AN EVALUATION OF ESTIMATING PEAK
RUNOFF with Tc for GREEN INFRASTRUCTURE
TC Equation Relationship to
Rational Method Peak Flow
Rational Method Equation and Variables:
Q = C i A
Where:
Q = Maximum Rate of Runoff (cfs)
C = Runoff Coefficient
i = Average Rainfall Intensity (in/hr)
A = Drainage Area (in acres)
The EQUATION (Q)
Rational Method Equation and Variables:
Where:
C = Runoff Coefficient
R = Total Depth of Runoff (in)
P = Total Depth of Precipitation (in)
RUNOFF COEFFICIENT (C)
Rossmiller (1981) C = 7.210-7 CN3 T0.05 (0.01CN)-0.6s-.02
((0.001CN)1.48 )0.15 – 0.1I ((P+1)/2) 0.7
Where: CN is the Soil Conservation Service Curve Number; T is the recurrence interval (years); S is the average land slope (%);
I is the intensity (in/hr); and P is percent imperviousness.
C =
𝑅 𝑑
𝑃 𝑑
Rational Method Equation and Variables:
RAINFALL INTENSITY (i)
The determination of rainfall intensity (i)
for use in the Rational Formula involves
consideration of three factors:
• Average frequency of occurrence
• Intensity-duration characteristics for
a selected rainfall frequency.
• The time of concentration (tc).
Rainfall Intensities Based upon I-D-F Curves
As the Tc goes up, the “I” goes down.
Rainfall Intensities are
obtained by entering the
Log-Log nomograph with
the Time of Concentration
along the abscissa,
intersecting the Storm
Return Period Curve, and
proceeding horizontally to
the Rainfall Intensity.
http://hdsc.nws.noaa.gov/hdsc/pfds/index.html
Rational Equation with an “R” Runoff Ratio:
Where: q = Maximum Rate of Runoff (cfs), c = Runoff Coefficient, i = Average Rainfall Intensity (in/hr), A = Drainage Area (acres)
𝐑𝐚𝐭𝐢𝐨𝐧𝐚𝐥 Equation 𝐀𝐫𝐫𝐚𝐧𝐠𝐞𝐝 to ‘c’ Coeff. & ‘A’ Area
𝐜 =
𝐪(𝐜𝐟𝐬)
𝐢 ∗ 𝐀
𝐀 =
𝐪(𝐜𝐟𝐬)
𝐢 ∗ 𝐜
𝐑𝐮𝐧𝐨𝐟𝐟 𝐑𝐚𝐭𝐢𝐨 =
𝐝𝐢𝐬𝐜𝐡𝐚𝐫𝐠𝐞 𝐫𝐚𝐭𝐞
𝐢𝐧𝐭𝐞𝐧𝐬𝐢𝐭𝐲
= 𝐑 =
𝐪(cfs)
𝐢 (
in
hr
)
R = 2 cfs/4 in. = 2.0
Or
R= 4 cfs/2 in. = 0.5
c =
R
A
Now A =
R
c
&
Where:
Plotting the Rational Equation using
“R” Runoff Ratio with “c” coefficient
Plotting the Rational Equation using
“R” Runoff Ratio with “A” area
Rational Method Assumptions & Limitations
• Maximum watershed area has a 200 acre limit
• The method is applicable when the time of
concentration (tc) for the drainage area is less
than the duration of peak rainfall intensity.
• The time of concentration (tc) is the time
required for water to travel from the
hydraulically most remote point of the basin to
the point of interest within the basin.
• The calculated runoff is directly proportional
to the rainfall intensity.
• Rainfall intensity is uniform throughout the
duration of the storm.
• The frequency of occurrence for the peak
discharge is the same as the frequency of
the rainfall producing that event.
Rational Method Assumptions & Limitations
• Rainfall is distributed uniformly over the
drainage area.
• The minimum duration to be used for
computation of rainfall intensity is 10
Minutes. (Several jurisdictions use a 5
minute minimum)
• The rational method does not account for
storage in the drainage area. Available
storage is assumed to be filled.
Rational Method Assumptions & Limitations
Rational Method Equation and Variables:
TIME OF CONCENTRATION (tc)
• If the chosen storm duration > tc, then the rainfall
intensity will be less than that at tc (Peak discharge
< optimal value).
• If the chosen storm duration < tc, then the watershed
is not fully contributing runoff to the outlet for that
storm length (i.e. optimal value will not be realized).
• Therefore, use storm duration = tc for peak discharge.
Unified TC Equation for Channelization using ‘C’
Tc =
𝟏−𝑪avg
𝟑
𝒔
𝟏𝟐𝟓
𝑳
+
𝟑 𝒔
𝟏𝟒
• Tc = Time of Concentration (minutes)
• 𝑳 = Length of Flow Path (feet)
• 𝑪avg = Rational method’s average runoff coefficient
• 𝒔 = % Slope of Flow Path (decimal format)
• Equation Limits: 1 to 225 acres for drainage basin
1 to 12 percent slope for flow path
0.10 to 0.95 rational runoff coefficient
‘C’ Relationships for Soil Types
using a 10yr. Storm Event
Unified Tc ‘C’ Equation uses an average ‘C‘
coefficient (near B soil type)
Basin weighed ‘C’ value is attained by
adjusting ‘C’ soil types to a ‘Cavg’ type
Cavg =
𝑪𝒕𝒚𝒑𝒆 𝟐𝟏+𝟎.𝟕𝒙+𝟎.𝟏𝟓𝒙 𝟐 −𝒙+𝟏.𝟓
𝟐𝟐.𝟓
Cavg = Average C values used in Kirpich-Velocity Eq.
𝑪𝒕𝒚𝒑𝒆 = Rational method’s runoff coefficient per soil type
𝒙 = NRCS’s soil type factor shown below
Type A Soil: x = 0 Type B Soil: x = 1
Type C Soil: x = 2 Type D Soil: x = 3
Mockus (USDA 1973) developed an empirical relationship
between flow length and drainage area using data from
Agricultural Research Service (ARS) watersheds.
Time of Concentration’s Flow Length
and Drainage Area Relationship
National Engineering Handbook
630.1502 Methods for estimating time of concentration
Eq. 15-5 𝒍 = 𝟐𝟎𝟗 𝑨 𝟎.𝟔
Where:
l = length of runoff flow, (ft)
A = drainage area, (acres)
Kirpich Equation compared to NRCS
Equation by Area of Drainage Basin
Tc =
𝟏−𝑪avg
𝟑
𝒔
𝟏𝟐𝟓
209 𝑨
0.6 +
𝟑 𝒔
𝟏𝟒
Unified TC Equation with ‘C’ for a Basin Area
UTC Equation arranged for Rational Runoff
Coefficient ‘c’ for Basin Areas at 5 & 10 Minutes
𝟓 𝐨𝐫 𝟏𝟎 𝐦𝐢𝐧. 𝐓 𝐜 =
1 − 𝑪
3
𝒔
125
209 𝑨0.6 +
3
𝒔
14
𝒄 = 1 − 5 3
𝒔
125
209 𝑨0.6
+
3
𝒔
14
𝒄 = 1 − 10 3
𝒔
125
209 𝑨0.6
+
3
𝒔
14
5 min. Runoff Coefficient ‘c’ 10 min. Runoff Coefficient ‘c’
Total Hydraulic Time Calculations
(TR55, Velocity, or SCS Method)
Sheet Flow Tt = 0.007(nL)0.8/(P2
0.5S0.4)
Shallow Concentrated Flow Tt = L /3600V
Open Channel Flow Tt= (L*n) /(1.49R0.67S 0.5)
(Manning’s Equation)
Where Hydraulic Radius = conveyance flow depth then:
Manning’s equation becomes Tt = L/3600V
Total Watershed Time of Concentration
tc=STt
L= ft., Tt = hr., S= % slope, R= ft., P= in.(2yr.24hr.) , V= ft./sec.
Sheet Flow
TR-55 Sheet Flow—The sheet flow time computed for each area of
sheet flow that requires the following input data:
Hydraulic Length—Defined flow length for the sheet flow.
Manning's n—Manning's roughness value of the sheet flow.
Slope— The defined slope of the sheet flow/catchment.
Precipitation
Infiltration
Kinematic Wave Eq.
Technical Paper No. 40 Rainfall Frequency Atlas of the
U.S. for a 2 yr. Return Period with 24 hr. Storm Duration
Kirpich Equation compared to NRCS
Equation with a P2 Sheet Flow of 2 inches
Equations Confluence
Kirpich Equation compared to NRCS
Equation with a P2 Sheet Flow of 4 inches
Equations Confluence
Kirpich Equation compared to NRCS
Equation with a P2 Sheet Flow of 6 inches
Equations Confluence
Unified TC ‘C’ Equation compared to
Kirpich & NRCS’s P2 Sheet Flow of 2”
UTC & Kirpich
Confluence
Unified TC ‘C’ Equation compared to
Kirpich & NRCS’s P2 Sheet Flow of 4”
UTC & Kirpich
Confluence
Unified TC ‘C’ Equation compared to
Kirpich & NRCS’s P2 Sheet Flow of 6”
UTC & Kirpich
Confluence
Unified TC Equation Plotted to Rational
Equation Runoff Ratio ‘R’ per Basin Area
Unified TC Equation Plotted to Rational
Equation Runoff Ratio ‘R’ per ‘c’ Coefficient
UTC Eq. for 2% Slope Plotted to Rational Eq.
Runoff Ratio ‘R’ per ‘c’ Coefficient
UTC Eq. for 10% Slope Plotted to Rational
Eq. Runoff Ratio ‘R’ per ‘c’ Coefficient
UTC Equation Plotted to Rational Runoff
Ratio ‘R’ per a ‘c’ Coefficient Variable
A Graphical Representation & Significance of a 5 Minute
UTC Equation Intersection to a Rational Ratio‘R’ Equation
A Graphical Representation & Significance of a 10 Minute
UTC Equation Intersection to a Rational Ratio‘R’ Equation
 Area #1: The rational equation can be used without
checks. No verification of rainfall intensity or time of
concentration reassessment.
 Area #2: The rational equation is limited only by
the Tc time. Time of concentration verification is
necessary to confirm the total time is less than Tc.
 Area #3: The rational equation is limited by rainfall
intensity. There is an iterative process to verification
rainfall intensity or a Tc reassessment.
These Areas Offer Insight to the Rational Equation’s
Restrictions on Runoff Calculations in the Following:
What are the 3 Areas Under the Curves?
Rational ‘c’ Equivalent Values for the
Rational Equation & 5 minute Tc Equation
Where:
C = Runoff Coefficient
s = Average flow path slope (ft./ft.) (decimal)
(with Slope limits from 2% to 12%)
R = Rational Ratio 𝐑 = 𝐪(cfs) / 𝐢 (in./hr.)
(with R limit ratios from 0.2 to 10)
An Equation for a 5 minute Balance ‘c’
𝒄 =
0.82 𝑹
4.8 𝒔 + 𝑹
Rational ‘c’ Equivalent Values for the
Rational Equation & 10 minute Tc Equation
An Equation for a 10 minute Balance ‘c’
𝒄 =
0.76 𝑹
13.7 𝒔 + 𝑹Where:
C = Runoff Coefficient
s = Average flow path slope (ft./ft.) (decimal)
(with Slope limits from 2% to 12%)
R = Rational Ratio 𝐑 = 𝐪(cfs) / 𝐢 (in./hr.)
(with R limit ratios from 0.2 to 10)
Rational ‘c’ Equivalent Values for the Rational
Equation & a Calculated UTC Tc
A Balance ‘c’ Equation for UTC and Rational Eq.
Where:
C = Runoff Coefficient
S = Average flow path slope (ft./ft.) (decimal)
(with Slope limits from 2% to 12%)
R = Rational Ratio 𝐑 = 𝐪(cfs) / 𝐢 (in./hr.)
(with R limit ratios from 0.2 to 10)
Tc = Time of Concentration (minutes) (5-20 min.)
𝒄 =
)(𝒕 𝒄
−0.12
𝑹
0.5 𝒕 𝒄
1.46 𝒔 + 𝑹
Previous Equations are Established for
Green Infrastructure on Small Basins
• The TC comparisons are graphed to the rational
empirical equation that convey runoff with a related
surface rational ‘c’ coefficient.
• These empirical equations provide runoff estimations
for homogenous rainfall intensities and a uniform
watershed surface coefficient.
• Runoff time calculations are estimated for small
drainage basins of 60 acres or less and maintain a
primary pattern of a dominate “surface” flow attribute.
Ken Kagy, P.E., CFM, CPSWQ, CPESC (678) 242-2543 ken.kagy@cityofmiltonga.us
 Understand each required variable in the time of concentration equation.
 Understand the limits to each time of concentration equation’s variables.
 Understand the basin’s flow path with its flow type, length, depth, and slope.
 Apply acceptable surface roughness Tc coefficients that correlate to equivalent
hydrology’s surface roughness conditions used to calculate the hydrograph.
Time of Concentration Equations Improve Accuracy with the following:
The End

Mais conteúdo relacionado

Mais procurados

Chapter 3 surface water hydrology
Chapter 3 surface water hydrologyChapter 3 surface water hydrology
Chapter 3 surface water hydrology
Mohammed Salahat
 

Mais procurados (20)

Weirs on Permeable Foundations
Weirs on Permeable FoundationsWeirs on Permeable Foundations
Weirs on Permeable Foundations
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
 
Unit hydrograph
Unit hydrographUnit hydrograph
Unit hydrograph
 
Flood estimation
Flood estimation Flood estimation
Flood estimation
 
Chapter 3 surface water hydrology
Chapter 3 surface water hydrologyChapter 3 surface water hydrology
Chapter 3 surface water hydrology
 
Silt excluders
Silt excludersSilt excluders
Silt excluders
 
Hydrograph
HydrographHydrograph
Hydrograph
 
Hyetograph and hydrograph analysis
Hyetograph and hydrograph analysisHyetograph and hydrograph analysis
Hyetograph and hydrograph analysis
 
Kennedy's and laccy's theory
Kennedy's and laccy's theoryKennedy's and laccy's theory
Kennedy's and laccy's theory
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 
Stream Gauging
Stream GaugingStream Gauging
Stream Gauging
 
Duty delta etc
Duty delta etcDuty delta etc
Duty delta etc
 
Water requirements of crops
Water requirements of cropsWater requirements of crops
Water requirements of crops
 
River engineering flood design
River engineering flood designRiver engineering flood design
River engineering flood design
 
Hydrology ( computation of average rainfall )
Hydrology ( computation of average rainfall )Hydrology ( computation of average rainfall )
Hydrology ( computation of average rainfall )
 
Streamflow-measurement.ppt
Streamflow-measurement.pptStreamflow-measurement.ppt
Streamflow-measurement.ppt
 
Flood routing
Flood routingFlood routing
Flood routing
 
Rainfall measurement methods
Rainfall measurement methodsRainfall measurement methods
Rainfall measurement methods
 
Stream flow measurement
Stream flow  measurementStream flow  measurement
Stream flow measurement
 

Semelhante a July 30-130-Ken Kagy2

5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).ppt
JohnAyele
 
150860106006 54 55_62
150860106006 54 55_62150860106006 54 55_62
150860106006 54 55_62
Riya2001998
 

Semelhante a July 30-130-Ken Kagy2 (20)

runoff.pdf
runoff.pdfrunoff.pdf
runoff.pdf
 
July 30-130-Ken Kagy1
July 30-130-Ken Kagy1July 30-130-Ken Kagy1
July 30-130-Ken Kagy1
 
5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).ppt
 
Class lectures on Hydrology by Rabindra Ranjan Saha Lecture 12
Class lectures on Hydrology by Rabindra Ranjan Saha Lecture 12Class lectures on Hydrology by Rabindra Ranjan Saha Lecture 12
Class lectures on Hydrology by Rabindra Ranjan Saha Lecture 12
 
designing simple drainage system.pptx
designing simple drainage system.pptxdesigning simple drainage system.pptx
designing simple drainage system.pptx
 
C-039.pdf
C-039.pdfC-039.pdf
C-039.pdf
 
Hydrology ( Hydro graph )
Hydrology ( Hydro graph )Hydrology ( Hydro graph )
Hydrology ( Hydro graph )
 
Runoff & Flood Frequency Analysis
Runoff & Flood Frequency AnalysisRunoff & Flood Frequency Analysis
Runoff & Flood Frequency Analysis
 
RunoffEstimation from a given catchment area.pptx
RunoffEstimation from a given catchment area.pptxRunoffEstimation from a given catchment area.pptx
RunoffEstimation from a given catchment area.pptx
 
Hydrology (Estimation of peak flood discharge)
Hydrology (Estimation of peak flood discharge)Hydrology (Estimation of peak flood discharge)
Hydrology (Estimation of peak flood discharge)
 
WATERSHED CATCHMENT.pptx
WATERSHED CATCHMENT.pptxWATERSHED CATCHMENT.pptx
WATERSHED CATCHMENT.pptx
 
Deck drainage design
Deck drainage designDeck drainage design
Deck drainage design
 
2012 pe review__hyd_
2012 pe review__hyd_2012 pe review__hyd_
2012 pe review__hyd_
 
150860106006 54 55_62
150860106006 54 55_62150860106006 54 55_62
150860106006 54 55_62
 
Lecture22012.pptx
Lecture22012.pptxLecture22012.pptx
Lecture22012.pptx
 
Airport drainage
Airport drainageAirport drainage
Airport drainage
 
Flow in Pipes
Flow in PipesFlow in Pipes
Flow in Pipes
 
Airport drainage
Airport drainageAirport drainage
Airport drainage
 
RP-BRIDGE HYDRAULICS.pptx
RP-BRIDGE HYDRAULICS.pptxRP-BRIDGE HYDRAULICS.pptx
RP-BRIDGE HYDRAULICS.pptx
 
NEW HYDRO DESIGN OF MINOR BRIDGE OF RIVER .pptx
NEW HYDRO DESIGN OF MINOR BRIDGE OF RIVER .pptxNEW HYDRO DESIGN OF MINOR BRIDGE OF RIVER .pptx
NEW HYDRO DESIGN OF MINOR BRIDGE OF RIVER .pptx
 

Mais de Soil and Water Conservation Society

Mais de Soil and Water Conservation Society (20)

September 1 - 0939 - Catherine DeLong.pptx
September 1 - 0939 - Catherine DeLong.pptxSeptember 1 - 0939 - Catherine DeLong.pptx
September 1 - 0939 - Catherine DeLong.pptx
 
September 1 - 830 - Chris Hay
September 1 - 830 - Chris HaySeptember 1 - 830 - Chris Hay
September 1 - 830 - Chris Hay
 
August 31 - 0239 - Yuchuan Fan
August 31 - 0239 - Yuchuan FanAugust 31 - 0239 - Yuchuan Fan
August 31 - 0239 - Yuchuan Fan
 
August 31 - 0216 - Babak Dialameh
August 31 - 0216 - Babak DialamehAugust 31 - 0216 - Babak Dialameh
August 31 - 0216 - Babak Dialameh
 
August 31 - 0153 - San Simon
August 31 - 0153 - San SimonAugust 31 - 0153 - San Simon
August 31 - 0153 - San Simon
 
August 31 - 0130 - Chuck Brandel
August 31 - 0130 - Chuck BrandelAugust 31 - 0130 - Chuck Brandel
August 31 - 0130 - Chuck Brandel
 
September 1 - 1139 - Ainis Lagzdins
September 1 - 1139 - Ainis LagzdinsSeptember 1 - 1139 - Ainis Lagzdins
September 1 - 1139 - Ainis Lagzdins
 
September 1 - 1116 - David Whetter
September 1 - 1116 - David WhetterSeptember 1 - 1116 - David Whetter
September 1 - 1116 - David Whetter
 
September 1 - 1053 - Matt Helmers
September 1 - 1053 - Matt HelmersSeptember 1 - 1053 - Matt Helmers
September 1 - 1053 - Matt Helmers
 
September 1 - 1030 - Chandra Madramootoo
September 1 - 1030 - Chandra MadramootooSeptember 1 - 1030 - Chandra Madramootoo
September 1 - 1030 - Chandra Madramootoo
 
August 31 - 1139 - Mitchell Watkins
August 31 - 1139 - Mitchell WatkinsAugust 31 - 1139 - Mitchell Watkins
August 31 - 1139 - Mitchell Watkins
 
August 31 - 1116 - Shiv Prasher
August 31 - 1116 - Shiv PrasherAugust 31 - 1116 - Shiv Prasher
August 31 - 1116 - Shiv Prasher
 
August 31 - 1053 - Ehsan Ghane
August 31 - 1053 - Ehsan GhaneAugust 31 - 1053 - Ehsan Ghane
August 31 - 1053 - Ehsan Ghane
 
August 31 - 1030 - Joseph A. Bubcanec
August 31 - 1030 - Joseph A. BubcanecAugust 31 - 1030 - Joseph A. Bubcanec
August 31 - 1030 - Joseph A. Bubcanec
 
September 1 - 130 - McBride
September 1 - 130 - McBrideSeptember 1 - 130 - McBride
September 1 - 130 - McBride
 
September 1 - 0216 - Jessica D'Ambrosio
September 1 - 0216 - Jessica D'AmbrosioSeptember 1 - 0216 - Jessica D'Ambrosio
September 1 - 0216 - Jessica D'Ambrosio
 
September 1 - 0153 - Mike Pniewski
September 1 - 0153 - Mike PniewskiSeptember 1 - 0153 - Mike Pniewski
September 1 - 0153 - Mike Pniewski
 
September 1 - 0130 - Johnathan Witter
September 1 - 0130 - Johnathan WitterSeptember 1 - 0130 - Johnathan Witter
September 1 - 0130 - Johnathan Witter
 
August 31 - 1139 - Melisa Luymes
August 31 - 1139 - Melisa LuymesAugust 31 - 1139 - Melisa Luymes
August 31 - 1139 - Melisa Luymes
 
August 31 - 1116 - Hassam Moursi
August 31 - 1116 - Hassam MoursiAugust 31 - 1116 - Hassam Moursi
August 31 - 1116 - Hassam Moursi
 

Último

Corporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptxCorporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptx
arnab132
 
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi EscortsHigh Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
Monica Sydney
 

Último (20)

Jumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptxJumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptx
 
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 
NO1 Google Kala Jadu Expert Specialist In Qatar Kala Jadu Expert Specialist I...
NO1 Google Kala Jadu Expert Specialist In Qatar Kala Jadu Expert Specialist I...NO1 Google Kala Jadu Expert Specialist In Qatar Kala Jadu Expert Specialist I...
NO1 Google Kala Jadu Expert Specialist In Qatar Kala Jadu Expert Specialist I...
 
Introduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptxIntroduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptx
 
Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667
Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667
Call Girl in Faridabad ₹7.5k Pick Up & Drop With Cash Payment #8168257667
 
Corporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptxCorporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptx
 
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi EscortsHigh Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
 
2,6-Dichlorophenol - Material Safety Data Sheet.pptx
2,6-Dichlorophenol - Material Safety Data Sheet.pptx2,6-Dichlorophenol - Material Safety Data Sheet.pptx
2,6-Dichlorophenol - Material Safety Data Sheet.pptx
 
Research.pptxdfdddddddddddddddddddddddddddddddddddd
Research.pptxdfddddddddddddddddddddddddddddddddddddResearch.pptxdfdddddddddddddddddddddddddddddddddddd
Research.pptxdfdddddddddddddddddddddddddddddddddddd
 
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptxHertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
 
Call Girls Brigade Road ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Brigade Road ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Brigade Road ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Brigade Road ( 8250092165 ) Cheap rates call girls | Get low budget
 
Russian Call girl Dubai 0503464457 Dubai Call girls
Russian Call girl Dubai 0503464457 Dubai Call girlsRussian Call girl Dubai 0503464457 Dubai Call girls
Russian Call girl Dubai 0503464457 Dubai Call girls
 
Test bank for beckmann and ling s obstetrics and gynecology 8th edition by ro...
Test bank for beckmann and ling s obstetrics and gynecology 8th edition by ro...Test bank for beckmann and ling s obstetrics and gynecology 8th edition by ro...
Test bank for beckmann and ling s obstetrics and gynecology 8th edition by ro...
 
Deforestation
DeforestationDeforestation
Deforestation
 
Environmental Topic : Soil Pollution by Afzalul Hoda.pptx
Environmental Topic : Soil Pollution by Afzalul Hoda.pptxEnvironmental Topic : Soil Pollution by Afzalul Hoda.pptx
Environmental Topic : Soil Pollution by Afzalul Hoda.pptx
 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
 
Climate Change
Climate ChangeClimate Change
Climate Change
 

July 30-130-Ken Kagy2

  • 1. AN EVALUATION OF ESTIMATING PEAK RUNOFF with Tc for GREEN INFRASTRUCTURE TC Equation Relationship to Rational Method Peak Flow
  • 2. Rational Method Equation and Variables: Q = C i A Where: Q = Maximum Rate of Runoff (cfs) C = Runoff Coefficient i = Average Rainfall Intensity (in/hr) A = Drainage Area (in acres) The EQUATION (Q)
  • 3. Rational Method Equation and Variables: Where: C = Runoff Coefficient R = Total Depth of Runoff (in) P = Total Depth of Precipitation (in) RUNOFF COEFFICIENT (C) Rossmiller (1981) C = 7.210-7 CN3 T0.05 (0.01CN)-0.6s-.02 ((0.001CN)1.48 )0.15 – 0.1I ((P+1)/2) 0.7 Where: CN is the Soil Conservation Service Curve Number; T is the recurrence interval (years); S is the average land slope (%); I is the intensity (in/hr); and P is percent imperviousness. C = 𝑅 𝑑 𝑃 𝑑
  • 4. Rational Method Equation and Variables: RAINFALL INTENSITY (i) The determination of rainfall intensity (i) for use in the Rational Formula involves consideration of three factors: • Average frequency of occurrence • Intensity-duration characteristics for a selected rainfall frequency. • The time of concentration (tc).
  • 5. Rainfall Intensities Based upon I-D-F Curves As the Tc goes up, the “I” goes down. Rainfall Intensities are obtained by entering the Log-Log nomograph with the Time of Concentration along the abscissa, intersecting the Storm Return Period Curve, and proceeding horizontally to the Rainfall Intensity. http://hdsc.nws.noaa.gov/hdsc/pfds/index.html
  • 6. Rational Equation with an “R” Runoff Ratio: Where: q = Maximum Rate of Runoff (cfs), c = Runoff Coefficient, i = Average Rainfall Intensity (in/hr), A = Drainage Area (acres) 𝐑𝐚𝐭𝐢𝐨𝐧𝐚𝐥 Equation 𝐀𝐫𝐫𝐚𝐧𝐠𝐞𝐝 to ‘c’ Coeff. & ‘A’ Area 𝐜 = 𝐪(𝐜𝐟𝐬) 𝐢 ∗ 𝐀 𝐀 = 𝐪(𝐜𝐟𝐬) 𝐢 ∗ 𝐜 𝐑𝐮𝐧𝐨𝐟𝐟 𝐑𝐚𝐭𝐢𝐨 = 𝐝𝐢𝐬𝐜𝐡𝐚𝐫𝐠𝐞 𝐫𝐚𝐭𝐞 𝐢𝐧𝐭𝐞𝐧𝐬𝐢𝐭𝐲 = 𝐑 = 𝐪(cfs) 𝐢 ( in hr ) R = 2 cfs/4 in. = 2.0 Or R= 4 cfs/2 in. = 0.5 c = R A Now A = R c & Where:
  • 7. Plotting the Rational Equation using “R” Runoff Ratio with “c” coefficient
  • 8. Plotting the Rational Equation using “R” Runoff Ratio with “A” area
  • 9. Rational Method Assumptions & Limitations • Maximum watershed area has a 200 acre limit • The method is applicable when the time of concentration (tc) for the drainage area is less than the duration of peak rainfall intensity. • The time of concentration (tc) is the time required for water to travel from the hydraulically most remote point of the basin to the point of interest within the basin.
  • 10. • The calculated runoff is directly proportional to the rainfall intensity. • Rainfall intensity is uniform throughout the duration of the storm. • The frequency of occurrence for the peak discharge is the same as the frequency of the rainfall producing that event. Rational Method Assumptions & Limitations
  • 11. • Rainfall is distributed uniformly over the drainage area. • The minimum duration to be used for computation of rainfall intensity is 10 Minutes. (Several jurisdictions use a 5 minute minimum) • The rational method does not account for storage in the drainage area. Available storage is assumed to be filled. Rational Method Assumptions & Limitations
  • 12. Rational Method Equation and Variables: TIME OF CONCENTRATION (tc) • If the chosen storm duration > tc, then the rainfall intensity will be less than that at tc (Peak discharge < optimal value). • If the chosen storm duration < tc, then the watershed is not fully contributing runoff to the outlet for that storm length (i.e. optimal value will not be realized). • Therefore, use storm duration = tc for peak discharge.
  • 13. Unified TC Equation for Channelization using ‘C’ Tc = 𝟏−𝑪avg 𝟑 𝒔 𝟏𝟐𝟓 𝑳 + 𝟑 𝒔 𝟏𝟒 • Tc = Time of Concentration (minutes) • 𝑳 = Length of Flow Path (feet) • 𝑪avg = Rational method’s average runoff coefficient • 𝒔 = % Slope of Flow Path (decimal format) • Equation Limits: 1 to 225 acres for drainage basin 1 to 12 percent slope for flow path 0.10 to 0.95 rational runoff coefficient
  • 14. ‘C’ Relationships for Soil Types using a 10yr. Storm Event
  • 15. Unified Tc ‘C’ Equation uses an average ‘C‘ coefficient (near B soil type) Basin weighed ‘C’ value is attained by adjusting ‘C’ soil types to a ‘Cavg’ type Cavg = 𝑪𝒕𝒚𝒑𝒆 𝟐𝟏+𝟎.𝟕𝒙+𝟎.𝟏𝟓𝒙 𝟐 −𝒙+𝟏.𝟓 𝟐𝟐.𝟓 Cavg = Average C values used in Kirpich-Velocity Eq. 𝑪𝒕𝒚𝒑𝒆 = Rational method’s runoff coefficient per soil type 𝒙 = NRCS’s soil type factor shown below Type A Soil: x = 0 Type B Soil: x = 1 Type C Soil: x = 2 Type D Soil: x = 3
  • 16. Mockus (USDA 1973) developed an empirical relationship between flow length and drainage area using data from Agricultural Research Service (ARS) watersheds. Time of Concentration’s Flow Length and Drainage Area Relationship National Engineering Handbook 630.1502 Methods for estimating time of concentration Eq. 15-5 𝒍 = 𝟐𝟎𝟗 𝑨 𝟎.𝟔 Where: l = length of runoff flow, (ft) A = drainage area, (acres)
  • 17. Kirpich Equation compared to NRCS Equation by Area of Drainage Basin
  • 18. Tc = 𝟏−𝑪avg 𝟑 𝒔 𝟏𝟐𝟓 209 𝑨 0.6 + 𝟑 𝒔 𝟏𝟒 Unified TC Equation with ‘C’ for a Basin Area UTC Equation arranged for Rational Runoff Coefficient ‘c’ for Basin Areas at 5 & 10 Minutes 𝟓 𝐨𝐫 𝟏𝟎 𝐦𝐢𝐧. 𝐓 𝐜 = 1 − 𝑪 3 𝒔 125 209 𝑨0.6 + 3 𝒔 14 𝒄 = 1 − 5 3 𝒔 125 209 𝑨0.6 + 3 𝒔 14 𝒄 = 1 − 10 3 𝒔 125 209 𝑨0.6 + 3 𝒔 14 5 min. Runoff Coefficient ‘c’ 10 min. Runoff Coefficient ‘c’
  • 19. Total Hydraulic Time Calculations (TR55, Velocity, or SCS Method) Sheet Flow Tt = 0.007(nL)0.8/(P2 0.5S0.4) Shallow Concentrated Flow Tt = L /3600V Open Channel Flow Tt= (L*n) /(1.49R0.67S 0.5) (Manning’s Equation) Where Hydraulic Radius = conveyance flow depth then: Manning’s equation becomes Tt = L/3600V Total Watershed Time of Concentration tc=STt L= ft., Tt = hr., S= % slope, R= ft., P= in.(2yr.24hr.) , V= ft./sec.
  • 20. Sheet Flow TR-55 Sheet Flow—The sheet flow time computed for each area of sheet flow that requires the following input data: Hydraulic Length—Defined flow length for the sheet flow. Manning's n—Manning's roughness value of the sheet flow. Slope— The defined slope of the sheet flow/catchment. Precipitation Infiltration Kinematic Wave Eq.
  • 21. Technical Paper No. 40 Rainfall Frequency Atlas of the U.S. for a 2 yr. Return Period with 24 hr. Storm Duration
  • 22. Kirpich Equation compared to NRCS Equation with a P2 Sheet Flow of 2 inches Equations Confluence
  • 23. Kirpich Equation compared to NRCS Equation with a P2 Sheet Flow of 4 inches Equations Confluence
  • 24. Kirpich Equation compared to NRCS Equation with a P2 Sheet Flow of 6 inches Equations Confluence
  • 25. Unified TC ‘C’ Equation compared to Kirpich & NRCS’s P2 Sheet Flow of 2” UTC & Kirpich Confluence
  • 26. Unified TC ‘C’ Equation compared to Kirpich & NRCS’s P2 Sheet Flow of 4” UTC & Kirpich Confluence
  • 27. Unified TC ‘C’ Equation compared to Kirpich & NRCS’s P2 Sheet Flow of 6” UTC & Kirpich Confluence
  • 28. Unified TC Equation Plotted to Rational Equation Runoff Ratio ‘R’ per Basin Area
  • 29. Unified TC Equation Plotted to Rational Equation Runoff Ratio ‘R’ per ‘c’ Coefficient
  • 30. UTC Eq. for 2% Slope Plotted to Rational Eq. Runoff Ratio ‘R’ per ‘c’ Coefficient
  • 31. UTC Eq. for 10% Slope Plotted to Rational Eq. Runoff Ratio ‘R’ per ‘c’ Coefficient
  • 32. UTC Equation Plotted to Rational Runoff Ratio ‘R’ per a ‘c’ Coefficient Variable
  • 33. A Graphical Representation & Significance of a 5 Minute UTC Equation Intersection to a Rational Ratio‘R’ Equation
  • 34. A Graphical Representation & Significance of a 10 Minute UTC Equation Intersection to a Rational Ratio‘R’ Equation
  • 35.  Area #1: The rational equation can be used without checks. No verification of rainfall intensity or time of concentration reassessment.  Area #2: The rational equation is limited only by the Tc time. Time of concentration verification is necessary to confirm the total time is less than Tc.  Area #3: The rational equation is limited by rainfall intensity. There is an iterative process to verification rainfall intensity or a Tc reassessment. These Areas Offer Insight to the Rational Equation’s Restrictions on Runoff Calculations in the Following: What are the 3 Areas Under the Curves?
  • 36. Rational ‘c’ Equivalent Values for the Rational Equation & 5 minute Tc Equation Where: C = Runoff Coefficient s = Average flow path slope (ft./ft.) (decimal) (with Slope limits from 2% to 12%) R = Rational Ratio 𝐑 = 𝐪(cfs) / 𝐢 (in./hr.) (with R limit ratios from 0.2 to 10) An Equation for a 5 minute Balance ‘c’ 𝒄 = 0.82 𝑹 4.8 𝒔 + 𝑹
  • 37. Rational ‘c’ Equivalent Values for the Rational Equation & 10 minute Tc Equation An Equation for a 10 minute Balance ‘c’ 𝒄 = 0.76 𝑹 13.7 𝒔 + 𝑹Where: C = Runoff Coefficient s = Average flow path slope (ft./ft.) (decimal) (with Slope limits from 2% to 12%) R = Rational Ratio 𝐑 = 𝐪(cfs) / 𝐢 (in./hr.) (with R limit ratios from 0.2 to 10)
  • 38. Rational ‘c’ Equivalent Values for the Rational Equation & a Calculated UTC Tc A Balance ‘c’ Equation for UTC and Rational Eq. Where: C = Runoff Coefficient S = Average flow path slope (ft./ft.) (decimal) (with Slope limits from 2% to 12%) R = Rational Ratio 𝐑 = 𝐪(cfs) / 𝐢 (in./hr.) (with R limit ratios from 0.2 to 10) Tc = Time of Concentration (minutes) (5-20 min.) 𝒄 = )(𝒕 𝒄 −0.12 𝑹 0.5 𝒕 𝒄 1.46 𝒔 + 𝑹
  • 39. Previous Equations are Established for Green Infrastructure on Small Basins • The TC comparisons are graphed to the rational empirical equation that convey runoff with a related surface rational ‘c’ coefficient. • These empirical equations provide runoff estimations for homogenous rainfall intensities and a uniform watershed surface coefficient. • Runoff time calculations are estimated for small drainage basins of 60 acres or less and maintain a primary pattern of a dominate “surface” flow attribute.
  • 40. Ken Kagy, P.E., CFM, CPSWQ, CPESC (678) 242-2543 ken.kagy@cityofmiltonga.us  Understand each required variable in the time of concentration equation.  Understand the limits to each time of concentration equation’s variables.  Understand the basin’s flow path with its flow type, length, depth, and slope.  Apply acceptable surface roughness Tc coefficients that correlate to equivalent hydrology’s surface roughness conditions used to calculate the hydrograph. Time of Concentration Equations Improve Accuracy with the following: The End