SlideShare uma empresa Scribd logo
1 de 69
uniselU N I V E R S I T Y S E L A N G O R
Engineered by:
1. Eng. Feroz Faizmand
2. Eng. Mustafa Jameel
3. Eng. Ahmad Habib
4. Eng. Sayed Asadullah
Table of Contents
 Introduction to Project
 Earthworks
 Road Works
 Drainage System
 Sewage System
 Water Supply System
 Environmental and Management Planning
CHPTER ONE
The Project
FAMA Consultant is pleased to introduce his new project with
the following descriptions.
---
Introduction
Address Total Area The Project
Mukim Datu
Mengkebang,
Derah Batu
Mengkebang,
Jajahan Kuala
Kari, Negeri
Kelantan Darul
Naim
42,834.00
m2
1. Site Clearance, Cut and Fill, Slopes and
Retaining walls
2. Drainage System
3. Sewage System
4. Water Supply System
5. Road, Shoulder and Road Curbs
The Project
---
Land Usages
Type Of Property Quantity Total Area Used m2 Total Area Used %
Double Story Houses 82 12,786.5 29.85
Green Area and STP 1 1,459.85 3.41
Surau 1 676.91 1.58
Sport Complex 1 1,069.68 2.50
Water Tank 1 649.49 1.52
Roads, Side walks and
Drainage
- 24,714.59 57.70
Double Story Shops 8 695.42 1.62
Slope and Retaining wall - 781.56 1.82
CHPTER TWO
 Earthworks are essential activity need to be done before
any construction activity starts.
 Creating a levelled or sloppy plat forms.
 It includes number of activities from site clearing, to
excavating for structures or pipes.
 Earthwork is one of most risky phases in the construction
of a project because of the multitude of unknowns.
Earth Work
---
Introduction:
Earth Work
Earth Work
Earth Work
1)Sites Clearing
 Clearing of the area
 Grubbing
 Stripping Topsoil
 Backfill of holes
 Dumping
2)Excavation
 Excavation in Soil
3)Filling
 Fill the material
 Compaction of Filling
Earth Work
---
Earth Work Stages:
 An earthmoving operations in which material is
excavated and removed from one location and
is used as a fill material at another location.
Earth Work
---
Cut and Fill
 Control Line Method
 Cross Sectional Method
 Grid method
 Software
Earth Work
---
Calculation Method:
 The grid system method involves; dividing the area into small equal
squares, purposing a level for the ground and calculating the volume of
the soil, (Either cut or Fill).
Earth Work
---
Grid Method:
For this project the cut and fill volume after calculation
using grid method are:
 Cutting volume = 59,498.37 m³
 Filling volume = 59,486.83 m3
Earth Work
---
Calculation Summary:
Item Work Description
Measured units Quantity Rate (RM) Amount (RM)
1 Cutting
1.1 common excavation in cuttings m^3 59,498.37 3.5 208,244.30
2 Fill
m^3 59,486.83 2.5 148,717.08
2.1
Suitable material from common excavation to form
embankment (Fill)
3 Retaining Wall
m^2 702 250 175,500.00
3.1
Supply and installation of wall component including
reinforcing 10 dons, anchor blocks, joint fillers cushion
pads, fasteners and inclusive of cast in situ wall panels
4 Slop works
m 1,415.25 62 87,745.50
4.1
Slope stabilization works horizontal drains, supply and
install 100 mm horizontal drains with 75 mm diameter
perforated PVC pipe wrapped with non woven Geotextile,
9 m long
5 TOTAL COST 620,206.88
Earth Work
---
Bill of Quantity:
 The difference in cut and fill will be used to
make a hilly area.
 Earthwork was designed using grid
method. From the calculation data, the
amount of cutting volume is 59,498.37 m³
and filling volume 59,486.83 m³.
Earth Work
---
Conclusion:
CHPTER THREE
 Road is an important aspect in development of certain area, it
provide linkage between area to another area and hence improve
the social growth to an area.
Road Work
---
Introduction:
 The location of a road and its design are considerably influenced by the
topography, physical features, and land use of the area traversed. The
topography of the profile of a road can generally be divided into three groups,
namely flat, rolling and mountainous.
Road Work
---
Introduction:
Type Description
Flat terrain
The natural ground cross slopes in a flat terrain are
generally below 3%
Rolling terrain
The natural ground cross slopes in a rolling terrain are
generally between 3 – 25%
Mountainous
terrain
The natural ground slopes in a mountainous terrain are
generally above 25%
 To propose the vertical and horizontal alignment of the
service road.
 To design the flexible pavement thickness for each
layer of the pavement structure.
 To propose safe and convenient route of road user by
complying with all technical Requirements.
Road Work
---
Objectives:
 The critical point of any road pavement design is the
commercial vehicle which is considering the main
parameter of designing
 In our area the volume of commercial vehicle per day is
too low, so that’s why we used the JKR new standard
for the low volume of commercial vehicle, thus
assuming that a the surrounding area will be developed
in the early future so we design the main road by
assuming a higher amount of commercial vehicle.
Road Work
---
Road Design:
Road Work
---
Road Design: Main Road
Road Work
---
Road Design: Sub Road
 Traffic signs or road signs are signs erected at the side of
or above roads to provide information to road users.
 Road signs in Malaysia are standardized road signs
similar to those used in other nations but with certain
distinctions.
 Malaysian traffic signs use Malay, the official and national
language in Malaysia. However, English is also used for
important public places as tourist attractions, airports,
railway stations and immigration checkpoint. Some
places, both of the language, Malay and English are used
in the road sign.
Road Work
---
Road Sign
 Road signage is including the road marking
and also signage board. Most of the road
signage put at the T-junction. Hump used to
control the speed of vehicles to slow down the
speed of vehicles.
 The proposed road marking and signage plan
is shown in the project plan.
Road Work
---
Road Design:
Item Work Description measuresd
units
Quantity Rate (RM)
Amount
(RM)
1 Main Road
1.1
Sub-Base
Sand blanket/blinding or approval equivalent material as sub-base
compacted to required gradients, cambers, falls and cross falls as
specified
250mm Thick, to receive crusher run
m^2 2,736.89 7.50 20,526.68
1.2
Road-base
Crusher run spread, levelled and compacted to required gradients,
cambers, falls and cross falls as specified
150mm Thick, to receive bitumen binder
m^2 2,736.89 13.91 38,070.14
1.3
Surfacing
Asphaltic concrete binder course as specified
100mm Thick, slopping not exceeding 15 degree from horizontal
m^2 2,736.89 24.50 67,053.81
Road Work
---
Bill of Quantity:
2 Sub-Road
m^2 7,994.63 6.24 49,886.49
2.1
Sub-Base
Sand blanket/blinding or approval equivalent material as sub-base
compacted to required gradients, cambers, falls and cross falls as
specified
150mm Thick, to receive crusher run
2.2
Road-base
Crusher run spread, levelled and compacted to required gradients,
cambers, falls and cross falls as specified
200mm Thick, to receive bitumen binder
m^2 7,994.63 15.91 127,194.56
2.3
Surfacing
Asphaltic concrete binder course as specified
40mm Thick, slopping not exceeding 15 degree from horizontal
m^2 7,994.63 20.50 163,889.92
Road Work
---
Bill of Quantity:
4
Road Kerb Cast-in-situ
concrete kerb including jointing, excavation, backfilling, bedding and disposal of
surplus materials. Type SM2
m 2,318.00 34.70 80,434.60
5
Road Marking Hot-applied
superimposed reflectorised thermoplastic road markings 3mm thick hot-applied
superimposed reflectorised thermoplastic road markings with 20% glassbead as
specified in BS 3262 and in the drawing.
ma) Continuity Line 869.15 2.70 2,346.71
c) Center Line/Lane Line 202.40 1.80 364.32
d) Edge Line 2,318.00 2.70 6,258.60
e) Stop Line 60.50 5.40 326.70
6
Signagen
No
a) Kilometre post: inclusive of all necessary works at location 6.00 140.00 840.00
b) Direction arrow 26.00 65.00 1,690.00
c) Stop Sign 26.00 65.00 1,690.00
7 TOTAL COST 560,572.5
Road Work---
Bill of Quantity:
 Ministry of Works Malaysia, MOWs tried to provide a
better safety of road in Malaysia alongside with the
Government efforts to reduce traffic accident and to
achieve its targets.
 Although studies shown that causes to most of the
accident is because of the drivers themselves
 MOWs always make it positive effort in order to improve
traffic accident by giving further stress on engineering
aspect with proactive and reactive action during design,
construction and maintenance stage.
Road Work
---
Conclusion:
CHPTER FOUR
Drainage System
 Water is the main contributor to the wear and damage of roads. The
water can be in the form of ground water, surface water (streams
and rivers) or rain and it can damage the road in several ways:
• By washing away the soil (erosion and scouring)
• By making the road body less resistant to traffic (i.e. weakening the load bearing
capacity)
• By depositing soils (silting) which may obstruct the passage of water, or
• By washing away entire sections of the road or its structures.
 Typical problems caused by poor drainage include:
---
Introduction
• Rutting • Cracking
• Potholes • Erosion
• Washout • Heaving and Flooding
Drainage System
An efficient drainage system is essential to allow water to flow off and away from
the road as quickly as possible. This is achieved by a system consisting of the
following components:
 Road surface drainage which enables the water to flow off the road surface,
 Side drains which collect and lead the water away from the road,
 Road embankments in flood prone terrain, lifting the road surface well above
the highest flood levels,
 Catch-water drains which catch surface water before it reaches the road,
 Scour checks, preventing erosion in the ditches by slowing down the flow of
the water,
 Culverts which lead the water from the side drains under the road to the
other (lower) side,
 Bridges and drifts which allows the road to cross rivers and streams in a
controlled manner throughout the seasons.
---
Objectives
Drainage System
The design of drainage system is based on:
Urban storm water management Manual for Malaysia (MASMA) published by department of
irrigation & drainage, Malaysia, 2000.
Polynomial approximation of IDF curves:
Polynomial expressions in the form of equation have been fitted to publish IDF curves for the 35
main cities/towns in Malaysia. From MASMA.
Ln ( r I t)= a + b ln (t) + c ( ln (t))2 + d (Ln (t))3 ……….. (1)
Where:
( r I t)= The average rainfall intensity (mm/hr) for ARI and duration t
r= Average return interval (years)
t= Duration (minutes)
a,b,c,d are Fitting constants dependent on ARI
---
Design Rainfall Intensity
Drainage System
 Description:
---
Design Rainfall Intensity
Average return interval (ARI) a b c d
50 years 5.3578 0.5094 -0.2056 0.0131
100 years 5.0646 0.7917 -0.2583 0.0161
The value of a,b,c, &d obtained from Table 13.A MASMA Manual Coefficients
for the IDF Equations for the Different Major Cities and Towns in Malaysia (30≤
t ≤ 1000 min) selected t= 12 hrs = 720 min
Summary of design rainfall intensity: total design rainfall using rational method
Design Intensity for 50 years= 50 I 720 = 34.37 mm/hr Q100= CIA
Design intensity for 100 years= 100 I 720= 39.65 mm/hr Main channel Q100= 0.61 m3/s
Sub-channel Q100=0.024 m3/s
Drainage System
To design the channel we have to use the manning’s equation
Q= 1/n AR2/3 S1/2
Summary of channel design
Main channel design Q= 2.7 m3/s > 0.61 m3/s ok!
v= 2.18 m/s < 4.00 m/s ok!
Sub-channel design Q= 0.4 m3/s > 0.024 m3/s ok!
v= 1.36 m/s < 4.00 m/s ok!
---
Channel Design
Drainage System
---
Channel Provided
Sub- channelMain channel
Drainage System
A culvert is a device used to channel water.
There are three primary materials that culverts are made out of steel,
precast concrete and polymer (plastic). They can also be built as a
hybrid between steel and concrete.
For this project, we have decided to use 1500x1500mm precast box
culvert proposed as the culvert for road crossing the drain.
---
Culvert Provided
Type: Precast culvert
Size : 1500x1500mm
Drainage System
---
Bill of Quantity
Item Work Description measuresd
units
Quantity Rate (RM) Amount (RM)
1 Main Drain
1.1
SURFACE DRAINAGE
DRAINAGE
Excavation
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes not exceeding 200mm
nominal
size, not exceeding 2.00m average 1.00m deep
m 119.18 11.33 1,350.31
1.2
Main drain
Supply, lay and joint precast U‐drain size
1200x900 with dry weather flow and
without lid
119.18 410.00 48,863.80
Drainage System
---
Bill of Quantity
2 Sub Drain
m 3,258.26 11.33 36,916.09
2.1
SURFACE DRAINAGE
DRAINAGE
Excavation
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes not exceeding 200mm nominal
size, not exceeding 2.00m average 1.00m deep
2.2
sub drain
Supply, lay and joint precast U‐drain size
600x450 with dry weather flow and
without lid
m 3,258.26 140.00 456,156.40
3 cover
m 3258.26 105 342117.3
3.1
Precast reinforced concrete drain cover
size 1000mm x 600mm x 225mm thick
4 culvert
m 78.44 900 70596
4.1
Construct and complete box culvert
including all necessary works; size
1500mm x 1500mm
5 TOTAL 905,785.79
Drainage System
The 1.2 m width x 0.9 m depth main drains have proposed, and for
sub drains the 0.6 m width x 0.45m depth channel is proposed. To
drain out the storm water. Culvert 1500x1500mm have been
proposed at the road which crossing the drain. Overall theses
proposed channels and culverts can carry the amount of rainfall for
this area. The overall cost for the drainage system is RM905785.79
---
Summary
CHPTER FIVE
Sewage System
 Sewerage system is essential for any commercial,
residential and industrial buildings.
 Sewerage system is a network of pipes, pumps, and force
mains for the collection of wastewater or sewage, from a
community to ensure their hygiene and health.
 Modern sewerage systems fall under two categories:
domestic and industrial sewers and storm sewers.
Sometimes a combined system provides only one network
of pipes, mains, and outfall sewers for all types of sewage
---
Introduction
 This part is to study and plan for the overall
sewage generation and collection based on the
present layout plan.
Sewage System
---
Objectives
 Proposed sewer lines will collect the sewage
generated from the new residence buildings,
commercial buildings, surau, sport complex and
will transfer them using the proposed pipes and
manholes to the sewerage treatment plan within the
project site.
 The proposed reticulation system will consist of
HDPE pipe and precast clay manholes.
Sewage System
---
Proposed Sewage Design
The design of the sewer pipes and manholes of
this project are based on the following standards:
 “ M.S 1228: 1991, code of practice of design and
installation of sewerage systems” by the standard and
industrial research institute Malaysia ( SIRIM).
 “Malaysia sewerage industry guidelines (volume I –
V)” by national water services commission or
suruhanjaya perkhidamtan Air Negara (SPAN)
Sewage System
---
Design Standards
Sewage System
---
Summary of Calculation and Design
Defention Main Pipe Sub Pipe
Q Produced m3/s 4.85x10^-3 1.0*10^-3
material HDPE HDPE
n value 0.0120 0.0120
Diameter mm 250.0000 100.0000
angle 93.0400 93.0400
AREA mm^2 49062.5000 7850.0000
hydraulic radius R 0.1575 0.0855
slope 0.0025 0.0025
Q pipe m^3/s 0.1550 0.0590
Discharge Checking 0.155 > 4.85x10^-3 0.059 > 1.0x10^-3
Result OK! OK!
Velocity Produced 0.9 0.85
Velocity Checking m/s 0.8<0.9<4 0.8<0.85<4
Result OK! OK!
Length m 153.20 764.22
Sewage System
---
Bill of Quantity
Item Work Description
Measuresd
units
Quantity
Rate
(RM)
Amount
(RM)
1
Main Pipe
Excavation and filling with Pipe size 200mm (HDPE) m 153.20 86.50 13,251.80
2
Sub Pipe
Excavation and filling with Pipe size 100 mm (HDPE) m 764.22 67.50 51,584.85
3
Manholes
Type: Clay Material
Cover: Steel
Size: 1200*1200*1000
With Installation
Unit 14.00 300.00 4,200.00
4 TOTAL 69,036.65
CHPTER SIX
 The water supply industry is important not only to
maintain the health of the community, but for the
sustainability of industry, business and agriculture.
 Without adequate water supplies our present
society would never have evolved, and our lives
today would be unrecognizable.
 Like the other service providers, electricity,
telephone and gas, the water utilities deliver their
product to the home, which requires a network of
distribution pipes to service each household.
Water Supply
---
Introduction:
 To comply with design manual published
by Syarikat Air Terengganu (SATU) and
Malaysian Standard (MS) 1395 :
Specification For Pillar Hydrant
 To provide sufficient water supply
requirement for the development area
based on domestic demand and external
fire hydrant system
Water Supply
---
Objectives:
1- 2-
3-
Water Supply
---
Water Supply Components:
 In our stage we
are going to
design the
distribution
system
 Which contain
the Reservoir
(storage tank),
Main pipes, Sup-
pipes, Fire
hydrant.
Water Supply
 In order to design the water distribution system
we need to know the water demand for our area
 Water demand is based on population served,
per capita consummation, and service factor,
industrial and other special demand.
 In estimating water demand, various factors
should be taken into account directly or indirectly.
Water Supply
---
Water Demands:
Water demand in our area is basically contain
1. 82 units with 5 person each house + Fire hydrant
2. Surau 150 person
3. Complex centre 200 person
4. 8 Shopes
Summary of water demand
175380+1200+11000+3000= 190580 L/day
= 190580 L/day X 2.5 (factor)
= 476.45 m3/day
Water required for 3 days
= 476.45 m3/day x 3 = 1429.35 m3/day
Water Supply
---
Water Demands:
TANK DESIGN
The design of tank is based on 3 days water demand.
Tank shape; circular
Diameter = 23 m
Height = 3.5 m
Total volume of tank = (π (11.5)2) x 3.5= 1454.16 m3 > 1429.35 m3 ok!
Tank material is Fibber Reinforced plastic
PIPE DESIGN
Four types of pipes have been used
1. Main pipe
2. Fire hydrant pipe
3. Pipe in one raw of the houses
4. Pipe for one house
Water Supply
---
Tank and Pipe Design:
1- Main pipe
Q demand = 0.004 m3/s
Pipe provided : steel pipe of 150mm diameter
Q design = 0.009 m3/s > 0.004 m3/s
2- Fire hydrant pipe
Q demand = 0.001 m3/s
Pipe provided : steel pipe of 120mm diameter
Q design = 0.004 m3/s > 0.001 m3/s
3- Pipe in one raw
Q demand = 0.0003 m3/s
Pipe provided : PVC pipe of 50 mm diameter
Q design = 0.0057 m3/s > 0.0003 m3/s
4- Pipe for one house
Q demand = 0.00003 m3/s
Pipe provided : PVC pipe of 20 mm diameter
Q design = 0.00053 m3/s > 0.00003 m3/s
Water Supply
---
Tank and Pipe Design:
Item Work Description Measured Units Quantity
Rate
(RM)
Amount
(RM)
1 Main Pipe
1.1 Excavation and Installation m 480.00 21.25 10,200.00
1.2 Pipe: Steel, 150mm m 480.00 133.30 63,984.00
1.3
Pipe Fittings:
Unit
T- Shape 10 23.20 232.00
90- Degree 7 30.40 212.80
45- Degree 4 15.60 62.40
Water Supply
---
Bill of Quantity:
2 Sub Pipe
2.1 Excavation and Installation m 641.53 20.00
12,830.6
0
2.2 Pipe: PVC, 50mm m 641.53 2.20 1,411.37
2.3
Pipe Fittings:
Unit
T- Shape 81 20.50 1,660.50
90- Degree 108 30.40 3,283.20
45- Degree 8 15.20 121.60
3 Water Meter
3.1 Water Meter Unit 92 37.00 3,404.00
Water Supply
---
Bill of Quantity:
4 Fire Hydrant
4.1 Fire Hydrant Unit 9
1,945.0
0
17,505.00
4.2
Pipe: Steel, 150mm m 400 10.60 4,240.00
Pipe Fittings:
Unit
T- Shape 6 31.50 189.00
90- Degree 10 50.40 504.00
45- Degree 4 18.90 75.60
5 Water Tank
5.1
water tank together with tank
tower and instullation
Unit 1
500,000
.00
500,000.00
6 TOTAL COST 619,916.07
Water Supply
---
Bill of Quantity:
 VPC pipes are no longer use in Malaysia because it’s easy to break.
 Fiberglass Reinforced Plastic (FRP) Tank is proposed as a elevated
storage water tank. Because it is easily to be assembled by bolting
them together, The designed meet highest standard of sanitary
storage and Have high strength to weight ratio and it is lighter than
steel panel.
Water Supply
---
Conclusion:
CHAPTER SEVEN
E.M.P
 EMP is a process which ensures that all environmental matters are taken
into account quite early in the project at planning process itself.
 It takes into consideration not only technical and economic considerations
but also, traditional aspects like impact on local people, biodiversity etc.
Purpose of EMP
• EMP was formulated to protect the environment and provide a
guide for an overall environmental management
• It also forms the basis for reporting on an environmental
management performance during the implementation of various
activities during construction and operations of the proposed
project
---
What is EMP?
E.M.P
 Identification of key potential environmental impacts and proposing an action plan
for mitigation during pre-construction, construction & operational stages
 Establishing appropriate standards and procedures for mitigation and monitoring
the environmental impacts
Benefits & Advantages of EMP
 Lower project costs in the long-term
 Increased project acceptance
 Improved project design
 Informed decision making
 Environmentally sensitive decisions
 Increased accountability and transparency
 Reduced environmental damage
 Improved integration of projects into their environmental and social settings
---
Objectives
E.M.P
 Agriculture
 Construction (Road networks, Malls, Townships, Dam etc)
 Industries
 Electrical projects
 Waste disposal
 Any developmental projects around Protected Areas / Nature Preserves
 Clean Development Mechanism CDM project
---
Which type of projects under go EMP?
E.M.P
 The proposed development has been studied from all angles
 This report has recommended various measures to control and
manage the environment and hence reduce the environmental
impact to its minimum level
 The proposed development is expected to improve the living
standard of the surrounding residents and community
---
Summary
N
O
DESCRIPTION COST (RM)
1 EARTH WORK 620,206.88
2 ROAD WORK 560,572.50
3 DRAINAGE 905,785.79
4 SEWAGE 69,036.65
5 WATER SUPPLY 619,916.07
6 TOTAL 2,775,517.89
TOTAL COST OF THE
PROJECT
Presentation sayed

Mais conteúdo relacionado

Mais procurados

Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Pankti Jethi
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
Cordon line survey
Cordon line surveyCordon line survey
Cordon line surveyNilgabs1
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume StudyAbontee
 
UTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by ManjuraliUTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by ManjuraliManjurali Balya
 
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptxDESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptxSamirsinh Parmar
 
Traffic & Transportation surveys
Traffic & Transportation surveysTraffic & Transportation surveys
Traffic & Transportation surveysDhwani Shah
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Study of IS 962 1989 – Code of Practice for Architectural and Building
Study of IS 962 1989 – Code of Practice for Architectural and BuildingStudy of IS 962 1989 – Code of Practice for Architectural and Building
Study of IS 962 1989 – Code of Practice for Architectural and BuildingRohan Dasgupta
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topicsShubham Sadh
 
Road arboriculture
Road arboricultureRoad arboriculture
Road arboricultureAtif Khan
 
Types of failure in rigid pavements
Types of failure in rigid pavementsTypes of failure in rigid pavements
Types of failure in rigid pavementsAglaia Connect
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySai Santosh Yakkali
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Urban Transportation system - mass transit system
Urban Transportation system - mass transit systemUrban Transportation system - mass transit system
Urban Transportation system - mass transit systemEddy Ankit Gangani
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Civil Zone
 
project final year civil
project final year civilproject final year civil
project final year civilAlankar jaiswal
 

Mais procurados (20)

Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Cordon line survey
Cordon line surveyCordon line survey
Cordon line survey
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
UTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by ManjuraliUTS- Transportation Surveys by Manjurali
UTS- Transportation Surveys by Manjurali
 
Road construction
Road constructionRoad construction
Road construction
 
Highway planning and alignment
Highway planning and alignmentHighway planning and alignment
Highway planning and alignment
 
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptxDESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
DESIGN OF HILL ROADS AND ITS ALIGNMENT.pptx
 
Traffic & Transportation surveys
Traffic & Transportation surveysTraffic & Transportation surveys
Traffic & Transportation surveys
 
Road drainage
Road drainageRoad drainage
Road drainage
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Study of IS 962 1989 – Code of Practice for Architectural and Building
Study of IS 962 1989 – Code of Practice for Architectural and BuildingStudy of IS 962 1989 – Code of Practice for Architectural and Building
Study of IS 962 1989 – Code of Practice for Architectural and Building
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topics
 
Road arboriculture
Road arboricultureRoad arboriculture
Road arboriculture
 
Types of failure in rigid pavements
Types of failure in rigid pavementsTypes of failure in rigid pavements
Types of failure in rigid pavements
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Urban Transportation system - mass transit system
Urban Transportation system - mass transit systemUrban Transportation system - mass transit system
Urban Transportation system - mass transit system
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)
 
project final year civil
project final year civilproject final year civil
project final year civil
 

Destaque

Destaque (10)

Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment Presentation
 
Measurement Presentation
Measurement PresentationMeasurement Presentation
Measurement Presentation
 
Road
RoadRoad
Road
 
Drainage
DrainageDrainage
Drainage
 
Highways and motorways of pakistan
Highways and motorways of pakistanHighways and motorways of pakistan
Highways and motorways of pakistan
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
 
HIGHWAY ENGINEERING
HIGHWAY ENGINEERINGHIGHWAY ENGINEERING
HIGHWAY ENGINEERING
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 

Semelhante a Presentation sayed

Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometricsKHUSHBU SHAH
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfDanielWisman1
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Malyar Talash
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Gargharshit315
 
geometric design ppt unit 3 (1).ppt
geometric design ppt unit 3 (1).pptgeometric design ppt unit 3 (1).ppt
geometric design ppt unit 3 (1).pptGate20241
 
Design & Construction of B.I.T. Driveway (As per rural specification)
Design & Construction of B.I.T. Driveway (As per rural specification)Design & Construction of B.I.T. Driveway (As per rural specification)
Design & Construction of B.I.T. Driveway (As per rural specification)IJERA Editor
 
Design of low volume road in dallo manna, ethiopia
Design of low volume road in dallo manna, ethiopiaDesign of low volume road in dallo manna, ethiopia
Design of low volume road in dallo manna, ethiopiaeSAT Journals
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDevesh Chaurasia
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemeakram akhtar
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESMalay Talaviya
 
PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUSubhendu Samui
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUISubhendu Samui
 
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptHill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptswaongniyogi
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNTarun2222
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highwayholegajendra
 
Improvement to Village Road Based on Traffic Characteristics
Improvement to Village Road Based on Traffic CharacteristicsImprovement to Village Road Based on Traffic Characteristics
Improvement to Village Road Based on Traffic CharacteristicsIJERA Editor
 
Road bridge &amp; railway construction pdf
Road bridge &amp; railway construction pdfRoad bridge &amp; railway construction pdf
Road bridge &amp; railway construction pdfSaqib Imran
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTUVATSAL PATEL
 

Semelhante a Presentation sayed (20)

Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Garg
 
geometric design ppt unit 3 (1).ppt
geometric design ppt unit 3 (1).pptgeometric design ppt unit 3 (1).ppt
geometric design ppt unit 3 (1).ppt
 
Design & Construction of B.I.T. Driveway (As per rural specification)
Design & Construction of B.I.T. Driveway (As per rural specification)Design & Construction of B.I.T. Driveway (As per rural specification)
Design & Construction of B.I.T. Driveway (As per rural specification)
 
Design of low volume road in dallo manna, ethiopia
Design of low volume road in dallo manna, ethiopiaDesign of low volume road in dallo manna, ethiopia
Design of low volume road in dallo manna, ethiopia
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeT
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage system
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDU
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
 
Hill_Roads
Hill_RoadsHill_Roads
Hill_Roads
 
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptHill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUN
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
Improvement to Village Road Based on Traffic Characteristics
Improvement to Village Road Based on Traffic CharacteristicsImprovement to Village Road Based on Traffic Characteristics
Improvement to Village Road Based on Traffic Characteristics
 
Road bridge &amp; railway construction pdf
Road bridge &amp; railway construction pdfRoad bridge &amp; railway construction pdf
Road bridge &amp; railway construction pdf
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 

Presentation sayed

  • 1.
  • 2. uniselU N I V E R S I T Y S E L A N G O R Engineered by: 1. Eng. Feroz Faizmand 2. Eng. Mustafa Jameel 3. Eng. Ahmad Habib 4. Eng. Sayed Asadullah
  • 3. Table of Contents  Introduction to Project  Earthworks  Road Works  Drainage System  Sewage System  Water Supply System  Environmental and Management Planning
  • 5. The Project FAMA Consultant is pleased to introduce his new project with the following descriptions. --- Introduction Address Total Area The Project Mukim Datu Mengkebang, Derah Batu Mengkebang, Jajahan Kuala Kari, Negeri Kelantan Darul Naim 42,834.00 m2 1. Site Clearance, Cut and Fill, Slopes and Retaining walls 2. Drainage System 3. Sewage System 4. Water Supply System 5. Road, Shoulder and Road Curbs
  • 6. The Project --- Land Usages Type Of Property Quantity Total Area Used m2 Total Area Used % Double Story Houses 82 12,786.5 29.85 Green Area and STP 1 1,459.85 3.41 Surau 1 676.91 1.58 Sport Complex 1 1,069.68 2.50 Water Tank 1 649.49 1.52 Roads, Side walks and Drainage - 24,714.59 57.70 Double Story Shops 8 695.42 1.62 Slope and Retaining wall - 781.56 1.82
  • 8.  Earthworks are essential activity need to be done before any construction activity starts.  Creating a levelled or sloppy plat forms.  It includes number of activities from site clearing, to excavating for structures or pipes.  Earthwork is one of most risky phases in the construction of a project because of the multitude of unknowns. Earth Work --- Introduction:
  • 12. 1)Sites Clearing  Clearing of the area  Grubbing  Stripping Topsoil  Backfill of holes  Dumping 2)Excavation  Excavation in Soil 3)Filling  Fill the material  Compaction of Filling Earth Work --- Earth Work Stages:
  • 13.  An earthmoving operations in which material is excavated and removed from one location and is used as a fill material at another location. Earth Work --- Cut and Fill
  • 14.  Control Line Method  Cross Sectional Method  Grid method  Software Earth Work --- Calculation Method:
  • 15.  The grid system method involves; dividing the area into small equal squares, purposing a level for the ground and calculating the volume of the soil, (Either cut or Fill). Earth Work --- Grid Method:
  • 16. For this project the cut and fill volume after calculation using grid method are:  Cutting volume = 59,498.37 m³  Filling volume = 59,486.83 m3 Earth Work --- Calculation Summary:
  • 17. Item Work Description Measured units Quantity Rate (RM) Amount (RM) 1 Cutting 1.1 common excavation in cuttings m^3 59,498.37 3.5 208,244.30 2 Fill m^3 59,486.83 2.5 148,717.08 2.1 Suitable material from common excavation to form embankment (Fill) 3 Retaining Wall m^2 702 250 175,500.00 3.1 Supply and installation of wall component including reinforcing 10 dons, anchor blocks, joint fillers cushion pads, fasteners and inclusive of cast in situ wall panels 4 Slop works m 1,415.25 62 87,745.50 4.1 Slope stabilization works horizontal drains, supply and install 100 mm horizontal drains with 75 mm diameter perforated PVC pipe wrapped with non woven Geotextile, 9 m long 5 TOTAL COST 620,206.88 Earth Work --- Bill of Quantity:
  • 18.  The difference in cut and fill will be used to make a hilly area.  Earthwork was designed using grid method. From the calculation data, the amount of cutting volume is 59,498.37 m³ and filling volume 59,486.83 m³. Earth Work --- Conclusion:
  • 20.  Road is an important aspect in development of certain area, it provide linkage between area to another area and hence improve the social growth to an area. Road Work --- Introduction:
  • 21.  The location of a road and its design are considerably influenced by the topography, physical features, and land use of the area traversed. The topography of the profile of a road can generally be divided into three groups, namely flat, rolling and mountainous. Road Work --- Introduction: Type Description Flat terrain The natural ground cross slopes in a flat terrain are generally below 3% Rolling terrain The natural ground cross slopes in a rolling terrain are generally between 3 – 25% Mountainous terrain The natural ground slopes in a mountainous terrain are generally above 25%
  • 22.  To propose the vertical and horizontal alignment of the service road.  To design the flexible pavement thickness for each layer of the pavement structure.  To propose safe and convenient route of road user by complying with all technical Requirements. Road Work --- Objectives:
  • 23.  The critical point of any road pavement design is the commercial vehicle which is considering the main parameter of designing  In our area the volume of commercial vehicle per day is too low, so that’s why we used the JKR new standard for the low volume of commercial vehicle, thus assuming that a the surrounding area will be developed in the early future so we design the main road by assuming a higher amount of commercial vehicle. Road Work --- Road Design:
  • 26.  Traffic signs or road signs are signs erected at the side of or above roads to provide information to road users.  Road signs in Malaysia are standardized road signs similar to those used in other nations but with certain distinctions.  Malaysian traffic signs use Malay, the official and national language in Malaysia. However, English is also used for important public places as tourist attractions, airports, railway stations and immigration checkpoint. Some places, both of the language, Malay and English are used in the road sign. Road Work --- Road Sign
  • 27.  Road signage is including the road marking and also signage board. Most of the road signage put at the T-junction. Hump used to control the speed of vehicles to slow down the speed of vehicles.  The proposed road marking and signage plan is shown in the project plan. Road Work --- Road Design:
  • 28. Item Work Description measuresd units Quantity Rate (RM) Amount (RM) 1 Main Road 1.1 Sub-Base Sand blanket/blinding or approval equivalent material as sub-base compacted to required gradients, cambers, falls and cross falls as specified 250mm Thick, to receive crusher run m^2 2,736.89 7.50 20,526.68 1.2 Road-base Crusher run spread, levelled and compacted to required gradients, cambers, falls and cross falls as specified 150mm Thick, to receive bitumen binder m^2 2,736.89 13.91 38,070.14 1.3 Surfacing Asphaltic concrete binder course as specified 100mm Thick, slopping not exceeding 15 degree from horizontal m^2 2,736.89 24.50 67,053.81 Road Work --- Bill of Quantity:
  • 29. 2 Sub-Road m^2 7,994.63 6.24 49,886.49 2.1 Sub-Base Sand blanket/blinding or approval equivalent material as sub-base compacted to required gradients, cambers, falls and cross falls as specified 150mm Thick, to receive crusher run 2.2 Road-base Crusher run spread, levelled and compacted to required gradients, cambers, falls and cross falls as specified 200mm Thick, to receive bitumen binder m^2 7,994.63 15.91 127,194.56 2.3 Surfacing Asphaltic concrete binder course as specified 40mm Thick, slopping not exceeding 15 degree from horizontal m^2 7,994.63 20.50 163,889.92 Road Work --- Bill of Quantity:
  • 30. 4 Road Kerb Cast-in-situ concrete kerb including jointing, excavation, backfilling, bedding and disposal of surplus materials. Type SM2 m 2,318.00 34.70 80,434.60 5 Road Marking Hot-applied superimposed reflectorised thermoplastic road markings 3mm thick hot-applied superimposed reflectorised thermoplastic road markings with 20% glassbead as specified in BS 3262 and in the drawing. ma) Continuity Line 869.15 2.70 2,346.71 c) Center Line/Lane Line 202.40 1.80 364.32 d) Edge Line 2,318.00 2.70 6,258.60 e) Stop Line 60.50 5.40 326.70 6 Signagen No a) Kilometre post: inclusive of all necessary works at location 6.00 140.00 840.00 b) Direction arrow 26.00 65.00 1,690.00 c) Stop Sign 26.00 65.00 1,690.00 7 TOTAL COST 560,572.5 Road Work--- Bill of Quantity:
  • 31.  Ministry of Works Malaysia, MOWs tried to provide a better safety of road in Malaysia alongside with the Government efforts to reduce traffic accident and to achieve its targets.  Although studies shown that causes to most of the accident is because of the drivers themselves  MOWs always make it positive effort in order to improve traffic accident by giving further stress on engineering aspect with proactive and reactive action during design, construction and maintenance stage. Road Work --- Conclusion:
  • 33. Drainage System  Water is the main contributor to the wear and damage of roads. The water can be in the form of ground water, surface water (streams and rivers) or rain and it can damage the road in several ways: • By washing away the soil (erosion and scouring) • By making the road body less resistant to traffic (i.e. weakening the load bearing capacity) • By depositing soils (silting) which may obstruct the passage of water, or • By washing away entire sections of the road or its structures.  Typical problems caused by poor drainage include: --- Introduction • Rutting • Cracking • Potholes • Erosion • Washout • Heaving and Flooding
  • 34. Drainage System An efficient drainage system is essential to allow water to flow off and away from the road as quickly as possible. This is achieved by a system consisting of the following components:  Road surface drainage which enables the water to flow off the road surface,  Side drains which collect and lead the water away from the road,  Road embankments in flood prone terrain, lifting the road surface well above the highest flood levels,  Catch-water drains which catch surface water before it reaches the road,  Scour checks, preventing erosion in the ditches by slowing down the flow of the water,  Culverts which lead the water from the side drains under the road to the other (lower) side,  Bridges and drifts which allows the road to cross rivers and streams in a controlled manner throughout the seasons. --- Objectives
  • 35. Drainage System The design of drainage system is based on: Urban storm water management Manual for Malaysia (MASMA) published by department of irrigation & drainage, Malaysia, 2000. Polynomial approximation of IDF curves: Polynomial expressions in the form of equation have been fitted to publish IDF curves for the 35 main cities/towns in Malaysia. From MASMA. Ln ( r I t)= a + b ln (t) + c ( ln (t))2 + d (Ln (t))3 ……….. (1) Where: ( r I t)= The average rainfall intensity (mm/hr) for ARI and duration t r= Average return interval (years) t= Duration (minutes) a,b,c,d are Fitting constants dependent on ARI --- Design Rainfall Intensity
  • 36. Drainage System  Description: --- Design Rainfall Intensity Average return interval (ARI) a b c d 50 years 5.3578 0.5094 -0.2056 0.0131 100 years 5.0646 0.7917 -0.2583 0.0161 The value of a,b,c, &d obtained from Table 13.A MASMA Manual Coefficients for the IDF Equations for the Different Major Cities and Towns in Malaysia (30≤ t ≤ 1000 min) selected t= 12 hrs = 720 min Summary of design rainfall intensity: total design rainfall using rational method Design Intensity for 50 years= 50 I 720 = 34.37 mm/hr Q100= CIA Design intensity for 100 years= 100 I 720= 39.65 mm/hr Main channel Q100= 0.61 m3/s Sub-channel Q100=0.024 m3/s
  • 37. Drainage System To design the channel we have to use the manning’s equation Q= 1/n AR2/3 S1/2 Summary of channel design Main channel design Q= 2.7 m3/s > 0.61 m3/s ok! v= 2.18 m/s < 4.00 m/s ok! Sub-channel design Q= 0.4 m3/s > 0.024 m3/s ok! v= 1.36 m/s < 4.00 m/s ok! --- Channel Design
  • 39. Drainage System A culvert is a device used to channel water. There are three primary materials that culverts are made out of steel, precast concrete and polymer (plastic). They can also be built as a hybrid between steel and concrete. For this project, we have decided to use 1500x1500mm precast box culvert proposed as the culvert for road crossing the drain. --- Culvert Provided Type: Precast culvert Size : 1500x1500mm
  • 40. Drainage System --- Bill of Quantity Item Work Description measuresd units Quantity Rate (RM) Amount (RM) 1 Main Drain 1.1 SURFACE DRAINAGE DRAINAGE Excavation Excavating trenches starting from formation level; earthwork support, part return, fill in and ram and remainder deposit, spread and level within site To receive drain pipes not exceeding 200mm nominal size, not exceeding 2.00m average 1.00m deep m 119.18 11.33 1,350.31 1.2 Main drain Supply, lay and joint precast U‐drain size 1200x900 with dry weather flow and without lid 119.18 410.00 48,863.80
  • 41. Drainage System --- Bill of Quantity 2 Sub Drain m 3,258.26 11.33 36,916.09 2.1 SURFACE DRAINAGE DRAINAGE Excavation Excavating trenches starting from formation level; earthwork support, part return, fill in and ram and remainder deposit, spread and level within site To receive drain pipes not exceeding 200mm nominal size, not exceeding 2.00m average 1.00m deep 2.2 sub drain Supply, lay and joint precast U‐drain size 600x450 with dry weather flow and without lid m 3,258.26 140.00 456,156.40 3 cover m 3258.26 105 342117.3 3.1 Precast reinforced concrete drain cover size 1000mm x 600mm x 225mm thick 4 culvert m 78.44 900 70596 4.1 Construct and complete box culvert including all necessary works; size 1500mm x 1500mm 5 TOTAL 905,785.79
  • 42. Drainage System The 1.2 m width x 0.9 m depth main drains have proposed, and for sub drains the 0.6 m width x 0.45m depth channel is proposed. To drain out the storm water. Culvert 1500x1500mm have been proposed at the road which crossing the drain. Overall theses proposed channels and culverts can carry the amount of rainfall for this area. The overall cost for the drainage system is RM905785.79 --- Summary
  • 44. Sewage System  Sewerage system is essential for any commercial, residential and industrial buildings.  Sewerage system is a network of pipes, pumps, and force mains for the collection of wastewater or sewage, from a community to ensure their hygiene and health.  Modern sewerage systems fall under two categories: domestic and industrial sewers and storm sewers. Sometimes a combined system provides only one network of pipes, mains, and outfall sewers for all types of sewage --- Introduction
  • 45.  This part is to study and plan for the overall sewage generation and collection based on the present layout plan. Sewage System --- Objectives
  • 46.  Proposed sewer lines will collect the sewage generated from the new residence buildings, commercial buildings, surau, sport complex and will transfer them using the proposed pipes and manholes to the sewerage treatment plan within the project site.  The proposed reticulation system will consist of HDPE pipe and precast clay manholes. Sewage System --- Proposed Sewage Design
  • 47. The design of the sewer pipes and manholes of this project are based on the following standards:  “ M.S 1228: 1991, code of practice of design and installation of sewerage systems” by the standard and industrial research institute Malaysia ( SIRIM).  “Malaysia sewerage industry guidelines (volume I – V)” by national water services commission or suruhanjaya perkhidamtan Air Negara (SPAN) Sewage System --- Design Standards
  • 48. Sewage System --- Summary of Calculation and Design Defention Main Pipe Sub Pipe Q Produced m3/s 4.85x10^-3 1.0*10^-3 material HDPE HDPE n value 0.0120 0.0120 Diameter mm 250.0000 100.0000 angle 93.0400 93.0400 AREA mm^2 49062.5000 7850.0000 hydraulic radius R 0.1575 0.0855 slope 0.0025 0.0025 Q pipe m^3/s 0.1550 0.0590 Discharge Checking 0.155 > 4.85x10^-3 0.059 > 1.0x10^-3 Result OK! OK! Velocity Produced 0.9 0.85 Velocity Checking m/s 0.8<0.9<4 0.8<0.85<4 Result OK! OK! Length m 153.20 764.22
  • 49. Sewage System --- Bill of Quantity Item Work Description Measuresd units Quantity Rate (RM) Amount (RM) 1 Main Pipe Excavation and filling with Pipe size 200mm (HDPE) m 153.20 86.50 13,251.80 2 Sub Pipe Excavation and filling with Pipe size 100 mm (HDPE) m 764.22 67.50 51,584.85 3 Manholes Type: Clay Material Cover: Steel Size: 1200*1200*1000 With Installation Unit 14.00 300.00 4,200.00 4 TOTAL 69,036.65
  • 51.  The water supply industry is important not only to maintain the health of the community, but for the sustainability of industry, business and agriculture.  Without adequate water supplies our present society would never have evolved, and our lives today would be unrecognizable.  Like the other service providers, electricity, telephone and gas, the water utilities deliver their product to the home, which requires a network of distribution pipes to service each household. Water Supply --- Introduction:
  • 52.  To comply with design manual published by Syarikat Air Terengganu (SATU) and Malaysian Standard (MS) 1395 : Specification For Pillar Hydrant  To provide sufficient water supply requirement for the development area based on domestic demand and external fire hydrant system Water Supply --- Objectives:
  • 53. 1- 2- 3- Water Supply --- Water Supply Components:
  • 54.  In our stage we are going to design the distribution system  Which contain the Reservoir (storage tank), Main pipes, Sup- pipes, Fire hydrant. Water Supply
  • 55.  In order to design the water distribution system we need to know the water demand for our area  Water demand is based on population served, per capita consummation, and service factor, industrial and other special demand.  In estimating water demand, various factors should be taken into account directly or indirectly. Water Supply --- Water Demands:
  • 56. Water demand in our area is basically contain 1. 82 units with 5 person each house + Fire hydrant 2. Surau 150 person 3. Complex centre 200 person 4. 8 Shopes Summary of water demand 175380+1200+11000+3000= 190580 L/day = 190580 L/day X 2.5 (factor) = 476.45 m3/day Water required for 3 days = 476.45 m3/day x 3 = 1429.35 m3/day Water Supply --- Water Demands:
  • 57. TANK DESIGN The design of tank is based on 3 days water demand. Tank shape; circular Diameter = 23 m Height = 3.5 m Total volume of tank = (π (11.5)2) x 3.5= 1454.16 m3 > 1429.35 m3 ok! Tank material is Fibber Reinforced plastic PIPE DESIGN Four types of pipes have been used 1. Main pipe 2. Fire hydrant pipe 3. Pipe in one raw of the houses 4. Pipe for one house Water Supply --- Tank and Pipe Design:
  • 58. 1- Main pipe Q demand = 0.004 m3/s Pipe provided : steel pipe of 150mm diameter Q design = 0.009 m3/s > 0.004 m3/s 2- Fire hydrant pipe Q demand = 0.001 m3/s Pipe provided : steel pipe of 120mm diameter Q design = 0.004 m3/s > 0.001 m3/s 3- Pipe in one raw Q demand = 0.0003 m3/s Pipe provided : PVC pipe of 50 mm diameter Q design = 0.0057 m3/s > 0.0003 m3/s 4- Pipe for one house Q demand = 0.00003 m3/s Pipe provided : PVC pipe of 20 mm diameter Q design = 0.00053 m3/s > 0.00003 m3/s Water Supply --- Tank and Pipe Design:
  • 59. Item Work Description Measured Units Quantity Rate (RM) Amount (RM) 1 Main Pipe 1.1 Excavation and Installation m 480.00 21.25 10,200.00 1.2 Pipe: Steel, 150mm m 480.00 133.30 63,984.00 1.3 Pipe Fittings: Unit T- Shape 10 23.20 232.00 90- Degree 7 30.40 212.80 45- Degree 4 15.60 62.40 Water Supply --- Bill of Quantity:
  • 60. 2 Sub Pipe 2.1 Excavation and Installation m 641.53 20.00 12,830.6 0 2.2 Pipe: PVC, 50mm m 641.53 2.20 1,411.37 2.3 Pipe Fittings: Unit T- Shape 81 20.50 1,660.50 90- Degree 108 30.40 3,283.20 45- Degree 8 15.20 121.60 3 Water Meter 3.1 Water Meter Unit 92 37.00 3,404.00 Water Supply --- Bill of Quantity:
  • 61. 4 Fire Hydrant 4.1 Fire Hydrant Unit 9 1,945.0 0 17,505.00 4.2 Pipe: Steel, 150mm m 400 10.60 4,240.00 Pipe Fittings: Unit T- Shape 6 31.50 189.00 90- Degree 10 50.40 504.00 45- Degree 4 18.90 75.60 5 Water Tank 5.1 water tank together with tank tower and instullation Unit 1 500,000 .00 500,000.00 6 TOTAL COST 619,916.07 Water Supply --- Bill of Quantity:
  • 62.  VPC pipes are no longer use in Malaysia because it’s easy to break.  Fiberglass Reinforced Plastic (FRP) Tank is proposed as a elevated storage water tank. Because it is easily to be assembled by bolting them together, The designed meet highest standard of sanitary storage and Have high strength to weight ratio and it is lighter than steel panel. Water Supply --- Conclusion:
  • 64. E.M.P  EMP is a process which ensures that all environmental matters are taken into account quite early in the project at planning process itself.  It takes into consideration not only technical and economic considerations but also, traditional aspects like impact on local people, biodiversity etc. Purpose of EMP • EMP was formulated to protect the environment and provide a guide for an overall environmental management • It also forms the basis for reporting on an environmental management performance during the implementation of various activities during construction and operations of the proposed project --- What is EMP?
  • 65. E.M.P  Identification of key potential environmental impacts and proposing an action plan for mitigation during pre-construction, construction & operational stages  Establishing appropriate standards and procedures for mitigation and monitoring the environmental impacts Benefits & Advantages of EMP  Lower project costs in the long-term  Increased project acceptance  Improved project design  Informed decision making  Environmentally sensitive decisions  Increased accountability and transparency  Reduced environmental damage  Improved integration of projects into their environmental and social settings --- Objectives
  • 66. E.M.P  Agriculture  Construction (Road networks, Malls, Townships, Dam etc)  Industries  Electrical projects  Waste disposal  Any developmental projects around Protected Areas / Nature Preserves  Clean Development Mechanism CDM project --- Which type of projects under go EMP?
  • 67. E.M.P  The proposed development has been studied from all angles  This report has recommended various measures to control and manage the environment and hence reduce the environmental impact to its minimum level  The proposed development is expected to improve the living standard of the surrounding residents and community --- Summary
  • 68. N O DESCRIPTION COST (RM) 1 EARTH WORK 620,206.88 2 ROAD WORK 560,572.50 3 DRAINAGE 905,785.79 4 SEWAGE 69,036.65 5 WATER SUPPLY 619,916.07 6 TOTAL 2,775,517.89 TOTAL COST OF THE PROJECT