SlideShare uma empresa Scribd logo
1 de 14
PMP Exam
Preparation
Eng. Shamil Habet; MSc; PMP; JPE
Based on PMBOK 6th
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 1
Closing Project
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 2
CLOSE PROJECT OR PHASE
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 3
Close Project or Phase is the process of finalizing all activities for the project, phase, or
contract.
The key benefits of this process are the project or phase information is archived, the
planned work is completed, and organizational team resources are released to pursue new
endeavors.This process is performed once or at predefined points in the project.
Lessons Learned Repository: Lessons learned and knowledge gained throughout the
project are transferred to the lessons learned repository for use by future projects.
When closing the project, the project manager reviews the project management plan to
ensure that all project work is completed and that the project has met its objectives.
The activities necessary for the administrative closure of the project or
phase include but are not limited to:
1. Activities related to the completion of the contractual agreements applicable to
the project or project phase such as:
- Confirming the formal acceptance of the seller’s work,
- Finalizing open claims,
- Updating records to reflect final results, and
- Archiving such information for future use.
CLOSE PROJECT OR PHASE
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 4
2. Actions and activities necessary to satisfy completion or exit criteria for the phase
or project such as:
- Making certain that all documents and deliverables are up-to-date and that all
issues are resolved;
- Confirming the delivery and formal acceptance of deliverables by the customer;
- Ensuring that all costs are charged to the project;
- Closing project accounts;
- Reassigning personnel;
- Dealing with excess project material;
- Reallocating project facilities, equipment, and other resources;
- Elaborating the final project reports as required by organizational policies.
Important Note:
Activities needed to:
- Collect project or phase records,
- Audit project success or failure,
- Manage knowledge sharing and transfer,
- Identify lessons learned,
- Archive project information for future use by the organization.
CLOSE PROJECT OR PHASE
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 5
3. Actions and activities necessary to transfer the project’s products, services, or
results to the next phase or to production and/or operations.
4. Collecting any suggestions for improving or updating the policies and procedures
of the organization, and sending them to the appropriate organizational unit.
5. Measuring stakeholder satisfaction.
Important Note:
- The Close Project or Phase process also establishes the procedures to investigate
and document the reasons for actions taken if a project is terminated before
completion. In order to successfully achieve this, the project manager needs to
engage all the proper stakeholders in the process.
- Benefits Management Plan vs. Business Case: The benefits management plan
is used to measure whether the benefits of the project were achieved as planned.
While the business case that is used to determine if the expected outcomes from
the economic feasibility study used to justify the project occurred.
CLOSE PROJECT OR PHASE
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 6
CLOSE PROJECT OR PHASE (T & T)
 Meetings
Meetings are used to confirm that the deliverables have been accepted,
- To validate that the exit criteria have been met,
- To formalize the completion of the contracts,
- To evaluate the satisfaction of the stakeholders,
- To gather lessons learned,
- To transfer knowledge and information from the project,
- To celebrate success.
- Attendees may include
Important Note:
- Meetings may be face-to-face, virtual, formal, or informal.
- Types of meetings include but are not limited to close-out reporting meetings,
customer wrap-up meetings,lessons learned meetings,and celebration meetings.
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 7
CLOSE PROJECT OR PHASE (Outputs)
 Final Product, Service, or ResultTransition
This output refers to this transition of the final product, service, or result that the
project was authorized to produce (or in the case of phase closure, the
intermediate product, service, or result of that phase) from one team to another.
Important Note:
- A product, service, or result, once delivered by the project, may be handed over
to a different group or organization that will operate, maintain, and support it
throughout its life cycle. (i.e. Continuing its Product Life Cycle).
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 8
 Final Report
The final report provides a summary of the project performance. It includes:
- Summary level description of the project or phase.
- Scope objectives, the criteria used to evaluate the scope, and evidence that the
completion criteria were met.
- Quality objectives, the criteria used to evaluate the project and product quality,
the verification and actual milestone delivery dates, and reasons for variances.
- Cost objectives, including the acceptable cost range, actual costs, and reasons
for any variances.
- Summary of the validation information for the final product, service, or result.
- Schedule objectives including whether results achieved the benefits that the
project was undertaken to address. If the benefits are not met at the close of
the project, indicate the degree to which they were achieved and estimate for
future benefits realization.
- Summary of how the final product, service, or result achieved the business
needs identified in the business plan. If the business needs are not met at the
close of the project, indicate the degree to which they were achieved and
estimate for when the business needs will be met in the future.
- Summary of any risks or issues encountered on the project and how they were
addressed.
CLOSE PROJECT OR PHASE (Outputs)
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 9
Code of Ethics and
Professional Conduct
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 10
 Professionalism
- Maintain high standards of integrity and professionalism.
- Adhere to legal requirements and ethical standards.
- Protect the community and your stakeholders.
- Share lessons learned, best practices, research, etc.
- Improve yourself; improve the quality of project management services.
- Build the capabilities of your colleagues and enhance individual competences.
- Interact with team and stakeholders in a professional and cooperative manner.
- Balance stakeholder’s objectives.
- Accept responsibility for the actions.
- Encourage others in the profession to act in an ethical and professional manner.
- Improve your competencies as a project manager.
- Perform self-assessment and competencies development plan.
CODE OF ETHICS AND PROFESSIONAL CONDUCT
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 11
 Responsibility
- Make decisions based on the best interests of society, public safety, and the
environment.
- Accept only those assignments that are consistent with your background,
experience, skills, and qualifications.
- Accept accountability.
- Protect proprietary or confidential information.
- Do what you promised to do.
- Report any unethical or illegal conduct to appropriate management members.
 RESPECT
- Respect personal, ethnic, and cultural differences.
- Avoid engaging in behaviors might be considered as disrespectful.
- Understand others’ point of view.
- Approach directly those persons with whom you have a conflict or disagreement.
- Do not act in an abusive manner towards others.
- Respect the property rights of others.
CODE OF ETHICS AND PROFESSIONAL CONDUCT
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 12
 FAIRNESS
- Practice with fairness and honesty.
- Strive for fair solution.
- Ensure transparency in your decision-making process.
- Reexamine your impartiality and objectivity on constant basis, and take
corrective actions as appropriate.
- Provide equal access to information to those who are authorized to have that
information.
- Make opportunities equally available to qualified candidates.
- Do not hire or fire, reward or punish, or award or deny contracts based on
personal considerations, including favoritism, nepotism, or bribery.
 HONESTY
- Be truthful in our communications and conduct.
- Provide accurate information in a timely manner.
- Provide accurate and truthful representation to the public.
- Negotiate in good faith.
- Make commitments and promises, implied or explicit, in good faith.
- Strive to create an environment in which others feel safe to tell the truth.
- Avoid conflict of interest or appearance of impropriety.
CODE OF ETHICS AND PROFESSIONAL CONDUCT
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 13
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 14

Mais conteúdo relacionado

Mais procurados

Project management office value
Project management office valueProject management office value
Project management office valueHumanWare
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...Shamil Habet
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off PresentationEbru Seiwert
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Managementguest90bddb
 
project Scope management
project Scope management project Scope management
project Scope management Mohamed , PMP
 
PMP Chapter 3 of 6 Planning Process Group (24- Processes) (Based on PMBOK 6t...
PMP Chapter 3 of 6  Planning Process Group (24- Processes) (Based on PMBOK 6t...PMP Chapter 3 of 6  Planning Process Group (24- Processes) (Based on PMBOK 6t...
PMP Chapter 3 of 6 Planning Process Group (24- Processes) (Based on PMBOK 6t...Shamil Habet
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!Sasan Hosseyni
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management Ahmad Maharma, PMP,RMP
 
PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary Amr Miqdadi
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management MethodologyC.Y Wong
 
PMBOK six edition dataflow diagram by english with MS-visio
PMBOK six edition dataflow diagram by english with MS-visioPMBOK six edition dataflow diagram by english with MS-visio
PMBOK six edition dataflow diagram by english with MS-visioKose Jumnichi
 

Mais procurados (20)

PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
Project management office value
Project management office valueProject management office value
Project management office value
 
Project management
Project managementProject management
Project management
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
Real example of PMO deployment
Real example of PMO deploymentReal example of PMO deployment
Real example of PMO deployment
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off Presentation
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
project Scope management
project Scope management project Scope management
project Scope management
 
PMP Chapter 3 of 6 Planning Process Group (24- Processes) (Based on PMBOK 6t...
PMP Chapter 3 of 6  Planning Process Group (24- Processes) (Based on PMBOK 6t...PMP Chapter 3 of 6  Planning Process Group (24- Processes) (Based on PMBOK 6t...
PMP Chapter 3 of 6 Planning Process Group (24- Processes) (Based on PMBOK 6t...
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!Pmbok Processes Flow, ALL!
Pmbok Processes Flow, ALL!
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management
 
Pmipmo
PmipmoPmipmo
Pmipmo
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
PMBOK six edition dataflow diagram by english with MS-visio
PMBOK six edition dataflow diagram by english with MS-visioPMBOK six edition dataflow diagram by english with MS-visio
PMBOK six edition dataflow diagram by english with MS-visio
 

Semelhante a PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th edition) and code of ethics

PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)Shamil Habet
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...Shamil Habet
 
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & SkillsPMC Mentor
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionJohn Khateeb
 
PMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfPMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfDivya Malik
 
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...PDUs2Go.com
 
Project management consulting
Project management consultingProject management consulting
Project management consultingKholwa_Lwazi
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptxHamzaMessaoudi10
 
Introduction to PMP, Professional responsibility and Introduction to project ...
Introduction to PMP, Professional responsibility and Introduction to project ...Introduction to PMP, Professional responsibility and Introduction to project ...
Introduction to PMP, Professional responsibility and Introduction to project ...Gunesh Apte
 
Topic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdfTopic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdfHuyNguyen657394
 
Get An Attractive Score in PMI-CP Certification Exam.pdf
Get An Attractive Score in PMI-CP Certification Exam.pdfGet An Attractive Score in PMI-CP Certification Exam.pdf
Get An Attractive Score in PMI-CP Certification Exam.pdfMeghna Arora
 
PM Notebook - Chapter 4: Integration Management
PM Notebook - Chapter 4: Integration ManagementPM Notebook - Chapter 4: Integration Management
PM Notebook - Chapter 4: Integration ManagementMohammad Elsheimy
 
Project Management Policy
Project Management PolicyProject Management Policy
Project Management PolicyDemand Metric
 
Project management professional exam outline
Project management professional exam outlineProject management professional exam outline
Project management professional exam outlineDadunoor Kamati
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slidesWilber Tuttleman
 

Semelhante a PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th edition) and code of ethics (20)

PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
 
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
PMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfPMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdf
 
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
 
Project management consulting
Project management consultingProject management consulting
Project management consulting
 
P3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management FrameworkP3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management Framework
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptx
 
Pmp
PmpPmp
Pmp
 
Introduction to PMP, Professional responsibility and Introduction to project ...
Introduction to PMP, Professional responsibility and Introduction to project ...Introduction to PMP, Professional responsibility and Introduction to project ...
Introduction to PMP, Professional responsibility and Introduction to project ...
 
Topic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdfTopic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdf
 
PMI-PgMP Application Development
PMI-PgMP Application DevelopmentPMI-PgMP Application Development
PMI-PgMP Application Development
 
Get An Attractive Score in PMI-CP Certification Exam.pdf
Get An Attractive Score in PMI-CP Certification Exam.pdfGet An Attractive Score in PMI-CP Certification Exam.pdf
Get An Attractive Score in PMI-CP Certification Exam.pdf
 
PM Notebook - Chapter 4: Integration Management
PM Notebook - Chapter 4: Integration ManagementPM Notebook - Chapter 4: Integration Management
PM Notebook - Chapter 4: Integration Management
 
Pmp
PmpPmp
Pmp
 
Project Management Policy
Project Management PolicyProject Management Policy
Project Management Policy
 
Pmp
PmpPmp
Pmp
 
Project management professional exam outline
Project management professional exam outlineProject management professional exam outline
Project management professional exam outline
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 

Último

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...RKavithamani
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 

Último (20)

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 

PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th edition) and code of ethics

  • 1. PMP Exam Preparation Eng. Shamil Habet; MSc; PMP; JPE Based on PMBOK 6th PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 1
  • 2. Closing Project PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 2
  • 3. CLOSE PROJECT OR PHASE PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 3
  • 4. Close Project or Phase is the process of finalizing all activities for the project, phase, or contract. The key benefits of this process are the project or phase information is archived, the planned work is completed, and organizational team resources are released to pursue new endeavors.This process is performed once or at predefined points in the project. Lessons Learned Repository: Lessons learned and knowledge gained throughout the project are transferred to the lessons learned repository for use by future projects. When closing the project, the project manager reviews the project management plan to ensure that all project work is completed and that the project has met its objectives. The activities necessary for the administrative closure of the project or phase include but are not limited to: 1. Activities related to the completion of the contractual agreements applicable to the project or project phase such as: - Confirming the formal acceptance of the seller’s work, - Finalizing open claims, - Updating records to reflect final results, and - Archiving such information for future use. CLOSE PROJECT OR PHASE PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 4
  • 5. 2. Actions and activities necessary to satisfy completion or exit criteria for the phase or project such as: - Making certain that all documents and deliverables are up-to-date and that all issues are resolved; - Confirming the delivery and formal acceptance of deliverables by the customer; - Ensuring that all costs are charged to the project; - Closing project accounts; - Reassigning personnel; - Dealing with excess project material; - Reallocating project facilities, equipment, and other resources; - Elaborating the final project reports as required by organizational policies. Important Note: Activities needed to: - Collect project or phase records, - Audit project success or failure, - Manage knowledge sharing and transfer, - Identify lessons learned, - Archive project information for future use by the organization. CLOSE PROJECT OR PHASE PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 5
  • 6. 3. Actions and activities necessary to transfer the project’s products, services, or results to the next phase or to production and/or operations. 4. Collecting any suggestions for improving or updating the policies and procedures of the organization, and sending them to the appropriate organizational unit. 5. Measuring stakeholder satisfaction. Important Note: - The Close Project or Phase process also establishes the procedures to investigate and document the reasons for actions taken if a project is terminated before completion. In order to successfully achieve this, the project manager needs to engage all the proper stakeholders in the process. - Benefits Management Plan vs. Business Case: The benefits management plan is used to measure whether the benefits of the project were achieved as planned. While the business case that is used to determine if the expected outcomes from the economic feasibility study used to justify the project occurred. CLOSE PROJECT OR PHASE PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 6
  • 7. CLOSE PROJECT OR PHASE (T & T)  Meetings Meetings are used to confirm that the deliverables have been accepted, - To validate that the exit criteria have been met, - To formalize the completion of the contracts, - To evaluate the satisfaction of the stakeholders, - To gather lessons learned, - To transfer knowledge and information from the project, - To celebrate success. - Attendees may include Important Note: - Meetings may be face-to-face, virtual, formal, or informal. - Types of meetings include but are not limited to close-out reporting meetings, customer wrap-up meetings,lessons learned meetings,and celebration meetings. PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 7
  • 8. CLOSE PROJECT OR PHASE (Outputs)  Final Product, Service, or ResultTransition This output refers to this transition of the final product, service, or result that the project was authorized to produce (or in the case of phase closure, the intermediate product, service, or result of that phase) from one team to another. Important Note: - A product, service, or result, once delivered by the project, may be handed over to a different group or organization that will operate, maintain, and support it throughout its life cycle. (i.e. Continuing its Product Life Cycle). PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 8
  • 9.  Final Report The final report provides a summary of the project performance. It includes: - Summary level description of the project or phase. - Scope objectives, the criteria used to evaluate the scope, and evidence that the completion criteria were met. - Quality objectives, the criteria used to evaluate the project and product quality, the verification and actual milestone delivery dates, and reasons for variances. - Cost objectives, including the acceptable cost range, actual costs, and reasons for any variances. - Summary of the validation information for the final product, service, or result. - Schedule objectives including whether results achieved the benefits that the project was undertaken to address. If the benefits are not met at the close of the project, indicate the degree to which they were achieved and estimate for future benefits realization. - Summary of how the final product, service, or result achieved the business needs identified in the business plan. If the business needs are not met at the close of the project, indicate the degree to which they were achieved and estimate for when the business needs will be met in the future. - Summary of any risks or issues encountered on the project and how they were addressed. CLOSE PROJECT OR PHASE (Outputs) PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 9
  • 10. Code of Ethics and Professional Conduct PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 10
  • 11.  Professionalism - Maintain high standards of integrity and professionalism. - Adhere to legal requirements and ethical standards. - Protect the community and your stakeholders. - Share lessons learned, best practices, research, etc. - Improve yourself; improve the quality of project management services. - Build the capabilities of your colleagues and enhance individual competences. - Interact with team and stakeholders in a professional and cooperative manner. - Balance stakeholder’s objectives. - Accept responsibility for the actions. - Encourage others in the profession to act in an ethical and professional manner. - Improve your competencies as a project manager. - Perform self-assessment and competencies development plan. CODE OF ETHICS AND PROFESSIONAL CONDUCT PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 11
  • 12.  Responsibility - Make decisions based on the best interests of society, public safety, and the environment. - Accept only those assignments that are consistent with your background, experience, skills, and qualifications. - Accept accountability. - Protect proprietary or confidential information. - Do what you promised to do. - Report any unethical or illegal conduct to appropriate management members.  RESPECT - Respect personal, ethnic, and cultural differences. - Avoid engaging in behaviors might be considered as disrespectful. - Understand others’ point of view. - Approach directly those persons with whom you have a conflict or disagreement. - Do not act in an abusive manner towards others. - Respect the property rights of others. CODE OF ETHICS AND PROFESSIONAL CONDUCT PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 12
  • 13.  FAIRNESS - Practice with fairness and honesty. - Strive for fair solution. - Ensure transparency in your decision-making process. - Reexamine your impartiality and objectivity on constant basis, and take corrective actions as appropriate. - Provide equal access to information to those who are authorized to have that information. - Make opportunities equally available to qualified candidates. - Do not hire or fire, reward or punish, or award or deny contracts based on personal considerations, including favoritism, nepotism, or bribery.  HONESTY - Be truthful in our communications and conduct. - Provide accurate information in a timely manner. - Provide accurate and truthful representation to the public. - Negotiate in good faith. - Make commitments and promises, implied or explicit, in good faith. - Strive to create an environment in which others feel safe to tell the truth. - Avoid conflict of interest or appearance of impropriety. CODE OF ETHICS AND PROFESSIONAL CONDUCT PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 13
  • 14. PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 14