Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Clean Rivers, Clean Lake 8 -- Milwaukee's New I and I Reduction Project/ Zafar Yousuf
1. APRIL 30, 2012 PRESENTATION
AT DISCOVERY WORLD
BY ZAFAR YOUSUF, P.E.
SEWER DESIGN MANAGER
CITY OF MILWAUKEE
City of Milwaukee, Environmental 1
Engineering
2. CITY-MMSD PARTNERSHIP
CITY-MMSD PARTNERSHIP TO
IMPLEMENT I/I REDUCTION
PROJECT
IN THE AREA BOUNDED BY:
N. 82nd ST. TO N. 92ND ST. FROM
W. CENTER ST. TO W. BURLEIGH
ST.
City of Milwaukee, Environmental 2
Engineering
3. CITY BACKGROUND
THE CITY HAS 96 SQUARE MILES AREA,
WITH ABOUT 600,000 POPULATION AS PER
2010 CENSUS DATA
THERE ARE 940 MILES OF SANITARY
SEWERS IN THE CITY COMPRISING OF
ABOUT 850 SYSTEMS.
A SANITARY SYSTEM IS DEFINED WHERE A
CITY SEWER MAIN NETWORK CONNECTS
DIRECTLY TO THE MMSD’S OWNED AND
MAINTAINED METROPOLITAN INTERCEPTOR
SEWER (MIS)
City of Milwaukee, Environmental 3
Engineering
4. I/I in the City of Milwaukee
Systems are monitored to compare sanitary base flow
to peak flows during rain events
Based on the data and subsequent modeling, 8% of
sanitary systems showed high levels of I/I and were
determined to be non-compliant by Milwaukee
Metropolitan Sewerage District (MMSD).
* Non Compliant meter sheds are those meter sheds that
exceed the maximum flows established by MMSD's
rules.
City of Milwaukee, Environmental 4
Engineering
5. Where does I/I come from ?
Cracks in pipes
Roots thru joints
Storm Water Inflow
Sanitary Sewer
Foundation Drain
Connections
Storm Sewer
Downspout
Connections City of Milwaukee, Environmental
Engineering
5
6. Area Bounded by:
N. 82nd St to N. 92nd St from
W. Center St to W. Burleigh St
City of Milwaukee, Environmental 6
Engineering
7. I/I Investigation
Non-Compliant
Dye Flooding Video
sanitary sewer system
Examination
showing high levels of
I/I were dye tested
The storm sewer was
flooded with dye and
the sanitary sewer
was examined
Dye testing Results
showed private
laterals as a source of
75% of the I/I City of Milwaukee, Environmental
Engineering
7
8. Why was this area chosen?
This area was identified by the Wisconsin Department of Natural
Resources (WDNR) and the Milwaukee Metropolitan Sewerage
District (MMSD) as having high levels of Inflow and Infiltration (I/I)
26-times base flow
24-times base flow
City of Milwaukee, Environmental 8
Engineering
9. I/I Demonstration Project
This project consists of inspecting and rehabilitating the
sanitary building sewers (laterals) of homes
This program was 100% voluntary and homeowners will
not incur any costs
This area has reported numerous basement backups over
the last few years
City of Milwaukee, Environmental 9
Engineering
10. SANITARY SYSTEM INFORMATION
THIS SYSTEM IS COMPRISED OF APPROXIMATELY
18,500 FEET OF 8-INCH TO 12 INCH DIAMETER
SANITARY SEWERS ORIGINALLY BUILT IN THE
1940’S
ALL SANITARY SEWER MAINS WERE CURED-IN-
PLACE LINED IN 2010
THERE ARE 70 SANITARY MANHOLES THAT WERE
ALSO LINED IN 2010
THERE ARE 563 PROPERTIES IN THIS SYSTEM
City of Milwaukee, Environmental 10
Engineering
11. PURPOSE
REDUCE SANITARY SEWER OVERFLOWS
REDUCE BASEMENT BACKUPS
REDUCE MAINTAINANCE COSTS
REDUCE WASTE WATER TREATMENT
COSTS
City of Milwaukee, Environmental 11
Engineering
12. Project Details
Letters were sent to all 563 home owners
regarding inspection and rehabilitation of their
sanitary sewer lateral. As of April 24, 2012, 512
home owners , approximately (91%), have
consented for the rehabilitation.
The City has worked with residents to minimize
disruptions and inconvenience during the project
Post rehabilitation flow monitoring data will be
compared with pre-rehabilitation data to estimate
the effectiveness that lateral lining has on flow
reduction
City of Milwaukee, Environmental 12
Engineering
13. What is being done?
A 4-Step Process
1. Sanitary Lateral Inspection
2. Cleanout Installation
3. Roof drain dye testing
4. Lateral Rehabilitation 13
City of Milwaukee, Environmental
Engineering
14. 1. Sanitary Lateral Inspection
A camera is
inserted in the
lateral from the
sewer in the
street
The lateral
condition is
assessed for
rehabilitation City of Milwaukee, Environmental
Engineering
14
16. 2. Cleanout Installation
A hole is hydro-
excavated as close
to the house as
possible
A Vac-A-Tee is
installed on the
sanitary lateral
The hole is then
backfilled to grade 16
City of Milwaukee, Environmental
Engineering
17. VAC-A TEE
City of Milwaukee, Environmental 17
Engineering
18. 3. Roof drain dye testing
A green dye is
pumped into the
roof gutters
A video camera is
inserted in the
sanitary lateral to
detect any dye
leaking in the
sanitary lateral
City of Milwaukee, Environmental 18
Engineering
20. 4. Sanitary Lateral Rehabilitation
The existing sanitary Before
laterals were televised
(roots and cracks are evident)
The sanitary lateral is
rehabilitated with a cured- During
in-place lining method
from the public sewer
main in the street
The liner is installed to After
the cleanout
City of Milwaukee, Environmental 20
Engineering
22. CURRENT PROJECT STATUS
512 HOME OWNERS CONSENTED FOR
LATERAL REHABILITATION (91%)
382 LATERALS HAVE BEEN LINED
(75%)
PROJECT COMPLETION DATE IS MAY 25
City of Milwaukee, Environmental 22
Engineering
23. PROJECT COSTS
TOTAL PROJECT COST=$ 3.8 MILLION
MMSD ALLOCATED FUNDS= $ 3.4
MILLION
CITY FUNDS= $ 0.4 MILLION
(In addition, city spent $ 600,000 for mainline lining)
AVERAGE COST PER HOME=$ 7,700
City of Milwaukee, Environmental 23
Engineering
24. COST BREAKDOWN
TV CAMERA INSPECTION-$ 5 PER LIN. FT.
(Average lateral length 60 lin. ft per home)= $ 300
LATERAL TRACING- $ 200 EACH
CLEAN OUT- $ 1,600 EACH
ROOF DRAIN DYE TEST- $ 200
LATERAL LINER INSTALLATION
$ 80 PER LIN. FT x 60 = $ 4,800
City of Milwaukee, Environmental 24
Engineering
25. EXAMPLES OF OTHER CITIES DOING SUCH
PROJECTS
CITY OF NEW CASTLE, DELAWARE REDUCED ITS
TOTAL FLOWS BY 73 PERCENT IN A SANITARY
BASIN*
ACHIEVED A 55 PERCENT REDUCTION IN PEAK FLOW
RATES OF THE SANITARY BASIN*
* TO JUDGE THE REHABILITATION EFFECTIVENESS,
PRE-REHABILITATION FLOWS WERE COMPARED WITH
POST-REHABILITATION FLOWS
City of Milwaukee, Environmental 25
Engineering
26. EXAMPLES OF OTHER CITIES DOING SUCH
PROJECTS
CITY OF NAPERVILLE, ILLINOIS REDUCED ITS TOTAL
YEARLY FLOW TO THE TREATMENT PLANT BY 192
MILLION GALLONS IN ONE YEAR
THEY ACHIEVED THIS BY LINING 65 MILES OF
SANITARY MAIN LINES AND REHABILITATING 3,000
LATERALS SINCE 2002
DOING SUCH IMPROVEMENTS ALLOWED THEM TO
DEFER CONSTRUCTION OF A NEW TREATMENT PLANT
City of Milwaukee, Environmental 26
Engineering
27. Our Goals
Reduce chances of sanitary sewer overflows and
basement backups during heavy rain events
Reduce the maximum amount of I/I in the sanitary
sewer system
Judge the rehabilitation effectiveness by analyzing
pre-rehabilitation flows with post- rehabilitation flows.
Improve public health and the overall quality of life in
the City
City of Milwaukee, Environmental 27
Engineering
28. Follow up
A post rehabilitation survey
was sent to all residents for
comments and concerns
regarding the project
To date, approximately
95% of responses have
been positive regarding the
project (50% response
rate)
City of Milwaukee, Environmental 28
Engineering
29. USEFUL WEBSITES
MILWAUKEE METROPOLITAN SEWERAGE
DISTRICT (MMSD)
http://basementconnection.mmsd.com/
PRIVATE PROPERTY VIRTUAL LIBRARY (PPVL)
http://www.wef.org/PrivateProperty/
LMK ENTERPRISES, INC.
http://www.performanceliner.com/
City of Milwaukee, Environmental 29
Engineering
30. QUESTIONS
?
City of Milwaukee, Environmental 30
Engineering