakdowns” occur relative to improper root
cause identification
TOOLS: KPIs/Metrics, Performance Mgt, SA&D, Standard Work,
Audit
1. Clarify & Validate the Problem
a. Does this problem, when solved,help meet needs identified by the
organization?
- Is it linked to theSA&D of organization?
- Does it help satisfy customer needs (VOC)?
b. Does this problem, when solved,address key issues identified
during SWOT analysis?
c. Has this problem been identified and directed by a Value Stream
Map at the appropriate level?
- What does the “FutureState” need?
- What resources have been identified to address this issue?
d. What opportunities were identified or observed by the process or
problem area “walk”?
- Will addressing or improving theseissues deliver results that relate to
#a or #b?
- Will addressing or improving this problem deliver the desired future
statefrom #c?
TOOLS: SA&D, Voice of Customer, VSM, Go & See
2. Break Down the Problem/Identify
Performance Gaps
a. Does the problem require more analysis or does leadership have
enough information to execute a solution?
- Is this simply a leadership directive?
b. If more data is needed,how do we measure performance now?
- What are the KPIs? What is the performance gap?
c. Does other“non-existent” data need to be gathered?
d. What does the data indicate are the potential root causes?
e. Does the data review indicate a bottleneck or constraint?
TOOLS: KPI/Metrics, Performance Gap Analysis,Bottleneck Analysis
3. Set Improvement Target
a. Is the improvement target measurable? Is it concrete? Is it
challenging?
b. Is the target “Output Oriented”?
- What is the desired output?
- Should be “things to achieve”; should avoid “things to do”
-- Will be addressed by Action Plans (Step 5)
c. The desired target should:
- Do what? By how much? By when?
d. If it is a Process Problem, what is the future state?
- How will it be realized?
TOOLS: Ideal State, Future State Mapping,B-SMART
4. Determine Root Cause
a. What root cause analysis tools are necessary?
- Why are these tools necessary?
- What benefit will be gained by using them?
- Who will need to be involved in theroot cause analysis?
-- 10 heads are better than one
-- Remember “cultural” issues related to problem
b. What is (are) the root cause(s)according to the tools?
c. How will the root cause be addressed?
d. Will addressing these address the performance gap?
e. Can the problem be turned on or off by addressing the root cause?
f. Does the root cause make sense if the 5 Whys are worked in reverse?
- Working in reverse, say “therefore” between each of the“whys”
TOOLS: 5 Whys,Brainstorming, Pareto, Affinity, Fishbone,
Control Charts
6. See Countermeasures Through
a. Which philosophy best prescribes tools that address root cause(s)?
b. Which tools best address root cause(s)?
c. Which method for implementation fits the tool and improvement
need?
- Rapid Improvement Event?
- Improvement Project?
- Point Improvement or “Just Do It”?
d. If RIE or Project, create “Charter” and communicate
e. What training or education is needed? By Whom?
TOOLS: 6S & Visual Mgt, Standard Work, Cell Design, Variation
Reduction, Error Proofing, Quick Changeover, TPM, RIE
5. Develop Countermeasures
a. Develop potential countermeasures
- Tools and philosophies from Lean, TOC, 6 Sigma and BPR as
appropriate
b. Select the most practical and effective countermeasures
c. Build consensuswith others by involving all stakeholders
appropriately
- Communicate, communicate, communicate
d. Create clear and detailed action plan
- B-SMART actions
- Reference Facilitation Techniques as appropriate
TOOLS: A3, Action Plans, Timelines, Financial Reporting Template
8. Standardize Successful Processes
a. What is needed to Standardize Improvements?
- Tech Order changes?
- Air Force Instruction changes?
- Official Instruction changes?
b. How should improvements and lessons learned be communicated?
- Continuous Process Improvement-Mgt Tool (PowerSteering)
- Key meetings?
c. Were other opportunities or problems identified by the Problem
Solving Process?
- Restart OODA Loop
TOOLS: Checkpoints/Standardization Table, Report Out Theme Story,
Broad Implementation, CPI Mgt Tool
OODA – Observe, Orient, Decide, & Act
8-Step Problem Solving Process
Approval Information/SignaturesUSAF Problem-Solving Process
& Related Toolsets

Mais conteúdo relacionado

Mais procurados

PDCA Problem Solving Technique & Tools
PDCA Problem Solving Technique & ToolsPDCA Problem Solving Technique & Tools
PDCA Problem Solving Technique & Tools
Flevy.com Best Practices
 
8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training
Bryan Len
 

Mais procurados (20)

Presentation On G8D
Presentation On G8DPresentation On G8D
Presentation On G8D
 
Basic 8D Problem Solving Tools & Methods - Part 2
Basic 8D Problem Solving Tools & Methods - Part 2Basic 8D Problem Solving Tools & Methods - Part 2
Basic 8D Problem Solving Tools & Methods - Part 2
 
8 Disciplines (8D) Training
8 Disciplines (8D) Training8 Disciplines (8D) Training
8 Disciplines (8D) Training
 
Applying PDCA, A3 Thinking & Problem Solving
Applying PDCA, A3 Thinking & Problem SolvingApplying PDCA, A3 Thinking & Problem Solving
Applying PDCA, A3 Thinking & Problem Solving
 
Dmaic
DmaicDmaic
Dmaic
 
Basic 8D Problem Solving Tools & Methods - Part 1
Basic 8D Problem Solving Tools & Methods - Part 1Basic 8D Problem Solving Tools & Methods - Part 1
Basic 8D Problem Solving Tools & Methods - Part 1
 
Useful Tools for Problem Solving by Operational Excellence Consulting
Useful Tools for Problem Solving by Operational Excellence ConsultingUseful Tools for Problem Solving by Operational Excellence Consulting
Useful Tools for Problem Solving by Operational Excellence Consulting
 
Quality Management Analysis PowerPoint Presentation Slides
Quality Management Analysis PowerPoint Presentation SlidesQuality Management Analysis PowerPoint Presentation Slides
Quality Management Analysis PowerPoint Presentation Slides
 
8D Problem Solving Poster
8D Problem Solving Poster8D Problem Solving Poster
8D Problem Solving Poster
 
Metrics-Based Process Mapping
Metrics-Based Process MappingMetrics-Based Process Mapping
Metrics-Based Process Mapping
 
TPM: Focused Improvement (Kobetsu Kaizen) Poster
TPM: Focused Improvement (Kobetsu Kaizen) PosterTPM: Focused Improvement (Kobetsu Kaizen) Poster
TPM: Focused Improvement (Kobetsu Kaizen) Poster
 
PDCA Problem Solving Technique & Tools
PDCA Problem Solving Technique & ToolsPDCA Problem Solving Technique & Tools
PDCA Problem Solving Technique & Tools
 
Problem solving preview
Problem solving previewProblem solving preview
Problem solving preview
 
8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training
 
Root Cause Analysis
Root Cause AnalysisRoot Cause Analysis
Root Cause Analysis
 
Lean Six Sigma Overview (presentation version)
Lean Six Sigma Overview (presentation version)Lean Six Sigma Overview (presentation version)
Lean Six Sigma Overview (presentation version)
 
#8 Root Cause Analysis
#8 Root Cause Analysis#8 Root Cause Analysis
#8 Root Cause Analysis
 
8D analysis presentation
8D analysis presentation8D analysis presentation
8D analysis presentation
 
Lean 6 Sigma Training | By ex-Deloitte & McKinsey Consultants
Lean 6 Sigma Training | By ex-Deloitte & McKinsey ConsultantsLean 6 Sigma Training | By ex-Deloitte & McKinsey Consultants
Lean 6 Sigma Training | By ex-Deloitte & McKinsey Consultants
 
Problem solving techniques
Problem solving techniquesProblem solving techniques
Problem solving techniques
 

Semelhante a 8-step Problem Solving (Management)V2 (2)

Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_Payroll
Balaguru SP
 

Semelhante a 8-step Problem Solving (Management)V2 (2) (20)

Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summary
 
PROJECT STORYBOARD: Reducing Software Bug Fix Lead Time From 25 to 15 days
PROJECT STORYBOARD: Reducing Software Bug Fix Lead Time From 25 to 15 daysPROJECT STORYBOARD: Reducing Software Bug Fix Lead Time From 25 to 15 days
PROJECT STORYBOARD: Reducing Software Bug Fix Lead Time From 25 to 15 days
 
Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_Payroll
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
 
The Effective Management of Time
The Effective Management of TimeThe Effective Management of Time
The Effective Management of Time
 
Puneet Green Belt(13th feb).pptx
Puneet Green Belt(13th feb).pptxPuneet Green Belt(13th feb).pptx
Puneet Green Belt(13th feb).pptx
 
Rita's Process Chart
Rita's Process ChartRita's Process Chart
Rita's Process Chart
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
1B project MS V2
1B project MS V21B project MS V2
1B project MS V2
 
Test Estimation
Test Estimation Test Estimation
Test Estimation
 
D07 Project Charter
D07 Project CharterD07 Project Charter
D07 Project Charter
 
Chapter 15; Short-Term Scheduling
Chapter 15; Short-Term SchedulingChapter 15; Short-Term Scheduling
Chapter 15; Short-Term Scheduling
 
Pmp6
Pmp6Pmp6
Pmp6
 
Thomas Axen - Lean Kaizen Applied To Software Testing - EuroSTAR 2010
Thomas Axen - Lean Kaizen Applied To Software Testing - EuroSTAR 2010Thomas Axen - Lean Kaizen Applied To Software Testing - EuroSTAR 2010
Thomas Axen - Lean Kaizen Applied To Software Testing - EuroSTAR 2010
 
Quality improvement
Quality improvementQuality improvement
Quality improvement
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
8 D Report
8 D Report8 D Report
8 D Report
 
PGP New Product Generation Project 2003
PGP New Product Generation Project 2003PGP New Product Generation Project 2003
PGP New Product Generation Project 2003
 
OMTEC-2015_Mazzeo_BIQ.pdf
OMTEC-2015_Mazzeo_BIQ.pdfOMTEC-2015_Mazzeo_BIQ.pdf
OMTEC-2015_Mazzeo_BIQ.pdf
 

Mais de Steve Nails

Maintennace Squadron Process Improvement Tracking Tool
Maintennace Squadron Process Improvement Tracking ToolMaintennace Squadron Process Improvement Tracking Tool
Maintennace Squadron Process Improvement Tracking Tool
Steve Nails
 
Ground Support Equipment Efficiency & Innovation Project
Ground Support Equipment Efficiency & Innovation ProjectGround Support Equipment Efficiency & Innovation Project
Ground Support Equipment Efficiency & Innovation Project
Steve Nails
 
CCAF Instr Tech_Mil Science
CCAF Instr Tech_Mil ScienceCCAF Instr Tech_Mil Science
CCAF Instr Tech_Mil Science
Steve Nails
 
CCAF Professional Manager
CCAF Professional ManagerCCAF Professional Manager
CCAF Professional Manager
Steve Nails
 
CCAF A.A.S. AGE Tech
CCAF A.A.S. AGE TechCCAF A.A.S. AGE Tech
CCAF A.A.S. AGE Tech
Steve Nails
 
Process Improvement Tng Cert
Process Improvement Tng CertProcess Improvement Tng Cert
Process Improvement Tng Cert
Steve Nails
 
8_STEP Problem Solving Tng Cert
8_STEP Problem Solving Tng Cert8_STEP Problem Solving Tng Cert
8_STEP Problem Solving Tng Cert
Steve Nails
 

Mais de Steve Nails (10)

Maintennace Squadron Process Improvement Tracking Tool
Maintennace Squadron Process Improvement Tracking ToolMaintennace Squadron Process Improvement Tracking Tool
Maintennace Squadron Process Improvement Tracking Tool
 
Ground Support Equipment Efficiency & Innovation Project
Ground Support Equipment Efficiency & Innovation ProjectGround Support Equipment Efficiency & Innovation Project
Ground Support Equipment Efficiency & Innovation Project
 
CCAF Instr Tech_Mil Science
CCAF Instr Tech_Mil ScienceCCAF Instr Tech_Mil Science
CCAF Instr Tech_Mil Science
 
AMU HR Cert
AMU HR CertAMU HR Cert
AMU HR Cert
 
CCAF Professional Manager
CCAF Professional ManagerCCAF Professional Manager
CCAF Professional Manager
 
CCAF A.A.S. AGE Tech
CCAF A.A.S. AGE TechCCAF A.A.S. AGE Tech
CCAF A.A.S. AGE Tech
 
AFSO21 Green Belt tng cert
AFSO21 Green Belt tng certAFSO21 Green Belt tng cert
AFSO21 Green Belt tng cert
 
Process Improvement Tng Cert
Process Improvement Tng CertProcess Improvement Tng Cert
Process Improvement Tng Cert
 
AFSO Tng Cert
AFSO Tng CertAFSO Tng Cert
AFSO Tng Cert
 
8_STEP Problem Solving Tng Cert
8_STEP Problem Solving Tng Cert8_STEP Problem Solving Tng Cert
8_STEP Problem Solving Tng Cert
 

8-step Problem Solving (Management)V2 (2)

  • 1. 1. Clarify & Validate the Problem Project Opportunity Statement: Findings revealed during a May- Dec, 2012 data collection of the 305 MXS Inspection Flight have identified a total of 123.3 task hours resulting in delays during KC-10 A- Check insp and 113.6 hours during C-17 HSC Insp. O O D AO O D A 0 200 KC-10 C-17 Inspection Hrs 11/9 Non-Value Hrs 2. Break Down the Problem and Identify Performance Gaps 11 of 26 Pre-Dock meetings missing key Mx personnel 24 of 26 Pre-Dock meetings required additional research by MXS personnel (missing TNB/Supply information). Avg weekly delay time for: KC-10 = 11hrs C-17 = 9hrs O O D AO O D A 3. Set Improvement Target Develop and implement countermeasures that will contribute to the 20% HSC/A-Check delays initiative, by Dec 1, 2013. O O D AO O D A 0 50 100 1-Mar 1-Apr 1-May 1-Jun 1-Jul 1-Aug 1-Sep 1-Oct 1-Nov 1-Dec Inspection Delays Inspection Delays 4. Determine Root Cause 20%of all HSC and A- Checkdelays attributed to currentManagement processes Personnel Process Machine Policy Complacency (not everyone attending the Pre- dockmeeting) SheetMetal discrepanciesnot evail'dprior to HSC/A-Ck P & S holds conducts meeting. MXS has little voice inoutcome TNB and Supply status not verifiedprior to Pre-Dockmeeting No enforced attendance to Pre-DockmeetingNot enough specialists to cover 24-7 operations (wait to sign off write ups. 781Kwrite-up verbage leads FL to await HSC/A-Ck. No standardized pre-dockmeeting process AFI-21-101 Key results from RCA: - Pre-Dock planning, attendance and process lack standardization - Flight line processes priorto acft accepted by MXS are creating delays that could be avoided O O D AO O D A 6. See Countermeasures Through Event POC Sched Status Generate new predock requirements SSgt Biggs 27-Mar-13 c/w Generate MXSPredock attendance requirement proced TSgt White 27-Mar-13 c/w Change Metals Tech shift schedule to 24 hour coverage MSgt Harrell 15 April13 c/w Implement: Doc #’s and TNB verified prior to Pre-Dock meet TSgt White 15 April13 c/w Implemented MXSpre-pre-dock meeting SMSgt Davies 15 April13 3 Jan 14 c/w ID manning document issues regarding KC-10 positions Chief Snelgrow 1 Oct 13 12 Apr 14 c/w O O D AO O D A 5. Develop Countermeasures O O D AO O D A 7. Confirm Results & Process Great efficiency realized with the combined efforts of Combs, Production, & DC Pre-Dock Meeting Supply Number (Parts) Specialist Availability TNB Status Acft downtime (after flying) All required members now present. Document #’s categorized appropriatelyand valid Expertise now available 24 hrs per day Parts on-hand detailedby GO81 rep at Pre-Dock Flight Line realizedseverity of time, now work c/w inside hangar Impact: Acft Status is known by all Impact: 98.9% delays reduced/ correct parts issued Impact: Drastic decrease in inspectiontime to FMC status Impact: Major reduction in DD’s returned to flight line Impact: Inspectioncycle time decreasedto parts availability Combs= Parts issuer DC= Dock Chief Delays reduced >20% O O D AO O D A 8. Standardize Successful Processes With the implementation of stardardized managerial practices, the delays have greatly been reduced. By utilizing various AFSO21 methods the ACFT phased inspection delays have been reduced by > 20%  Created Benchmark achievement for other bases to emulate  New Pre-Dock meetings are standardized by written policy  Manning document reviewed and updated to reflect need of assets  All meetings are tracked by production superintendent and sustained through documentation  Entry into CPI-MT/approval to proceed with future events of the project O O D AO O D A Team Lead:TSgt White Team Members: Chief Snelgrow, SMSgt Bondi, MSgt Kennedy, SMSgt Evans, Facilitors(s):(L)MSgt Patrick Muma, (CoFac) MSgt Nails, (Ob) TSgt SmithJ. Approval Information/Signatures Champion: Maj Szatkowski, 305 MXS/CC Process Owner: Capt Sarrah Jones,305 MXS/MOO USAF Problem-Solving Process 305 MXS HSC/A-Check Management Delays: Improvement Event #1 Pre-Dock Meeting Supply Number (Parts) Specialist Availability TNB Status Acft downtime (after flying) Key members not present. Document #’s not valid Expertise not available 24 hrs per day Parts on-hand unknown at Pre-Dock Often several days from last Acft flt toMXS accept Impact: True Acft Status is Unkn at meet Impact: Parts needre-order and delay duringfix Impact: Delays to insp, waiting for next shift Impact: DD’s pushedback to AMXS Impact: Ineffic. use of time, before acft enters hangar VSM Highlights -Est and enforce Pre-Dock process -Generate and enforce Pre- Dock attendance by all req. - Implemented MXS pre-pre- dock meeting - Implement: Doc #’s and TNB verified prior to Pre-Dock meet - Change Metals Tech shift schedule to 24 hour coverage - ID manning document issues regarding KC-10 positions
  • 2. 7. Confirm Results & Process a. How are we performing relative to the Observe phase (Steps 1 & 2)? b. How are we performing relative to Step 3? c. How are we performing relative to Financial Reporting Template projections? d. If we are not meeting targets, do we need to return to Step 4? - Most problemsolving “breakdowns” occur relative to improper root cause identification TOOLS: KPIs/Metrics, Performance Mgt, SA&D, Standard Work, Audit 1. Clarify & Validate the Problem a. Does this problem, when solved,help meet needs identified by the organization? - Is it linked to theSA&D of organization? - Does it help satisfy customer needs (VOC)? b. Does this problem, when solved,address key issues identified during SWOT analysis? c. Has this problem been identified and directed by a Value Stream Map at the appropriate level? - What does the “FutureState” need? - What resources have been identified to address this issue? d. What opportunities were identified or observed by the process or problem area “walk”? - Will addressing or improving theseissues deliver results that relate to #a or #b? - Will addressing or improving this problem deliver the desired future statefrom #c? TOOLS: SA&D, Voice of Customer, VSM, Go & See 2. Break Down the Problem/Identify Performance Gaps a. Does the problem require more analysis or does leadership have enough information to execute a solution? - Is this simply a leadership directive? b. If more data is needed,how do we measure performance now? - What are the KPIs? What is the performance gap? c. Does other“non-existent” data need to be gathered? d. What does the data indicate are the potential root causes? e. Does the data review indicate a bottleneck or constraint? TOOLS: KPI/Metrics, Performance Gap Analysis,Bottleneck Analysis 3. Set Improvement Target a. Is the improvement target measurable? Is it concrete? Is it challenging? b. Is the target “Output Oriented”? - What is the desired output? - Should be “things to achieve”; should avoid “things to do” -- Will be addressed by Action Plans (Step 5) c. The desired target should: - Do what? By how much? By when? d. If it is a Process Problem, what is the future state? - How will it be realized? TOOLS: Ideal State, Future State Mapping,B-SMART 4. Determine Root Cause a. What root cause analysis tools are necessary? - Why are these tools necessary? - What benefit will be gained by using them? - Who will need to be involved in theroot cause analysis? -- 10 heads are better than one -- Remember “cultural” issues related to problem b. What is (are) the root cause(s)according to the tools? c. How will the root cause be addressed? d. Will addressing these address the performance gap? e. Can the problem be turned on or off by addressing the root cause? f. Does the root cause make sense if the 5 Whys are worked in reverse? - Working in reverse, say “therefore” between each of the“whys” TOOLS: 5 Whys,Brainstorming, Pareto, Affinity, Fishbone, Control Charts 6. See Countermeasures Through a. Which philosophy best prescribes tools that address root cause(s)? b. Which tools best address root cause(s)? c. Which method for implementation fits the tool and improvement need? - Rapid Improvement Event? - Improvement Project? - Point Improvement or “Just Do It”? d. If RIE or Project, create “Charter” and communicate e. What training or education is needed? By Whom? TOOLS: 6S & Visual Mgt, Standard Work, Cell Design, Variation Reduction, Error Proofing, Quick Changeover, TPM, RIE 5. Develop Countermeasures a. Develop potential countermeasures - Tools and philosophies from Lean, TOC, 6 Sigma and BPR as appropriate b. Select the most practical and effective countermeasures c. Build consensuswith others by involving all stakeholders appropriately - Communicate, communicate, communicate d. Create clear and detailed action plan - B-SMART actions - Reference Facilitation Techniques as appropriate TOOLS: A3, Action Plans, Timelines, Financial Reporting Template 8. Standardize Successful Processes a. What is needed to Standardize Improvements? - Tech Order changes? - Air Force Instruction changes? - Official Instruction changes? b. How should improvements and lessons learned be communicated? - Continuous Process Improvement-Mgt Tool (PowerSteering) - Key meetings? c. Were other opportunities or problems identified by the Problem Solving Process? - Restart OODA Loop TOOLS: Checkpoints/Standardization Table, Report Out Theme Story, Broad Implementation, CPI Mgt Tool OODA – Observe, Orient, Decide, & Act 8-Step Problem Solving Process Approval Information/SignaturesUSAF Problem-Solving Process & Related Toolsets