P3 AGREEMENTS
Stephanie W. Kam, Esq.
14 November 2016
Toronto
Typical P3 Structure
2
Government
Private Entity
Contractor Operator
Shareholders Lenders
Concession
Agreement
Shareholders
Agreement
Financing
Agreement
Constructions
Contract
Operations
Contract
Direct
Agreement
Typical P3 Agreements
Purpose
1. Specify the Relationship between the
government and the private entity
2. Define the Responsibilities of both parties
3. Identify the Requirements necessary to
efficiently and effectively perform tasks
The Concession Agreement
3
• Government’s perspective:
– Defines the service delivery by the private entity
– Fixes the budget for a public facility
– Ensures value for money
• Private entity’s perspective:
– Defines compensation for service delivery
– Enables long-term planning
– Minimizes political interference
– Provides clarity on expectations of the government
4
The Concession Agreement
• Scope
– Description of physical area and rights
• Duration
– Period for which concession is being granted
• Termination
– Material breach
– Insolvency
– Misrepresentations
– Assignment
– Payment default
– Failure to comply with arbitral award
5
Principal Contract Terms
• Government’s Obligations
– Granting right of access to site
– Providing licences, permits, approvals
– Procuring leases, easements, rights of way
– Passing legislation
– Availability payment and/or user fees
• Private Entity’s Obligations
– Financing, construction, operations, maintenance
– Compliance with applicable legislation
– Minimum number of national citizens (if applicable)
– Concession fees (if applicable)
6
Principal Contract Terms
• Force Majeure
– General description of events
– Risk shared between the parties
– Mitigation of force majeure events
– Extension of concession, cap?
• Change in Law
– Extension of concession
– Grace period
• Governing Law
• Dispute Resolution
7
Principal Contract Terms
Thank you
Stephanie Kam
skam@cpcs.ca
8

Mais conteúdo relacionado

Mais procurados

Project Financing
Project FinancingProject Financing
Project Financingkcbradley
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesCNC
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Analytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP ProjectsAnalytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP ProjectsSugiharto TuPiichai
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...
Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...
Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...San Diego County Water Authority
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 

Mais procurados (20)

Project Financing
Project FinancingProject Financing
Project Financing
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Analytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP ProjectsAnalytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP Projects
 
Epc contracts-in-the-power-sector
Epc contracts-in-the-power-sectorEpc contracts-in-the-power-sector
Epc contracts-in-the-power-sector
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...
Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...
Overview of Key Terms for a Water Purchase Agreement between the San Diego Co...
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 

Semelhante a P3 Fundamentals Seminar - P3 Agreements

#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahi#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahiSN Panigrahi, PMP
 
LEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and bestLEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and best2cd
 
The ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsThe ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsAnatoly Darov, P.E.
 
Texas Promulgated Contract Forms
Texas Promulgated Contract FormsTexas Promulgated Contract Forms
Texas Promulgated Contract FormsPeggy Santmyer
 
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...Kullarat Phongsathaporn
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar
 
corporate legal environment (contract).docx
corporate legal environment (contract).docxcorporate legal environment (contract).docx
corporate legal environment (contract).docxDoon Business School
 
Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6KHogan62
 
Web program slides (2) (2)
Web program slides (2) (2)Web program slides (2) (2)
Web program slides (2) (2)Carol Buckmann
 
NCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations articleNCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations articleLeona Charles
 
Essential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key InclusionsEssential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key InclusionsezLandlordForms
 
Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015SDMinBC
 
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...SN Panigrahi, PMP
 
Breach of contract (1)
Breach of contract (1)Breach of contract (1)
Breach of contract (1)Dr.Aravind TS
 
Running Head ELEMENTS OF A CONTRACT 1 .docx
Running Head ELEMENTS OF A CONTRACT   1            .docxRunning Head ELEMENTS OF A CONTRACT   1            .docx
Running Head ELEMENTS OF A CONTRACT 1 .docxtodd271
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Dr. Zaid Mahayni
 

Semelhante a P3 Fundamentals Seminar - P3 Agreements (20)

#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahi#How to Terminate a contract# By SN panigrahi
#How to Terminate a contract# By SN panigrahi
 
LEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and bestLEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and best
 
The ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsThe ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and Towns
 
Texas Promulgated Contract Forms
Texas Promulgated Contract FormsTexas Promulgated Contract Forms
Texas Promulgated Contract Forms
 
Ac 11
Ac 11Ac 11
Ac 11
 
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
A16: TFA and SEC | Negotiating contracts and FinTech Laws and Regulations (5 ...
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_Rwanda
 
corporate legal environment (contract).docx
corporate legal environment (contract).docxcorporate legal environment (contract).docx
corporate legal environment (contract).docx
 
Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6Contracts 101 PJM400 Mod6
Contracts 101 PJM400 Mod6
 
Web program slides (2) (2)
Web program slides (2) (2)Web program slides (2) (2)
Web program slides (2) (2)
 
Evergreen Clause Fundamentals
Evergreen Clause FundamentalsEvergreen Clause Fundamentals
Evergreen Clause Fundamentals
 
NCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations articleNCMA Fart Part 49- terminations article
NCMA Fart Part 49- terminations article
 
Essential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key InclusionsEssential Elements for Montana Lease Agreements: Key Inclusions
Essential Elements for Montana Lease Agreements: Key Inclusions
 
Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015Sdm in bc final report ppt march 2015
Sdm in bc final report ppt march 2015
 
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
#GST on Penalties & Liquidated Damages Levied by Govt. or Local Authorities# ...
 
Ac 17
Ac 17Ac 17
Ac 17
 
Breach of contract (1)
Breach of contract (1)Breach of contract (1)
Breach of contract (1)
 
Running Head ELEMENTS OF A CONTRACT 1 .docx
Running Head ELEMENTS OF A CONTRACT   1            .docxRunning Head ELEMENTS OF A CONTRACT   1            .docx
Running Head ELEMENTS OF A CONTRACT 1 .docx
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
 
Nce603 mod unit4
Nce603 mod unit4Nce603 mod unit4
Nce603 mod unit4
 

P3 Fundamentals Seminar - P3 Agreements

  • 1. P3 AGREEMENTS Stephanie W. Kam, Esq. 14 November 2016 Toronto
  • 2. Typical P3 Structure 2 Government Private Entity Contractor Operator Shareholders Lenders Concession Agreement Shareholders Agreement Financing Agreement Constructions Contract Operations Contract Direct Agreement Typical P3 Agreements
  • 3. Purpose 1. Specify the Relationship between the government and the private entity 2. Define the Responsibilities of both parties 3. Identify the Requirements necessary to efficiently and effectively perform tasks The Concession Agreement 3
  • 4. • Government’s perspective: – Defines the service delivery by the private entity – Fixes the budget for a public facility – Ensures value for money • Private entity’s perspective: – Defines compensation for service delivery – Enables long-term planning – Minimizes political interference – Provides clarity on expectations of the government 4 The Concession Agreement
  • 5. • Scope – Description of physical area and rights • Duration – Period for which concession is being granted • Termination – Material breach – Insolvency – Misrepresentations – Assignment – Payment default – Failure to comply with arbitral award 5 Principal Contract Terms
  • 6. • Government’s Obligations – Granting right of access to site – Providing licences, permits, approvals – Procuring leases, easements, rights of way – Passing legislation – Availability payment and/or user fees • Private Entity’s Obligations – Financing, construction, operations, maintenance – Compliance with applicable legislation – Minimum number of national citizens (if applicable) – Concession fees (if applicable) 6 Principal Contract Terms
  • 7. • Force Majeure – General description of events – Risk shared between the parties – Mitigation of force majeure events – Extension of concession, cap? • Change in Law – Extension of concession – Grace period • Governing Law • Dispute Resolution 7 Principal Contract Terms