Traffic
Impact
Accessment
Traffic Impact Assessment or Traffic
Impact Analysis (TIA) is the effect of
the proposed project traffic on the
existing surrounding and road.
Presentation By
STUDENT | PLACK SOKHIT | M-TIE
Submitted to
DR | PHUN VENG KHEANG | DECEMBER | 23
STANDARD DEFINITIONS
Traffic impact accessment or Traffic Impact Analysis (TIA)
is the effect of the proposed project traffic on the existing surrounding and road.
Speed
Speed: The rate of motion or individual vehicles of a traffic stream. It is measured in meters
per second or kilometers per hour.
Volume
Volume: The number of vehicles at a given point on a road during a designated time
interval.
Time means Speed
Time means Speed: It is the mean speed of vehicles observed at a point on the road over a
period of time. 𝑉 =
𝑑
𝑡
Space mean speed
Space mean speed: It is the mean speed of vehicles in a traffic stream at any instant of time
over a certain length of the road. 𝑺𝑴𝑺 =
𝒅
𝒕
𝒏
Density
Density: It is the number of vehicles occupying in a unit length of a road at an instant of
time. The unit length is generally one kilometer
Capacity
Capacity: It is defined as the maximum hourly volume (vehicle per hour) at which vehicles
can reasonably be expected to traverse a point or uniform section of lane or roadways
during a given time period under prevailing roadways, traffic and control conditions.
Peak hour factor
Peak hour factor: It is defined as the traffic volume during peak hour expressed as a
percentage of average daily traffic. The peak hour volume in this case is taken as the highest
hourly volume based on actual traffic counts.
Presentation By
STUDENT | PLACK SOKHIT | M-TIE
Submitted to
DR | PHUN VENG KHEANG | DECEMBER | 23
IMPORTANT TERMS
Volume-Demand-to-Capacity Ratio (V/C):
It is a measure that reflects mobility and quality of travel
of a facility or a section of a facility. It compares roadway
demand (vehicle volumes) with roadway supply (carrying
capacity). For example, a V/C of 1.00 indicates the
roadway facility is operating at its capacity. It is a
common performance measure and is widely used in
transportation studies
PCU – Passenger Car Unit or ECS –
Equivalent Car Space:
It is the unit used for the conversion of different types of
vehicles on the road into a single unit for the ease of
calculation of the capacity of the road.
LoS – Level of Service
It is the measure of the current level of a particular
infrastructure and direct representation of the Volume to
Capacity Ratio, ranging from A to F.
Vehicle Type PCU/ECS
Factor
2 Wheeler 0.5
Car/Jeep/Taxi 1
Auto Rickshaw 1
LCV 1.5
Buses/2-Axle 3
Trucks-3 Axle 4
Trailer 5
Level of
Service
V/C Ratio
Description
2 Wheeler <0.3 Free Flow
Car/Jeep/Taxi
0.3 - 0.5
Reasonably Free
Flow
Auto Rickshaw 0.5 - 0.7 Stable Flow
LCV
0.7 - 0.9
Approaching
unstable Flow
Buses/2-Axle 1 Unstable Flow
Trucks-3 Axle >1 Forced Flow
What is TIA?
Traffic Impact Assessment
TIA is an important tool used to determine the transportation
and traffic impact of a proposed site development project
(upon full development) on the surrounding traffic and
transportation systems.Listen wie diese hier:
● It identifies the need for mitigation measures for a
transportation system to reduce congestion, as well as to
maintain or improve road safety.
● Local Authorities will use TIA as basic for assessing and
apportioning a developer’s contribution to road
improvements.
● Local Authorities also will use TIA to evaluate Traffic
Management Plan proposals.
● Provides necessary technical input to other relevant
reports such as Environmental Impact Assessment , Social
Impact Assessment, Development Plan ( Structure and
Local Plan), Transport Master Plan and the Road Safety
Audits.
WHY DO WE NEED TIA?
To offer
alternatives
Solution to traffic
improvement as well
as measures for the
road users.
To obtain the degree of control
At access requested by the
private/ government entities
To determine what type
of access required to be
considered and construction
To predetermine
future expansion
if its required 1
4
2
3
Level of Service (LOS)
LOS
60
B.NO DELAYS
No congestion
Reasonably free
flow,but speed depands
on Traffic flow
30
E.MINIMAL
DELAYS
Severe congestion
Very unstable flow,
possible short stoppages
70
A.NO DELAYS
No Congestion ,Free flow
with low traffic volumes
and high speeds
50
C.MINIMA
L DELAYS
Moderate congestion
Unstable flow;
Restricted drivers
chosen speed
30
F.SIGNIFICAT
DELAYS
Extreme congestion
Unacceptable
congestion ,stop-and-go
traffic; forced flow
40
D.MINIMAL
DELAYS
Moderate congestion
Unstable flow ; Restricted
drivers chosen speed
Level of Service
LOS provides an indication or measure
of the operational condition of the facility
concerned.
A range from “A” to “F” is
applicable, LOS “A” represents an
excellent level of operational
condition, while LOS “F” an
undesirable, exceedingly congested
and failed situation.
Reference: Road Traffic Volume Malaysia (RVTM) 2018
No Delays
<10 Delay per
vehicle(second)
Highest quality of service. Free traffic
flow with few restriction on
maneuverability or speed
LEVEL OF SERVICE (LOS) for Unsignalized Intersections
10-15 Delay per
vehicle(second)
Stable traffic flow. Speed becoming
slightly restricted. Low restricted
on maneuverability
15-25 Delay per
vehicle(second)
Stable traffic flow, but less
freedom to select speed,
change lanes or pass
25-35 Delay per
vehicle(second)
Traffic flow becoming unstable.
Speeds subject to sudden change.
Passing is difficult
35-50 Delay per
vehicle(second)
Unstable traffic flow.
Speeds change quickly and
maneuverability is low
>50 Delay per
vehicle(second)
Heavily congested traffic.
Demand exceeds capacity
and speeds vary greatly.
Very Short Delay
Minimal Delays
Minimal Delays
Significant Delays
Considerable
Delays
Delay per vehicle(second)
<10
Delay per vehicle(second)
11-20
Delay per vehicle(second)
21-35
Delay per vehicle(second)
36-55
Delay per vehicle(second)
56-80
Traffic Signal Condition
LOS
FACTOR
AFFECTING
LOS
OF
SIGNALIZED
INTERSECTIONS
Geometric Condition
Traffic Condition
 Signal Coordination
 Cycle Length
 Protected left turn
 Timing
 Pre-timed or Traffic
activated signal
 Ect.
 Signal Coordination
 Cycle Length
 Protected left turn
 Percent of truck
traffic
 Number of
pedestrian
 Etc..
Delay per vehicle(second)
>80
A
B
C
D
E
F
TRAFFIC IMPACT ASSESSMENT (TIA) PROCESS
FLOW
6
Collate existing data and
information
2 Architect/Town Planner
8
5
Discussion to determine
the scope, study area
and study methodology
1
Developer
3
Local Authority
7
Traffic Study
4 Appointment of a
Transport Engineer
9
Review the original layout
plan and propose any
improvement to the client
and land use.
Analyses:
 Trip generation
 Model split
 Trip distribution
 Trip assignment
 Analyses of LOS
 Problem to alleviate
or reduce the
identified probem
Part 1: Identification of site context and road
inventory
Site Name Distance from the proposed
project
● Nearest Arterial Road
● Nearest Sub Arterial
Road
● Nearest Railway Station
● Nearest Bus Station
 The hierarchy in terms of the network of roads is to ensure scale and efficient circulation of traffic. To achieve this,
through traffic routes are not be used for direct access to buildings or even to minor roads serving the buildings,
because in that case not only the capacity of the through routes will be reduced but the intersections will also be
unsafe.
 The principal factors considered in designation roads into appropriate classifications are the existing and proposed
land uses, overall travel demand, pattern of movement by various modes of transportation safety of traffic,
environmental considerations etc.
 The major Arterial, Sub-arterial and Collector Roads need to be identified in order to calculate the exact traffic
impact of the project.
Part 2: TRAFFIC SURVEY
Part 3: PEAK HOUR TRAFFIC, CAPACITY ANALYSIS AND FUTURE PROJECTION
Part 4: ESTIMATING PEAK HOUR TRAFFIC GENERATED BY PROPOSED PROJECT
Trip generation and forecasting
Four step model for demand assessment
 Trip generation models strive to predict the number of trips generated
by a zone. How many trips will be generated by a given location and
when will these trips happen?
 Trip distribution models strive to predict the number of trips that will
be made between a pair of zones for a particular trip purpose
What are the origins and destinations of these trips?
 Mode choice: the different modes available for a certain trip and what
factors affect the choice of a mode selection for a particular trip
Which mode of Transportation will be used to make the trip?
 Traffic assignment: Which route on the transportation network will be
used when making the trip?
Part 5: ADDING THE PROJECT GENERATED TRAFFIC TO TRAFFIC PROJECTION
 The Level of Service on the proposed road is going from D (Approaching Unstable Flow) to E (Unstable Flow).
 Therefore, the project is seen to have adverse effect on the surrounding area traffic and mitigation measures have to be put
in place for an efficient traffic management during and after the project construction.
CONCLUSIONS
Gmail and Facebook
sokhit1@gmail.com
+855 97 7258 825 sokhit1@gmail.com
Please keep this slide for attribution

Mais conteúdo relacionado

Mais procurados

Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume StudyAbontee
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodMd. Abdul Kader
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal DesignVijai Krishnan V
 
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Vijai Krishnan V
 
TRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIESTRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIEStp jayamohan
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume studyZawad khalil
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume StudiesMd Tanvir Alam
 
TRANSPORTATION PLANNING
TRANSPORTATION PLANNINGTRANSPORTATION PLANNING
TRANSPORTATION PLANNINGintan fatihah
 
O and d study
O and d studyO and d study
O and d studymeetmksvs
 
Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )Ahmad Ali Miftah
 
Land use transportation cycle
Land use transportation cycleLand use transportation cycle
Land use transportation cycleUday Yadav
 
Methods of route assignment
Methods of route assignmentMethods of route assignment
Methods of route assignmentKathan Sindhvad
 
Capacity analysis Of Highways
Capacity analysis Of HighwaysCapacity analysis Of Highways
Capacity analysis Of HighwaysLatif Hyder Wadho
 
UTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by ManjuraliUTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by ManjuraliManjurali Balya
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume surveyRashed Alam
 
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination surveyAkash Pandey
 

Mais procurados (20)

Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal Design
 
Design traffic For Highways
Design traffic For HighwaysDesign traffic For Highways
Design traffic For Highways
 
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
TRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIESTRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIES
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
 
TRANSPORTATION PLANNING
TRANSPORTATION PLANNINGTRANSPORTATION PLANNING
TRANSPORTATION PLANNING
 
O and d study
O and d studyO and d study
O and d study
 
Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )Transportation modeling and planning ( The Four-Step Model )
Transportation modeling and planning ( The Four-Step Model )
 
Land use transportation cycle
Land use transportation cycleLand use transportation cycle
Land use transportation cycle
 
Methods of route assignment
Methods of route assignmentMethods of route assignment
Methods of route assignment
 
Traffic speed study
Traffic speed studyTraffic speed study
Traffic speed study
 
Capacity analysis Of Highways
Capacity analysis Of HighwaysCapacity analysis Of Highways
Capacity analysis Of Highways
 
IMPACT OF BRTS ON CITIES
IMPACT OF BRTS ON CITIESIMPACT OF BRTS ON CITIES
IMPACT OF BRTS ON CITIES
 
UTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by ManjuraliUTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by Manjurali
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume survey
 
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination survey
 

Semelhante a PLACK Sokhit_Traffic Impact assessment (TIA).pptx

Evaluation of level of service at chatikara, Mathura
Evaluation of level of service at chatikara, MathuraEvaluation of level of service at chatikara, Mathura
Evaluation of level of service at chatikara, MathuraSHASHANK KAMAL
 
IRJET- Capacity and Level of Service for Highways Segments in Nigeria
IRJET- Capacity and Level of Service for Highways Segments in NigeriaIRJET- Capacity and Level of Service for Highways Segments in Nigeria
IRJET- Capacity and Level of Service for Highways Segments in NigeriaIRJET Journal
 
Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2Latif Hyder Wadho
 
Traffic volume studies
Traffic volume studiesTraffic volume studies
Traffic volume studiesJanak Parmar
 
Operational analysis of two lane highway
Operational analysis of two lane highwayOperational analysis of two lane highway
Operational analysis of two lane highwayBharat Upadhyay
 
Traffic volume study report by pronob ghosh buet 1204011
Traffic volume study report by pronob ghosh buet 1204011 Traffic volume study report by pronob ghosh buet 1204011
Traffic volume study report by pronob ghosh buet 1204011 Pronob Ghosh
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Civil Zone
 
ATE - U-I.pptx
ATE - U-I.pptxATE - U-I.pptx
ATE - U-I.pptxCivilhod15
 
TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...
TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...
TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...Sukrati Pandit
 
Capacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghwaysCapacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghwaysRaghupathi Kandiboina
 
TRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdf
TRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdfTRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdf
TRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdfPriya Sarita Mane
 
TRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOW
TRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOWTRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOW
TRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOWAbdul Aziz
 
Volume study presentation grp 04
Volume study presentation grp 04Volume study presentation grp 04
Volume study presentation grp 04Stone Rayhan
 
Traffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & ProceduresTraffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & Proceduresgscplanning
 
Bus 16 (Transportation Engineering Dr.Lina Shbeeb)
Bus 16 (Transportation Engineering Dr.Lina Shbeeb)Bus 16 (Transportation Engineering Dr.Lina Shbeeb)
Bus 16 (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...civejjour
 
INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...
INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...
INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...civej
 

Semelhante a PLACK Sokhit_Traffic Impact assessment (TIA).pptx (20)

Evaluation of level of service at chatikara, Mathura
Evaluation of level of service at chatikara, MathuraEvaluation of level of service at chatikara, Mathura
Evaluation of level of service at chatikara, Mathura
 
IRJET- Capacity and Level of Service for Highways Segments in Nigeria
IRJET- Capacity and Level of Service for Highways Segments in NigeriaIRJET- Capacity and Level of Service for Highways Segments in Nigeria
IRJET- Capacity and Level of Service for Highways Segments in Nigeria
 
Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2
 
Traffic volume studies
Traffic volume studiesTraffic volume studies
Traffic volume studies
 
Operational analysis of two lane highway
Operational analysis of two lane highwayOperational analysis of two lane highway
Operational analysis of two lane highway
 
Traffic volume study report by pronob ghosh buet 1204011
Traffic volume study report by pronob ghosh buet 1204011 Traffic volume study report by pronob ghosh buet 1204011
Traffic volume study report by pronob ghosh buet 1204011
 
Traffic Engineering.pptx
Traffic Engineering.pptxTraffic Engineering.pptx
Traffic Engineering.pptx
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)
 
Volume study (group 5)
Volume study (group  5)Volume study (group  5)
Volume study (group 5)
 
ATE - U-I.pptx
ATE - U-I.pptxATE - U-I.pptx
ATE - U-I.pptx
 
Unit 3
Unit 3Unit 3
Unit 3
 
TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...
TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...
TRAFFIC VOLUME STUDY AT SECTOR 18 NOIDA SECTION AND FUTURE FORECASTING USING ...
 
Capacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghwaysCapacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghways
 
TRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdf
TRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdfTRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdf
TRAFFIC ENGINEERING & HIGHWAY DRAINAGE_.pdf
 
TRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOW
TRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOWTRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOW
TRAFFIC IMPROVEMENTS FOR SMOOTH MOVEMENT OF TRAFFIC FLOW
 
Volume study presentation grp 04
Volume study presentation grp 04Volume study presentation grp 04
Volume study presentation grp 04
 
Traffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & ProceduresTraffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & Procedures
 
Bus 16 (Transportation Engineering Dr.Lina Shbeeb)
Bus 16 (Transportation Engineering Dr.Lina Shbeeb)Bus 16 (Transportation Engineering Dr.Lina Shbeeb)
Bus 16 (Transportation Engineering Dr.Lina Shbeeb)
 
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
Intelligent Transportation System Based Traffic Congestion Modeling for Urban...
 
INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...
INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...
INTELLIGENT TRANSPORTATION SYSTEM BASED TRAFFIC CONGESTION MODELLING FOR URBA...
 

Último

COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 

Último (20)

COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 

PLACK Sokhit_Traffic Impact assessment (TIA).pptx

  • 1. Traffic Impact Accessment Traffic Impact Assessment or Traffic Impact Analysis (TIA) is the effect of the proposed project traffic on the existing surrounding and road. Presentation By STUDENT | PLACK SOKHIT | M-TIE Submitted to DR | PHUN VENG KHEANG | DECEMBER | 23
  • 2. STANDARD DEFINITIONS Traffic impact accessment or Traffic Impact Analysis (TIA) is the effect of the proposed project traffic on the existing surrounding and road. Speed Speed: The rate of motion or individual vehicles of a traffic stream. It is measured in meters per second or kilometers per hour. Volume Volume: The number of vehicles at a given point on a road during a designated time interval. Time means Speed Time means Speed: It is the mean speed of vehicles observed at a point on the road over a period of time. 𝑉 = 𝑑 𝑡 Space mean speed Space mean speed: It is the mean speed of vehicles in a traffic stream at any instant of time over a certain length of the road. 𝑺𝑴𝑺 = 𝒅 𝒕 𝒏 Density Density: It is the number of vehicles occupying in a unit length of a road at an instant of time. The unit length is generally one kilometer Capacity Capacity: It is defined as the maximum hourly volume (vehicle per hour) at which vehicles can reasonably be expected to traverse a point or uniform section of lane or roadways during a given time period under prevailing roadways, traffic and control conditions. Peak hour factor Peak hour factor: It is defined as the traffic volume during peak hour expressed as a percentage of average daily traffic. The peak hour volume in this case is taken as the highest hourly volume based on actual traffic counts. Presentation By STUDENT | PLACK SOKHIT | M-TIE Submitted to DR | PHUN VENG KHEANG | DECEMBER | 23
  • 3. IMPORTANT TERMS Volume-Demand-to-Capacity Ratio (V/C): It is a measure that reflects mobility and quality of travel of a facility or a section of a facility. It compares roadway demand (vehicle volumes) with roadway supply (carrying capacity). For example, a V/C of 1.00 indicates the roadway facility is operating at its capacity. It is a common performance measure and is widely used in transportation studies PCU – Passenger Car Unit or ECS – Equivalent Car Space: It is the unit used for the conversion of different types of vehicles on the road into a single unit for the ease of calculation of the capacity of the road. LoS – Level of Service It is the measure of the current level of a particular infrastructure and direct representation of the Volume to Capacity Ratio, ranging from A to F. Vehicle Type PCU/ECS Factor 2 Wheeler 0.5 Car/Jeep/Taxi 1 Auto Rickshaw 1 LCV 1.5 Buses/2-Axle 3 Trucks-3 Axle 4 Trailer 5 Level of Service V/C Ratio Description 2 Wheeler <0.3 Free Flow Car/Jeep/Taxi 0.3 - 0.5 Reasonably Free Flow Auto Rickshaw 0.5 - 0.7 Stable Flow LCV 0.7 - 0.9 Approaching unstable Flow Buses/2-Axle 1 Unstable Flow Trucks-3 Axle >1 Forced Flow
  • 4. What is TIA? Traffic Impact Assessment TIA is an important tool used to determine the transportation and traffic impact of a proposed site development project (upon full development) on the surrounding traffic and transportation systems.Listen wie diese hier: ● It identifies the need for mitigation measures for a transportation system to reduce congestion, as well as to maintain or improve road safety. ● Local Authorities will use TIA as basic for assessing and apportioning a developer’s contribution to road improvements. ● Local Authorities also will use TIA to evaluate Traffic Management Plan proposals. ● Provides necessary technical input to other relevant reports such as Environmental Impact Assessment , Social Impact Assessment, Development Plan ( Structure and Local Plan), Transport Master Plan and the Road Safety Audits.
  • 5. WHY DO WE NEED TIA? To offer alternatives Solution to traffic improvement as well as measures for the road users. To obtain the degree of control At access requested by the private/ government entities To determine what type of access required to be considered and construction To predetermine future expansion if its required 1 4 2 3
  • 6. Level of Service (LOS) LOS 60 B.NO DELAYS No congestion Reasonably free flow,but speed depands on Traffic flow 30 E.MINIMAL DELAYS Severe congestion Very unstable flow, possible short stoppages 70 A.NO DELAYS No Congestion ,Free flow with low traffic volumes and high speeds 50 C.MINIMA L DELAYS Moderate congestion Unstable flow; Restricted drivers chosen speed 30 F.SIGNIFICAT DELAYS Extreme congestion Unacceptable congestion ,stop-and-go traffic; forced flow 40 D.MINIMAL DELAYS Moderate congestion Unstable flow ; Restricted drivers chosen speed Level of Service LOS provides an indication or measure of the operational condition of the facility concerned. A range from “A” to “F” is applicable, LOS “A” represents an excellent level of operational condition, while LOS “F” an undesirable, exceedingly congested and failed situation. Reference: Road Traffic Volume Malaysia (RVTM) 2018
  • 7. No Delays <10 Delay per vehicle(second) Highest quality of service. Free traffic flow with few restriction on maneuverability or speed LEVEL OF SERVICE (LOS) for Unsignalized Intersections 10-15 Delay per vehicle(second) Stable traffic flow. Speed becoming slightly restricted. Low restricted on maneuverability 15-25 Delay per vehicle(second) Stable traffic flow, but less freedom to select speed, change lanes or pass 25-35 Delay per vehicle(second) Traffic flow becoming unstable. Speeds subject to sudden change. Passing is difficult 35-50 Delay per vehicle(second) Unstable traffic flow. Speeds change quickly and maneuverability is low >50 Delay per vehicle(second) Heavily congested traffic. Demand exceeds capacity and speeds vary greatly. Very Short Delay Minimal Delays Minimal Delays Significant Delays Considerable Delays
  • 8. Delay per vehicle(second) <10 Delay per vehicle(second) 11-20 Delay per vehicle(second) 21-35 Delay per vehicle(second) 36-55 Delay per vehicle(second) 56-80 Traffic Signal Condition LOS FACTOR AFFECTING LOS OF SIGNALIZED INTERSECTIONS Geometric Condition Traffic Condition  Signal Coordination  Cycle Length  Protected left turn  Timing  Pre-timed or Traffic activated signal  Ect.  Signal Coordination  Cycle Length  Protected left turn  Percent of truck traffic  Number of pedestrian  Etc.. Delay per vehicle(second) >80 A B C D E F
  • 9. TRAFFIC IMPACT ASSESSMENT (TIA) PROCESS FLOW 6 Collate existing data and information 2 Architect/Town Planner 8 5 Discussion to determine the scope, study area and study methodology 1 Developer 3 Local Authority 7 Traffic Study 4 Appointment of a Transport Engineer 9 Review the original layout plan and propose any improvement to the client and land use. Analyses:  Trip generation  Model split  Trip distribution  Trip assignment  Analyses of LOS  Problem to alleviate or reduce the identified probem
  • 10. Part 1: Identification of site context and road inventory Site Name Distance from the proposed project ● Nearest Arterial Road ● Nearest Sub Arterial Road ● Nearest Railway Station ● Nearest Bus Station  The hierarchy in terms of the network of roads is to ensure scale and efficient circulation of traffic. To achieve this, through traffic routes are not be used for direct access to buildings or even to minor roads serving the buildings, because in that case not only the capacity of the through routes will be reduced but the intersections will also be unsafe.  The principal factors considered in designation roads into appropriate classifications are the existing and proposed land uses, overall travel demand, pattern of movement by various modes of transportation safety of traffic, environmental considerations etc.  The major Arterial, Sub-arterial and Collector Roads need to be identified in order to calculate the exact traffic impact of the project.
  • 11. Part 2: TRAFFIC SURVEY
  • 12. Part 3: PEAK HOUR TRAFFIC, CAPACITY ANALYSIS AND FUTURE PROJECTION
  • 13. Part 4: ESTIMATING PEAK HOUR TRAFFIC GENERATED BY PROPOSED PROJECT Trip generation and forecasting Four step model for demand assessment  Trip generation models strive to predict the number of trips generated by a zone. How many trips will be generated by a given location and when will these trips happen?  Trip distribution models strive to predict the number of trips that will be made between a pair of zones for a particular trip purpose What are the origins and destinations of these trips?  Mode choice: the different modes available for a certain trip and what factors affect the choice of a mode selection for a particular trip Which mode of Transportation will be used to make the trip?  Traffic assignment: Which route on the transportation network will be used when making the trip?
  • 14. Part 5: ADDING THE PROJECT GENERATED TRAFFIC TO TRAFFIC PROJECTION  The Level of Service on the proposed road is going from D (Approaching Unstable Flow) to E (Unstable Flow).  Therefore, the project is seen to have adverse effect on the surrounding area traffic and mitigation measures have to be put in place for an efficient traffic management during and after the project construction. CONCLUSIONS
  • 15. Gmail and Facebook sokhit1@gmail.com +855 97 7258 825 sokhit1@gmail.com Please keep this slide for attribution