Project Performance
Measurement -
Earned Value
Simon Robertson
© 2010 Robertson Consulting Ltd June 2010
2
Benefits of EVM
• An up-to-date accurate status of the
project
• Solid input to proactively make corrections
• Allows managing stakeholder expectations
• Historic reference for future estimates
• No surprises to the customer
• More accurate representation of on-time
completion
© 2010 Robertson Consulting Ltd 2
3
MSProject 2010 & EVM
© 2010 Robertson Consulting Ltd When? Just after you develop the Schedule….. 3
4
MSProject 2010 & EVM
• Important Issue
Indicators
o Cost overrun – may be
working additional hours to
keep timeline
o Time overrun – may be
availability of resources
limited
o Cost and Time overrun –
may be project control,
poor quality, rework was
necessary
© 2010 Robertson Consulting Ltd
• Steps to prepare
o Ensure all Resources and
Materials are in MSProject
o Ensure all planning complete
and schedule agreed
o Establish project baseline from
where the variances will be
calculated and presented
o Add Columns to reflect the EV
measures
o Prepare project management
documents to meet the
tracking and reporting
requirements from the various
project stakeholders
o Set expectations with the
project team, address any
concerns and get buy-in
4
5
MSProject 2010 & EVM
Typical Measures
o Planned Value (PV) – amount budgeted
to be spent between task’s start date and
the status date
o Actual Cost (AC) – amount spent while
preforming work on a task during a given
period
o Earned Value (EV) – amount that that
should have been spent for a given
percentage of work performed on a task
© 2010 Robertson Consulting Ltd 5
6
MSProject 2010 & EVM
Typical Variance Metrics
oCost Variance(CV) – links spending
to earned value
CV = EV – AC or BCWP - ACWP
oSchedule Variance (SV) – links the
work accomplished (earned) with
planned
SV = EV – PV or BCWP - BCWS
© 2010 Robertson Consulting Ltd 6
7
MSProject 2010 & EVM
Typical Performance Indicators
o Cost Performance Index
CPI = EV/AC or BCWP/ACWP
o Schedule Performance Index
SPI = EV/PV or BCWP/BCWS
o Critical Ratio (?)
CR = CPI x SPI or BCWP2/ACWP x
BCWS
© 2010 Robertson Consulting Ltd 7
8
MSProject 2010 & EVM
Typical Forecasting Metrics
o Estimate at Completion (EAC)– apply CPI and SPI
as performance factors (PF)
o Mathematical EAC (uses PF = 1)
EACm = (BAC – EV) + AC
or EACm = BAC – CV
o Low End EAC (uses PF = CPI)
EACL= [(BAC-EV)/ (CPI)] + AC
Or EACL = (BAC)/ (CPI)
o High End EAC (uses PF = CPI x SPI)
EACH = [(BAC – EV)/(CPI x SPI)] + AC
© 2010 Robertson Consulting Ltd 8
9
MSProject 2010 & EVM
Typical Cost Corrective Action Metrics
o To Complete Performance Index (TCPI)
TCPI = (Work remaining)/ (Funds Remaining)
o To stay within original BAC
TCPI = (BAC – EV) / (BAC – AC)
o To stay within newly forecasted LRE where
baseline remains at original BAC
TCPI = (BAC – EV) / (LRE – AC )
Where LRE (Latest Revised Estimate)
LRE (or EACE) = ETC + AC
© 2010 Robertson Consulting Ltd 9
10
MSProject 2010 & EVM
Typical Schedule Corrective Action Metrics
o To Complete Schedule Performance Index
(TCSPI)
TCSPI = (Unearned Duration Remaining)/ (Actual
Duration Remaining)
o To stay within original PMB
TCSPI = [PD – (AD)(SPI)] / [(PD - AD)]
o To stay within the latest revised Schedule (LRS)
where baseline remains at original PMB
TCSPI = ([PD – (AD)(SPI)] / [(LRS - AD)]
© 2010 Robertson Consulting Ltd 10
11
Typical Information Collection Table
Values Variance Performance Index
WBS Element
Planned
Value (PV)
Earned
Value
Actual
Cost
(AC)
Schedule
EV-PV
Cost
EV-AC
Schedule
EV/PV
Cost
EV/AC
1.0 Pre-Pilot
Plan
63,000 58,000 62,500 (5,000) (4,500) 0.92 0.93
2.0 Checklists 64,000 48,000 46,800 (16,000) 1,200 0.75 1.03
3.0 Curriculum 23,000 20,000 23,500 (3,000) (3,500) 0.87 0.85
4.0 Mid-Term
Evaluation
68,000 68,000 72,500 - (4,500) 1.00 0.94
5.0
Implementation
Support
12,000 10,000 10,000 (2,000) - 0.83 1.00
6.0 Practice
Manual
7,000 6,200 6,000 (800) 200 0.89 1.03
7.0 Roll-out
Plan
20,000 13,500 18,100 (6,500) (4,600) 0.68 0.75
Totals 257,000 223,700 239,400 (33,000) (15,700) 0.87 0.93
© 2010 Robertson Consulting Ltd 11
12
Earned Value Analysis
0
1
2
3
4
5
6
7
Initiation Planning Execution Close Down
Actual
Budgetted
Earned Value
CV
SV
CV = EV – AC (BCWP – ACWP)
CPI = EV/ AC ( BCWP / ACWP)
SV = EV – PV (BCWP – BCWS)
SPI = EV/PV (BCWP/BCWS)
CR = CPI x SPI ((BCWP2 / (ACWP x BCWS))
STATUS
DATE
12© 2010 Robertson Consulting Ltd
Analysis Design Develop Deploy Operate
13
Earned Value Useful Notes
Main EV measures:
 CV = EV – AC (BCWP- ACWP)
 SV = EV – PV (BCWP-BCWS)
 Above result “0” is on target
 CPI = EV/AC (BCWP/ACWP)
 SPI = EV/PV (BCWP/BCWS)
 CPI, SPI = 1 is on target
 CR = CPI x SPI
 CR >= 1.0 is good
Integrates Scope, Time and Cost
• Cost Variance (CV)
• Schedule Variance (SV)
• Time Variance (TV)
• Earned Value (EV = BCWP)
• Actual Cost (AC = ACWP) – (if per time
= Burn rate)
• Planned Value (PV = BCWS)
• Budget at Completion (BAC)
• Schedule at Completion (SAC)
• Cost Performance Index (CPI)
• Schedule Performance Index (SPI)
• Critical Ratio (CR)
13© 2010 Robertson Consulting Ltd
14
Can I help further?
• Training in Earned Value
• PMI Training
• Project Consultancy – making it work on the ground
• Project Management Maturity Model Assessment
• Organisational Maturity Model Assessment
• Bespoke Training or facilitation solutions
Simon Robertson
+44 (0)7967300344
simon@robertsonconsulting.co.uk
14

Mais conteúdo relacionado

Mais procurados

Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGlen Alleman
 
Estimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulationEstimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulationGlen Alleman
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountGlen Alleman
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccessGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsGlen Alleman
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Glen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?Glen Alleman
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineGlen Alleman
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountGlen Alleman
 
SE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of SuccessSE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of SuccessGlen Alleman
 
Program Management Office Services
Program Management Office ServicesProgram Management Office Services
Program Management Office ServicesGlen Alleman
 

Mais procurados (20)

Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
 
Estimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulationEstimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulation
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
SE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of SuccessSE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of Success
 
Program Management Office Services
Program Management Office ServicesProgram Management Office Services
Program Management Office Services
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 

Destaque

Performance management
Performance managementPerformance management
Performance managementEmma Yaks
 
Advanced network performance measurement techniques
Advanced network performance measurement techniquesAdvanced network performance measurement techniques
Advanced network performance measurement techniquesMartin Geddes
 
Techniques for measurement of productivity
Techniques for measurement of productivityTechniques for measurement of productivity
Techniques for measurement of productivityANSHUL AHUJA
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performanceliviu00
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Glen Alleman
 
Project performance tracking analysis and reporting
Project performance tracking analysis and reportingProject performance tracking analysis and reporting
Project performance tracking analysis and reportingCharles Cotter, PhD
 
Project-performance appraisal
Project-performance appraisalProject-performance appraisal
Project-performance appraisalabhisaxena
 
Measurement and scaling techniques
Measurement  and  scaling  techniquesMeasurement  and  scaling  techniques
Measurement and scaling techniquesUjjwal 'Shanu'
 
Performance Management
Performance ManagementPerformance Management
Performance ManagementGautam Ghosh
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedSlideShare
 

Destaque (15)

Performance management
Performance managementPerformance management
Performance management
 
Measurement Techniques V1.01 S
Measurement Techniques V1.01 SMeasurement Techniques V1.01 S
Measurement Techniques V1.01 S
 
Advanced network performance measurement techniques
Advanced network performance measurement techniquesAdvanced network performance measurement techniques
Advanced network performance measurement techniques
 
Project Performance Reporting
Project Performance ReportingProject Performance Reporting
Project Performance Reporting
 
Techniques for measurement of productivity
Techniques for measurement of productivityTechniques for measurement of productivity
Techniques for measurement of productivity
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performance
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®
 
performance measures
performance measuresperformance measures
performance measures
 
Project performance - some thoughts and reflections
Project performance - some thoughts and reflectionsProject performance - some thoughts and reflections
Project performance - some thoughts and reflections
 
Project performance tracking analysis and reporting
Project performance tracking analysis and reportingProject performance tracking analysis and reporting
Project performance tracking analysis and reporting
 
Project-performance appraisal
Project-performance appraisalProject-performance appraisal
Project-performance appraisal
 
Measurement and scaling techniques
Measurement  and  scaling  techniquesMeasurement  and  scaling  techniques
Measurement and scaling techniques
 
Performance Management
Performance ManagementPerformance Management
Performance Management
 
Project Management KPIs
Project Management KPIsProject Management KPIs
Project Management KPIs
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Semelhante a Project Performance Measurement Earned Value A Starter

Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the NumbersPMI-Montréal
 
Earned value
Earned valueEarned value
Earned valueOliver
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...Aquamarine Emerald
 
Webinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset managementWebinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset managementStork
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfDr Mohamed Elfarran
 
project-management-process
project-management-processproject-management-process
project-management-processJose P. Banuelos
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_managementSayed Ahmed
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptvitumbikokhoswe1
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptyogeshagrawal84
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfElyes ELEBRI
 
An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...Association for Project Management
 

Semelhante a Project Performance Measurement Earned Value A Starter (20)

Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value
Earned valueEarned value
Earned value
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Webinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset managementWebinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset management
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
project-management-process
project-management-processproject-management-process
project-management-process
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdf
 
An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...
 

Último

Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Victor Rentea
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024The Digital Insurer
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfOverkill Security
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024The Digital Insurer
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Angeliki Cooney
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Zilliz
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024The Digital Insurer
 

Último (20)

Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdf
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 

Project Performance Measurement Earned Value A Starter

  • 1. 1 Project Performance Measurement - Earned Value Simon Robertson © 2010 Robertson Consulting Ltd June 2010
  • 2. 2 Benefits of EVM • An up-to-date accurate status of the project • Solid input to proactively make corrections • Allows managing stakeholder expectations • Historic reference for future estimates • No surprises to the customer • More accurate representation of on-time completion © 2010 Robertson Consulting Ltd 2
  • 3. 3 MSProject 2010 & EVM © 2010 Robertson Consulting Ltd When? Just after you develop the Schedule….. 3
  • 4. 4 MSProject 2010 & EVM • Important Issue Indicators o Cost overrun – may be working additional hours to keep timeline o Time overrun – may be availability of resources limited o Cost and Time overrun – may be project control, poor quality, rework was necessary © 2010 Robertson Consulting Ltd • Steps to prepare o Ensure all Resources and Materials are in MSProject o Ensure all planning complete and schedule agreed o Establish project baseline from where the variances will be calculated and presented o Add Columns to reflect the EV measures o Prepare project management documents to meet the tracking and reporting requirements from the various project stakeholders o Set expectations with the project team, address any concerns and get buy-in 4
  • 5. 5 MSProject 2010 & EVM Typical Measures o Planned Value (PV) – amount budgeted to be spent between task’s start date and the status date o Actual Cost (AC) – amount spent while preforming work on a task during a given period o Earned Value (EV) – amount that that should have been spent for a given percentage of work performed on a task © 2010 Robertson Consulting Ltd 5
  • 6. 6 MSProject 2010 & EVM Typical Variance Metrics oCost Variance(CV) – links spending to earned value CV = EV – AC or BCWP - ACWP oSchedule Variance (SV) – links the work accomplished (earned) with planned SV = EV – PV or BCWP - BCWS © 2010 Robertson Consulting Ltd 6
  • 7. 7 MSProject 2010 & EVM Typical Performance Indicators o Cost Performance Index CPI = EV/AC or BCWP/ACWP o Schedule Performance Index SPI = EV/PV or BCWP/BCWS o Critical Ratio (?) CR = CPI x SPI or BCWP2/ACWP x BCWS © 2010 Robertson Consulting Ltd 7
  • 8. 8 MSProject 2010 & EVM Typical Forecasting Metrics o Estimate at Completion (EAC)– apply CPI and SPI as performance factors (PF) o Mathematical EAC (uses PF = 1) EACm = (BAC – EV) + AC or EACm = BAC – CV o Low End EAC (uses PF = CPI) EACL= [(BAC-EV)/ (CPI)] + AC Or EACL = (BAC)/ (CPI) o High End EAC (uses PF = CPI x SPI) EACH = [(BAC – EV)/(CPI x SPI)] + AC © 2010 Robertson Consulting Ltd 8
  • 9. 9 MSProject 2010 & EVM Typical Cost Corrective Action Metrics o To Complete Performance Index (TCPI) TCPI = (Work remaining)/ (Funds Remaining) o To stay within original BAC TCPI = (BAC – EV) / (BAC – AC) o To stay within newly forecasted LRE where baseline remains at original BAC TCPI = (BAC – EV) / (LRE – AC ) Where LRE (Latest Revised Estimate) LRE (or EACE) = ETC + AC © 2010 Robertson Consulting Ltd 9
  • 10. 10 MSProject 2010 & EVM Typical Schedule Corrective Action Metrics o To Complete Schedule Performance Index (TCSPI) TCSPI = (Unearned Duration Remaining)/ (Actual Duration Remaining) o To stay within original PMB TCSPI = [PD – (AD)(SPI)] / [(PD - AD)] o To stay within the latest revised Schedule (LRS) where baseline remains at original PMB TCSPI = ([PD – (AD)(SPI)] / [(LRS - AD)] © 2010 Robertson Consulting Ltd 10
  • 11. 11 Typical Information Collection Table Values Variance Performance Index WBS Element Planned Value (PV) Earned Value Actual Cost (AC) Schedule EV-PV Cost EV-AC Schedule EV/PV Cost EV/AC 1.0 Pre-Pilot Plan 63,000 58,000 62,500 (5,000) (4,500) 0.92 0.93 2.0 Checklists 64,000 48,000 46,800 (16,000) 1,200 0.75 1.03 3.0 Curriculum 23,000 20,000 23,500 (3,000) (3,500) 0.87 0.85 4.0 Mid-Term Evaluation 68,000 68,000 72,500 - (4,500) 1.00 0.94 5.0 Implementation Support 12,000 10,000 10,000 (2,000) - 0.83 1.00 6.0 Practice Manual 7,000 6,200 6,000 (800) 200 0.89 1.03 7.0 Roll-out Plan 20,000 13,500 18,100 (6,500) (4,600) 0.68 0.75 Totals 257,000 223,700 239,400 (33,000) (15,700) 0.87 0.93 © 2010 Robertson Consulting Ltd 11
  • 12. 12 Earned Value Analysis 0 1 2 3 4 5 6 7 Initiation Planning Execution Close Down Actual Budgetted Earned Value CV SV CV = EV – AC (BCWP – ACWP) CPI = EV/ AC ( BCWP / ACWP) SV = EV – PV (BCWP – BCWS) SPI = EV/PV (BCWP/BCWS) CR = CPI x SPI ((BCWP2 / (ACWP x BCWS)) STATUS DATE 12© 2010 Robertson Consulting Ltd Analysis Design Develop Deploy Operate
  • 13. 13 Earned Value Useful Notes Main EV measures:  CV = EV – AC (BCWP- ACWP)  SV = EV – PV (BCWP-BCWS)  Above result “0” is on target  CPI = EV/AC (BCWP/ACWP)  SPI = EV/PV (BCWP/BCWS)  CPI, SPI = 1 is on target  CR = CPI x SPI  CR >= 1.0 is good Integrates Scope, Time and Cost • Cost Variance (CV) • Schedule Variance (SV) • Time Variance (TV) • Earned Value (EV = BCWP) • Actual Cost (AC = ACWP) – (if per time = Burn rate) • Planned Value (PV = BCWS) • Budget at Completion (BAC) • Schedule at Completion (SAC) • Cost Performance Index (CPI) • Schedule Performance Index (SPI) • Critical Ratio (CR) 13© 2010 Robertson Consulting Ltd
  • 14. 14 Can I help further? • Training in Earned Value • PMI Training • Project Consultancy – making it work on the ground • Project Management Maturity Model Assessment • Organisational Maturity Model Assessment • Bespoke Training or facilitation solutions Simon Robertson +44 (0)7967300344 simon@robertsonconsulting.co.uk 14